CN203911008U - Ground wire clamp - Google Patents
Ground wire clamp Download PDFInfo
- Publication number
- CN203911008U CN203911008U CN201420317257.5U CN201420317257U CN203911008U CN 203911008 U CN203911008 U CN 203911008U CN 201420317257 U CN201420317257 U CN 201420317257U CN 203911008 U CN203911008 U CN 203911008U
- Authority
- CN
- China
- Prior art keywords
- column
- hook portion
- entablature
- crossbeam
- screwed hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Electric Cable Installation (AREA)
Abstract
Description
技术领域 technical field
本实用新型涉及电力设施领域,具体涉及一种接地线夹。 The utility model relates to the field of electric facilities, in particular to a grounding clamp.
背景技术 Background technique
在电力系统中,为防止已停电设备或线路上意外出现电流,必须在设备或线路上连接接地线,以将意外出现的电流引入大地,从而保证工作人员的人身安全。接地线通过接地线夹与设备或线路连接,目前江苏省电力公司统一配送的接地线夹由E型夹头和操作杆组成,E型夹头的上、下横梁分别与立柱固定连接,中横梁和立柱上分别设有匹配的滑轨、滑槽,通过滑轨、滑槽可沿立柱升降,下横梁上设有竖直的螺纹孔,操作杆顶端连接有与螺纹孔匹配的螺杆,螺杆顶端穿过螺纹孔后与活动夹板的下表面连接,活动夹板上表面与上横梁之间为夹持区,安装接地线时,工作人员将上横梁悬挂在设备或线路上,转动操作杆,通过螺杆将活动夹板向上顶,直到活动夹板与上横梁将设备或线路夹紧;在安装过程中,E型夹头上横梁与设备或线路之间只有因重力作用产生的摩擦力,当工作人员旋转操作杆的力大于摩擦力时,E型夹头也会随着操作杆转动,很容易从设备或线路上脱落,工作人员必须重新悬挂上横梁,当夹持区间距很小时,重新悬挂的难度大,往往需要反向旋转操作杆扩大夹持区,在一条接地线的安装过程中往往要重复数次,使得接地线安装工作平均要花费8分钟左右,对工作人员的体力消耗大,效率低;另外,当设备或线路比较密集时,E型夹头脱落容易触碰到附近带电的设备或线路,E型夹头和连接在E型夹头上的接地线都是良导体,很容易发生触电事故,安全系数低。 In the power system, in order to prevent accidental current on equipment or lines that have been powered off, a grounding wire must be connected to the equipment or lines to introduce the unexpected current into the ground, thereby ensuring the personal safety of the staff. The grounding wire is connected to the equipment or line through the grounding wire clamp. At present, the grounding wire clamp uniformly distributed by Jiangsu Electric Power Company is composed of an E-shaped clamp and an operating rod. The upper and lower beams of the E-shaped clamp are fixedly connected to the column respectively, and the middle beam There are matching slide rails and chute on the column respectively, through which the column can be lifted and lowered, and a vertical threaded hole is provided on the lower beam, and the top of the operating rod is connected with a screw that matches the threaded hole, and the top of the screw After passing through the threaded hole, it is connected to the lower surface of the movable splint. The clamping area is between the upper surface of the movable splint and the upper beam. When installing the grounding wire, the staff hangs the upper beam on the equipment or line, turns the operating rod, and passes through the screw. Push the movable splint upwards until the movable splint and the upper beam clamp the equipment or lines; during the installation process, there is only friction between the upper beam of the E-type chuck and the equipment or lines due to gravity, when the staff rotates and operates When the force of the rod is greater than the frictional force, the E-type chuck will also rotate with the operating rod, and it is easy to fall off from the equipment or the line. The staff must re-hang the upper beam. When the distance between the clamping areas is small, it is very difficult to re-suspend. , It is often necessary to reversely rotate the operating lever to expand the clamping area. In the installation process of a grounding wire, it is often repeated several times, so that the installation of the grounding wire takes about 8 minutes on average, which consumes a lot of physical strength for the staff and low efficiency; In addition, when the equipment or lines are relatively dense, the E-type clamp will fall off and easily touch the nearby live equipment or lines. The E-type clamp and the grounding wire connected to the E-type clamp are both good conductors, and it is easy to cause electric shock Accidents, low safety factor.
发明内容 Contents of the invention
本实用新型要解决的技术问题是提供一种接地线夹,可以解决现有接地线夹上横梁与设备或线路之间只有因重力作用产生的摩擦力,夹头很容易脱落,导致安装工作效率低和安全系数低的问题。 The technical problem to be solved by the utility model is to provide a grounding wire clamp, which can solve the problem that only the friction force generated by gravity between the upper beam of the existing grounding wire clamp and the equipment or line, the chuck is easy to fall off, resulting in the installation work efficiency Low and low safety factors.
本实用新型通过以下技术方案实现: The utility model is realized through the following technical solutions:
一种接地线夹,包括E型夹头和操作杆,所述E型夹头由立柱、上横梁、下横梁和活动夹板组成,所述上横梁、下横梁分别固定连接于立柱上、下两端,所述活动夹板一端滑动连接于立柱,可沿立柱升降,所述下横梁上设有竖直的螺纹孔,所述操作杆顶端连接有与螺纹孔匹配的螺杆,所述螺杆顶端穿过螺纹孔后与活动夹板的下表面连接,所述活动夹板上表面与上横梁之间为夹持区,所述上横梁的外端部设有向下延伸的钩部,所述钩部与立柱的间距略大于活动夹板的长度,所述钩部的长度为上横梁与下横梁间距的0.3~0.5倍。 A grounding clamp, including an E-shaped chuck and an operating rod. The E-shaped chuck is composed of a column, an upper beam, a lower beam and a movable splint. The upper beam and the lower beam are respectively fixedly connected to the upper and lower sides of the column. One end of the movable splint is slidably connected to the column, and can be lifted up and down along the column. The lower beam is provided with a vertical threaded hole, and the top end of the operating rod is connected with a screw matching the threaded hole. After the threaded hole, it is connected with the lower surface of the movable splint. There is a clamping area between the upper surface of the movable splint and the upper beam. The outer end of the upper beam is provided with a hook extending downward. The hook and the column The spacing is slightly greater than the length of the movable splint, and the length of the hook is 0.3 to 0.5 times the spacing between the upper beam and the lower beam.
所述钩部的材质与E型夹头上横梁相同,所述钩部与上横梁通过焊接或粘接或一体铸造成型或螺纹连接或夹持的方式连接为一体。 The material of the hook is the same as that of the upper beam of the E-type chuck, and the hook and the upper beam are connected as a whole by welding or bonding or integral casting or screw connection or clamping.
所述立柱上设有竖直的滑轨,所述活动夹板一端设有与滑轨匹配的滑槽。 The column is provided with a vertical slide rail, and one end of the movable splint is provided with a chute matching the slide rail.
所述E型夹头的立柱、上横梁、下横梁为一体铸造成型。 The column, the upper beam and the lower beam of the E-type chuck are integrally cast and formed.
本实用新型与现有技术相比的优点在于: Compared with the prior art, the utility model has the following advantages:
一、通过设置钩部避免E型夹头因随操作杆旋转而从设备或线路脱落,大幅降低安装接地线夹的难度,提高工作效率,同时避免了因E型夹头脱落误碰其他带电设备或线路而带来的安全隐患,提高安全系数; 1. By setting the hook to prevent the E-type chuck from falling off from the equipment or line due to the rotation with the operating lever, it greatly reduces the difficulty of installing the grounding clamp and improves work efficiency. At the same time, it avoids accidental contact with other live equipment due to the E-type chuck falling off Potential safety hazards caused by or lines, improve the safety factor;
二、结构简单、成本低廉、实施方便、效果显著。 Two, the structure is simple, the cost is low, the implementation is convenient, and the effect is remarkable.
附图说明 Description of drawings
图1为本实用新型的结构示意图。 Fig. 1 is the structural representation of the utility model.
具体实施方式 Detailed ways
如图1所示的一种接地线夹,包括E型夹头和操作杆6,所述E型夹头由立柱3、上横梁1、下横梁4和活动夹板2组成,所述上横梁1、下横梁4分别固定连接于立柱3上、下两端,所述E型夹头的立柱3、上横梁1、下横梁4为一体铸造成型,所述立柱3上设有竖直的滑轨8,所述活动夹板2一端设有与滑轨8匹配的滑槽,所述活动夹板2滑动连接于立柱3,可沿立柱3升降,所述下横梁4上设有竖直的螺纹孔,所述操作杆6顶端连接有与螺纹孔匹配的螺杆5,所述螺杆5顶端穿过螺纹孔后与活动夹板2的下表面连接,所述活动夹板2上表面与上横梁1之间为夹持区,所述上横梁1的外端部设有向下延伸的钩部7,所述钩部7与立柱3的间距略大于活动夹板2的长度,所述钩部7的长度为上横梁1与下横梁4间距的0.3~0.5倍。 A ground clamp as shown in Figure 1 includes an E-shaped chuck and an operating rod 6. The E-shaped chuck is composed of a column 3, an upper beam 1, a lower beam 4 and a movable splint 2. The upper beam 1 , the lower beam 4 are respectively fixedly connected to the upper and lower ends of the column 3, the column 3, the upper beam 1, and the lower beam 4 of the E-shaped chuck are integrally cast, and the column 3 is provided with a vertical slide rail 8. One end of the movable splint 2 is provided with a chute matching the slide rail 8, the movable splint 2 is slidably connected to the column 3, and can be raised and lowered along the column 3, and the lower beam 4 is provided with a vertical threaded hole, The top end of the operating rod 6 is connected with a screw rod 5 matching the threaded hole, and the top end of the screw rod 5 passes through the threaded hole and is connected with the lower surface of the movable splint 2, and the upper surface of the movable splint 2 and the upper beam 1 are clamped. The outer end of the upper beam 1 is provided with a downwardly extending hook 7, and the distance between the hook 7 and the column 3 is slightly greater than the length of the movable splint 2, and the length of the hook 7 is the length of the upper beam. 1 and 0.3 to 0.5 times the distance between the lower beam 4.
所述钩部7的材质与E型夹头上横梁1相同,所述钩部7设有通孔,所述上横梁1上设有螺纹孔,通过穿过通孔并连接于螺纹孔的螺栓夹持连接为一体。 The material of the hook portion 7 is the same as that of the upper beam 1 of the E-type chuck, the hook portion 7 is provided with a through hole, and the upper beam 1 is provided with a threaded hole, and the bolt passed through the through hole and connected to the threaded hole The clamping connection is integrated.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420317257.5U CN203911008U (en) | 2014-06-16 | 2014-06-16 | Ground wire clamp |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201420317257.5U CN203911008U (en) | 2014-06-16 | 2014-06-16 | Ground wire clamp |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN203911008U true CN203911008U (en) | 2014-10-29 |
Family
ID=51785254
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201420317257.5U Expired - Fee Related CN203911008U (en) | 2014-06-16 | 2014-06-16 | Ground wire clamp |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN203911008U (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104752988A (en) * | 2015-04-14 | 2015-07-01 | 国家电网公司 | Electric bonding lead component of overhead line and operating mechanism of electric bonding lead component |
| CN104901028A (en) * | 2015-05-07 | 2015-09-09 | 国家电网公司 | Safety grounding device |
| CN106207512A (en) * | 2016-08-31 | 2016-12-07 | 国家电网公司 | A kind of transmission of electricity bus grounding device |
| CN107565230A (en) * | 2017-08-23 | 2018-01-09 | 国网福建省电力有限公司 | A kind of flat mouth type ground wire fixture and its application method |
| CN109449630A (en) * | 2018-11-30 | 2019-03-08 | 国网浙江省电力有限公司培训中心 | A kind of conductive end structure of ground line and its application method |
-
2014
- 2014-06-16 CN CN201420317257.5U patent/CN203911008U/en not_active Expired - Fee Related
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104752988A (en) * | 2015-04-14 | 2015-07-01 | 国家电网公司 | Electric bonding lead component of overhead line and operating mechanism of electric bonding lead component |
| CN104901028A (en) * | 2015-05-07 | 2015-09-09 | 国家电网公司 | Safety grounding device |
| CN104901028B (en) * | 2015-05-07 | 2018-02-27 | 国家电网公司 | A kind of safety grounding device |
| CN106207512A (en) * | 2016-08-31 | 2016-12-07 | 国家电网公司 | A kind of transmission of electricity bus grounding device |
| CN107565230A (en) * | 2017-08-23 | 2018-01-09 | 国网福建省电力有限公司 | A kind of flat mouth type ground wire fixture and its application method |
| CN107565230B (en) * | 2017-08-23 | 2019-05-21 | 国网福建省电力有限公司 | A flat-type grounding wire clamp and using method thereof |
| CN109449630A (en) * | 2018-11-30 | 2019-03-08 | 国网浙江省电力有限公司培训中心 | A kind of conductive end structure of ground line and its application method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203911008U (en) | Ground wire clamp | |
| CN207671624U (en) | A kind of power equipment installation lifting apparatus | |
| CN103066526B (en) | A kind of ground connection line method and separated earthing instrument for ultra-high-tension power transmission line | |
| CN203013969U (en) | U-shape bayonet spiral compaction ground clamp | |
| CN205231281U (en) | A high -pressure discharge stick for distribution network overhauls | |
| CN205944466U (en) | Portable power construction grounding device | |
| CN106680586A (en) | Transformer measuring discharge device | |
| CN204858003U (en) | A ground clamp | |
| CN204905454U (en) | Dry -type transformer earthing device | |
| CN106099412B (en) | A kind of Portable power construction grounding device and its application method | |
| CN204103349U (en) | The auxiliary fixing elevation and subsidence regulating device of electric power live line working action bars | |
| CN202678786U (en) | Spring stretching tool used for electric power construction | |
| CN204243620U (en) | A kind of pre-twisting type overhang installation wire lifting device | |
| CN103762517B (en) | High-voltage ground wire installation method | |
| CN202259718U (en) | Movable-type grounding pile | |
| CN202772467U (en) | Isolating switch unilateral-electrification overhaul insulation device | |
| CN104600447B (en) | Automatic grounding wire clamping device | |
| CN202026035U (en) | Wire fixing device for live line work of overhead line | |
| CN202957491U (en) | Lifting and hanging support for on-load voltage regulating device body | |
| CN203048389U (en) | Breaker hoisting tool | |
| CN202657875U (en) | Novel porcelain insulator displacement device | |
| CN202721386U (en) | utility model | |
| CN202586166U (en) | Tackle for disconnecting lead from tubular busbar and connecting lead to tubular busbar | |
| CN204144631U (en) | A kind of distribution transforming inspection earthing line is met an urgent need crossover tool | |
| CN204982569U (en) | Vertically move hydraulic haulage winch of railway switch |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20141029 Termination date: 20190616 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |