CN2177925Y - High-temp. pot-string type waste steel preheating device - Google Patents

High-temp. pot-string type waste steel preheating device Download PDF

Info

Publication number
CN2177925Y
CN2177925Y CN 93246990 CN93246990U CN2177925Y CN 2177925 Y CN2177925 Y CN 2177925Y CN 93246990 CN93246990 CN 93246990 CN 93246990 U CN93246990 U CN 93246990U CN 2177925 Y CN2177925 Y CN 2177925Y
Authority
CN
China
Prior art keywords
batch
preheating
electric arc
flue gas
string type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 93246990
Other languages
Chinese (zh)
Inventor
常来吉
耿学溥
尹启新
赵明义
张小成
张占元
何顺庄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shijiazhuang Valve Factory No1
Original Assignee
Shijiazhuang Valve Factory No1
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shijiazhuang Valve Factory No1 filed Critical Shijiazhuang Valve Factory No1
Priority to CN 93246990 priority Critical patent/CN2177925Y/en
Application granted granted Critical
Publication of CN2177925Y publication Critical patent/CN2177925Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Furnace Details (AREA)
  • Waste-Gas Treatment And Other Accessory Devices For Furnaces (AREA)
  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The utility model relates to a high-temperature pot-string type waste steel preheating device, which is composed of an electric arc furnace, material preheating pipes, and a connecting pipe. The utility model is characterized in that more than two material preheating pipes are arranged, and each material preheating pipe is connected in series; the inlet of the first material preheating pipe is connected with the high temperature smoke outlet of the electric arc furnace, and the smoke outlet of the last material preheating pipe is connected with a deduster. The utility model has the advantages that the power consumption of steel producing is greatly reduced, the consumption of electrodes and fireproof materials are both decreased, power efficiency is enhanced, and the producing time is shortened by about eight percent.

Description

High-temp. pot-string type waste steel preheating device
The utility model relates to a kind of high temperature pot-string type preheating scrap device.Be used to recycle the heat energy of the high-temperature flue gas that electrical arc furnace discharges, reach the energy-conservation purpose of electric furnace steel making.
" the NKK scrap preheater " of NKK's development is made up of electric arc furnaces, water-cooled combustion chamber, preheating chamber, batch can, circulating fan and connecting pipeline.The flue gas that produces by electric furnace steel making, earlier behind the water-cooled combustion chamber, enter preheating chamber again and in preheating chamber the steel scrap in the batch can carry out heat exchange, it belongs to the low-temperature prewarming device of pre-heat utilization after the first cooled flue gas.First jar of material of its first preheating, charging again after hanging away or drawing off, second jar of material of preheating afterwards belongs to the interruption preheating.Because it belongs to the low-temperature prewarming device, the flue gas mean temperature that is utilized is 325-400 ℃, so very unfavorable to the heat energy that reclaims flue gas.
The high temperature preheating steel scrap device of Germany Krupp industrial technology company development, it is made up of electric furnace, combustion chamber, preheating chamber, batch can, heat exchanger, air exhauster and connecting pipeline etc.The flue gas that is produced by electric furnace steel making directly enters the combustion chamber, after fully burning in the combustion chamber, directly enter preheating chamber again and remove to heat steel scrap in the batch can, then through heat exchanger and air exhauster to deduster.This preheating device also belongs to the interruption preheating.It is earlier pre-heat utilization, and back cooled flue gas claims high temperature preheating, and it is heated to about 550 ℃ with steel scrap, and can reclaim the waste gas sensible heat as far as possible.
In above-mentioned two kinds of scrap preheaters, second kind flue gas heat energy recovery rate obviously is higher than first kind, but still has its weak point: the first, the rate of recovery still can improve 5-10%; The second, the high temperature of high-temperature flue gas still has 50-100 ℃ to fail to utilize; Three, discharge flue-gas temperature from preheating chamber and still have 400-700 ℃ to fail to utilize, the way that its adopts heat exchanger and sneaks into cold air reduces exhaust temperature.
The purpose of this utility model is at above-mentioned shortcoming of the prior art, and a kind of high temperature pot-string type preheating scrap device is provided.
The purpose of this utility model is achieved in that
A kind of high temperature pot-string type preheating scrap device of forming by electric arc furnaces, preheating batch can and connecting pipeline, its design feature is that the preheating batch can is more than 2, and each preheating batch can is a coupled in series, the inlet of first preheating batch can connects the high-temperature flue gas outlet of electric arc furnaces, and the exhanst gas outlet of last preheating batch can connects dust arrester.
Another embodiment of the present utility model is on the basis of such scheme, sets up the combustion chamber between electric arc furnaces and first preheating batch can.
Below in conjunction with drawings and Examples the utility model is further described:
Fig. 1 is a front view of the present utility model.
Fig. 2 is the vertical view of Fig. 1.
Fig. 3 is the left view of Fig. 1.
By as can be known embodiment illustrated in fig. 1, it is made up of electric furnace 1, preheating batch can 3, connecting pipeline, connecting gear, jacking mechanism, detent mechanism etc., the preheating batch can is composed in series by 4, the inlet of first preheating batch can connects the high-temperature flue gas outlet of electric arc furnaces, and the exhanst gas outlet of last preheating batch can connects dust arrester.
Preheating batch can 3 is made up of petticoat pipe in the activity 6, batch can main body and movable petticoat pipe 15 down.Connecting gear is made up of batch can car 9, top-pushing mechanism 10, guide rail 19 and support frame 12.Jacking mechanism is positioned at the below of each preheating batch can, sits with the 15 joining movable flue gas tube connectors 20 of petticoat pipe under the activity of each preheating batch can be contained on the jacking mechanism, and jacking mechanism is made up of jack-up oil cylinder 14, platform 21 and guide rail 22.Detent mechanism 11 is contained on the support frame 12, it be positioned at each preheating batch can and the corresponding position of batch can car on, detent mechanism is made up of oil cylinder 23 and the triangle channel 24 that is positioned on the batch can car.Among the figure, 2 is the water-cooled bend pipe, and 4 is No. 1 high-temperature valve, and 5 is No. 4 high-temperature valves, and 7 is No. 2 high-temperature valves, and 8 is that No. 3 valves, 13 are unloading valve, and 16 for keeping off a car mechanism, and 17 is movable transfer box, and 18 is movable smoke pipe.
The operating instruction of this high temperature pot-string type preheating scrap device:
1, generally adorns two jars of material by smelting one heat steel.
2, install the batch can of steel scrap, move to No. 3, No. 2, No. 1 jar position successively from No. 4 jar positions.
3, high-temperature flue gas (high temperature 1000-1250 ℃, low temperature 700-800 ℃, Continuous Flow is crossed from low to high) at first enters the jar position No. 1, is 2,3,4 jars successively, and the flue gas of extracting out from No. 4 jars is sent to deduster.
4, to the requirement of process equipment, pipeline:
(1) No. 4 jar and before equipment, conduit enclosure temperature≤50 ℃.
(2) each connecting link is wanted strict good seal, stand 600-700mmH 2The suction of O post.
(3) 40 tons and above high power electric furnace are established 4 batch can continuously pre-heatings, and 30 tons to 10 tons electric furnaces are established 3 batch cans, because of in the flue-gas temperature of electric rangette low.
The utility model preheating technology process conditions are as follows:
1, enters the preheating chamber flue-gas temperature of (referring to batch can): heat of oxidation melting stage
600℃-1250℃
2, connect preheating batch can number simultaneously: the 1st jar of material: go into 1200 ℃-1250 ℃
Go out 900 ℃
The 2nd jar of material: go into 900 ℃
Go out 600 ℃
The 3rd jar of material: go into 600 ℃
Go out 350 ℃
The 4th jar of material: go into 350 ℃
Go out 150 ℃
3, enter the exhaust gas volumn of preheating chamber: 70-75% is arranged approximately
4, reclaim the sensible heat amount of flue gas: 65-75% is arranged approximately
Economic benefit of the present utility model:
Figure 932469906_IMG2
The utility model has the advantages that and to recycle fully the 65-75% that flue gas in the EAF Steelmaking Process is taken away heat energy, and by in the hot scrap steel band freshening steel electric furnace, the steel-making power consumption is reduced, reduce simultaneously electrode and refractory consumption rate, improve the thermal efficiency and shorten the heat about 8%. Electric furnace flue gas is taken away in the 10-20% situation that heat energy accounts for overall balance heat energy, and corresponding to save electric energy be 40-105kwh/t, saves electrode 0.3-0.8kg/t. This device has been broken through flue gas and has been taken away heat energy and be lower than 15% conclusion that just is unworthy reclaiming preheating scrap. Low, the remarkable in economical benefits of this device operating cost.

Claims (6)

1, a kind of high temperature pot-string type preheating scrap device of forming by electric arc furnaces, preheating batch can and connecting pipeline, it is characterized in that the preheating batch can is more than 2, and each preheating batch can is for being connected in series, the inlet of first preheating batch can connects the high-temperature flue gas outlet of electric arc furnaces, and the exhanst gas outlet of last preheating batch can connects dust arrester.
2, device according to claim 1 is characterized in that between electric arc furnaces and first preheating batch can the combustion chamber being housed.
3, device according to claim 1 and 2 is characterized in that the preheating batch can plays petticoat pipe to form by petticoat pipe, batch can main body, activity in the activity.
4, device according to claim 3 is characterized in that it is provided with connecting gear, and connecting gear is made up of batch can car, top-pushing mechanism, guide rail and support frame.
5, device according to claim 3, it is characterized in that with each preheating batch can activity under the joining movable flue gas tube connector of petticoat pipe sit and be contained on the jacking mechanism, jacking mechanism is made up of jack-up oil cylinder, platform and guide rail.
6, device according to claim 5 is characterized in that being provided with detent mechanism on the support frame with on each preheating batch can and the corresponding position of batch can car, and detent mechanism is made up of oil cylinder and the triangle channel that is positioned on the batch can car.
CN 93246990 1993-12-09 1993-12-09 High-temp. pot-string type waste steel preheating device Expired - Fee Related CN2177925Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 93246990 CN2177925Y (en) 1993-12-09 1993-12-09 High-temp. pot-string type waste steel preheating device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 93246990 CN2177925Y (en) 1993-12-09 1993-12-09 High-temp. pot-string type waste steel preheating device

Publications (1)

Publication Number Publication Date
CN2177925Y true CN2177925Y (en) 1994-09-21

Family

ID=33819509

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 93246990 Expired - Fee Related CN2177925Y (en) 1993-12-09 1993-12-09 High-temp. pot-string type waste steel preheating device

Country Status (1)

Country Link
CN (1) CN2177925Y (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1102662C (en) * 1997-11-27 2003-03-05 Sms舒路曼-斯玛公司 Apparatus and process system for preheating of steel scrap for melting metallurgical furnaces with concurrent flow of scrap and heating gases
CN103822489A (en) * 2014-03-21 2014-05-28 张昌剑 Waste-steel continuous preheating method and waste-steel continuous preheating device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1102662C (en) * 1997-11-27 2003-03-05 Sms舒路曼-斯玛公司 Apparatus and process system for preheating of steel scrap for melting metallurgical furnaces with concurrent flow of scrap and heating gases
CN103822489A (en) * 2014-03-21 2014-05-28 张昌剑 Waste-steel continuous preheating method and waste-steel continuous preheating device
CN103822489B (en) * 2014-03-21 2015-07-01 张昌剑 Waste-steel continuous preheating method and waste-steel continuous preheating device

Similar Documents

Publication Publication Date Title
CN2697565Y (en) Horizontal continuous waste steel feeding preheater for arc furnace steel making
CN2177925Y (en) High-temp. pot-string type waste steel preheating device
CN103352128A (en) Direct zinc-coal mixing cyclone burning type zinc oxide production system
CN106679402A (en) Energy-saving environment-friendly efficient hot blast cupola
CN205382195U (en) Low -grade reviver smelting slag fuming furnace processing system
CN201199127Y (en) Waste heat boiler integrated fuming furnace
CN2256085Y (en) Coal-fired hot-air furnace
CN220230106U (en) Waste heat recycling device of oxygen-enriched smelting furnace
CN117029373A (en) High Wen Zhaliao cooling and heat energy recycling method and device
WO2020151771A1 (en) Energy-saving, environmentally friendly recycled lead multi-chamber metal smelting furnace and processing method
CN201852070U (en) Flue type shell-and-tube heat exchanger of waste heat boiler
CN101713032A (en) Method for preparing magnesium metal by multi-layer energy-saving reducing furnace
CN216432464U (en) Re-smoke smelting equipment for nickel-containing scrap
CN210765454U (en) Regenerative lead multi-chamber smelting heat accumulating type energy-saving furnace device
KR20040056270A (en) A hybrid steelmaking apparatus and method
CN200968776Y (en) Multifunctional industry furnace
CN103017523A (en) Oxygen-rich side-blown smelting reduction furnace and lead-rich material lead smelting method
CN114608312A (en) Method for preheating secondary air of rotary kiln by utilizing high-temperature flue gas of submerged arc furnace
CN1031206C (en) Method and equipment for integrated direct flow type continuous iron-smelting
CN208869612U (en) A device for reducing and treating scrap steel
CN222718640U (en) Smelting system of water-cooled secondary lead multi-chamber smelting furnace
CN2711660Y (en) Hot air cupola
CN219083761U (en) A scrap steel preheating horizontal feeding conveying equipment
CN1073212A (en) Integral downstream continuous ironmaking and steelmaking method and equipment
CN1052334A (en) The hot air smelting method of lead blast furnace and wind jacket in furnace thereof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee