DE1172211B - Bolting for the steel pit construction - Google Patents
Bolting for the steel pit constructionInfo
- Publication number
- DE1172211B DE1172211B DEST15310A DEST015310A DE1172211B DE 1172211 B DE1172211 B DE 1172211B DE ST15310 A DEST15310 A DE ST15310A DE ST015310 A DEST015310 A DE ST015310A DE 1172211 B DE1172211 B DE 1172211B
- Authority
- DE
- Germany
- Prior art keywords
- hammer
- bolts
- bolting
- holding pieces
- bent ends
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims description 4
- 239000010959 steel Substances 0.000 title claims description 4
- 238000010276 construction Methods 0.000 title 1
- 230000000903 blocking effect Effects 0.000 claims 1
- 235000000396 iron Nutrition 0.000 claims 1
- 229910000746 Structural steel Inorganic materials 0.000 description 2
- 238000006243 chemical reaction Methods 0.000 description 1
- 230000003247 decreasing effect Effects 0.000 description 1
- 238000010304 firing Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/28—Longitudinal struts, i.e. longitudinal connections between adjoining arches
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Joining Of Building Structures In Genera (AREA)
Description
Verbolzung für den stählernen Grubenausbau Die Hauptpatentanmeldung St 12906 VI / 5 c (deutsche Auslegesehrift 1042 503) geht von einer Verbolzung für den stählernen Grubenausbau aus, die als Hammerschlagbolzen bekannt ist. Die Enden der Bolzen umfassen die Profile der Grubenausbaurahmen. Die Bolzen sind vor den umzubiegenden Enden mit Aussparungen versehen, in denen sich auch die Innenseiten der Ausbauprofile abstützen. Die inneren Seitenflächen der Aussparungen sind unterschnitten ausgebildet. Das an die Aussparungen anschließende, umzubiegende Bolzenende weist im Längsschnitt einen Winkel von über 90° auf.Bolting for the steel pit lining The main patent application St 12906 VI / 5 c (German Auslegesehrift 1042 503) assumes a bolting for the steel pit lining, known as hammer bolts. The ends the bolts enclose the profiles of the pit support frames. The bolts are in front of the The ends to be bent are provided with recesses in which the insides are also located the support profiles. The inner side surfaces of the recesses are undercut educated. The end of the bolt to be bent, adjoining the recesses, points in the longitudinal section at an angle of over 90 °.
Die freien Enden der Hammerschlagbolzen werden um die Profile der Grubenausbaurahmen durch Schlag herumgebogen. Die aufeinanderfolgenden Rahmen sind durch mehrere parallele Reihen, deren Anzahl sich nach den Gebirgsverhältnissen richtet, von Hammerschlagbolzen gegeneinander verbolzt. Die in einer Reihe aufeinanderfolgenden Hammerschlagbolzen sind an den Grubenausbaurahmen jeweils um ihre Breite wechselweise gegeneinander versetzt angebracht. Die Enden dieser aufeinanderfolgenden Bolzen umgreifen also den Rahmen abwechselnd über- und untereinander bzw. nebeneinander. Auf jeder Seite des Rahmens stehen also ein umgebogenes Bolzenende und ein durchlaufender gerader Bolzen nebeneinander.The free ends of the hammer bolts are around the profiles of the Pit support frame bent around by impact. The consecutive frames are by several parallel rows, the number of which depends on the mountain conditions aligned, bolted against each other by hammer bolts. The consecutive ones in a row Hammer bolts are on the pit support frame alternately by their width attached offset from each other. The ends of these consecutive bolts so embrace the frame alternately above and below or next to each other. On each side of the frame there is a bent pin end and a continuous one straight bolts next to each other.
Nach der Hauptpatentanmeldung werden die umgebogenen Enden der Hammerschlagbolzen derart verblockt, daß sie sich bei Zugbeanspruchung nicht aufbiegen bzw. zurückbiegen und die Zugfestigkeit der Bolzen ausgenutzt wird. An der überlappungsstelle zweier aufeinanderfolgender Hammerschlagbolzen sind über der Symmetrielinie eines Grubenausbaurahmens zwei gleiche Bügel spiegelbildlich zueinander mit Spiel miteinander verschraubt. Die Bügel tragen an ihren freien Enden fest verbundene Sperrbolzen, die zwischen die Außenfläche des umgebogenen Endes des einen Hammerschlagbolzens und die Flanschinnens2ite des parallelliegenden Hammerschlagbolzens geklemmt sind. Hierdurch wird die Belastbarkeit der Hammerschlagbolzen auf Zug wesentlich erhöht und damit die Anzahl der einzubauenden Bolzen vermindert.According to the main patent application, the bent ends of the hammer striker bolts blocked in such a way that they do not bend up or back under tensile stress and the tensile strength of the bolts is used. At the point of overlap of two successive hammer bolts are above the symmetry line of a pit support frame two identical brackets are screwed together mirror-inverted with play. The brackets have firmly connected locking pins at their free ends, which are between the outer surface of the bent end of one hammer bolt and the inner flange 2ite of the parallel hammer bolt are clamped. This increases the resilience the hammer firing bolt increases significantly on train and thus the number of to be installed Bolt decreased.
Bei der Ausführungsform nach der Hauptpatentanmeldung sind lose Bauteile vorhanden, die gesondert hergestellt, beim Ein- und Umbau verschraubt bzw. gelöst werden müssen und bei der Beförderung in Verlust geraten können.In the embodiment according to the main patent application, there are loose components available, which are manufactured separately, screwed or loosened during installation and conversion and can get lost in transit.
Erfindungsgemäß werden zum Verblocken Haltestücke, vorzugsweise Profilabschnitte, insbesondere von Winkeleisen, benutzt, die an den Hammerschlagbolzen über deren Profile hinaus befestigt sind und durch Zusammenschieben zweier aufeinanderfolgender Hammerschlagbolzen an deren umgebogenen Enden zur Anlage kommen. Zum Verblocken der umgebogenen Enden ist es also lediglich erforderlich, die vorspringenden Enden der Haltestücke in das jeweils benachbarte Bolzenprofil einzuschieben. Lose Bauteile und Verschraubungen kommen in Fortfall. Die Einbauweise der Hammerschlagbolzen selbst bleibt unverändert. Ebenso wie bei der Ausführungsform nach der Hauptpatentanmeldung biegen sich die umgebogenen Enden der Hammerschlagbolzen nach dem Verblocken nicht zurück, dessen Vorteile werden in gleicher Weise erreicht.According to the invention, holding pieces, preferably profile sections, are used for interlocking in particular of angle iron, used, which is attached to the hammer striker via their Profiles are also attached and by sliding two consecutive Hammer strikers come to rest on their bent ends. To block of the bent ends, it is only necessary to remove the protruding ends of the holding pieces into the adjacent bolt profile. Loose components and screw connections are no longer applicable. How the hammer bolts themselves are installed stays unchanged. As with the embodiment according to the main patent application The bent ends of the hammer bolts do not bend after locking back, its advantages are achieved in the same way.
B, -i einer bevorzugten Ausführungsform sind die Haltestücke an den umgebogenen Enden der Hammerschlagbolzen angeschweißt. Sie greifen nach dem Zusammenschieben aufeinanderfolgender Hammerschlagbolzen in Ausklinkungen in deren Stegen ein. Das umgebogene Ende des Hammerschlagbolzens wird bei dieser Ausführungsform am längeren Hebelarm verblockt. Die Ausklinkungen werden in einem Arbeitsgang beim Ausstanzen der Aussparungen hergestellt.B, -i a preferred embodiment, the holding pieces are on the bent ends of the hammer bolts welded on. They reach for being pushed together successive hammer bolts in notches in their webs. That The bent end of the hammer bolt is longer in this embodiment Lever arm blocked. The notches are punched out in one operation made of recesses.
Als Haltestücke können beliebige Profilabschnitte verwendet werden, vorzugsweise von Winkeleisen.Any profile sections can be used as holding pieces, preferably from angle iron.
In der Regel werden die Haltestücke nur einseitig an den Hammerschlagbolzen angebracht, weil diese meist in einer Flucht hintereinander eingebaut werden. Es ist aber auch möglich, die Haltestücke beiderseitig oder durchgehend anzubringen, wenn die Hammerschlagbolzen paarweise eingebaut werden.As a rule, the holding pieces are only attached to the hammer striker on one side appropriate because these are usually installed in a row one behind the other. It but it is also possible to attach the retaining pieces on both sides or continuously, if the hammer bolts are installed in pairs.
Verbolzungen gemäß der Erfindung können an beliebigen Profilen der Grubenausbaurahmen angebracht werden, vorzugsweise an Einstegprofilen und Rinnenprofilen. Die Belastbarkeit wird nicht nur für Zug, sondern auch für Druck erhöht, weil die druckaufnehmenden Flächen vergrößert sind und die Haltestücke Druckbeanspruchungen über den darauffolgenden Hammerschlagbolzen auf das Grubenausbauprofil leiten.Bolts according to the invention can be used on any profiles Pit support frame attached , preferably on single-bar profiles and gutter profiles. The resilience is not only for tension, but also for pressure increased because the pressure-absorbing surfaces are enlarged and the holding pieces are subject to pressure Guide it to the pit support profile via the hammer bolt that follows.
Die Zeichnung zeigt Verbolzungen gemäß der Erfindung.The drawing shows bolts according to the invention.
A b b. 1 ist ein Querschnitt durch ein I-förmiges Grubenausbauprofil mit zwei aufeinanderfolgenden Hammerschlagbolzen mit Haltestücken unter den Flanschen, A b b. 2 die Draufsicht auf A b b. 1, A b b. 3 ein Querschnitt durch ein Rinnenprofil, im übrigen wie A b b. 1, A b b. 4 ist ein gleicher Querschnitt durch ein I-förmiges Grubenausbauprofil, jedoch mit Haltestücken an den umgebogenen Enden der Hammerschlagbolzen, A b b . 5 die Draufsicht auf A b b. 4.A b b. 1 is a cross-section through an I-shaped pit support profile with two successive hammer bolts with holding pieces under the flanges, A b b. 2 the top view of A b b. 1, A b b. 3 a cross section through a channel profile, otherwise as in A b b. 1, A b b. 4 is the same cross-section through an I-shaped one Pit support profile, but with holding pieces at the bent ends of the hammer bolts, A b b. 5 the top view of A b b. 4th
Um das Grubenprofil 1 sind die freien Enden der beiden aufeinanderfolgenden Hammerschlagbolzen 2, von T-förmigem gebogenem Querschnitt. Das Grubenausbauprofil 1 ruht in den Aussparungen 3 der Hammerschlagbolzen 2. Deren umgebogene Enden sind mit 4 bezeichnet. In den A b b. 1 bis 8 sind die Haltestücke 5, unter den Flanschen der Hammerschlagbolzen 2, angeschweißt, in den A b b. 4 und 5 an den umgebogenen Enden 4. In diesen A b b. 4 und 5 sind die Hammerschlagbolzen 2 mit den Ausklinkunizen 6 versehen.To the pit profile 1 are the free ends of the two consecutive Hammer striker 2, of T-shaped curved cross-section. The pit support profile 1 rests in the recesses 3 of the hammer striker 2. The ends of which are bent over denoted by 4. In the A b b. 1 to 8 are the holding pieces 5, under the flanges the hammer bolt 2, welded, into the A b b. 4 and 5 on the bent Ends 4. In these A b b. 4 and 5 are the hammer bolts 2 with the notching units 6 provided.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DEST15310A DE1172211B (en) | 1959-07-03 | 1959-07-03 | Bolting for the steel pit construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DEST15310A DE1172211B (en) | 1959-07-03 | 1959-07-03 | Bolting for the steel pit construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE1172211B true DE1172211B (en) | 1964-06-18 |
Family
ID=7456647
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DEST15310A Pending DE1172211B (en) | 1959-07-03 | 1959-07-03 | Bolting for the steel pit construction |
Country Status (1)
| Country | Link |
|---|---|
| DE (1) | DE1172211B (en) |
-
1959
- 1959-07-03 DE DEST15310A patent/DE1172211B/en active Pending
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE2757450A1 (en) | CONCRETE FORMWORK | |
| DE1172211B (en) | Bolting for the steel pit construction | |
| DE648857C (en) | Sheet metal lining for line expansion in steel | |
| DE955402C (en) | Tensile connection of pit support frames with one another | |
| DE465753C (en) | Grate bar cross member designed as a lattice girder for traveling grids | |
| DE2150950C3 (en) | Coupling for concrete formwork elements | |
| DE1008682B (en) | Bolting for the pit construction | |
| DE1077168B (en) | Bolting for the steel pit construction | |
| DE971915C (en) | Small wander grate | |
| DE951205C (en) | Device for connecting successive expansion frames when expanding lines | |
| DE976720C (en) | Connection of metal bolts when extending the line | |
| DE936383C (en) | Chain made of longwall caps | |
| DE861103C (en) | Threshold for vehicle tracks | |
| DE2550292C2 (en) | Pressure- and tensile-proof bolting | |
| DE7739208U1 (en) | CONCRETE FORMWORK | |
| DE2517652A1 (en) | Mine roadway or heading support - overlaps with load acceptance bars and has segments as flange- adapted I beams | |
| DE2419655C3 (en) | Lattice-shaped warping mat for pit lining | |
| DE966519C (en) | Pit stamp | |
| DE1823309U (en) | FASTENING ARRANGEMENT OF DRAWING MATS IN UNDERGROUND TRAILS. | |
| DE1146827B (en) | Spacer for the tensile and pressure-resistant connection of neighboring track expansion frames | |
| DE1833618U (en) | CLAMPING DEVICE FOR EQUAL AXIS POSTED AGAINST LINE EXTENSION PROFILES. | |
| DE1851614U (en) | PIPE WEDGE LOCK BOLTING. | |
| DE1042503B (en) | Bolting for the steel pit construction | |
| DE1167292B (en) | Delay element for the tensile and pressure-resistant connection of expansion frames arranged one behind the other in the direction of the route | |
| DE1090609B (en) | Tensile and pressure-resistant bolting for pit construction |