DE10358753A1 - Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths - Google Patents
Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths Download PDFInfo
- Publication number
- DE10358753A1 DE10358753A1 DE2003158753 DE10358753A DE10358753A1 DE 10358753 A1 DE10358753 A1 DE 10358753A1 DE 2003158753 DE2003158753 DE 2003158753 DE 10358753 A DE10358753 A DE 10358753A DE 10358753 A1 DE10358753 A1 DE 10358753A1
- Authority
- DE
- Germany
- Prior art keywords
- lintel
- blank
- shell
- concrete filling
- fall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Ceased
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/20—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
- E04C3/22—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members built-up by elements jointed in line
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C2003/023—Lintels
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
Abstract
Die Erfindung betrifft einen Sturz, einen Sturzrohling sowie ein Verfahren zur Herstellung eines Sturzes bzw. eines Sturzrohlinges. Um einen Sturz, der hohe Lasten aufnehmen kann, einfach und kostengünstig herzustellen, ist bei einem Sturz mit einem Sturzkörper und einer in dem Sturzkörper ausgebildeten Rinne (8) vorgesehen, daß der Sturzkörper aus mindestens einem in Längserstreckung schmalen U-Schalen-Stein (1) besteht, in welchem eine flache Rinne (8) (U-Schale) ausgebildet ist, wobei jeder U-Schalen-Stein (1) in Längserstreckung eine der 1/8 m oder dem 1/4 m angepaßte Länge von etwa 123 mm bzw. 248 mm aufweist.The invention relates to a fall, a lintel blank as well as a method for producing a lintel or a lintel blank. In order to produce a fall, the high loads, simple and inexpensive to manufacture, is provided in a fall with a lintel and a trained in the lintel trough (8) that the lintel of at least one narrow in the longitudinal direction U-shell stone (1 ), in which a flat channel (8) (U-shell) is formed, each U-shell stone (1) in the longitudinal extension of the 1/8 m or 1/4 m adapted length of about 123 mm or 248 mm.
Description
Die Erfindung betrifft einen Sturz, einen Sturzrohling sowie ein Verfahren zur Herstellung eines Sturzes bzw. Sturzrohlinges.The The invention relates to a lintel, a lintel blank and a method for producing a fall or lintel blank.
Stürze werden verwendet, um in Mauerwerk Tür- oder Fensteröffnungen zu überbrücken.To be falls used to masonry door or window openings to bridge.
Aus
Aus der Praxis sind ferner KS-Fertigteilstürze und KS-U-Schalen nach DIN V 106 (KS-Formsteine) für Stürze bekannt, bei denen ebenfalls durch eine betongefüllte Rinne und eine sich darin befindliche Stahleinlage Lasten an der Unterseite solche Bauteile im eingebauten Zustand aufgenommen werden sollen. Die Stahleinlage wird bei solchen Bauteilen auch als schlaffe Bewehrung bezeichnet.Out In practice also KS-ready lintels and KS-U-shells according to DIN V 106 (KS-shaped bricks) for bell in which also by a concrete-filled gutter and in it steel insert loads on the bottom of such components to be recorded in the installed state. The steel insert is referred to in such components as a slack reinforcement.
Im Rahmen der nachfolgenden Beschreibung bezeichnet der Begriff U-Schalen-Stein ein Element, welches unter Hinzunahme weiterer U-Schalen-Steine geeignet ist, einen Sturzrohling zu bilden. Ein mit einer Bewehrung versehener und mit Beton ausgegossener Sturzrohling wird als Sturz bezeichnet, wobei das den Beton umgebende Material auch als Sturzkörper bezeichnet wird.in the For the purposes of the following description, the term U-shell stone is used an element, which includes additional U-shell stones is suitable to form a lintel blank. One with a reinforcement provided with concrete poured lintel is called fall, wherein the material surrounding the concrete also referred to as a lintel becomes.
Der Erfindung liegt die Aufgabe zugrunde, einen Sturz sowie ein Verfahren zur Herstellung eines Sturzes zur Verfügung zu stellen, wobei sich Stürze einfach und kostengünstig herstellen lassen und hohe Lasten aufnehmen sollen.Of the Invention is based on the object, a fall and a method to provide for the production of a fall, wherein Crashes easily and cost-effective to produce and to absorb high loads.
Gemäß einem ersten Aspekt der Erfindung ist bei einem Sturz mit einem Sturzkörper und einer in dem Sturzkörper ausgebildeten Rinne vorgesehen, daß der Sturzkörper aus mindestens einem in Längsterstreckung schmalen U-Schalen-Stein besteht, in welchem eine flache Rinne (U-Schale) ausgebildet ist, wobei jeder U-Schalen-Stein in Längsterstreckung eine dem 1/8 Meter oder dem ¼ Meter angepaßte Länge von etwa 123 mm bzw. etwa 248 mm aufweist. Durch die Verwendung schmaler U-Schalen-Steine ist die Herstellung des Sturzes besonders einfach und kostengünstig, da sich solche U-Schalen-Steine wie einfache quaderförmige Mauer-Steine herstellen lassen und insbesondere die Trocknung und Härtung solcher Steine weniger Probleme bereitet, als die Herstellung großformatiger Elemente, was auch zur Folge hat, daß weniger Ausschuß entsteht. In diesem Zusammenhang ist es auch vom Vorteil, daß die U-Schalen-Steine, aus denen der erfindungsgemäße Sturz aufgebaut ist, eine flache Rinne (U-Schale) aufweisen, was wiederum die Herstellung erleichtert.According to one The first aspect of the invention is in a fall with a lintel and one in the lintel trained gutter provided that the lintel made at least one in longitudinal extension narrow U-shell stone consists, in which a shallow channel (U-shell) is formed, with each U-shell stone in longitudinal extension one 1/8 meter or 1/4 meter adapted length of about 123 mm or about 248 mm. By using narrower U-Cup stones making the fall is especially easy and inexpensive, since such U-shell stones produce as simple cuboid wall stones let and especially the drying and hardening of such stones less Problems, as the production of large-scale elements, what also As a result, less Committee arises. In In this context, it is also the advantage that the U-shell stones, from those of the fall according to the invention is constructed, have a shallow groove (U-shell), which in turn the Making easier.
Vorzugsweise ist die Höhe jedes U-Schalen-Steins größer/gleich 248 mm und kleiner/gleich 498 mm, insbesondere 373 mm, wobei die Tiefe der Rinne (U-Schale) kleiner ist als die halbe Höhe und größer ist als ¼ vorzugsweise größer als 1/3 der Höhe des jeweiligen U-Schalen-Steins. Durch die gewählte Dimensionierung ergibt sich eine besonders günstige Herstellung, denn es werden die Preßprobleme bei der Herstellung von U-Schalen-Steinen mit tiefer Rinne genauso vermieden wie das Erfordernis einer groß dimensionierten Bewehrung bei Elementen mit zur Elementhöhe extrem flacher U-Schale.Preferably is the height each U-shell stone greater / equal 248 mm and smaller / equal to 498 mm, in particular 373 mm, wherein the Depth of the gutter (U-shell) is less than half the height and larger as ¼ preferably greater than 1/3 of the height of the respective U-shell stone. By the chosen Dimensioning results in a particularly favorable production, because it become the pressing problems in the production of U-shell stones with deep groove as well avoided as the requirement of a large-scale reinforcement for elements with element height extremely shallow U-shell.
Wenn die Breite jedes U-Schalen-Steines etwa 115 mm oder 175 mm beträgt, weist ein aus solchen U-Schalen-Steinen aufgebaute Sturz eine Dimensionierung auf, mit der er sich ideal in bestehende Systeme einfügen läßt.If the width of each U-shell stone is about 115 mm or 175 mm a fall constructed from such U-shell stones sizing with which it can be ideally integrated into existing systems.
Gemäß einem zweiten Aspekt der Erfindung, für den auch selbständig Schutz beansprucht wird, ist bei einem Sturz mit einem Sturzkörper und einer in dem Sturzkörper ausgebildeten Rinne, in welcher sich eine schlaffe Bewehrung und eine Betonfüllung befinden, vorgesehen, daß in dem Sturzkörper an der die Rinne bildende Wandung eine Verankerungsstruktur ausgebildet ist, welche eine Verzahnung der Betonfüllung mit dem Sturzkörper bewirkt. Durch die Verankerungsstruktur und die mit ihr bewirkte Verzahnung wird erreicht, daß der Sturz insgesamt hohe Lasten aufnehmen kann.According to one second aspect of the invention, for also independently Protection is claimed in a fall with a lintel and one in the lintel trained gutter, in which a flabby reinforcement and a concrete filling, provided that in the lintel formed on the gutter forming wall an anchoring structure is, which causes a toothing of the concrete filling with the lintel. Due to the anchoring structure and the teeth created with it is achieved that the Camber altogether can absorb high loads.
Vorzugsweise ist die Verankerungsstruktur als sich in Längsrichtung der Rinne erstreckende Rippenstruktur ausgebildet. Eine solche Verankerungsstruktur lässt sich besonders einfach herstellen, insbesondere wenn die Rippenstruktur eine oder vorzugsweise mehrere sich über die gesamte Länge des Sturzes erstreckende Rippen aufweist.Preferably is the anchoring structure as extending in the longitudinal direction of the channel Rib structure formed. Such an anchoring structure can be particularly easy to produce, especially if the rib structure one or more preferably over the entire length of the fall having extending ribs.
Alternativ oder ergänzend zu Rippen kann die Verankerungsstruktur gemäß einer weiteren bevorzugten Ausführungsform mindestens eine, vorzugsweise mehrere noppenartige Erhöhungen oder muldenartige Vertiefungen aufweisen. Solche Erhöhungen bzw. Vertiefungen, welche sich insbesondere in Höhenrichtung des Sturzes erstrecken können, sind besonders gut geeignet, eine Ablösung der Betonfüllung von dem Sturzkörper aufgrund lastbedingter Verformungen zu verhindern.alternative or in addition to ribs, the anchoring structure according to another preferred embodiment at least one, preferably a plurality of knob-like elevations or trough-like Have depressions. Such elevations or depressions, which especially in the height direction of the fall are particularly suitable, a replacement the concrete filling from the lintel due to load-induced deformations.
Alternativ oder ergänzend zu Rippen kann die Verankerungsstruktur gemäß einer weiteren bevorzugten Ausführungsform mindestens eine sich in Längsrichtung der Rinne erstreckende Rillenstruktur aufweisen. Eine solche Rillenstruktur, die vorzugsweise mehrere sich über die gesamte Länge des Sturzes erstreckende, vorzugsweise in den Seitenwänden ausgebildete Rillen aufweist, läßt sich besonders kostengünstig herstellen, insbesondere wenn eines der nachfolgend beschriebenen Verfahren Anwendung findet.alternative or in addition to ribs, the anchoring structure according to another preferred embodiment at least one in the longitudinal direction having the groove extending groove structure. Such a groove structure, the preferably several over the entire length the fall extending, preferably formed in the side walls Has grooves, can be especially inexpensive especially if one of the following is described Procedure applies.
Die vorgenannten Rippen und noppenartigen Erhöhungen, aber auch andere Verankerungsstrukturen sind vorzugsweise durch eine Ausformung des Materials der Sturzwandung, insbesondere aus Kalksandstein gebildet. Dadurch erübrigen sich die Verwendung anderer Materialien erforderlichen Be- und Verarbeitungsschritte.The said ribs and knob-like elevations, but also other anchoring structures are preferably formed by a shaping of the material of the lintel, especially made of sand-lime brick. This is unnecessary the use of other materials required treatment and processing steps.
Gemäß einem weiteren Aspekt der Erfindung, für den auch unabhängig Schutz beansprucht wird, ist bei einem Sturz aus mindestens zwei U-Schalen-Steine vorgesehen, die U-Schalen-Steine an ihren Stirnseiten durch das Ausfüllen mit der Betonfüllung großflächig zu verbinden. Eine solche großflächige Verbindung, die sich allein durch das Ausgießen der Rinne mit der Betonfüllung ergibt, erfordert keine zusätzlichen Arbeitsschritte und gewährleistet dennoch eine sichere Verbindung der U-Schalen-Steine, die so zur Tragfähigkeit eines so gefertigten Sturzes beitragen. Mit der genannten großflächigen stirnseitigen Verbindung erübrigt sich insbesondere ein vorheriges Verbinden der U-Schalen-Steine unter einander, bevor diese mit der Betonfüllung ausgegossen werden.According to one Another aspect of the invention, for also independent Protection is claimed in a fall from at least two U-shell stones provided, the U-shell stones their faces by filling in with the concrete filling over a large area connect. Such a large-area connection, which results solely from the pouring of the gutter with the concrete filling, does not require additional Working steps and guaranteed Nevertheless, a secure connection of the U-shell stones, the so to Load capacity contribute to a fall made in this way. With the aforementioned large frontal Connection is unnecessary in particular a previous connecting the U-shell stones under each other before they are poured out with the concrete filling.
Das Verhältnis der genannten stirnseitigen Verbindungsfläche zur gesamten Stirnfläche des Sturzes ist gemäß einer bevorzugten Ausführungsform größer 1:2, vorzugsweise größer 2:3 und beträgt insbesondere 58 % der Stirnfläche des Sturzes. Die Betonfüllung, die sich in diesen Fällen am Material der U-Schalen-Steine ankrallt und dabei nicht nur mechanische sondern auch kristalline Verbindungen eingeht, wirkt im Ergebnis wie eine vorherige Vermörtelung der Strinseiten der U-Schalen-Steine.The relationship said end face connecting surface to the entire end face of the lintel is according to one preferred embodiment greater than 1: 2, preferably greater than 2: 3 and is in particular 58% of the frontal area of the fall. The concrete filling, which in these cases clawed at the material of the U-shell stones and not only mechanical but also crystalline compounds enters, acts as a result like a previous mortar the strin sides of the U-shell stones.
Um eine besonders hohe Tragkraft des Sturzes zu erreichen, ist gemäß einer weiteren bevorzugten Ausführungsform vorgesehen, daß die Betonfüllung aus faserverstärktem Beton besteht. Bei einer solchen Ausführungsform, bei der die Fasern der Betonfüllung vorzugsweise aus Polypropylen oder Stahl bestehen, ist es möglich, die Rinne kleiner als bei einer Betonfüllung ohne Faserverstärkung auszuführen, was zu einem insgesamt leichteren Bauteil führt und zudem eine schnellere Fertigung ermöglicht.Around To achieve a particularly high load capacity of the fall is according to a another preferred embodiment provided that the concrete filling made of fiber-reinforced Concrete exists. In such an embodiment, in which the fibers the concrete filling preferably made of polypropylene or steel, it is possible to Trough smaller than to perform a concrete filling without fiber reinforcement, what leads to an overall lighter component and also a faster Manufacturing possible.
Gemäß einem weiteren Aspekt der Erfindung, für den auch unabhängig Schutz beansprucht wird, ist vorgesehen, daß die Betonfüllung eingefärbt ist, um Belastungsklassen anzuzeigen. Bei einer Einfärbung der Betonfüllung ist es auch dann noch möglich, einen Sturz sicher zu identifizieren, wenn transport- oder witterungsbedingt aufgedruckte Kennzeichnungen unleserlich geworden sein sollten. Dadurch trägt ein solchermaßen ausgebildeter Sturz zu einem schnelleren Baufortschritt und zu einer größeren Sicherheit im Baubetrieb bei.According to one Another aspect of the invention, for also independent Protection is claimed, it is provided that the concrete filling is colored, to display load classes. When coloring the concrete filling is it still possible, to identify a fall safely, if transport- or weather-related printed labels should have become illegible. Thereby wearing in such a way trained fall to a faster construction progress and one greater security in the construction business.
Vorzugsweise besteht die Betonfüllung aus selbstverdichtendem Beton, wodurch weitere Arbeitsschritte eingespart werden.Preferably is the concrete filling made of self-compacting concrete, which saves further work steps become.
Um eine hohe Tragkraft des Sturzes zu erreichen, ist es insbesondere vorteilhaft, wenn die Betonfüllung aus hochfestem Beton, insbesondere aus einem Beton mit einer Druckfestigkeit größer oder gleich 50 N/mm2 besteht.In order to achieve a high load-bearing capacity of the lintel, it is particularly advantageous if the concrete infill consists of high-strength concrete, in particular of a concrete with a compressive strength greater than or equal to 50 N / mm 2 .
Grundsätzlich ist es möglich, die Rinne in dem Sturz so zu dimensionieren, daß diese im eingebauten Zustand des Sturzes an dessen Unter- aber auch Oberseite angeordnet ist. Vorzugsweise ist die Rinne jedoch so dimensioniert, daß die Betonfüllung im eingebauten Zustand des Sturzes an dessen Oberseite angeordnet ist. Dadurch ist es möglich, den Sturzkörper als Sichtstein auszuführen. Dies ist auch unter Brandschutzgesichtspunkten vorteilhaft.Basically it is possible the gutter in the fall to be dimensioned so that these in the installed state the fall is arranged on the bottom but also top. Preferably, however, the channel is dimensioned so that the concrete filling in built-in state of the fall is arranged at the top. This makes it possible for the fall body to execute as a visual stone. This is also advantageous from a fire protection point of view.
Das erfindungsgemäße Verfahren zur Herstellung eines Sturzrohlinges zeichnet sich dadurch aus, daß in dem ungehärteten Sturzrohling eine Verankerungsstruktur und/oder eine Eingriffsstruktur ausgebildet wird. Da der Sturzrohling, der in einer Presse aus einem Kalksandgemisch gefertigt wird und erst durch eine thermische Behandlung seine Endfestigkeit erhält, zunächst weich ist, lassen sich im ungehärteten Zustand Verankerungsstrukturen in dem Material des Sturzrohlinges besonders einfach und damit kostengünstig herstellen.The inventive method for producing a lintel blank is characterized by that in the unhardened Crash blank formed an anchoring structure and / or an engagement structure becomes. Because the lintel blank, which in a press from a Kalksandgemisch is manufactured and only by a thermal treatment its final strength gets first soft, can be unhardened Condition anchoring structures in the material of the lintel blank particularly simple and therefore inexpensive to produce.
Gemäß einer bevorzugten Ausführungsform des Verfahrens ist vorgesehen, daß das Ausbilden der Verankerungs- bzw. Eingriffsstruktur durch einen Pressvorgang erfolgt, wodurch die Kontur der Verankerungsstruktur sich besonders maßgenau erstellen läßt. Wenn dieser Pressvorgang gleichzeitig mit der Formung der Bodenwand und/oder der Seitenwände erfolgt, ist zur Ausbildung der Verankerungsstruktur ein separater Arbeitsschritt nicht erforderlich, was wiederum zu einem einfachen Verfahren und damit günstigen Herstellungskosten führt.According to one preferred embodiment of Method is provided that the Forming the anchoring or engagement structure by a pressing operation takes place, whereby the contour of the anchoring structure is particularly accurately can create. If this pressing process simultaneously with the formation of the bottom wall and / or the sidewalls is done to form the anchoring structure a separate step not required, which in turn becomes a simple procedure and so cheap Production costs leads.
Gemäß einer weiteren bevorzugten Ausführungsform des erfindungsgemäßen Verfahrens erfolgt das Ausbilden einer Verankerungs- bzw. Eingriffsstruktur durch einen Materialabtrag. Ein solcher Materialabtrag, der alternativ oder ergänzend zu einem Pressen von Verankerungs- bzw. Eingriffsstrukturen zu gegebenenfalls weiteren Verankerungs- bzw. Eingriffsstrukturen führt, hat den Vorteil, daß ein für das Pressen der Sturzrohlinge verwendetes Pressenwerkzeug einfach gehalten werden kann. Durch einen Materialabtrag lassen sich insbesondere Verankerungs- bzw. Eingriffsstrukturen ausbilden, die in Ebenen liegen, die sich quer zur Pressrichtung beim Pressen der Sturzrohlinge erstrecken.According to a further preferred embodiment of the method according to the invention, the formation of an anchoring or engagement structure is effected by a material removal. Such material removal, the alternative or supplementary to egg nem pressing of Anankerungs- or engagement structures to possibly further anchoring or engagement structures leads, has the advantage that a press tool used for pressing the lintel blanks can be kept simple. In particular anchoring or engagement structures, which lie in planes which extend transversely to the pressing direction during the pressing of the lintel blanks, can be formed by material removal.
Eine besonders bevorzugte Verfahrensvariante zeichnet sich durch ein Ausblasen aus, durch welches der Materialabtrag erfolgt. Ein Ausblasen hat gegenüber anderen Formen des Materialabtrages, beispielsweise einem Fräsen den Vorteil, daß an dem zum Ausblasen verwendeten Werkzeug nur ein unmerklicher Verschleiß eintritt, wodurch ein solches Verfahren geringe Werkzeugkosten zur Folge hat.A particularly preferred process variant is characterized by a Blow out, through which the material removal takes place. A blow out has across from other forms of Materialabtrages, such as a milling the Advantage that on the used for blowing out tool only an imperceptible wear occurs whereby such a method results in low tooling costs.
Vorzugsweise werden durch den oben beschriebenen Materialabtrag Rillen erzeugt, welche sich vorzugsweise in Längsrichtung der Sturzrohlinge erstrecken. Dadurch wird nicht nur eine besonders günstige Materialverankerung erreicht sondern auch eine einfach Herstellung, da der Positionieraufwand für ein den Materialabtrag ausführendes Werkzeug verringert wird, da im wesentlichen nur eine Positionierung in zwei Richtungen erforderlich ist und der Materialabtrag dann durch einen Vorschub des Werkzeuges oder einen Vorschub der noch ungehärteten Sturzrohlinge erfolgen kann. Wenn gleichzeitig eine erste und mindestens eine zweite Rille erzeugt werden, ist es möglich, eine komplexe Verankerungsstruktur in kurzer Zeit auszubilden.Preferably grooves are created by the ablation described above, which are preferably in the longitudinal direction the lintel blanks extend. This is not only a particularly favorable material anchoring achieved but also a simple production, since the positioning effort for a Material removal exporting Tool is reduced, since essentially only one positioning in two directions is required and then the material removal by a feed of the tool or a feed of the still unhardened lintels can be done. If at the same time a first and at least one second groove are generated, it is possible to have a complex anchoring structure to train in a short time.
Eine besonders kostengünstige Herstellung insbesondere auch unterschiedlich langer Stürze ergibt sich, wenn der Sturzkörper aus mehreren Sturzrohlingen, die insbesondere U-Schalen-Steine sind, aufgebaut ist. Bei einem solchen Aufbau aus Sturzrohlingen, die in ihren Dimensionen vorzugsweise kleinformatigen Steinen entsprechen, wird eine tragende Struktur durch die Bewehrung und die Betonfüllung erreicht. Für die Herstellung der vorgenannten Stürze ist es insbesondere vorteilhaft, wenn zunächst die Sturzrohlinge wie beschrieben gefertigt werden.A particularly cost-effective Production in particular also different lengths of falls results yourself when the lintel from several lintel blanks, which are in particular U-shell stones, constructed is. In such a construction of lintel blanks, in their dimensions preferably correspond to small-sized stones, becomes a bearing Structure achieved through the reinforcement and the concrete filling. For the production the aforementioned falls It is particularly advantageous if initially the lintel blanks be made described.
Sturzrohlinge zur Herstellung eines Sturzes, für die selbständig Schutz beansprucht wird, zeichnen sich gemäß einem weiteren Aspekt der Erfindung durch an den Stirnseiten der U-Schalen-Steine vorgesehene Eingriffsstrukturen aus. Eine solche Ausgestaltung erlaubt es bei der Herstellung eines Sturzes, zwei oder mehrere U-Schalen-Steine dicht aneinander zu setzen und nach dem Einlegen einer Bewehrung mittels einer Betonfüllung zu verbinden, ohne daß dafür eine die Rohlinge umgebende Schalung erforderlich wäre, denn die Eingriffsstrukturen verhindern, daß eingefüllter Beton seitlich aus der Rinne im Bereich des Stoßes zweier U-Schalen-Steine austritt. Darüber hinaus erleichtern die Eingriffsstrukturen ein fluchtgerechtes Ausrichten zweier oder mehrerer U-Schalen-Steine.fall blanks for making a fall, for the self-employed Protection is claimed, are characterized according to a further aspect of Invention provided by on the front sides of the U-shell stones Intervention structures. Such a configuration allows for making a fall, two or more U-shell stones close together to set and after inserting a reinforcement by means of a concrete filling connect, without that one Blanks surrounding formwork would be required because the engagement structures prevent that filled concrete Laterally from the gutter in the area of the impact of two U-shell stones exit. About that In addition, the engagement structures facilitate a flush alignment two or more U-shell stones.
Vorzugsweise ist bei Sturzrohlingen das Verhältnis der Tiefe des Rohlings zu dessen Länge größer 1:2. Bei einem solchen Verhältnis ergeben sich Sturzrohlinge, die in ihren Dimensionen üblichen Kunststeinen entsprechen, welche sich einfach herstellen und problemlos zwischenlagern lassen.Preferably is the ratio for lintel blanks the depth of the blank to its length greater 1: 2. In such a relationship result in crash blanks, the usual in their dimensions artificial stones which are easy to produce and store without any problems to let.
Im Hinblick auf eine hohe Tragkraft eines aus den vorgenannten Sturzrohlingen herzustellenden Sturzes ist es vorteilhaft, wenn in dem Rohling eine Rinne ausgebildet ist, an deren Wandung eine Verankerungsstruktur ausgebildet ist. Bei einer solchen Ausgestaltung ergeben sich die zuvor im Zusammenhang mit dem Sturz erörterten Vorteile, insbesondere wenn die Verankerungsstruktur sich in Längsrichtung erstreckende Rippen und/oder Vertiefungen und/oder Erhöhungen aufweist.in the With regard to a high load capacity of one of the aforementioned lintel blanks to be produced fall, it is advantageous if in the blank a channel is formed, on whose wall an anchoring structure is trained. In such an embodiment, the result previously discussed in connection with the fall, especially if the anchoring structure longitudinally extending ribs and / or depressions and / or elevations.
Gemäß einer besonders bevorzugten Ausführungsform weisen die an den U-Schalen-Steinen vorgesehenen Eingriffsstrukturen jeweils mindestens eine Halbtasche zur Aufnahme einer Betonfüllung auf. Wenn zwei U-Schalen-Steine mit ihren komplementären Eingriffsstrukturen an einander gestellt werden, ergibt sich so eine Tasche zur Aufnahme einer Betonfüllung, die es ermöglicht, zwei U-Schalen-Steine ohne vorheriges Vermörteln oder Verkleben allein durch das Ausfüllen der Rinne mit einer Betonfüllung zu verbinden.According to one particularly preferred embodiment have the engagement structures provided on the U-shell stones in each case at least one half-pocket for receiving a concrete filling. When two U-shell stones with their complementary engaging structures placed each other, this results in a bag for recording a concrete filling, which makes it possible two U-shell stones without previous mortaring or gluing alone by filling the gutter with a concrete filling connect.
Vorzugsweise sind die Halbtaschen derart dimensioniert, daß zwei mit einander verbundene U-Schalen-Steine über mindestens 50%, vorzugsweise mindestens 66% und insbesondere 85% der Stirnfläche eines fertigen Sturzes mit einander verbunden sind. Dadurch läßt sich ein volles Mittragen der U-Schalen-Steine erreichen.Preferably the half-pockets are dimensioned such that two interconnected U-shell stones over at least 50%, preferably at least 66% and in particular 85% of the end face of a finished camber associated with each other. This can be done to reach a full carrying of the U-shell stones.
Das zuvor beschriebene erleichterte fluchtgerechte Ausrichten zweier oder mehrerer U-Schalen-Steine wird gefördert, wenn die Eingriffsstrukturen mindestens eine Ausrichtrippe und mindestens eine Ausrichtnut aufweisen. Solche Strukturen, welche flach gehalten werden können, lassen sich besonders zuverlässig fertigen. Darüber hinaus wirken sie nicht nachteilig, wenn aus solchen hergestellte Stürze mit anderen Systemprodukten verbunden werden sollen, da sich eine zu benachbarten, planen Steinen ergebende Fuge nicht das zulässige Fugenmaß übersteigt.The previously described easier aligned alignment of two or more U-shell stones is promoted when the engagement structures have at least one alignment rib and at least one alignment groove. Such structures, which can be kept flat, let very reliable finished. About that In addition, they do not adversely affect when produced from such falls other system products should be connected, as one to adjacent joints that result from the planning do not exceed the permissible joint size.
Als besonders vorteilhaft hat es sich erwiesen, wenn Stürze oder Sturzrohlinge, derart gestaltet sind, daß sie mit bekannten Bausystemen harmonieren. Dementsprechend ist vorzugsweise vorgesehen, Stürze bzw. Sturzrohlinge und U-Schalen-Steine als Kalksandsteine oder Porenbetonbausteine auszuführen, wobei die Mindestdruckfestigkeit 12 N/mm2 betragen sollte.It has proved to be particularly advantageous if lintels or lintel blanks are designed in such a way that they harmonize with known building systems. Accordingly, it is preferably provided hen, falls or lintel stones and U-shell stones as sand-lime bricks or porous concrete blocks perform, the minimum compressive strength should be 12 N / mm 2 .
Weitere vorteilhafte Ausgestaltungen und Weiterbildungen der Erfindung ergeben sich aus den Unteransprüchen sowie aus der Beschreibung im Zusammenhang mit den Zeichnungen.Further yield advantageous embodiments and refinements of the invention from the dependent claims as well as from the description in connection with the drawings.
Es zeigen:It demonstrate:
Der
in
Der
gezeigte U-Schalen-Stein
Die
in
Um
den Sturzkörper
Die
in
Wie
bei der ersten Ausführungsform
ist der Sturzkörper
Die
In
der in
Aus
der in
Die
vorgenannten Eingriffsstrutkuren
Die
Höhe der
Eingriffsrippe in Richtung X des U-Schalen-Steines beträgt wie die entsprechende Tiefe
der Ausrichtnut
Es
sei der Vollständigkeit
noch darauf hingewiesen, daß in
Richtung des Pfeiles X gesehen, die Fläche der Halbtasche etwa 1/3
der gesamten Stirnfläche
des fertigen Sturzes beträgt,
wobei allerdings zu beachten ist, daß dieser Fläche noch die Querschnittsfläche der
Rinne
Die
in den
Die
Sturzrohlinge gemäß der sechsten
Ausführungsform
weisen als Verankerungsstruktur
Um
die genannten Rillen
Die
durch die Ausblasdüsen
Es hat sich als vorteilhaft erwiesen, für Stürze unterschiedlicher Dimensionen ein System von U-Schalen-Steinen (Sturzrohlingen) zu verwenden, die jeweils die gleiche Länge in Längserstreckung und die gleiche Breite senkrecht dazu aufweisen, jedoch bei gleicher Geometrie der Rinne (U-Schale) unterschiedliche Höhen aufweisen. Dadurch ist es möglich, zur Herstellung unterschiedlicher Stürze ein und denselben Pressenstempel zu verwenden. Die Höhe solcher Stürze läßt sich dann durch einfach gestaltete Gegenformen mit unterschiedlicher Höhe einstellen, und die Länge eines aus solchen U-Schalen-Steinen bzw. Sturzrohlingen hergestellten Sturzes ergibt sich durch ein Aneinanderlegen mehrerer U-Schalen-Steine bzw. Sturzrohlinge, wobei wenn gewünscht, auch eine Verklebung der U-Schalen-Steine bzw. Sturzrohlinge unter einander erfolgen kann. Sind die genannten U-Schalen-Steine bzw. Sturzrohlinge an einander gelegt bzw. mit einander verbunden, wird unter Zuhilfenahme von Abstandshaltern die erforderliche Bewehrung eingelegt, woraufhin dann das Betonieren erfolgen kann. Nach dem Erhärten des Betons, der vorzugsweise Normalbeton B25 ist, können die Stürze in Längen beispielsweise von 75,0 bis 300 cm verwendet werden. Wird die U-Schale nach oben offen vermauert, ergibt sich ein guter Brandschutz, da der Beton und die Bewehrung allseitig durch Kalksandstein oder Porenbeton umgeben ist.It has proven to be beneficial for falls of different dimensions a system of U-shell stones (Lintel blanks), each having the same length in the longitudinal and have the same width perpendicular thereto, but at the same Geometry of the channel (U-shell) have different heights. This makes it possible for producing different falls one and the same press stamp to use. The height such falls let yourself then by simply designed counterforms with different Adjust height, and the length one made of such U-shell stones or lintel blanks Fall is due to a juxtaposition of several U-shell stones or lintel blanks, where if desired, also a bond the U-shell stones or lintel blanks can be done together. Are the U-shell stones or lintel blanks to each other laid or connected with each other, with the help of Spacers the required reinforcement inserted, whereupon then the concreting can be done. After hardening of the concrete, preferably Normal concrete B25 is, can the falls in lengths For example, be used from 75.0 to 300 cm. Will the U shell bricked up open, results in a good fire protection, since the concrete and the reinforcement on all sides by limestone or aerated concrete is surrounded.
Claims (43)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE2003158753 DE10358753A1 (en) | 2003-12-12 | 2003-12-12 | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| DE2003158753 DE10358753A1 (en) | 2003-12-12 | 2003-12-12 | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| DE10358753A1 true DE10358753A1 (en) | 2005-07-14 |
Family
ID=34672772
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| DE2003158753 Ceased DE10358753A1 (en) | 2003-12-12 | 2003-12-12 | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths |
Country Status (1)
| Country | Link |
|---|---|
| DE (1) | DE10358753A1 (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108978995A (en) * | 2018-09-05 | 2018-12-11 | 上海建工五建集团有限公司 | Autoclave aerated concrete building block crosses girder construction and its construction method |
| CN109779144A (en) * | 2019-02-28 | 2019-05-21 | 广西建工集团建筑工程总承包有限公司 | Utilize the prefabricated lintel of U-shaped building block and its construction method |
Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CH325753A (en) * | 1954-04-08 | 1957-11-30 | Hoenger Hans | Lintel beam |
| DE1277536B (en) * | 1962-07-28 | 1968-09-12 | Erich Stockmann | Prefabricated beams, beams or other components made of split hollow stones that are connected to one another by mortar or concrete and reinforcement |
| AT400602B (en) * | 1991-05-14 | 1996-02-26 | Leitl Spannton Gmbh | CERAMIC COMPONENT |
| CH687339A5 (en) * | 1993-12-07 | 1996-11-15 | Lauper Prebeton Ag | Production method for heat-insulating capping plate |
| DE29715541U1 (en) * | 1997-08-29 | 1999-01-07 | Bösch, Berndt, Lustenau | Lost formwork element |
| AT2734U1 (en) * | 1997-11-10 | 1999-03-25 | Leitl Spannton Gmbh | CARRIER |
| DE19927793A1 (en) * | 1998-06-18 | 1999-12-23 | Stahlton Ag Zuerich | Multi-block lintel board for windows and doors |
| DE10123856A1 (en) * | 2001-03-23 | 2002-09-26 | Moritz Menge | Support structure for concrete components |
-
2003
- 2003-12-12 DE DE2003158753 patent/DE10358753A1/en not_active Ceased
Patent Citations (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CH325753A (en) * | 1954-04-08 | 1957-11-30 | Hoenger Hans | Lintel beam |
| DE1277536B (en) * | 1962-07-28 | 1968-09-12 | Erich Stockmann | Prefabricated beams, beams or other components made of split hollow stones that are connected to one another by mortar or concrete and reinforcement |
| AT400602B (en) * | 1991-05-14 | 1996-02-26 | Leitl Spannton Gmbh | CERAMIC COMPONENT |
| CH687339A5 (en) * | 1993-12-07 | 1996-11-15 | Lauper Prebeton Ag | Production method for heat-insulating capping plate |
| DE29715541U1 (en) * | 1997-08-29 | 1999-01-07 | Bösch, Berndt, Lustenau | Lost formwork element |
| AT2734U1 (en) * | 1997-11-10 | 1999-03-25 | Leitl Spannton Gmbh | CARRIER |
| DE19927793A1 (en) * | 1998-06-18 | 1999-12-23 | Stahlton Ag Zuerich | Multi-block lintel board for windows and doors |
| DE10123856A1 (en) * | 2001-03-23 | 2002-09-26 | Moritz Menge | Support structure for concrete components |
Non-Patent Citations (11)
| Title |
|---|
| .105,linke Sp. * |
| Bautechnik,Heft 2,2001,S.105-113 * |
| Bautechnik,Heft 2,2001,S.105-113;S.105,linke Sp.; |
| DIN V 106-1,Febr.2003, Tab.3,8,Bild 4 * |
| DIN V 106-1,Febr.2003, Tab.3,8,Bild 4; |
| Kalksandstein.KS-Lexikon,Broschüre,Bauen und Wohnen,5.Aufl.,Jan. 1999. Kalksanstein-Information GmbH & Co.KG, 30401 Hannover, S.1-56,S.24,29,35,39 * |
| Kalksandstein.KS-Lexikon,Broschüre,Bauen und Wohnen,5.Aufl.,Jan. 1999. Kalksanstein-Information GmbH & Co.KG, 30401 Hannover, S.1-56,S.24,29,35,39; |
| Mauerwerk-Kalender 2000.Ernst & Sohn Verlag,Berlin,S.942,947, ISBN 3-433-02838-9, S.59-62,939-951,S.59,re.Spalte,S.942,947 * |
| Mauerwerk-Kalender 2000.Ernst & Sohn Verlag,Berlin,S.942,947, ISBN 3-433-02838-9, S.59-62,939-951,S.59,re.Spalte,S.942,947; |
| Zement Taschenbuch,1976,1977,hrsg.vom Verein Deutscher Zement- werke e.V.,Düsseldorf,Bauverlag GmbH,Wiesbaden. ISBN 3-7625-0608-6, S.106-108,163,S.107,163 * |
| Zement Taschenbuch,1976,1977,hrsg.vom Verein Deutscher Zement- werke e.V.,Düsseldorf,Bauverlag GmbH,Wiesbaden. ISBN 3-7625-0608-6, S.106-108,163,S.107,163; |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108978995A (en) * | 2018-09-05 | 2018-12-11 | 上海建工五建集团有限公司 | Autoclave aerated concrete building block crosses girder construction and its construction method |
| CN109779144A (en) * | 2019-02-28 | 2019-05-21 | 广西建工集团建筑工程总承包有限公司 | Utilize the prefabricated lintel of U-shaped building block and its construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| DE102018101867A1 (en) | Shuttering device for the production of concrete columns, in particular for the production of parts of a wall forming vertical concrete columns | |
| DE4411122A1 (en) | Building consisting of prefabricated components | |
| DE10358753A1 (en) | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths | |
| DE4333981A1 (en) | Sound-insulating block | |
| DE19535790A1 (en) | Method of manufacturing pressed masonry block of any chosen length for building | |
| AT393525B (en) | METHOD FOR CUTTING A LOCAL CONCRETE PILE | |
| DE4216367A1 (en) | Prefab. masonry element of bricks with mortar joints - has building faces of stepped or toothed configuration | |
| DE2727625A1 (en) | LUMBER FOR ENTRANCE, DOOR AND WINDOW OPENINGS | |
| DE29902843U1 (en) | Equipment for the creation of dimensionally accurate large blocks made of concrete | |
| CH671990A5 (en) | ||
| DE9315423U1 (en) | Masonry | |
| DE4409923A1 (en) | Process for the mfr. of columnar concrete blocks with profiled surfaces | |
| DE3820606A1 (en) | Brick element for a self-supporting roller-blind casing in the form of an upside-down U and roller-blind casing of this type and process for the production thereof | |
| EP3456895B1 (en) | Wall provided with concrete supports and method for the construction of such a wall | |
| DE4421654C2 (en) | Masonry, as well as stone for the construction of such masonry | |
| DE19623659C2 (en) | Brick wall made of at least two prefabricated brick wall elements | |
| DE967730C (en) | Process for producing large mass concrete structures with contraction gaps | |
| DE4328453A1 (en) | Masonrywork structure, masonrywork block therefor, and process and apparatus for producing such masonrywork blocks | |
| DE859667C (en) | Formworkless steel stone or reinforced concrete ribbed ceiling | |
| DE4418872A1 (en) | Quadratic shaft element esp. for chimneys | |
| EP2787135A1 (en) | Concrete components and method for erecting the same | |
| AT307683B (en) | Component, in particular hollow molded brick, and components made from such components | |
| DE1276316B (en) | Prefabricated beams for covering openings in the masonry | |
| DE19949655A1 (en) | Concrete header beams for free-standing sheet pile retaining walls etc. is manufactured in one piece of long length by sliding shutter method | |
| DE9404911U1 (en) | Pillar-shaped concrete elements and device for their manufacture |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| OM8 | Search report available as to paragraph 43 lit. 1 sentence 1 patent law | ||
| 8127 | New person/name/address of the applicant |
Owner name: XELLA BAUSTOFFE GMBH, 47119 DUISBURG, DE |
|
| 8110 | Request for examination paragraph 44 | ||
| R016 | Response to examination communication | ||
| R002 | Refusal decision in examination/registration proceedings | ||
| R003 | Refusal decision now final |
Effective date: 20120414 |