CN211816452U - Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards - Google Patents
Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards Download PDFInfo
- Publication number
- CN211816452U CN211816452U CN201922237226.4U CN201922237226U CN211816452U CN 211816452 U CN211816452 U CN 211816452U CN 201922237226 U CN201922237226 U CN 201922237226U CN 211816452 U CN211816452 U CN 211816452U
- Authority
- CN
- China
- Prior art keywords
- foundation
- cover plate
- post
- backfill
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 239000002689 soil Substances 0.000 title claims abstract description 13
- 239000004567 concrete Substances 0.000 claims abstract description 41
- 238000010276 construction Methods 0.000 claims abstract description 29
- 238000005266 casting Methods 0.000 claims abstract description 28
- 238000007789 sealing Methods 0.000 claims description 8
- 230000002787 reinforcement Effects 0.000 claims description 2
- 238000000034 method Methods 0.000 description 12
- 239000010410 layer Substances 0.000 description 7
- 229910000831 Steel Inorganic materials 0.000 description 6
- 239000010959 steel Substances 0.000 description 6
- 239000011178 precast concrete Substances 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 description 2
- 230000001746 atrial effect Effects 0.000 description 2
- 239000012535 impurity Substances 0.000 description 2
- 239000004575 stone Substances 0.000 description 2
- 238000005056 compaction Methods 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 239000004744 fabric Substances 0.000 description 1
- 210000002837 heart atrium Anatomy 0.000 description 1
- 229910052742 iron Inorganic materials 0.000 description 1
- 230000014759 maintenance of location Effects 0.000 description 1
- 239000011376 self-consolidating concrete Substances 0.000 description 1
- 239000002356 single layer Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本实用新型涉及后浇带施工结构,具体为一种地下车库回填土基础后浇带先封闭后施工结构。解决车库地面施工中后浇带影响施工进度及工程质量的技术问题。包括地基基础,在地基基础上设有后浇带区,在后浇带区两侧设侧盖板,两个侧盖板之间通过对拉螺杆连接固定,在侧盖板之间设有钢筋网,在侧盖板上设有上盖板,上盖板上设有预留孔,预留孔内设有混凝土浇注管,在地基基础上设回填土层,所述的混凝土浇注管上管口设有挡板,所述的混凝土浇注管上管口高于回填土层。可有效解决提前进行地下室房心回填时基础后浇带封闭问题,保证后期后浇带施工质量,并且从总体上加快工程进度,同时可降低回填土施工及地下室结构施工难度。
The utility model relates to a post-pouring zone construction structure, in particular to a post-pouring zone of an underground garage backfilling foundation, which is closed first and then constructed. Solve the technical problem that the post-casting zone affects the construction progress and project quality in the garage ground construction. Including the foundation foundation, a post-casting belt area is arranged on the foundation foundation, and side cover plates are arranged on both sides of the post-casting belt area. There is an upper cover plate on the side cover plate, a reserved hole is arranged on the upper cover plate, a concrete pouring pipe is arranged in the reserved hole, and a backfill soil layer is arranged on the foundation, and the upper pipe of the concrete pouring pipe is arranged The mouth is provided with a baffle plate, and the upper mouth of the concrete pouring pipe is higher than the backfill soil layer. It can effectively solve the problem of closing the foundation post-cast zone when backfilling the basement in advance, ensure the construction quality of the post-cast zone in the later stage, and speed up the project progress as a whole, while reducing the difficulty of backfill construction and basement structure construction.
Description
技术领域technical field
本实用新型涉及后浇带施工结构,具体为一种地下车库回填土基础后浇带先封闭后施工结构。The utility model relates to a post-pouring zone construction structure, in particular to a post-pouring zone of an underground garage backfilling foundation, which is closed first and then constructed.
背景技术Background technique
近年来,结构设计时针对结构超长容易出现混凝土裂缝的质量通病,采用了设置后浇带的技术措施。而后浇带具有留设时间长,数量多、工序多、施工质量要求高的特点。In recent years, in the structural design, the technical measures of setting post-casting belts have been adopted in view of the common quality problem that the structure is too long and prone to concrete cracks. The post-casting belt has the characteristics of long retention time, large quantity, many processes and high construction quality requirements.
在地下车库的地面施工时,在通常情况下,基础沉降后浇带需在达到施工龄期之后方可进行浇筑。地下室房心回填需在基础后浇带施工完毕后方可进行,若需提前进行房心回填则需沿后浇带砌筑挡土墙,若采用挡土墙封堵后浇带,会极大增加回填土施工难度,同时工程进度也会造成延缓。地下车库的预留后浇带位于In the ground construction of the underground garage, under normal circumstances, the post-casting zone of the foundation settlement should be poured after the construction age is reached. The backfilling of the atrial heart of the basement can only be carried out after the construction of the foundation post-pouring zone. If the atrial heart backfill needs to be carried out in advance, a retaining wall must be built along the post-pouring zone. Backfill construction is difficult, and the progress of the project will also be delayed. The reserved post-pouring zone of the underground garage is located at
在现有技术中,公开了对于后浇带的一些处理技术。例如CN 209082573 U公开的一种沉降后浇带预先封闭构造。CN 209323574 U公开的提前封闭的地下室顶板沉降后浇带结构。都提出了使用盖板覆盖于后浇带上侧形成后浇带空间的思路。In the prior art, some processing techniques for post-cast strips are disclosed. For example, CN 209082573 U discloses a pre-closed structure for pouring after settling. CN 209323574 U discloses a pre-sealed basement roof settlement and post-casting belt structure. All have proposed the idea of using a cover plate to cover the upper side of the post-casting belt to form the space of the post-casting belt.
发明内容SUMMARY OF THE INVENTION
本实用新型为了解决车库地面施工中后浇带影响施工进度及工程质量的技术问题,提供了一种地下车库回填土基础后浇带先封闭后施工结构。In order to solve the technical problem that the post-pouring zone affects the construction progress and engineering quality during the ground construction of the garage, the utility model provides an underground garage backfill foundation post-pouring zone which is closed first and then constructed.
本实用新型的技术方案是,一种地下车库回填土基础后浇带先封闭后施工结构,包括地基基础,在地基基础上设有后浇带区,在后浇带区两侧设左侧盖板、右侧盖板,左侧盖板、右侧盖板之间通过对拉螺杆连接固定,在左侧盖板、右侧盖板之间设有钢筋网,在左侧盖板、右侧盖板上设有上盖板,上盖板上设有预留孔,预留孔内设有混凝土浇注管,在地基基础上设回填土层,所述的混凝土浇注管上管口设有挡板,所述的混凝土浇注管上管口高于回填土层。The technical scheme of the utility model is that a post-pouring zone of the backfill foundation of an underground garage is closed first and then constructed, including a foundation foundation, a post-pouring zone is arranged on the foundation foundation, and a left side cover is arranged on both sides of the post-pouring zone. plate, right cover, the left cover and right cover are connected and fixed by a pair of pull screws, there is a steel mesh between the left cover and the right cover, and the left cover and the right cover are The cover plate is provided with an upper cover plate, a reserved hole is arranged on the upper cover plate, a concrete pouring pipe is arranged in the reserved hole, a backfill soil layer is arranged on the foundation, and the upper nozzle of the concrete pouring pipe is provided with a stopper The upper nozzle of the concrete pouring pipe is higher than the backfill soil layer.
所述的上盖板上设有吊环。所述的预留孔之间间距不大于1米,直径不小于200mm。The upper cover plate is provided with a lifting ring. The spacing between the reserved holes is not more than 1 meter, and the diameter is not less than 200mm.
为了保证上盖板的强度,所述的上盖板宽度不大于1000mm,长度不大于1500mm,厚度不小于100mm。In order to ensure the strength of the upper cover plate, the width of the upper cover plate is not more than 1000mm, the length is not more than 1500mm, and the thickness is not less than 100mm.
所述的上盖板宽度大于后浇带区宽度,所述的上盖板两侧和地基基础表面接缝处设有斜坡形密封带,所述的混凝土浇注管和上盖板接缝处设有斜坡形密封带。可以防止回填土过程中杂质漏入后浇带中。The width of the upper cover plate is larger than the width of the post-casting zone, the two sides of the upper cover plate and the joints on the surface of the foundation are provided with slope-shaped sealing belts, and the joints between the concrete pouring pipe and the upper cover plate are provided. There is a slope-shaped sealing tape. It can prevent impurities from leaking into the post-casting zone during the backfilling process.
使用方法是,制作混凝预制盖板,在后浇带部位两侧设置侧盖板,侧盖板内侧混凝土面需凿毛处理,两侧的侧盖板之间通过对拉螺杆固定,在后浇带空间内设置钢筋网,上面设上盖板形成后浇带空间,在上盖板的孔内安装混凝土浇注管,然后在基础上进行回填土操作,回填到设计高度后,开始通过混凝土浇注管将混凝土灌进后浇带空间内,完成整个操作流程。The method of use is to make a concrete prefabricated cover plate, set side cover plates on both sides of the post-casting belt, and the inner side of the side cover plate needs to be chiseled. Reinforcement mesh is set in the pouring belt space, and the upper cover plate is placed on it to form the post-pouring belt space. Concrete pouring pipes are installed in the holes of the upper cover plate, and then the backfill operation is performed on the foundation. After backfilling to the design height, concrete pouring begins. The pipe pours the concrete into the post-pouring zone space to complete the entire operation process.
本实用新型所述的车库采用基础后浇带先封闭后施工结构,可有效解决提前进行地下室房心回填时基础后浇带封闭问题,保证后期后浇带施工质量,并且从总体上加快工程进度,同时可降低回填土施工及地下室结构施工难度。The garage of the utility model adopts the structure of first sealing the foundation post-casting belt and then constructing it, which can effectively solve the problem of closing the foundation post-casting belt when the basement atrium is backfilled in advance, ensure the construction quality of the post-casting belt in the later stage, and accelerate the progress of the project as a whole. At the same time, it can reduce the difficulty of backfill construction and basement structure construction.
附图说明Description of drawings
图1为本实用新型结构示意图Fig. 1 is the structural representation of the utility model
图2为上盖板结构示意图Figure 2 is a schematic diagram of the structure of the upper cover
图中:1-左侧盖板、2-对拉螺杆、3-钢筋网、4-挡板、5-混凝土浇注管、6-上盖板、7-右侧盖板、8-回填土层、9-地基基础、10-后浇带区、11-吊环、12-预留孔。In the picture: 1- left cover plate, 2- pair of pull screws, 3- steel mesh, 4- baffle plate, 5- concrete pouring pipe, 6- upper cover plate, 7- right cover plate, 8- backfill soil layer , 9- foundation foundation, 10- post-casting zone, 11- lifting ring, 12- reserved hole.
具体实施方式Detailed ways
如图1所示意,一种地下车库回填土基础后浇带先封闭后施工结构,包括地基基础9,在地基基础9内设有后浇带区10,在后浇带区10两侧设左侧盖板1、右侧盖板7,左侧盖板1、右侧盖板7之间通过对拉螺杆2连接固定,在左侧盖板1、右侧盖板7之间设有钢筋网3,在左侧盖板1、右侧盖板7上设有上盖板6,上盖板6上设有预留孔12,预留孔12内设有混凝土浇注管5,在地基基础9上设回填土层8,所述的混凝土浇注管5上管口设有挡板4,所述的混凝土浇注管5上管口高于回填土层8。As shown in FIG. 1 , a post-pouring zone of an underground garage backfill foundation is closed first and then constructed, including a
如图2所示意,所述的上盖板6上设有吊环11。所述的预留孔12之间间距不大于1米,直径不小于200mm。As shown in FIG. 2 , the upper cover plate 6 is provided with a
为了保证上盖板的强度,所述的上盖板6宽度不大于1000mm,长度不大于1500mm,厚度不小于100mm。In order to ensure the strength of the upper cover plate, the width of the upper cover plate 6 is not more than 1000mm, the length is not more than 1500mm, and the thickness is not less than 100mm.
所述的上盖板6宽度大于后浇带区10宽度,所述的上盖板6两侧和地基基础表面接缝处设有斜坡形密封带,所述的混凝土浇注管5和上盖板6接缝处设有斜坡形密封带。可以防止回填土过程中土壤等杂质漏入后浇带中。The width of the upper cover plate 6 is greater than the width of the
混凝土浇注管5上管口高于回填土层8距离不小于300mm。The distance between the upper nozzle of the
具体施工工艺specific construction process
预制混凝土盖板分带孔板与不带孔板两种。带孔预制混凝土盖板分为板中留孔及板边缘留孔,不带孔预制板除中间无预留圆洞外,其余均与带孔预制板相同。There are two kinds of precast concrete cover plate with perforated plate and without perforated plate. The precast concrete cover plate with holes is divided into holes in the plate and holes at the edge of the plate. The prefabricated plate without holes is the same as the prefabricated plate with holes except that there is no reserved round hole in the middle.
预制混凝土盖板宽度根据后浇带宽度确定,一般比后浇带宽度大200mm;长度根据施工图纸及现场实际情况确定,不宜超过1500mm,以方便人工可靠安装,厚度为100mm。盖板内配单层双向钢筋网片φ10@150,自拌c20细石混凝土浇筑。The width of the precast concrete cover plate is determined according to the width of the post-casting belt, which is generally 200mm larger than the width of the post-casting belt; the length is determined according to the construction drawings and the actual situation on site, and should not exceed 1500mm to facilitate manual and reliable installation, and the thickness is 100mm. The cover plate is equipped with a single-layer two-way steel mesh φ10@150, and it is poured with self-mixing c20 fine stone concrete.
预制混凝土盖板上表面宜设置2个φ12吊环,方便吊装。基础梁测及外墙侧面预制盖板需留置对拉螺杆眼,以便固定。预制盖板上留置直径200mm圆洞(尺寸可根据实际情况调节)作为下料管安装位置,留置间距不宜大于1m,以便于后续混凝土浇注过程中,混凝土充盈度。Two φ12 rings should be set on the surface of the precast concrete cover to facilitate hoisting. The foundation beams and the prefabricated cover plates on the side of the outer wall shall be left with the eyelets of the pulling screws for fixing. A circular hole with a diameter of 200mm (the size can be adjusted according to the actual situation) is reserved on the prefabricated cover plate as the installation position of the feeding pipe.
后浇带内密封网需剔除,混凝土面需凿毛处理,后浇带内部混凝土块等杂物需清理干净。调整后浇带内钢筋网,需顺直、规矩,满扣绑扎。调整完毕后进行隐蔽验收,合格后方可安装盖板。The sealing net in the post-casting belt needs to be removed, the concrete surface needs to be chiseled, and the sundries such as concrete blocks inside the post-casting belt need to be cleaned up. After adjustment, the steel mesh in the pouring belt should be straight, regular, and fully buckled. After the adjustment is completed, the concealed acceptance is carried out, and the cover plate can be installed only after passing the test.
预制的上盖板采用塔吊调运人工配合安装的方式铺设,因主楼周边基础结构复杂,铺设顺序需严格按照布置图所示位置进行铺设。铺设完毕后沿盖板边缘间距1m钻孔留置定位钢筋,以防回填土过程中盖板位置偏移。The prefabricated upper cover is laid by tower crane, transportation and manual installation. Due to the complex infrastructure around the main building, the laying sequence must be laid in strict accordance with the position shown in the layout drawing. After laying, drill holes for positioning steel bars at a distance of 1m along the edge of the cover plate to prevent the position of the cover plate from shifting during the backfilling process.
预制盖板铺设完毕后,沿盖板根部需做八字脚(R≥50mm),同时盖板表面接缝处需抹灰塞实,防止回填土过程中土流入后浇带内。After the prefabricated cover is laid, splayed feet (R≥50mm) should be made along the root of the cover, and the joints on the surface of the cover should be plastered and plugged to prevent soil from flowing into the post-pouring zone during the backfilling process.
预制盖板铺设完毕后进行下料的混凝土浇注管道的安装,管道上口需高出回填土设计标高面不小于300mm,预先按设计标高切出相应长度的薄壁铁管,插入预留洞口内,调整管道垂直度后,根部需抹八字脚(R≥100mm)固定,同时管道上口需进行封闭,使用多层板制作扣盖将上口盖住,防止回填土过程中土方进入后浇带内。After the prefabricated cover plate is laid, the concrete pouring pipeline shall be installed. The upper opening of the pipeline shall be no less than 300mm above the design elevation of the backfill. Cut out the corresponding length of thin-walled iron pipe in advance according to the design elevation and insert it into the reserved hole. , After adjusting the verticality of the pipeline, the root should be fixed with splayed feet (R≥100mm), and the upper opening of the pipeline should be closed, and the upper opening should be covered with a multi-layer board to make a buckle cover to prevent the earthwork from entering the post-pouring zone during the backfilling process. Inside.
回填土施工,预制的混凝土下料管之间以及混凝土下料管另一方向2m以内应采用人工回填,不可对预制管造成扰动;本年在回填土完成后需对回填土进行一次压实,待次年温度回升之后需对回填土进行二次压实,回填土压实系数≥0.93。For backfill construction, manual backfill should be used between the prefabricated concrete feed pipes and within 2m from the other direction of the concrete feed pipes, and the prefabricated pipes should not be disturbed; After the temperature rises in the next year, the backfill needs to be compacted twice, and the compaction coefficient of the backfill is ≥0.93.
后浇带混凝土浇筑采用“自由下落法”进行浇筑。后浇带浇筑时,混凝土塌落度需适当增大,有利于混凝土在后浇带内部的流动,增强密实度,或使用自密实混凝土浇筑。后浇带浇筑时,从后浇带两侧向中央连续浇筑。用振动棒从浇筑口辅助振捣,促进混凝土的流动与铺摊。一般要往复浇筑,同时用卷尺从浇筑口实量混凝土到管口的距离,根据预埋管的长度计算混凝土浇筑高度。保证每个间隔下料孔洞中最终浇筑高度至地下车库地面完成面下100mm,确保后浇带部位的混凝土密实度。混凝土养护,浇筑完成,在混凝土完成12h内对混凝土浇筑管内注水,并应对浇筑口采用塑料布临时封闭养护。The post-poured strip concrete is poured by the "free-fall method". When the post-casting belt is poured, the slump of the concrete needs to be appropriately increased, which is conducive to the flow of the concrete inside the post-casting belt and enhances the compactness, or uses self-compacting concrete for pouring. When pouring the post-casting belt, pour continuously from both sides of the post-casting belt to the center. The vibrating rod is used to assist the vibrating from the pouring port to promote the flow and spreading of the concrete. Generally, reciprocating pouring is required, and at the same time, the distance from the pouring port to the nozzle is measured with a tape measure, and the concrete pouring height is calculated according to the length of the embedded pipe. Ensure that the final pouring height in each interval blanking hole is 100mm below the completion surface of the underground garage floor, and ensure the concrete density of the post-pouring zone. Concrete curing, pouring is completed, pour water into the concrete pouring pipe within 12 hours after the completion of the concrete, and the pouring port should be temporarily closed with plastic cloth for curing.
浇筑口封闭,后浇带浇筑完成后,将浇筑管道内混凝土面以上管道剔除,周边混凝土面凿毛处理,用c20细石混凝土将凹坑浇筑至地面平,接茬处收面平整。The pouring port is closed. After the post-pouring belt is poured, the pipes above the concrete surface in the pouring pipeline are removed, and the surrounding concrete surface is chiseled. C20 fine stone concrete is used to pour the pit to the ground level, and the stubble end surface is flat.
经济效益:回填土单价预计降低2元/m³,4900m³*2元/m³=9800元,Economic benefits: The unit price of backfill is expected to decrease by 2 yuan/m³, 4900m³*2 yuan/m³=9800 yuan,
地面垫层单价预计降低1元/㎡,6393㎡*1元/㎡=6393元,减少地下室结构冬季施工费用约10万元,社会效益:通过本工程地下车库回填土施工的尝试,缩短施工工期15天,为以后工程后浇带的做法提供了成功的范例,可供参考和鉴借。The unit price of the ground cushion is expected to be reduced by 1 yuan/㎡, 6393㎡*1 yuan/㎡=6393 yuan, and the winter construction cost of the basement structure will be reduced by about 100,000 yuan. Social benefits: Through the trial of backfilling the underground garage of this project, the construction period will be shortened For 15 days, it provides a successful example for the practice of post-casting in the future project, which can be used for reference and reference.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922237226.4U CN211816452U (en) | 2019-12-13 | 2019-12-13 | Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201922237226.4U CN211816452U (en) | 2019-12-13 | 2019-12-13 | Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN211816452U true CN211816452U (en) | 2020-10-30 |
Family
ID=73140891
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201922237226.4U Expired - Fee Related CN211816452U (en) | 2019-12-13 | 2019-12-13 | Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN211816452U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117684571A (en) * | 2024-01-30 | 2024-03-12 | 郑州一建集团有限公司 | A kind of advanced backfilling construction method for foundation beam post-cast belt and post-cast belt vibration device |
-
2019
- 2019-12-13 CN CN201922237226.4U patent/CN211816452U/en not_active Expired - Fee Related
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117684571A (en) * | 2024-01-30 | 2024-03-12 | 郑州一建集团有限公司 | A kind of advanced backfilling construction method for foundation beam post-cast belt and post-cast belt vibration device |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104018673B (en) | Ultra-large volume concrete one-time continuous pours into a mould multi cycle real-time temperature control construction technology | |
| CN100585094C (en) | Construction method of circular deep foundation pit support | |
| CN102587416B (en) | Construction method of basement attached lane structure | |
| CN209837281U (en) | Basement outer wall and bottom plate corner waterproof node | |
| CN206844275U (en) | Mutual buckle type precast concrete cover ditch and its suspender | |
| CN114215114A (en) | A kind of construction structure and construction method of water dispersing around cantilever plate | |
| CN218148527U (en) | Subside post-cast strip structure sealed in advance | |
| CN115387393A (en) | Quick construction method of post-pouring belt pre-sealing | |
| CN208023601U (en) | A kind of prefabricated pile foundation support table side form of mutual buckle type | |
| CN217949734U (en) | Formwork support system serving as single side and top plate of outer wall | |
| CN113565143A (en) | Basement roof settlement post-cast strip construction method | |
| CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
| CN111456104A (en) | Outer wall post-cast strip advanced sealing and finalizing combined type prefabricated cover plate | |
| CN211816452U (en) | Underground garage backfill soil foundation post-cast strip seals earlier and constructs structure afterwards | |
| CN217710835U (en) | Upward inclined retaining wall with prefabricated drainage reverse filtering structure | |
| CN209429046U (en) | Gravity dam transverse joint drainage channel structure | |
| CN216787229U (en) | Basement outer wall post-cast strip assembled shutoff steel sheet structure | |
| CN115199041A (en) | A construction method for inserting a basement roof in advance | |
| CN202899153U (en) | Oblique column type anti-corrosion foundation device for power transmission line of salt-lake region | |
| CN213979066U (en) | A kind of counterweight anti-floating and hydrophobic ground | |
| CN110004787A (en) | Pier storage yard road concrete surface construction method | |
| CN206279561U (en) | A kind of poured band of outer wall of basement prefab-form system | |
| CN105544832B (en) | Shell roof and construction method thereof | |
| CN109235439B (en) | A pressure-maintaining pouring method for outsourcing large-volume concrete below the waistline of a volute of a hydropower project | |
| CN204676607U (en) | Poured band of outer wall of basement plugging structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20201030 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |