CN201162277Y - Assembly type integrated house component and assembly type integrated house - Google Patents

Assembly type integrated house component and assembly type integrated house Download PDF

Info

Publication number
CN201162277Y
CN201162277Y CNU2008200162805U CN200820016280U CN201162277Y CN 201162277 Y CN201162277 Y CN 201162277Y CN U2008200162805 U CNU2008200162805 U CN U2008200162805U CN 200820016280 U CN200820016280 U CN 200820016280U CN 201162277 Y CN201162277 Y CN 201162277Y
Authority
CN
China
Prior art keywords
coating panel
combination
packed layer
panel
layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2008200162805U
Other languages
Chinese (zh)
Inventor
许刚
王云山
刘昭勇
许维堂
王娇
刘昭生
李丽
常向华
刘毅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CNU2008200162805U priority Critical patent/CN201162277Y/en
Application granted granted Critical
Publication of CN201162277Y publication Critical patent/CN201162277Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/90Passive houses; Double facade technology

Landscapes

  • Building Environments (AREA)

Abstract

The utility model relates to an assembly type integration building component which comprises a building framework structure, an external wall plate combination, a sloping roof plate combination, an internal wall plate combination and a building carrier plate; wherein, the external wall plate combination and the sloping roof plate combination respectively comprises an outer laying plat, an inner laying plat and a filling layer arranged between the outer laying plat and the inner laying plat; and the two sides of the filling layer are provided with pressure sensitive adhesive and release paper. The building carrier plate consists of a reinforcing frame body, an upper laying plate, a lower laying plate, honeycomb filling material and a water-proof layer. The internal wall plate combination comprises laying plates on two sides and a filling layer in the middle; and the two sides of the filling layer are provided with pressure sensitive adhesive and release paper. Components used in the assembly type integration building component provided by the utility model are all processed and standardized in plants and can be transported long distance conveniently; the combination parts of the external wall plate combination, the sloping roof plate combination and the internal wall plate combination are manufactured separately and assembled on the site. The assembly type integration building component can be assembled easily, orderly, quickly and conveniently with low labor intensity. Buildings constructed with the assembly type integration building component provided by the utility model have good integrity, excellent sound-proof performance and can preserve and insulate heat. The assembly type integration building component is environment-friendly and healthy and can save energy and material.

Description

Assembled integrated house component and assembled integrated house
Technical field
The utility model belongs to building and construction method field thereof, particularly a kind of assembled integrated house.
Background technology
Assembled integrated house has become the developing direction of modern and future architecture.Green building, ecotecture not only require building energy-saving, environmental protection, comfortable, healthy, also require high-quality and high-efficiency, low consumptive material, standardization, batch production, general applicability and scientific rationality.Traditional integrated room roughly is divided at present: 1, ultralight steel joist type: to fill out inorganic cotton or plastic foam in the commercially available multi-layered board flush coat (as Thistle board, wood based panel etc.); 2, light steel steel structure: the foamed cement sandwiched plate is inserted, adds interior external wall plastering with woven roving then; 3, steel mesh, inorganic cotton or formula steel mesh plastic foam add several structures and construction form such as plaster.Though advantage is respectively arranged, also exists a lot of limitation: complex process, installation is loaded down with trivial details, cost is high, the manual rate of manpower is high or the not environmental protection of constructing, of poor quality, efficiency of construction is low, be subjected to many deficiencies such as climatic effect is big.
Summary of the invention
The assembled integrated house that technical problem to be solved in the utility model provides a kind of assembled integrated house component and utilizes this member to construct, simple in order, rapid and convenient, house good integrity, environment protection health, energy-saving material-saving are installed in member factory normalization processing.
The utility model assembled integrated house component is characterized in that comprising house frame structure, side fascia combination, the combination of sloping top board, floor support plate, wherein:
Described side fascia combination comprises the packed layer between outer coating panel, interior coating panel and outer coating panel and the interior coating panel, and the two sides of packed layer has pressure sensitive adhesive and strippable paper,
Described sloping top board combination comprises the packed layer between outer coating panel, interior coating panel and outer coating panel and the interior coating panel, and the two sides of packed layer has pressure sensitive adhesive and strippable paper,
Described floor support plate constitutes by strengthening framework, last coating panel, following coating panel, honeycomb packing material and waterproofing course, inlay the honeycomb packing material in the sash of enhancing framework, compound respectively coating panel, following coating panel, the surface recombination waterproofing course of last coating panel and following coating panel gone up in the two sides of framework and honeycomb packing material.
Assembled integrated house component of the present utility model also comprises the inner wall panel combination, comprises the coating panel of both sides and packed layer therebetween, and the two sides of packed layer has pressure sensitive adhesive and strippable paper.
Described side fascia combination, the combination of sloping top board, inner wall panel combination also comprise the transition heat-insulating bridge-cut-off.
The utility model utilizes the house frame structure, the side fascia combination, slope top board combination, floor support plate, the inner wall panel combination is mutually permanently connected and is assembled into the house, during assembling, the two sides of the packed layer of side fascia is thrown off strippable paper and is flushed (after being added with the transition heat-insulating bridge-cut-off with the exterior wall framework of house frame structure, flush with transition heat-insulating bridge-cut-off layer), seal by fluid sealant in packed layer and the exterior wall frame gap, compound respectively fixing outer coating panel in the both sides of framework and packed layer and interior coating panel, the two sides of the packed layer of slope top board is thrown off strippable paper and is flushed (after being added with the transition heat-insulating bridge-cut-off with the sloping top frame of house frame structure, flush with transition heat-insulating bridge-cut-off layer), seal by fluid sealant in packed layer and the sloping top frame gap, compound respectively fixing outer coating panel in the both sides of framework and packed layer and interior coating panel, seam between the top, two slopes is covered by marine glue or waterproof roll, floor support plate places on the framework of floor location, fixing between floor support plate and the framework, seam between the floor support plate is sealed by glue, the packed layer of inner wall panel flushes (after being added with the transition heat-insulating bridge-cut-off with the interior wall framework of house frame structure, flush with transition heat-insulating bridge-cut-off layer), by the fluid sealant sealing, the both sides of framework and packed layer are compound fixedly coating panel respectively in packed layer and the interior exterior wall frame gap.
The exterior wall framework of house frame structure and outside between the coating panel or and outer coating panel, interior coating panel between all be added with transition heat-insulating bridge-cut-off layer, between sloping top frame and the outer coating panel or and outer coating panel, interior coating panel between all be added with transition heat-insulating bridge-cut-off layer.
Exterior wall described in the utility model refers to the supporting part in an element of construction (for example room).Interior wall is the compartment in the element of construction.
Below describe the utility model in detail.
One, the house frame structure is steel work or wooden construction and steel wood combination construction.Type of attachment: steel work is welding, screw connects or welding wire mixes binding.Steel wood combination construction can welding wire, nail etc. mixes and links.The material of steel work can be used H steel, I shaped steel, C shaped steel, rectangular tube or pipe.According to using position choose reasonable kind, the sheet material specification also should be considered in the house when making according to designing requirement.The house frame structure Design, install substantially with the known technology or the mode that all can realize according to description those of ordinary skills of the present utility model.
Two, side fascia.Comprise outer coating panel, interior coating panel, packed layer composition.The two sides of packed layer or inside and outside coating panel and packed layer binding face have at least a face to scribble adhesive.
Outer coating panel comprises flush coat base material, waterproofing course and finish coat, temporary protective film or paper.
1, the flush coat base material can be that calcium silicate board, glass strengthen thin plates such as pressure cement board, magnesium oxide plate to intensity preferably.Thickness is between 0.5-3cm.Its outside of sheet material is added with waterproof coating or composite of water-proof coiled material through waterproofing work.If be the coatings decoration layer, preferably liquid or paste waterproofing work coating are as waterproof organosilicon, waterproof selenium cement; If cladding facing as various cladding plates, can be various waterproof rolls; Also can be directly compound, as not only waterproof but also the material that can do to decorate, as aluminium-plastic panel.At compound one deck temporary protective film of finish coat or protection sheet.
2, packed layer can adopt that more than one coefficient of thermal conductivity such as layered composite of plastic foam, inorganic cotton plate, flame-retardant mould-proof paper, cellular board or these materials are lower, heat insulation effect better and can satisfy the material of requirement of strength.Call adiabatic packed layer in the following text.The two sides of adiabatic packed layer scribbles adhesive phase, is covered with the topping of interim strippable paper or film as the outside of high-strength pressure-sensitive (water base or oil base), pressure sensitive adhesive.The thickness of adiabatic packed layer can and add that transition heat-insulating bridge-cut-off layer thickness is equal to according to corresponding steel structure frame thickness.The thickness that adiabatic packed layer embeds in the steel structure frame is slightly less than steel structure frame, generally speaking should be between 2-10mm, and the one, be beneficial to and embed steel structure framework, the 2nd, conveniently link into an integrated entity at periphery and steel structure framework with adhesive.
Interior coating panel selection can be the plate of the same race of above-mentioned outer coating panel, also can be Thistle board or articifial wood scutum.The indoor surface of interior coating panel has paint finishing or is compounded with wallpaper or finishing paper.Its skin was compounded with protection sheet or diaphragm when batch production was made.
When batch production was made, the built-up section of exterior wall composite plate (outer coating panel, interior coating panel, packed layer) was made respectively, on-the-spot then the installation.
Three, sloping top board: sloping top board combination is basic identical with the side fascia combination.Outer coating panel, adiabatic packed layer and interior coating panel are arranged.Outer coating panel is suitable for composite of water-proof coiled material, and interior coating panel is suitable for the composite decoration ply of paper, and adiabatic packed layer is identical with the adiabatic packed layer of side fascia, can be that the two sides scribbles pressure sensitive adhesive in advance and has strippable paper.
Four, floor support plate: comprise strengthening framework, last coating panel, following coating panel, honeycomb packing material, waterproofing course.
1, strengthens framework: select for use wooden or articifial wood scutum or metal frame.Strengthen in the middle of the main frame a plurality of groined type grids are arranged.Material should be done protection against the tide, waterproof, preservative treatment.This enhancing framework mainly improves weight bearing power and becomes the carrier of honeycomb packing material.
2, upper and lower coating panel should select for use intensity preferably calcium silicate board, magnesium oxide plate, glass fibre cement plate and above-mentioned material add steel reinforcement plate material or wood based panel, articifial wood scutum etc.
3, honeycomb packing material: hexagon, corrugation shape, tubular type cellular material all can.Fill heat-insulating and sound-proof material in its honeycomb vestibule, packing material can be at last coating panel or down during the compound good wherein one side of coating panel, the formation box body, and filling pours into.
4, waterproofing course: floor support plate is carried out compound (bonding) waterproof roll layer on its two sides afterwards.Wherein, last coating panel can tile fixing or the cement-bonded band sand auger material or the coiled material of band nonwoven.
Preparation method:
After will strengthening framework and manufacturing, in sash, the honeycomb packing material closely is embedded in wherein earlier, the one side of coating panel is inlayed on the face of two honeycomb packing materials more up and down then, be fixed with nailing, pour into heat-insulating and sound-proof material in the honeycomb with opening again, fixing with nailing behind the gluing on gluing and the coating panel on framework and the honeycomb then, descending the two sides complex waterproof layer at last thereon.
Five, inner wall panel: form by the coating panel of both sides and the packed layer between two coating panels.
1, coating panel: the one side of coating panel scribbles coating ornamental surface layer or compound wall coverings paper in advance, and has diaphragm.The coating panel substrate can be a Thistle board, also can be wood-base fibre and particle panel material or magnesia, calcium silicates, cement fibrolite plate etc.
2, packed layer: can be engineering with honeycomb card board or inorganic cotton or plastic foam, perhaps the complex of above-mentioned material be inorganic cotton sandwich as the centre, and both sides are extrusion molding foam.Can the centre be inorganic cotton also, both sides be engineering honeycomb card boards, guarantee that the two sides of packed layer is smooth smooth, and gluing obtains good compound peel strength easily.If use the precoating pressure sensitive adhesive, can compound interim strippable paper diaphragm, also can be on-the-spot gluing, as PU foamed glue, polyvinyl acetate emulsion copolymer etc.
Six, transition heat-insulating bridge-cut-off:
The main effect of transition heat-insulating bridge-cut-off is insulation capacity and the sound insulation value that improves exterior wall and sloping top board, the effect of being convenient to Fast Installation (use nailing) simultaneously in addition and improving the shock resistance of building.
Transition heat-insulating bridge-cut-off of the present utility model can use the wood-based plate with water-proof function of sandwich construction and anticorrosion plank, wood to mould plate etc.Because the coefficient of thermal conductivity of steel structure is higher, form heat bridge, steel structure frame position heat-insulating property is relatively poor, and steel structure frame and body of wall bond sites belong to being rigidly connected and cause the paddy resonance that coincide, and forms the sound bridge, occurs leaking voice phenomenon easily.Therefore handling steel structure and keel connecting portion plays an important role for the thermal insulation and the sound insulation value of the utility model building.
Mounting method of the present utility model is:
Earlier shaped steel (wood) is carried out cutting stock in factory, operation such as punch on request then, anticorrosion according to Design Requirement Drawing.Form house frame by wire connection or welding again.Floor support plate, sloping top board, side fascia and inner wall panel are installed then.Can floor support plate be installed earlier for easy construction and be convenient to the operation of climbing to a higher point, sloping top board is installed again, be beneficial to rain and sun etc.Side fascia is installed then, can be installed simultaneously when mechanical condition is convenient, because all be that autonomous system can non-interfering operation.
One, the mounting method of floor support plate:
In four kinds of sheet material prefabricated components of the utility model prefabricated, having only floor support plate is complete prefabricated shaping, the position of prefabricated floor support plate directly can be lifted and be arranged on the floor frame, seam crossing uses PU foamed glue or waterproof filleting silicone adhesive or rubber-type filleting special glue, makes every floor support plate be connected to an integral body.
Two, the installation of wallboard is one of most important technology of the utility model building, also is the place of embodying the key of building comprehensive quality and efficiency of construction.
Three, electric wire, waterline, warm line lay in the utility model building, can be according to path, position poling walking in the steel structure of designing requirement and design drawing.When in body of wall, walking, carry out reservations such as perforate cutting in the prefabricated component region of interest, the ditch hole, the line box is fixing can fix with adhesive or thread tapping, as the PU foamed adhesive.
Can be when last splash line passes through floor support plate according to the pipeline pore size; on prefabricated component, cut and hole; then its perforate position is sealed with waterproof and sealing material, be enclosed within the perforate perforate is protected and tapping is carried out reinforcement with metallo-plastic or gum sleeve along the hole.
After designing and producing according to drawing, each independently will fixedly mount the position of wallboard in the unit at steel framed structure, in advance transition heat-insulating bridge-cut-off layer is fixed on the outside or two sides, the interior outside of frame construction, and useful binders or screw connect in the time of fixedly.If when using the composite plate of plastic foam plate and wood based panel, the one side of plastic foam plate should be obedient to steel structure face.Because of wood based panel and inside and outside coating panel are realized nail joint easily, also play the effect of heat-insulating bridge-cut-off simultaneously.
After each exterior wall steel structure frame installed and fixed transition heat-insulating bridge-cut-off layer, can install and fix the exterior wall composite plate.The erection sequence of exterior wall composite plate can be that outer coating panel is installed earlier, and adiabatic packed layer is installed then, flush coat flaggy in installing again.Also can after inlaying adiabatic packed layer in the steel structure framework, fixedly mount inside and outside coating panel again.Because utilize the efficient of the utility model fabrication techniques integrated house just to be embodied in the flexibility that this procedure is installed.Outer coating panel and interior coating panel can each does what he thinks is right carry out independent installation, unaffected mutually.Because Item Weight is light, need not rely on lifting machine to install easily.This mounting method has also avoided corner that short phenomenon in the foreign minister that compound good forming wall plate occurs is installed, and reserves recessed female mouthful when connecting, sound bridge and the heat bridge that cause in the gap of groove and keel or steel structure, thereby reduction sound insulation value and insulating energy-saving performance.
This combined installation method of the present utility model can also be easy to handle electric wire, waterline, the warm three-way installation of line.After installing steel structure framework, can on steel structure framework, fix three-way as required.According to three-way trend, cut adiabatic packed layer and on interior coating panel prefabricated fluting, static line box and draw pipeline.
A kind of concrete connected mode is provided below:
1) outer coating panel is fixed on the prefabricated transition heat-insulating bridge-cut-off layer, elder generation behind transition heat-insulating bridge-cut-off layer location, is fixed with ail gun outer coating panel card along fixed frame.
2) subsequently, the strippable paper of adiabatic packed layer one side is removed the outside coating panel inboard of card in framework, exert pressure, make its adiabatic packed layer paste outer coating panel and get final product.To inject fluid sealant in adiabatic packed layer and the frame gap then, as PU foam seal glue, making adiabatic packed layer and framework compound is one, removes the pressure sensitive adhesive protection strippable paper of adiabatic packed layer another side simultaneously.
3) fixing interior coating panel, behind interior coating panel location, card is exerted pressure to adiabatic packed layer, makes it be bonded as one, with nailing coating panel in it is fixed with nail along transition heat-insulating bridge-cut-off layer then.Interior coating panel side also can not add the transition heat-insulating bridge-cut-off.
4) with inside and outside coating panel and heat insulation layer fixing after, must after the seam crossing on the inside and outside coating panel and the nailing place of damaging handle with waterproof agent, cord belt and caulk compound, cover with paint, lacquer, colour wash, etc. again, covering treatment.Position, nail hole on interior coating panel hides with the decorations suspension member, as the gypsum ornamental thread with carry sole etc.
Also adiabatic packed layer can be installed earlier, install and fix inside and outside coating panel then simultaneously, this in practice method installation rate is fast, quality good.Adiabatic packed layer is embedded in the framework, the transition heat-insulating bridge-cut-off layer that makes itself and framework in one plane, then with the slit of periphery in inject fluid sealant, remove the strippable paper on both sides after fixing, fixing respectively then inside and outside coating panel, exert pressure after should aiming at the position before the nailing mechanical fixation, making insulation material layer and inside and outside coating panel compound is one.According to this mounting method of the present utility model, the side fascia of each floor height is combined on the steel structure.If multilayer can begin to install from one deck earlier, upwards install successively, until being mounted to the top layer pediment, also can successively install downwards from the top layer pediment.
Four, the installation of sloping top board:
Slope top board aggregate erection is identical with the installation of exterior wall composite plate basically.Can be earlier the interior coating panel of sloping top board be installed and fixed, then a strippable paper of adiabatic packed layer is peelled off the back and embedded in the steel structure framework, with fluid sealant with compound around it with steel structure framework connecting place be one.Peel off the another side strippable paper again, card closes fixing outer coating panel.Successively top, two slopes is is tightly installed and fixed side by side, with marine glue or web process seam.On its sloping top board, install at last or stickup tile, ridge tiles etc.
In the framework of door of reserving or window with the fixing transition heat-insulating bridge-cut-off layer of the frame inner rim of exterior wall vertical direction, when being used for door or window are installed, easy and convenient screw connects, and has cut off the heat bridge and the sound bridge of door or window and steel structure framework simultaneously, thereby has improved its heat-proof quality and sound insulation value.
In whole erection sequential process of the present utility model, relatively the order of science be since when making the steel structure from bottom to top, floor support plate preferably is installed earlier, be beneficial to like this and pricking shelf on the floor support plate, climb to a higher point and on floor support plate, placing material.When steel structure framework is installed to when top, sloping top board is installed earlier, can scientifically utilize shelf like this, simultaneously after installing sloping top board at room frame constructor's rain and snow, sun-proof certain convenience arranged.The aggregate erection of inner wall panel have on the framework condition of steel structure basic identical with the installation of side fascia.
Advantage of the present utility model:
The processing of member factory normalization is convenient to the classification long-distance transport, and is subjected to climatic effect little, and efficient improves 3-5 doubly.Simple in order, rapid and convenient are installed, and labour intensity is low.The house good integrity, thermal insulation, sound insulation value are good, environment protection health, energy-saving material-saving.
Description of drawings
Fig. 1 is the cross section structure schematic diagram of side fascia;
Fig. 2 is the structural representation of floor support plate;
Fig. 3 is the A-A view among Fig. 2;
Fig. 4 is the cross section structure schematic diagram of sloping top board;
Fig. 5 is the cross section structure schematic diagram of inner wall panel;
Fig. 6 is a kind of schematic diagram of house frame structure;
Fig. 7 is the structural representation between house frame structure and packed layer;
Fig. 8, Fig. 9 are respectively the mounting structure schematic diagram of side fascia;
Figure 10 is the B-B view among Fig. 9.
Among the figure: coating panel 4 strengthens 10 times coating panels of coating panel 9 honeycomb packing materials, 11 outer coating panel 12 adiabatic packed layers 13 interior coating panel 14 coating panels 15 packed layers 16 sloping top frame 17 floor support plate frameworks 18 exterior wall frameworks 19 interior wall frameworks 20 fluid sealants 21 transition heat-insulating bridge-cut-offs on framework 5 honeycomb ceramics 6 heat-insulating and sound-proof materials 7 waterproofing courses 8 in the 1 outer coating panel 2 adiabatic packed layers 3
The specific embodiment
As Fig. 1, side fascia is finally formed by the adiabatic packed layer 2 compound (by bonding) between outer coating panel 1, interior coating panel 3 and outer coating panel and the interior coating panel.
As Fig. 2, Fig. 3, floor support plate constitutes by strengthening framework 4, last coating panel 8, following coating panel 10, honeycomb packing material 9 and waterproofing course 7, inlay honeycomb packing material 9 in the intersecting parallels sash of enhancing framework 4, compound respectively coating panel 8, following coating panel 10, the surface recombination waterproofing course 7 of last coating panel and following coating panel gone up in the two sides of framework and honeycomb packing material.Honeycomb packing material 9 adopt hexagons, corrugation shape, tubular type honeycomb ceramics 5 all can, be filled with heat-insulating and sound-proof material 6 in its honeycomb vestibule.
As Fig. 4, the same external wall panel structure of the structure of sloping top board is finally formed by the adiabatic packed layer 12 compound (by bonding) between outer coating panel 11, interior coating panel 13 and outer coating panel and the interior coating panel.
As Fig. 5, the same external wall panel structure of the structure of inner wall panel, finally coating panel 14 and the packed layer between the coating panel of both sides 15 compound (by bonding) by both sides forms.
The structural meterials of side fascia, sloping top board, floor support plate, inner wall panel is with described in the utility model.
As Fig. 6, the house frame structure is common steel work or wooden construction and steel wood combination construction.Type of attachment: steel work is welding, screw connects or welding wire mixes binding.Steel wood combination construction can welding wire, nail etc. mixes and links.The material of steel work can be used H steel, I shaped steel, C shaped steel, rectangular tube or pipe.To exterior wall framework 18, floor support plate framework 17, sloping top frame 16, interior wall framework 19 should be arranged, should leave a door unlocked in advance or the framework of window according to the drawing design according to the known technology mode.
The mounting structure of side fascia can be two kinds of methods described in the utility model.As Fig. 7~10,21 layers of transition heat-insulating bridge-cut-offs are fixed on the outside (Fig. 8) or two sides, the interior outside (Fig. 9) of frame construction, useful binders or screw connect in the time of fixedly.21 layers of the transition heat-insulating bridge-cut-offs of adiabatic packed layer 2 and framework in one plane, then with the slit of periphery in inject fluid sealant 20.After the strippable paper on adiabatic packed layer two sides is thrown off, respectively with outer coating panel and the bonding pressing of interior coating panel.Fix at periphery.
The installation form of slope top board, inner wall panel is identical with the form of structure of side fascia.
The mounting method of integral house is with the above-described method of the utility model.
After testing:
Floor support plate: the bending resistance load of 120 * 3000 * 1200mm specification, up to 1000kg/m 2, surpass nearly 5 times of GB/T50204-2002 minimum essential.
Side fascia (sloping top board): the coefficient of thermal conductivity of the compound external wall panel of 150mm is 0.045W/mK, is equivalent to the insulation of 1500mm brick wall, reaches energy-conservation effect more than 80%.Actual measurement air sound insulation factor is 450dB, therefore has good energy-conservation and defening effect.Fire endurance is according to GB/T9978, and actual measurement fire endurance 1.2h fills heat insulation layer GB/T8624, B1 level nonflammable material, GB/T8627 wherein, smoke density grade≤5.
The ecological house that utilizes the utility model to build is built and finished, and can move in, and is healthy comfortable.After testing, its GB/T18580, burst size of methanal≤0.02mg/L, near zero, negative oxygen ion content up to 5000/more than the L.Specific radioactivity test GB/T6763, healthy and safe, use unrestricted.
The ecological house that utilizes the utility model to build has good whole and shock resistance and anti-hurricane.Can resist nine grades big shakes and ten secondary strong wind (manual simulation) after tested.
The ecological house that utilizes the utility model to build, dry construction does not have the three wastes, does not endanger environment, simultaneously in the lake, complex-terrains such as river shoal and the mountain ridge, basic less investment, speed is fast, and is minimum to ambient influnence, keeps the environment style and features substantially.

Claims (9)

1, a kind of assembled integrated house component is characterized in that comprising house frame structure, side fascia combination, the combination of sloping top board, floor support plate, wherein:
Described side fascia combination comprises the packed layer between outer coating panel, interior coating panel and outer coating panel and the interior coating panel, and the two sides of packed layer has pressure sensitive adhesive and strippable paper,
Described sloping top board combination comprises the packed layer between outer coating panel, interior coating panel and outer coating panel and the interior coating panel, and the two sides of packed layer has pressure sensitive adhesive and strippable paper,
Described floor support plate constitutes by strengthening framework, last coating panel, following coating panel, honeycomb packing material and waterproofing course, inlay the honeycomb packing material in the sash of enhancing framework, compound respectively coating panel, following coating panel, the surface recombination waterproofing course of last coating panel and following coating panel gone up in the two sides of framework and honeycomb packing material.
2, assembled integrated house component according to claim 1 is characterized in that comprising the inner wall panel combination, and the combination of interior wall composite plate comprises the coating panel of both sides and packed layer therebetween, and the two sides of packed layer has pressure sensitive adhesive and strippable paper.
3, assembled integrated house component according to claim 1 is characterized in that described side fascia combination, the combination of sloping top board include the transition heat-insulating bridge-cut-off.
4, assembled integrated house component according to claim 2 is characterized in that described inner wall panel combination comprises the transition heat-insulating bridge-cut-off.
5, a kind of assembled integrated house that utilizes the described assembled integrated house component of claim 1 to form, it is characterized in that by the house frame structure, the side fascia combination, slope top board combination, floor support plate is mutually permanently connected, wherein: the two sides of the packed layer of side fascia combination is thrown off strippable paper and is flushed with the exterior wall framework of house frame structure, filling with sealant in packed layer and the exterior wall frame gap, compound respectively fixing outer coating panel in the both sides of framework and packed layer and interior coating panel, the two sides of the packed layer of slope top board combination is thrown off strippable paper and is flushed with the sloping top frame of house frame structure, filling with sealant in packed layer and the sloping top frame gap, compound respectively fixing outer coating panel in the both sides of framework and packed layer and interior coating panel, floor support plate places on the framework of floor location, fixing between floor support plate and the framework, the seam between the floor support plate is sealed by glue.
6, assembled integrated house according to claim 5, it is characterized in that the exterior wall framework of house frame structure and outside be added with transition heat-insulating bridge-cut-off layer between the coating panel, the packed layer of side fascia combination flushes with transition heat-insulating bridge-cut-off layer, be added with transition heat-insulating bridge-cut-off layer between slope top frame and the outer coating panel, the packed layer of sloping top board combination flushes with transition heat-insulating bridge-cut-off layer.
7, assembled integrated house according to claim 5, it is characterized in that the exterior wall framework of house frame structure and outside be added with transition heat-insulating bridge-cut-off layer between coating panel and the interior coating panel, the packed layer of side fascia combination flushes with transition heat-insulating bridge-cut-off layer, be added with transition heat-insulating bridge-cut-off layer between slope top frame and outer coating panel and the interior coating panel, the packed layer of sloping top board combination flushes with transition heat-insulating bridge-cut-off layer.
8, assembled integrated house according to claim 5, it is characterized in that being provided with the inner wall panel combination, the two sides of the packed layer of inner wall panel combination is thrown off strippable paper and is flushed with the interior wall framework of house frame structure, and the both sides of framework and packed layer are compound fixedly coating panel respectively.
9, assembled integrated house according to claim 8 is characterized in that being added with transition heat-insulating bridge-cut-off layer between the interior wall framework of house frame structure and coating panel, and packed layer flushes with transition heat-insulating bridge-cut-off layer.
CNU2008200162805U 2008-01-08 2008-01-08 Assembly type integrated house component and assembly type integrated house Expired - Fee Related CN201162277Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2008200162805U CN201162277Y (en) 2008-01-08 2008-01-08 Assembly type integrated house component and assembly type integrated house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2008200162805U CN201162277Y (en) 2008-01-08 2008-01-08 Assembly type integrated house component and assembly type integrated house

Publications (1)

Publication Number Publication Date
CN201162277Y true CN201162277Y (en) 2008-12-10

Family

ID=40183215

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2008200162805U Expired - Fee Related CN201162277Y (en) 2008-01-08 2008-01-08 Assembly type integrated house component and assembly type integrated house

Country Status (1)

Country Link
CN (1) CN201162277Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503518A (en) * 2017-08-31 2017-12-22 温州楚天建设有限公司 A kind of operating method of steel house integrated system
CN109162356A (en) * 2018-09-27 2019-01-08 丰和营造集团股份有限公司 A kind of assembling type steel structure exempts from casting concrete building structure
CN113047632A (en) * 2021-04-16 2021-06-29 罗建月 Prefabricated steel-concrete beam, column and floor combined building construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503518A (en) * 2017-08-31 2017-12-22 温州楚天建设有限公司 A kind of operating method of steel house integrated system
CN109162356A (en) * 2018-09-27 2019-01-08 丰和营造集团股份有限公司 A kind of assembling type steel structure exempts from casting concrete building structure
CN113047632A (en) * 2021-04-16 2021-06-29 罗建月 Prefabricated steel-concrete beam, column and floor combined building construction method

Similar Documents

Publication Publication Date Title
US12152389B2 (en) Prefabricated insulated building panel with cured cementitious layer bonded to insulation
CN101158213B (en) Exterior outer-insulating system construction method for using direct-compress EPS inorganic clad plate
CN202017277U (en) Wall structure for light steel villa
CN101265723A (en) Building structure system and construction method assembled from composite building panels
CN100588810C (en) Prefabricated construction method for energy-saving renovation of existing buildings
CN204491984U (en) Stone facing precast wall panel and external wall system
CN201128990Y (en) Composite environment-friendly thermal insulation material for wall
CN104695662A (en) Stone facing prefabricated external wall plate as well as production method and external wall system thereof
CN201162277Y (en) Assembly type integrated house component and assembly type integrated house
CN103469887B (en) A kind of building with blocking external wall system
CN101481927A (en) Assembled integrated house component and building method of integrated house
CN204401814U (en) Light polyurethane heat preservation and decoration of outer wall system
CN201128995Y (en) Direct applying type ESP composite board and exterior wall external insulation system thereof
CN211690738U (en) Cold-formed thin-wall light steel structure building
CN211548402U (en) A kind of fast construction tile roof structure
RU90813U1 (en) ENERGY-SAVING HEAT-INSULATING AND DECORATIVE PANEL
CN215054296U (en) High strength fire prevention heat preservation partition wall structure
CN202108196U (en) Thermal-insulation decoration board for outer wall
CN111101594A (en) A cold-formed thin-walled light steel structure building
CN2479091Y (en) Foam thermal insulatino board for external wall
CN201554133U (en) Composite rock-wool board for assembled keel structure or slope roof
CN204510883U (en) Steel wood combination construction movable combined house
CN205476117U (en) Structure that passive form building parapet bears down on one
CN209227766U (en) A kind of light steel house
CN207700485U (en) Steel structural roof

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20090213

Address after: Room 316, block A, Pioneer Road, 135, Zibo hi tech Development Zone, Shandong, China, 255086

Patentee after: Zibo HaoTe Integrated House Making Co., Ltd.

Address before: Zibo City, Shandong province Linzi Qi Ling Street Industrial Park, Zibo Dayun special project Mstar Technology Ltd, zip code: 255400

Patentee before: Xu Gang

ASS Succession or assignment of patent right

Owner name: ZIBO HAOTE INTEGRATED HOUSE MANUFACTURING CO., LTD

Free format text: FORMER OWNER: XU GANG

Effective date: 20090213

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081210

Termination date: 20100208