[go: up one dir, main page]

CN201288328Y - Beam-plate integrated prefabricated split mounting type tower crane fixed foundation - Google Patents

Beam-plate integrated prefabricated split mounting type tower crane fixed foundation Download PDF

Info

Publication number
CN201288328Y
CN201288328Y CNU2008200378640U CN200820037864U CN201288328Y CN 201288328 Y CN201288328 Y CN 201288328Y CN U2008200378640 U CNU2008200378640 U CN U2008200378640U CN 200820037864 U CN200820037864 U CN 200820037864U CN 201288328 Y CN201288328 Y CN 201288328Y
Authority
CN
China
Prior art keywords
slabs
beams
tower machine
nut
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008200378640U
Other languages
Chinese (zh)
Inventor
邱益平
王跃仁
陆永恒
夏俊钱
单晓燕
邱皓波
张雪松
Original Assignee
邱益平
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 邱益平 filed Critical 邱益平
Priority to CNU2008200378640U priority Critical patent/CN201288328Y/en
Application granted granted Critical
Publication of CN201288328Y publication Critical patent/CN201288328Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Foundations (AREA)

Abstract

The utility model discloses a beam slab integrated prefabricated assembled tower crane fixed foundation, which is formed by connecting concrete beam slab members and weight blocks by 4 pieces in each way in a mechanical mode. The concrete beam and the plate are prefabricated into an integral component, so that the assembly process between the components is simplified, and the safety and reliability of the components are improved. The upper half part of the concrete beam plate component is provided with a plurality of reserved pipe holes and square holes, and the concrete beam plate component can adapt to anchoring of underframe of tower cranes of different manufacturers and models. The weight block and the beam slab member are connected into a whole, so that the weight block has a stable balance effect, plays multiple roles of torsion resistance and increase of contact area with the foundation, and can adapt to different geological conditions. Above-mentioned concrete prefabricated component and all connectors all can have enough to meet the need the use many times, and do not have the influence to the regional pipeline construction of foundation, practice thrift manpower, material resources, shortened the time limit for a project.

Description

Beam slab one precast splice type tower machine immobilizing foundation
(1) technical field:
The utility model relates to construction hoisting machinery and foundation technical field, relates to pillar crane concrete prefabricated parts pin-connected panel immobilizing foundation specifically.
(2) background technology:
The immobilizing foundation of pillar crane, conventional approach are to adopt the integral cast-in-situ concrete, and it is promptly discarded that the tower machine is removed the basis, back, is equipped with pipeline construction as base bits, also needs the basis is cleaned out, and causes the significant wastage of constructional materials and manpower.Applicant once obtained " the piecemeal pin-connected panel immobilizing foundation of pillar crane " utility model patent (patent No. is ZL94241543.4) in 1994.Vertical connectivity Bolt Connection is adopted in its precast beam assembly unit, fabrication and installation cost height, and " ten " font that in addition is assembled into basis is less than normal with the ground contact area, easily produces differential settlement when earth bearing strength is low, has therefore limited the large scale application of this technology.In recent years, domestic existing other forms of concrete precast assembly type foundation for tower crane is come out one after another, this type of basic primary structural component adopts steel hinge line stretch-draw to connect mostly, installation must have special equipment and professional, also adopt Bolt Connection on a small quantity, its common ground is that concrete prefabricated parts is complex-shaped, quantity is many, and processing and fabricating and installation difficulty are big, applies thereby also limited.
(3) summary of the invention:
Goal of the invention: provide a kind of simple for production, quick for installation, safe and reliable, and can adapt to the New Concrete component assembly formula tower machine immobilizing foundation of different type of machines and different soil conditions.
Technical scheme: for reaching above purpose, at the problems referred to above, the technical scheme that the utility model is taked is: this novel foundation is made of beams and slabs and coupling arrangement, saddle weight and fastening devices thereof, tower machine underframe anchor device; Beams and slabs is that beam and plate are made into one, the end is that rectangular beam structure, middle cross section are " ⊥ " tee beam and slab construction, afterbody is the concrete prefabricated parts of slab structure, beam slab is prefabricated into one, can simplify assembling process between member, improve the security reliability of member; 4 beams and slabs become " ten " font by the coupling arrangement assembling combination, 4 are trapezoidal saddle weight and are separately fixed on the plate of adjacent two beams and slabs by fastening devices, tower machine underframe anchor device is assemblied on the beam of beams and slabs, thereby forms this basic close set zoarium; Saddle weight plays stable equilibrium, antitorque and increase and the multiple action of ground contact area; The coupling arrangement of beams and slabs is made of beams and slabs central sill end cross pipe, junction plate, beam connecting bolt and nut; The fastening devices of saddle weight is made of beams and slabs middle part transverse pipe, pressing plate, ballast set bolt, nut; Tower machine underframe anchor device organizes the reservation square hole by the beams and slabs first half more and vertical duct, underframe set bolt, special washer nut and nut constitute, by selecting different pore combinations for use, the tower machine underframe of different manufacturers, different type of machines can be anchored on the assembly of the present utility model; The underframe set bolt lower end clamp nut and the pad that are used for the anchoring of tower machine underframe are made into one, form the special washer nut, reserve horizontal square hole coupling on its pad appearance and size and the concrete beam plate member, be convenient to fastening, fastening with double nut in underframe set bolt upper end, the anchoring connection produces loosening in the anti-tower machine operation process; For strengthening the shear resistance that the concrete member laterally connects, transverse pipe all adopts steel pipe pre-buried, and other vertical preformed hole pressure-bearings adopt plastic pipe pre-buried; Metallic element is all done antirust processing, is convenient to dismounting and turnover use.
Implementation result:
1, the handling of the utility model concrete beam plate member, saddle weight is in place quick, and assembling process is simple, and structure manufacture and installation cost are low, need not special equipment, and general unit in charge of construction all can grasp its manufacture craft and mounting process.
2, the utility model and ground contact area are big, not only are adapted to the area that geological conditions is good, earth bearing strength is high, also are applicable to other areas that earth bearing strength is relatively low.
3, reserve many group vertical ducts and supporting installation square hole on the concrete beam plate member, can adapt to the underframe anchoring needs of different manufacturers, different model tower machine.
4, each component parts of the utility model, connector all can repeatedly have enough to meet the need use, and the base area pipeline construction is not had influence, save human and material resources, have shortened the duration.
(4) description of drawings:
Fig. 1 is the vertical view of the utility model tower machine immobilizing foundation.1-concrete beam plate member A among the figure, 2-saddle weight, 3-junction plate, 4-pressing plate, 5-beams and slabs B.
Fig. 2 is Figure 1A-A sectional drawing.1-concrete beam plate member A among the figure, 6-vertical duct, 7-underframe set bolt, 8-nut A, 9-special washer nut.
Fig. 3 is Figure 1B-B sectional drawing.1-concrete beam plate member A among the figure, 2-saddle weight, 4-pressing plate, 10-transverse pipe A, 11-ballast set bolt, 12-nut B.
Fig. 4 is Fig. 1 C-C sectional drawing.1-concrete beam plate member A among the figure, 3-junction plate, 13-beam connecting bolt, 14-nut C, 15-transverse pipe B.
Fig. 5 is junction plate (horizontal positioned) front view.
Fig. 6 is Fig. 5 D-D sectional view.
Fig. 7 is the pressing plate front view.
(5) specific embodiment:
As shown in Figure 1, the utility model is formed by connection, fastening devices assembling combination by 2 beams and slabs A (1), 2 beams and slabs B (5) and 4 concrete saddle weights (2).All built-in fittings all are located on beams and slabs A (1) and the beams and slabs B (5), and wherein transverse pipe A (10) and transverse pipe B (15) are embedded steel tube, and vertical duct (6) is pre-buried plastic pipe.The end of beams and slabs A (1) and beams and slabs B (5) is the rectangular beam structure, and the middle part is " ⊥ " tee beam and slab construction, and tail end is a slab structure.Saddle weight (2) is the prefabricated trapezoidal flat board of concrete.
Site assembly: ground can carry out site assembly of the present utility model after the compacting levelling, building bed course or the processing of other reinforcement measures.Assembly technology is as follows:
1, earlier with 2 beams and slabs A (1) hoisted in position, the beam-ends alignment, both ends of the surface fit tightly; With 2 beams and slabs B (5) hoisted in position, vertical again with beams and slabs A (1), and align center, end face is close to the two sides of beams and slabs A (1) respectively.
2, be that junction plate (3), beam connecting bolt (13), nut C (14) are connected into integral body by transverse pipe B (15) with concrete beam plate member A (1), beams and slabs B (5) with coupling arrangement, be " ten " font.
3, tower machine underframe anchor device is installed: select corresponding vertical duct (6) and square hole combination according to type, underframe set bolt (7) is installed on beams and slabs A (1) and the beams and slabs B (5) with special washer nut (9) by vertical duct (6), as shown in Figure 2 (annotate: nut A (8) screws on after tower machine underframe is in place again).
4,4 saddle weights of handling (2) are placed on respectively on the back panel of beams and slabs A (1) and beams and slabs B (5), and its inclined-plane is close on the two member beam sides.
5, be pressing plate (4), ballast set bolt (11), nut B (12) with fastening devices,,, promptly form assembly of the present utility model, as Fig. 1, shown in Figure 3 with saddle weight (2) positioning and fixing by transverse pipe A (10).
After finishing, 1~5 operation can tower machine underframe and other structures be installed according to tower machine erection procedure.
6, after the tower machine installs, fill earth or yellow ground etc. at the position, space of saddle weight (2) and beams and slabs A (1), beams and slabs B (5) formation, the on-the-spot installation of the utility model promptly finished.

Claims (5)

1, beam slab one precast splice type tower machine immobilizing foundation, comprise beams and slabs and coupling arrangement thereof, saddle weight and fastening devices thereof, anchor device at the bottom of the tower machine, it is characterized in that: beams and slabs is that beam and plate are prefabricated into one, the end is the rectangular beam structure, middle cross section is " ⊥ " tee beam and slab construction, afterbody is the concrete prefabricated parts of slab structure, 4 beams and slabs become " ten " font by the coupling arrangement assembling combination, 4 are trapezoidal saddle weight and are separately fixed at by fastening devices on the plate of adjacent two beams and slabs, and tower machine underframe anchor device is assemblied on the beam of beams and slabs.
2, beam slab one precast splice type tower machine immobilizing foundation as claimed in claim 1, it is characterized in that: the coupling arrangement between its beams and slabs is to be made of beams and slabs beam end transverse pipe, junction plate, beam connecting bolt and nut.
3, beam slab one precast splice type tower machine immobilizing foundation as claimed in claim 1 is characterized in that: the fastening devices of saddle weight is to be made of beams and slabs middle part transverse pipe, pressing plate, ballast set bolt, nut.
4, beam slab one precast splice type tower machine immobilizing foundation as claimed in claim 1 is characterized in that: its tower machine underframe anchor device is to be made of many group reservation square holes and vertical duct, underframe set bolt, special washer nut and nut in the beams and slabs.
5, as claim 1 or 4 described beam slab one precast splice type tower machine immobilizing foundations, it is characterized in that: reserve the square hole coupling in pad appearance and size in the special washer nut and the beams and slabs, and pad and nut join together.
CNU2008200378640U 2008-07-07 2008-07-07 Beam-plate integrated prefabricated split mounting type tower crane fixed foundation Expired - Fee Related CN201288328Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200378640U CN201288328Y (en) 2008-07-07 2008-07-07 Beam-plate integrated prefabricated split mounting type tower crane fixed foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200378640U CN201288328Y (en) 2008-07-07 2008-07-07 Beam-plate integrated prefabricated split mounting type tower crane fixed foundation

Publications (1)

Publication Number Publication Date
CN201288328Y true CN201288328Y (en) 2009-08-12

Family

ID=40980005

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200378640U Expired - Fee Related CN201288328Y (en) 2008-07-07 2008-07-07 Beam-plate integrated prefabricated split mounting type tower crane fixed foundation

Country Status (1)

Country Link
CN (1) CN201288328Y (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101881029A (en) * 2010-05-05 2010-11-10 陈金生 Detachable tower foundation
CN102535507A (en) * 2011-12-16 2012-07-04 徐州金塔塔吊基础制造有限公司 Combined tower base
CN103195078A (en) * 2012-01-04 2013-07-10 赵正义 Module positioning structure of vertical connection bolt
CN103276745A (en) * 2013-06-18 2013-09-04 赵正义 Vertical connecting structure for tower crane and base
CN103276746A (en) * 2013-06-27 2013-09-04 赵正义 Vertical connecting and positioning structure for tower crane and foundation
CN103603365A (en) * 2013-11-11 2014-02-26 于顺平 Assembled-type tower crane foundation of below-80 tower crane
CN104264705A (en) * 2014-10-14 2015-01-07 赵正义 Assembling type perpendicular connecting structure for fixed tower crane and concrete foundation
CN108005099A (en) * 2017-11-24 2018-05-08 国网江苏省电力公司南京供电公司 A kind of shaft tower prefabricated assembled concrete stepped footing and its assembling method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101881029B (en) * 2010-05-05 2011-08-24 陈金生 Detachable tower foundation
CN101881029A (en) * 2010-05-05 2010-11-10 陈金生 Detachable tower foundation
CN102535507B (en) * 2011-12-16 2014-03-26 徐州金塔塔吊基础制造有限公司 Combined tower base
CN102535507A (en) * 2011-12-16 2012-07-04 徐州金塔塔吊基础制造有限公司 Combined tower base
CN103195078B (en) * 2012-01-04 2015-11-25 赵正义 The module locating structure of vertical connecting bolt
CN103195078A (en) * 2012-01-04 2013-07-10 赵正义 Module positioning structure of vertical connection bolt
CN103276745A (en) * 2013-06-18 2013-09-04 赵正义 Vertical connecting structure for tower crane and base
CN103276746A (en) * 2013-06-27 2013-09-04 赵正义 Vertical connecting and positioning structure for tower crane and foundation
CN103603365A (en) * 2013-11-11 2014-02-26 于顺平 Assembled-type tower crane foundation of below-80 tower crane
CN104264705A (en) * 2014-10-14 2015-01-07 赵正义 Assembling type perpendicular connecting structure for fixed tower crane and concrete foundation
CN104264705B (en) * 2014-10-14 2016-04-27 赵正义 The assembling vertical connection construction on fixed tower machine and concrete basis
CN108005099A (en) * 2017-11-24 2018-05-08 国网江苏省电力公司南京供电公司 A kind of shaft tower prefabricated assembled concrete stepped footing and its assembling method
CN108005099B (en) * 2017-11-24 2023-08-15 国网江苏省电力公司南京供电公司 Prefabricated assembled concrete stepped foundation for pole tower and assembling method thereof

Similar Documents

Publication Publication Date Title
CN201288328Y (en) Beam-plate integrated prefabricated split mounting type tower crane fixed foundation
CN104294753B (en) A kind of hollow pier stud syndeton of bridge prefabrication and construction
CN203834739U (en) End steel board connection, positioning and assembly type shear wall structure
CN204126048U (en) Bracket steel bar concrete shear force wall connecting pin contact assembled architecture
CN115821972B (en) A prefabricated rock anchor foundation for power transmission lines and its construction method
CN114457836A (en) Transmission line embedded type truss bearing platform anchor rod foundation
KR20130003993A (en) Reinforcement structure of steel tower and reinforcement method thereof
CN114991142A (en) An assembled slab-rock bolt composite foundation and construction method
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN114086554A (en) Permanent temporary combined type ground anchor and establishing method thereof
CN205502025U (en) Stagnant water stake is gone along with sb. to guard him to foundation ditch and shaped steel encloses connection structure between purlin
CN205531668U (en) Bored concrete pile basis assembled enclosure
CN111236416A (en) Prefabricated reinforced concrete structure house and installation method thereof
CN212836086U (en) A prefabricated composite wall based on H-beam
CN108678164A (en) Connect beam type Building block structure
CN204645343U (en) Prefabricated assembled concrete out-hung panel fastening devices
CN108729544B (en) Dry-and wet-type composite joint pin-connected panel construction
CN108729541B (en) Connect beam type Building block construction method
CN204174527U (en) The hollow pier stud syndeton of a kind of bridge prefabrication
CN212376009U (en) Prefabricated assembled reinforced concrete structure house
KR20110080676A (en) Concrete unit pillar member for column pre-installation method and permanent column pre-installation method using the same
CN212053436U (en) Strenghthened type precast concrete wallboard and connection structure with from structure of taking one's place
CN221372499U (en) Multilayer prefabricated close rib shear force footing connected node
CN204370831U (en) The additional Fabricated balcony structure in old community
CN220377306U (en) Prefabricated pile wall superposed assembled underground structure

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090812

Termination date: 20110707