A kind of detachable support for building engineering construction Download PDFInfo
- Publication number
- CN216238566U CN216238566U CN202122854076.9U CN202122854076U CN216238566U CN 216238566 U CN216238566 U CN 216238566U CN 202122854076 U CN202122854076 U CN 202122854076U CN 216238566 U CN216238566 U CN 216238566U
- Authority
- CN
- China
- Prior art keywords
- plate
- support
- baffle
- frame
- fixedly connected
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 title claims abstract description 17
- 238000003780 insertion Methods 0.000 claims description 7
- 230000037431 insertion Effects 0.000 claims description 7
- 238000009435 building construction Methods 0.000 claims 4
- 230000008093 supporting effect Effects 0.000 abstract description 14
- 238000010586 diagram Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 3
- 229910000831 Steel Inorganic materials 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 239000010959 steel Substances 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
- 239000002689 soil Substances 0.000 description 1
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
Description
技术领域technical field
本实用新型涉及可拆卸式支护技术领域,尤其涉及一种建筑工程施工用可拆卸式支护。The utility model relates to the technical field of detachable supports, in particular to a detachable support for building engineering construction.
背景技术Background technique
在进行建筑工程施工的时候,通常需要挖掘基坑,当基坑挖掘深度太深的时候就需要通过支护来对基坑的侧壁及周边进行支撑加固。In the construction of construction projects, it is usually necessary to excavate the foundation pit. When the excavation depth of the foundation pit is too deep, it is necessary to support and reinforce the side wall and the periphery of the foundation pit through support.
普通情况下,在对基坑进行加固的时候通常是使用螺丝或钉子来将钢板与钢杆对基坑的侧面进行加固,由于是使用螺丝或钉子进行加固,从而在拆卸的时候变得非常不便,需要消耗大量的拆卸时间。Under normal circumstances, when reinforcing the foundation pit, screws or nails are usually used to reinforce the side of the foundation pit with steel plates and steel rods. Because screws or nails are used for reinforcement, it becomes very inconvenient to disassemble. , need to consume a lot of disassembly time.
实用新型内容Utility model content
本实用新型的目的是为了解决现有技术中存在拆卸的时候非常不便,需要消耗大量的拆卸时间的缺点,而提出的一种建筑工程施工用可拆卸式支护。The purpose of the utility model is to solve the disadvantage of the prior art that it is very inconvenient to disassemble and needs to consume a lot of disassembly time, and proposes a detachable support for building engineering construction.
为了实现上述目的,本实用新型采用了如下技术方案:一种建筑工程施工用可拆卸式支护,包括挡板和拆卸结构,所述挡板的表面设置有拆卸结构,所述拆卸结构包括底板,所述底板与挡板的表面转动连接,所述底板的表面固定连接有转动架,所述转动架的表面转动连接有第一支撑板,所述第一支撑板的表面转动连接有第二支撑板,所述挡板的表面焊接有支撑框,通过使底板与挡板转动至垂直状态,接着转动第一支撑板与第二支撑板,使第一支撑板与第二支撑板展开,再使第二支撑板插入支撑框中,对挡板进行支撑。In order to achieve the above purpose, the utility model adopts the following technical scheme: a detachable support for building engineering construction, including a baffle plate and a disassembly structure, the surface of the baffle plate is provided with a disassembly structure, and the disassembly structure includes a bottom plate , the bottom plate is rotatably connected with the surface of the baffle plate, the surface of the bottom plate is fixedly connected with a turret, the surface of the turret is rotatably connected with a first support plate, and the surface of the first support plate is rotatably connected with a second The support plate, the surface of the baffle is welded with a support frame, by rotating the bottom plate and the baffle to a vertical state, then rotating the first support plate and the second support plate, so that the first support plate and the second support plate are unfolded, and then Insert the second support plate into the support frame to support the baffle.
优选的,所述第一支撑板的表面滑动连接有固定框,所述底板的内壁滑动连接有固定桩,使固定框移动到第一支撑板与第二支撑板的连接处,就可以通过固定框来防止第一支撑板与第二支撑板对折,而导致其失去支撑作用,将固定桩插入泥土中可以进行固定。Preferably, a fixing frame is slidably connected to the surface of the first support plate, and a fixing pile is slidably connected to the inner wall of the bottom plate, so that the fixing frame is moved to the connection between the first support plate and the second support plate, and the fixing The frame is used to prevent the first support plate and the second support plate from being folded in half, causing them to lose their supporting function, and can be fixed by inserting the fixing pile into the soil.
优选的,所述第二支撑板的表面焊接有方板,所述方板的表面固定连接有滑框,所述滑框的内壁滑动连接有拉钩,推动固定框,使固定框移动到第一支撑板与第二支撑板的连接处,接着使拉钩靠近固定框,让拉钩插入固定框中,从而将固定框固定住。Preferably, a square plate is welded on the surface of the second support plate, a sliding frame is fixedly connected to the surface of the square plate, and a pull hook is slidably connected to the inner wall of the sliding frame, and the fixed frame is pushed to move the fixed frame to the first At the connection between the support plate and the second support plate, the draw hook is then brought close to the fixing frame, and the draw hook is inserted into the fixing frame, so as to fix the fixing frame.
优选的,所述方板的表面焊接有抵板,所述抵板与拉钩之间固定连接有第一弹簧,可以通过第一弹簧的弹性来推动拉钩远离抵板,从而推动拉钩插入固定框中。Preferably, an abutment plate is welded on the surface of the square plate, a first spring is fixedly connected between the abutment plate and the hook, and the hook can be pushed away from the abutment plate by the elasticity of the first spring, thereby pushing the hook into the fixing frame .
优选的,所述挡板的表面设置有调节结构,所述调节结构包括加长板,所述加长板与挡板的内壁滑动连接,所述加长板的数量为两个,两个所述加长板分别位于挡板的两侧,所述加长板的表面固定连接有把手,通过把手可以将加长板拉出挡板的内部,从而增加支撑面积。Preferably, the surface of the baffle is provided with an adjustment structure, the adjustment structure includes an extension plate, the extension plate is slidably connected to the inner wall of the baffle, the number of the extension plates is two, and the two extension plates They are located on both sides of the baffle, respectively, and handles are fixedly connected to the surface of the elongated plate, and the elongated plate can be pulled out of the baffle through the handle, thereby increasing the supporting area.
优选的,所述挡板的表面固定连接有支撑架,所述支撑架的表面固定连接有伸缩杆,所述伸缩杆远离支撑架的一端固定连接有插块,所述插块与支撑架之间固定连接有第二弹簧,在使加长板移动时,加长板的表面会与插块上倾斜的表面接触,进而推动插块向着支撑架的方向移动,就可以通过第二弹簧来使插块抵在加长板的表面,继续移动加长板,插块会通过第二弹簧插入加长板的内部,就可以对加长板进行固定。Preferably, a support frame is fixedly connected to the surface of the baffle, a telescopic rod is fixedly connected to the surface of the support frame, and an end of the telescopic rod away from the support frame is fixedly connected with an insert block, and the insert block and the support frame are fixedly connected. A second spring is fixedly connected between them. When the extension board is moved, the surface of the extension board will contact the inclined surface of the insert block, and then push the insert block to move in the direction of the support frame, so that the insert block can be moved by the second spring. Abut on the surface of the extension board, continue to move the extension board, the insert block will be inserted into the interior of the extension board through the second spring, and the extension board can be fixed.
优选的,所述挡板的表面固定连接有固定块,所述固定块的内壁插设有插杆,所述挡板的表面转动连接有固定杆,通过使插杆向上移动,从而解除对固定杆的固定。Preferably, a fixing block is fixedly connected to the surface of the baffle, an insertion rod is inserted into the inner wall of the fixing block, and a fixing rod is rotatably connected to the surface of the baffle. Fixing of the rod.
与现有技术相比,本实用新型的优点和积极效果在于:Compared with the prior art, the advantages and positive effects of the present utility model are:
1、本实用新型中,在需要安装的时候,转动底板,使底板与挡板呈垂直状态,再将固定桩插入土地中,接着展开第一支撑板与第二支撑板,使第二支撑板插入支撑框中,然后使拉钩向着靠近抵板的方向移动,再使固定框顺着第一支撑板向着第二支撑板的方向移动,使固定框移动到第一支撑板与第二支撑板的连接处,这时松开拉钩,由于第一弹簧此时处于压缩状态,可以通过第一弹簧推动拉钩远离抵板,使拉钩插入固定框中,就可以将固定框固定住,防止固定框滑下来,通过固定框可以防止第一支撑板与第二支撑板对折,而失去支撑效果,当需要拆卸时反向操作上述步骤,就可以对其进行拆卸,通过设置拆卸结构可以方便快捷的进行拆卸,从而减少施工时间。1. In the present utility model, when it is necessary to install, the bottom plate is rotated to make the bottom plate and the baffle plate in a vertical state, and then the fixed pile is inserted into the ground, and then the first support plate and the second support plate are unfolded to make the second support plate. Insert the support frame, then move the draw hook toward the direction close to the contact plate, and then move the fixed frame along the first support plate to the direction of the second support plate, so that the fixed frame moves to the position between the first support plate and the second support plate. At the connection, release the hook at this time. Since the first spring is in a compressed state at this time, the first spring can push the hook away from the contact plate, so that the hook is inserted into the fixing frame, the fixing frame can be fixed, and the fixing frame can be prevented from sliding down. , through the fixing frame, the first support plate and the second support plate can be prevented from being folded in half, and the supporting effect is lost. When it needs to be disassembled, the above steps can be reversed to disassemble it, and it can be disassembled conveniently and quickly by setting the disassembly structure. Thereby reducing construction time.
2、本实用新型中,在对基坑的侧壁进行支撑的时候,仅仅通过一个挡板所能支撑的面积有限,导致在对基坑的侧壁进行支撑的时候需要安装大量的支护,因此在安装的时候可以使插杆向上移动,就可以解除对固定杆的固定,然后使固定杆向着远离挡板的方向转动,就可以取消对加长板的限位,再通过把手将加长板拉出挡板的内部,当加长板移动的时候,加长板会与插块上倾斜的表面接触,从而推动插块向支撑架的方向移动,再通过第二弹簧的弹性来推动插块抵在加长板的表面,当加长板移动到尽头的时候,插块会通过第二弹簧插入加长板的内部,从而对加长板的位置进行固定,当需要拆卸的时候,反向操作上述步骤,就可以将加长板收回去,以方便进行收拢,通过设置调节结构可以增加可以支撑的面积,减少需要安装的支护。2. In the present utility model, when supporting the side wall of the foundation pit, the area that can be supported by only one baffle plate is limited, which leads to the need to install a large number of supports when supporting the side wall of the foundation pit. Therefore, during installation, the insertion rod can be moved upward, the fixing of the fixing rod can be released, and then the fixing rod can be rotated in the direction away from the baffle to cancel the limit on the extension board, and then pull the extension board through the handle. Out of the baffle, when the extension board moves, the extension board will contact the inclined surface on the insert block, thereby pushing the insert block to move in the direction of the support frame, and then push the insert block against the extension block through the elasticity of the second spring On the surface of the board, when the extension board moves to the end, the insert block will be inserted into the inside of the extension board through the second spring, thereby fixing the position of the extension board. The extension board is retracted to facilitate the folding, and the area that can be supported can be increased by setting the adjustment structure, and the support that needs to be installed can be reduced.
附图说明Description of drawings
图1为本实用新型提出一种建筑工程施工用可拆卸式支护的立体结构示意图;Fig. 1 is a three-dimensional schematic diagram of a detachable support for the construction of a building project proposed by the present utility model;
图2为本实用新型提出一种建筑工程施工用可拆卸式支护图1中A处结构示意图;Fig. 2 is a structural schematic diagram at A in Fig. 1 that the utility model proposes a detachable support for building engineering construction;
图3为本实用新型提出一种建筑工程施工用可拆卸式支护图1中B处结构示意图;Fig. 3 is the structural schematic diagram at B in Fig. 1 that the utility model proposes a kind of detachable support for building engineering construction;
图4为本实用新型提出一种建筑工程施工用可拆卸式支护图1中C处结构示意图。FIG. 4 is a schematic structural diagram of a detachable support for construction of a building project proposed by the present utility model at C in FIG. 1 .
图例说明:1、挡板;2、拆卸结构;201、底板;202、固定桩;203、转动架;204、第一支撑板;205、固定框;206、第二支撑板;207、方板;208、抵板;209、第一弹簧;210、拉钩;211、滑框;212、支撑框;3、调节结构;301、加长板;302、把手;303、支撑架;304、插块;305、第二弹簧;306、伸缩杆;307、固定杆;308、固定块;309、插杆。Legend: 1. Baffle plate; 2. Demolition structure; 201, Bottom plate; 202, Fixed pile; 203, Turret; 204, First support plate; 205, Fixed frame; 206, Second support plate; ; 208, push plate; 209, first spring; 210, hook; 211, sliding frame; 212, support frame; 3, adjustment structure; 301, extension plate; 302, handle; 303, support frame; 304, insert; 305, the second spring; 306, the telescopic rod; 307, the fixed rod; 308, the fixed block; 309, the insertion rod.
具体实施方式Detailed ways
为了能够更清楚地理解本实用新型的上述目的、特征和优点,下面结合附图和实施例对本实用新型做进一步说明。需要说明的是,在不冲突的情况下,本申请的实施例及实施例中的特征可以相互组合。In order to be able to understand the above-mentioned objects, features and advantages of the present invention more clearly, the present invention will be further described below with reference to the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments may be combined with each other in the case of no conflict.
在下面的描述中阐述了很多具体细节以便于充分理解本实用新型,但是,本实用新型还可以采用不同于在此描述的其他方式来实施,因此,本实用新型并不限于下面公开说明书的具体实施例的限制。In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can also be implemented in other ways different from those described herein. Therefore, the present invention is not limited to the specific details of the following disclosure. Example limitations.
请参阅图1-4,本实用新型提供一种技术方案:一种建筑工程施工用可拆卸式支护,包括挡板1和拆卸结构2。Please refer to FIGS. 1-4 , the present utility model provides a technical solution: a detachable support for building engineering construction, comprising a
下面具体说一下其拆卸结构2和调节结构3的具体设置和作用。The specific settings and functions of the
本实施方案中:挡板1的表面设置有拆卸结构2,拆卸结构2包括底板201,底板201与挡板1的表面转动连接,底板201的表面固定连接有转动架203,转动架203的表面转动连接有第一支撑板204,第一支撑板204的表面转动连接有第二支撑板206,挡板1的表面焊接有支撑框212,转动底板201,使底板201与挡板1呈垂直状态,接着展开第一支撑板204与第二支撑板206,使第二支撑板206插入支撑框212中。In this embodiment: the surface of the
具体的,第一支撑板204的表面滑动连接有固定框205,底板201的内壁滑动连接有固定桩202,使固定框205移动到第一支撑板204与第二支撑板206的连接处,通过固定框205可以防止第一支撑板204与第二支撑板206对折,将固定桩202插入土地中进行固定。Specifically, a
具体的,第二支撑板206的表面焊接有方板207,方板207的表面固定连接有滑框211,滑框211的内壁滑动连接有拉钩210。Specifically, a
在本实施例中:使固定框205移动到第一支撑板204与第二支撑板206的连接处,推动拉钩210远离抵板208,使拉钩210插入固定框205中,就可以将固定框205固定住。In this embodiment, move the
具体的,方板207的表面焊接有抵板208,抵板208与拉钩210之间固定连接有第一弹簧209,松开拉钩210,由于第一弹簧209处于压缩状态,可以通过第一弹簧209推动拉钩210远离抵板208,使拉钩210插入固定框205中。Specifically, an
在本实施例中:挡板1的表面设置有调节结构3,调节结构3包括加长板301,加长板301与挡板1的内壁滑动连接,加长板301的数量为两个,两个加长板301分别位于挡板1的两侧,加长板301的表面固定连接有把手302,在对基坑的侧壁进行支撑的时候,仅仅通过一个挡板1所能支撑的面积有限,导致在对基坑的侧壁进行支撑的时候需要安装大量的支护,因此在安装的时候通过把手302将加长板301拉出挡板1的内部可以增加支撑面积。In this embodiment: the surface of the
具体的,挡板1的表面固定连接有支撑架303,支撑架303的表面固定连接有伸缩杆306,伸缩杆306远离支撑架303的一端固定连接有插块304,插块304与支撑架303之间固定连接有第二弹簧305,当加长板301移动的时候,加长板301会与插块304上倾斜的表面接触,从而推动插块304向支撑架303的方向移动,再通过第二弹簧305的弹性来推动插块304抵在加长板301的表面,当加长板301移动到尽头的时候,插块304会通过第二弹簧305插入加长板301的内部,从而对加长板301的位置进行固定。Specifically, a
具体的,挡板1的表面固定连接有固定块308,固定块308的内壁插设有插杆309,挡板1的表面转动连接有固定杆307。Specifically, a fixing
在本实施例中:使插杆309向上移动,就可以解除对固定杆307的固定。In this embodiment, by moving the
工作原理:在需要安装的时候,转动底板201,使底板201与挡板1呈垂直状态,再将固定桩202插入土地中,接着展开第一支撑板204与第二支撑板206,使第二支撑板206插入支撑框212中,然后使拉钩210向着靠近抵板208的方向移动,再使固定框205顺着第一支撑板204向着第二支撑板206的方向移动,使固定框205移动到第一支撑板204与第二支撑板206的连接处,这时松开拉钩210,由于第一弹簧209此时处于压缩状态,可以通过第一弹簧209推动拉钩210远离抵板208,使拉钩210插入固定框205中,就可以将固定框205固定住,防止固定框205滑下来,通过固定框205可以防止第一支撑板204与第二支撑板206对折,而失去支撑效果,当需要拆卸时反向操作上述步骤,就可以对其进行拆卸,在对基坑的侧壁进行支撑的时候,仅仅通过一个挡板1所能支撑的面积有限,导致在对基坑的侧壁进行支撑的时候需要安装大量的支护,因此在安装的时候可以使插杆309向上移动,就可以解除对固定杆307的固定,然后使固定杆307向着远离挡板1的方向转动,就可以取消对加长板301的限位,再通过把手302将加长板301拉出挡板1的内部,当加长板301移动的时候,加长板301会与插块304上倾斜的表面接触,从而推动插块304向支撑架303的方向移动,再通过第二弹簧305的弹性来推动插块304抵在加长板301的表面,当加长板301移动到尽头的时候,插块304会通过第二弹簧305插入加长板301的内部,从而对加长板301的位置进行固定,当需要拆卸的时候,反向操作上述步骤,就可以将加长板301收回去,以方便进行收拢。Working principle: When it is necessary to install, rotate the
以上所述,仅是本实用新型的较佳实施例而已,并非是对本实用新型作其它形式的限制,任何熟悉本专业的技术人员可能利用上述揭示的技术内容加以变更或改型为等同变化的等效实施例应用于其它领域,但是凡是未脱离本实用新型技术方案内容,依据本实用新型的技术实质对以上实施例所作的任何简单修改、等同变化与改型,仍属于本实用新型技术方案的保护范围。The above is only a preferred embodiment of the present invention, and is not intended to limit the present invention in other forms. Any person skilled in the art may use the technical content disclosed above to change or remodel to equivalent changes. Equivalent embodiments are applied in other fields, but any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present utility model still belong to the technical solutions of the present utility model without departing from the technical solution content of the present utility model. scope of protection.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202122854076.9U CN216238566U (en) | 2021-11-22 | 2021-11-22 | A kind of detachable support for building engineering construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202122854076.9U CN216238566U (en) | 2021-11-22 | 2021-11-22 | A kind of detachable support for building engineering construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN216238566U true CN216238566U (en) | 2022-04-08 |
Family
ID=80946075
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202122854076.9U Expired - Fee Related CN216238566U (en) | 2021-11-22 | 2021-11-22 | A kind of detachable support for building engineering construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN216238566U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115030191A (en) * | 2022-07-28 | 2022-09-09 | 江苏顺丰建设有限公司 | Building foundation pit supporting device with prevent function that sinks |
-
2021
- 2021-11-22 CN CN202122854076.9U patent/CN216238566U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN115030191A (en) * | 2022-07-28 | 2022-09-09 | 江苏顺丰建设有限公司 | Building foundation pit supporting device with prevent function that sinks |
| CN115030191B (en) * | 2022-07-28 | 2023-11-14 | 江苏顺丰建设有限公司 | Building foundation pit supporting device with sinking prevention function |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN111305228B (en) | Deep foundation pit supporting structure and supporting method thereof | |
| CN216238566U (en) | A kind of detachable support for building engineering construction | |
| CN205153572U (en) | Device of anti ability of collapsing of reinforcing cave dwelling | |
| CN201206336Y (en) | Support frame structure for drop-prevention net | |
| CN207863476U (en) | A kind of reinforcing aluminum alloy mould plate pulling-on piece system diagonal brace | |
| CN114687352A (en) | Self-stabilizing broken line sheet pile wall structure | |
| CN214614098U (en) | Deep foundation pit supporting structure capable of preventing deformation | |
| CN119801012A (en) | A temporary trench support structure for construction engineering | |
| CN212801554U (en) | Civil engineering weak soil deep basal pit step type slope form backplate | |
| CN214090890U (en) | An easy-to-remove steel structure support device | |
| CN214219654U (en) | Pipe pole reverse-pulling device | |
| CN105756067B (en) | A kind of method of horizontal temporary support support replacement in deep basal pit | |
| CN110258528A (en) | One kind can assemble insertion self-clamping type precast hollow diaphram wall and its construction method | |
| CN210976829U (en) | Building component rain shielding device for outdoor storage yard in factory | |
| CN110939471B (en) | Net support machine for tunnel support and use method thereof | |
| CN116479911A (en) | A foundation pit diagonal bracing structure and foundation pit diagonal bracing support method | |
| CN222949002U (en) | Side wall supporting structure for building engineering foundation pit | |
| CN115126271A (en) | A prefabricated concrete structure | |
| CN211573583U (en) | Supporting device for rescuing mine roadway | |
| CN215165678U (en) | Quick supporting device of engineering pipeline slot | |
| CN213927844U (en) | Foundation ditch safety device based on town road engineering | |
| CN210152242U (en) | A bidirectional hydraulic self-servo support device for unilateral formwork | |
| CN108330985B (en) | Steel sheet pile is strutted convenient to installation | |
| CN217679142U (en) | A brace convenient to detach for deep-cutting foundation ditch | |
| CN216428303U (en) | Additional strengthening is used in water conservancy construction cofferdam |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20230707 Address after: No. 1-7-1 beside the convoy of Yan'an Road Street Handling Company, Honghuagang District, Zunyi City, Guizhou Province, 563000 Patentee after: Guizhou Guihu Water Conservancy and Hydropower Engineering Co.,Ltd. Address before: 253600 housing and Urban Rural Development Bureau of Leling City, De Zhou City, Shandong Province Patentee before: Zhang Wenge |
|
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20220408 |