CN201236477Y - Integral climbing scaffold for high-rise building - Google Patents

Integral climbing scaffold for high-rise building Download PDF

Info

Publication number
CN201236477Y
CN201236477Y CNU2008200419509U CN200820041950U CN201236477Y CN 201236477 Y CN201236477 Y CN 201236477Y CN U2008200419509 U CNU2008200419509 U CN U2008200419509U CN 200820041950 U CN200820041950 U CN 200820041950U CN 201236477 Y CN201236477 Y CN 201236477Y
Authority
CN
China
Prior art keywords
scaffold
base
housed
guide rail
fork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008200419509U
Other languages
Chinese (zh)
Inventor
沈锐
杨华
张卫东
宗永胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANTONG HERO CONSTRUCTION INST
Original Assignee
NANTONG HERO CONSTRUCTION INST
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANTONG HERO CONSTRUCTION INST filed Critical NANTONG HERO CONSTRUCTION INST
Priority to CNU2008200419509U priority Critical patent/CN201236477Y/en
Application granted granted Critical
Publication of CN201236477Y publication Critical patent/CN201236477Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The whole climbing scaffold for high-rise buildings is characterized in that a base is arranged at the bottom of the scaffold, a connecting plate is arranged on the inner side of the base, and the connecting plate and a wall body are connected through wall penetrating bolts. And a cross beam is connected with the wall body and extends to the middle part of the scaffold. A hanging ring is arranged below the cross beam, and an electric hoist is arranged on the hanging ring. The rings below the electric block are connected to the scaffold base. The outer side of the wall body is provided with a vertical guide rail, and the guide rail is provided with an open slot. The inner vertical rod of the scaffold is connected with a movable half, the half is provided with a connecting rod, the other end of the connecting rod is provided with a fork, a roller is arranged in the fork by a pin shaft, and the roller is abutted against the inner edge of an open slot of the guide rail and rolls up and down along the guide rail. The scapular part of the fork is provided with a rolling ball, the mouth of the open slot is provided with a clamping plate by a screw, and the inner edge of the clamping plate is contacted with the rolling ball. And loosening the connecting bolts of the scaffold and the wall body, and operating the electric hoist to realize the ascending or descending of the scaffold. Use the utility model discloses a climbing scaffold, the consumptive material is few, and labour expenditure is little, and the time limit for a project is short, and the cost is low.

Description

The whole climbing scaffold of highrise building
Affiliated technical field
The utility model relates to the whole climbing scaffold of highrise building that building operations is used.
Background technology
For the scaffold that the construction of highrise building is set up, traditional way is to set up scaffold from ground, and how high high-rise building have, and how high the scaffold that sets up also have.Its weak point is: the consumptive material of scaffold is many, and workman's work expenditure is big, and it is long in time limit to finish building operations, the overall cost height of high-rise building.
The utility model content
The purpose of this utility model is to provide highrise building whole climbing scaffold in order to overcome above-mentioned weak point, and the consumptive material of scaffold is few, and workman's work expenditure is little, and it is short relatively to finish the building operations duration, and the overall cost of high-rise building is low relatively.
The technical scheme that its technical problem that solves the utility model adopts is: scaffold by steel pipe, fastener form 4-8 the joint operating platforms double steel pipe scaffold.Base is arranged at the bottom at scaffold, and there is the bar of elongation the inboard of base, and rod end is connected with junction plate, with through-wall bolt with junction plate and the placing of concrete body of wall couple together.Bear the bearing capacity of whole scaffold in order to strengthen base, in the outside of base lower edge engaging lug is housed, engaging lug also is equipped with in the body of wall outside below base, between two engaging lugs diagonal brace is housed.Climbing of scaffold realizes by climbing device: linking to each other with body of wall is connected to a crossbeam, stretches the middle part at scaffold.Suspension ring are housed below crossbeam, electric block is installed on the suspension ring.The suspension ring of electric block below then are connected on the scaffold base.In wall outer side vertical guide rail is housed, has open slot on the guide rail.Be connected with movable Hough on the medial shaft straight-bar of scaffold, horizontal connecting rod is housed on the Hough, the other end of connecting rod has fork, the fork in bearing pin roller is housed, roller is against the open slot inner edge of guide rail, at open slot along the guide rail scroll-up/down.Spin is equipped with at omoplate position at fork, with screw clamp is housed at the oral area of open slot, and the inner edge and the spin of clamp contact.When the needs hoisting scaffold, unclamp the connecting bolt of scaffold and body of wall, the operation electric block is realized the rising or the decline of scaffold.
Effective effect of the present utility model is, uses the whole climbing scaffold of highrise building of the present utility model, and the consumptive material of scaffold is few, and workman's work expenditure is little, and it is short relatively to finish the building operations duration, and the overall cost of high-rise building is low relatively.
Description of drawings
Fig. 1 is the structural representation of the whole climbing scaffold of highrise building of the present utility model.1-placing of concrete body of wall among the figure, 2-through-wall bolt, 3-junction plate, 4-movable Hough, 5-connecting rod, 6-guide rail, 7-the placing of concrete body of wall treated, 8-scaffold, 9--crossbeam, 10--suspension ring, the 11--electric block, 12--base, 13--diagonal brace, 14--bolt, 15--engaging lug.
Fig. 2 is the A-A cutaway view Amplified image among Fig. 1.1-placing of concrete body of wall among the figure, 4-movable Hough, 5-connecting rod, 6--guide rail, 16--roller, 17--bearing pin, 18--fork, 19--screw, 20--clamp, 21--bolt, the vertical bar of 22--, 23--spin.
The specific embodiment
Scaffold (8) by steel pipe, fastener form 4-8 the joint operating platforms double steel pipe scaffold.In the bottom of scaffold (8) base (12) is arranged, the inboard of base (12) has the bar of elongation, rod end to be connected with junction plate (3), with through-wall bolt (2) with junction plate (3) and placing of concrete body of wall (1) couple together.Bear the bearing capacity of whole scaffold (8) in order to strengthen base (12), engaging lug (15) is housed, engaging lug (15) also is housed, diagonal brace (13) is housed between two engaging lugs (15) in the body of wall outside of base (12) below in the outside of base (12) lower edge.Climbing of scaffold (8) realizes by climbing device: linking to each other with body of wall is connected to a crossbeam (9), stretches the middle part at scaffold.In the below of crossbeam (9) suspension ring (10) are housed, electric block (11) is installed on the suspension ring (10).The suspension ring of electric block (11) below then are connected on the scaffold base (12).In wall outer side vertical guide rail (6) is housed, guide rail has open slot on (6).On the medial shaft straight-bar (22) of scaffold, be connected with movable Hough (4), horizontal connecting rod (5) is housed on the Hough, the other end of connecting rod (5) has fork (18), with bearing pin (17) roller (16) is housed in the fork (18), roller (16) is against the open slot inner edge of guide rail (6), in open slot along guide rail (6) scroll-up/down.Spin (23) is equipped with at omoplate position at fork (18), with screw (19) clamp (20) is housed at the oral area of open slot, and the inner edge of clamp (20) and spin (23) contact.When the needs hoisting scaffold, unclamp the connecting bolt of scaffold and body of wall, operation electric block (11) is realized the rising or the decline of scaffold (8).

Claims (3)

1, the whole climbing scaffold of highrise building, it is characterized in that: base is arranged at the bottom at scaffold, there is the bar of elongation the inboard of base, rod end is connected with junction plate, with through-wall bolt with junction plate and the placing of concrete body of wall couple together; Linking to each other with body of wall is connected to a crossbeam, stretches the middle part at scaffold, and suspension ring are housed below crossbeam, and electric block is installed on the suspension ring, and the suspension ring of electric block below are connected on the scaffold base; In wall outer side vertical guide rail is housed, has open slot on the guide rail; On the medial shaft straight-bar of scaffold, be connected with movable Hough, horizontal connecting rod is housed on the Hough, the other end of connecting rod has fork, with bearing pin roller is housed in the fork, roller is against the open slot inner edge of guide rail, spin is equipped with at omoplate position at fork, with screw clamp is housed at the oral area of open slot, and the inner edge and the spin of clamp contact.
2, the whole climbing scaffold of highrise building according to claim 1 is characterized in that: 4-8 double steel pipe scaffolds that save operating platforms that scaffold is made up of steel pipe, fastener.
3, the whole climbing scaffold of highrise building according to claim 1, it is characterized in that: engaging lug is equipped with in the outside at the base lower edge, and engaging lug also is equipped with in the body of wall outside below base, between two engaging lugs diagonal brace is housed.
CNU2008200419509U 2008-08-04 2008-08-04 Integral climbing scaffold for high-rise building Expired - Fee Related CN201236477Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200419509U CN201236477Y (en) 2008-08-04 2008-08-04 Integral climbing scaffold for high-rise building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200419509U CN201236477Y (en) 2008-08-04 2008-08-04 Integral climbing scaffold for high-rise building

Publications (1)

Publication Number Publication Date
CN201236477Y true CN201236477Y (en) 2009-05-13

Family

ID=40649216

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200419509U Expired - Fee Related CN201236477Y (en) 2008-08-04 2008-08-04 Integral climbing scaffold for high-rise building

Country Status (1)

Country Link
CN (1) CN201236477Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013175156A1 (en) 2012-05-21 2013-11-28 Inderjit Singh Dhillon High rise building elevation concept
CN110259096A (en) * 2019-06-26 2019-09-20 重庆科技学院 Self-moving construction platform for civil engineering and using method thereof
CN113338603A (en) * 2021-05-31 2021-09-03 开友投资(海南)合伙企业(有限合伙) Automatic climbing device and climbing method for lifting equipment

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013175156A1 (en) 2012-05-21 2013-11-28 Inderjit Singh Dhillon High rise building elevation concept
CN110259096A (en) * 2019-06-26 2019-09-20 重庆科技学院 Self-moving construction platform for civil engineering and using method thereof
CN113338603A (en) * 2021-05-31 2021-09-03 开友投资(海南)合伙企业(有限合伙) Automatic climbing device and climbing method for lifting equipment

Similar Documents

Publication Publication Date Title
CN201236477Y (en) Integral climbing scaffold for high-rise building
CN202023353U (en) Integral lifting scaffold for building operations
CN201260050Y (en) 220KV bracket for replacing bus bar column insulator
CN208454342U (en) A kind of safety of tower crane platform and standard knot install conjoined device
CN202882376U (en) Elevator shaft template support platform
CN205955171U (en) Fall to ground scaffold collet device
CN212388962U (en) Attached type lifting scaffold wall-attached support for bay window
CN107313597A (en) Modularization ready-package discharging platform for assembled architecture
CN204456816U (en) One can promote supporting leg type elevator hoistway construction platform
CN210193197U (en) An assembled beam embracing suspension device
CN205688778U (en) A kind of elevating scaffold special over sling structure
CN206903168U (en) A kind of movable up-down builds scaffold by laying bricks or stones
CN202718380U (en) Hydraulic climbing frame for construction of high-rise building
CN201873949U (en) Bride prestress stretch-draw trolley
CN211622545U (en) Self-clamping type protective platform for operation in elevator shaft
CN213927434U (en) Auxiliary attachment device for attached lifting scaffold of overhead structure of super high-rise building
CN203755677U (en) Lower suspension hoisting type hoisting device for reinforced concrete floor construction
CN213174736U (en) High-rise building climbing frame falling prevention device
CN209493262U (en) Construction site stone material handling apparatus
CN201151954Y (en) Steel column and concrete column connection structure
CN216949391U (en) Scaffold frame that construction was used
CN206204795U (en) A kind of Hanging Basket with vertical lift limit function
CN204571334U (en) A kind of security protection platform built for piping lane
CN201756788U (en) Internally arranged construction bench moving according to floors of elevator shaft under construction
CN205822753U (en) A kind of climbing frame load-carrying members

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20090513

Termination date: 20150804

EXPY Termination of patent right or utility model