CN201129183Y - 小导管分段反复注浆装置 - Google Patents

小导管分段反复注浆装置 Download PDF

Info

Publication number
CN201129183Y
CN201129183Y CNU2007201911676U CN200720191167U CN201129183Y CN 201129183 Y CN201129183 Y CN 201129183Y CN U2007201911676 U CNU2007201911676 U CN U2007201911676U CN 200720191167 U CN200720191167 U CN 200720191167U CN 201129183 Y CN201129183 Y CN 201129183Y
Authority
CN
China
Prior art keywords
grouting
pipe
small conduit
wall
core pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007201911676U
Other languages
English (en)
Inventor
李治国
徐海廷
卓越
孙国庆
邹翀
张炜
杨勇
曹正喜
葛寨辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Technology Research of China Railway Tunnel Group Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CNU2007201911676U priority Critical patent/CN201129183Y/zh
Application granted granted Critical
Publication of CN201129183Y publication Critical patent/CN201129183Y/zh
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本实用新型属于隧道和地下工程软弱围岩超前注浆加固和堵水技术。提出的小导管分段反复注浆装置主要由注浆泵、进浆管(1)和小导管(6)、注浆芯管(4)构成,其中小导管前端为尖锥状结构且封闭,在其管壁上沿管子轴线方向间隔开置有多个溢浆孔(8),在溢浆孔处套置环形橡胶套(7)将溢浆孔封闭,橡胶套位于小导管(6)外壁上开置的环向凹槽内;注浆芯管位于小导管内其前端也为封闭结构,在注浆芯管前段的管壁上具有多个沿管子圆周分布的出浆孔(11),在出浆孔前后两侧的管壁上套置有多个环形止浆塞(9),止浆塞为皮碗式结构,位于管壁上的止浆塞其碗口方向朝向出浆孔,注浆芯管后端通过进浆管与注浆泵连通。本实用新型提出的注浆装置可满足分段反复注浆的需要。

Description

小导管分段反复注浆装置
技术领域
本实用新型属于隧道和地下工程软弱围岩超前注浆加固和堵水技术,主要提出一种小导管分段反复注浆装置。
背景技术
在软弱含水地层中进行隧道和地下工程施工,最容易出现的问题是围岩大变形和坍塌以及开挖面涌水、突泥,危及人员、设备安全,造成伤亡事故,严重时引起地表坍塌,植被破坏,影响居民正常生活,对地面环境造成破坏。为了保证施工安全,目前国内外常用的地层加固和堵水方法为注浆法,注浆法就是通过一定的压力把一定量的胶凝性材料注入岩层或土体,使其在岩层裂缝或土体空隙中流动、扩散、充填、固结,形成有一定强度和低透水性的胶结体,加固地层,封堵地下水,从而提高围岩的自稳定时间,为支护结构的施作创造条件。小导管注浆法为其中的主要方法之一。但现在的小导管注浆法通常采用全孔一次性注浆,无法根据需要进行分段反复注浆;所采用的小导管为钢花管结构,在顶入过程中,泥砂容易沿管子上的孔眼进入钢管,堵塞管子,造成注浆效果不好或注不进浆。
发明内容
本实用新型的目的即是提出一种小导管分段反复注浆装置,使其可满足分段反复注浆的需要。
本实用新型完成其发明任务所采取的技术方案是:其主要由注浆泵、进浆管和小导管、注浆芯管构成,其中小导管前端为尖锥状结构且封闭,在其管壁上沿管子轴线方向间隔开置有多个溢浆孔,在溢浆孔处套置环形橡胶套将溢浆孔封闭,橡胶套位于小导管外壁上开置的环向凹槽内;注浆芯管位于小导管内其前端也为封闭结构,在注浆芯管前段的管壁上具有多个沿管子圆周分布的出浆孔,在出浆孔前后两侧的管壁上套置有多个环形止浆塞,止浆塞为皮碗式结构,位于管壁上的止浆塞其碗口方向朝向出浆孔,注浆芯管后端通过进浆管与注浆泵连通。
本实用新型注浆工作过程:采用风钻钻孔至设计孔深,退出钻杆,将小导管装入钻孔内,用速凝水泥将管口外壁和钻孔内壁之间的空隙封住,将带有皮碗式止浆塞的注浆芯管进入小导管内到设计位置,注浆芯管后端与进浆管、注浆泵连通进行注浆,浆液从注浆芯管前段的出浆孔溢出,进入小导管与注浆芯管之间,在压力作用下位于出浆孔前后两侧的止浆塞膨胀扩张,顶紧小导管内壁,将小导管与注浆芯管外壁之间封闭,浆液将小导管溢浆孔上的橡胶塞冲开,由溢流孔进入地层完成该段注浆;停止注浆后,皮碗式止浆塞泄压内收恢复原状;向后拉动注浆芯管到下一段注浆位置,进行注浆,如此反复后退分段注浆直到该孔注浆结束,退出注浆芯管进行下一孔注浆施工。分段反复注浆使浆液扩散比较均匀,注浆质量容易得到保证。并可根据地层变形情况,反复多次对地层进行加固,获得更好的注浆效果。
本实用新型装置中小导管上的橡胶套可以反复使用,在注浆过程中,当压力达到一定程度冲开卡在溢浆孔上的橡胶套进行注浆,当注浆压力减小时,可以通过橡胶套的弹性关闭溢浆孔,从而在反复注浆施工中达到很好的密封效果;注浆芯管的结构设计可满足后退分段及反复注浆的需要。
附图说明
图1为本实用新型装置使用状态示意图。
图中,1、进浆管,2、进浆阀,3、泄压阀,4、注浆芯管,5、管箍,6、小导管,7、橡胶套,8、溢浆孔,9、止浆塞,11、出浆孔,12、闷盖。
具体实施方式
结合附图对本实用新型实施例加以说明:
如图1所示,本实用新型注浆装置主要包括注浆泵、进浆管1和小导管6、注浆芯管4(图中未显示注浆泵),小导管6前端为尖锥状结构且封闭,在其管壁上具有溢浆孔8,溢浆孔8沿管壁圆周分布且多排溢浆孔沿管子轴线方向间隔分布,溢浆孔处的管壁上环向铣有凹槽,槽内设置橡胶套7,橡胶套7将溢浆孔8封闭;注浆芯管4位于小导管内其前端具有闷盖12构成封闭结构,在注浆芯管4前段的管壁上具有出浆孔11,出浆孔11沿管子圆周分布且多排出浆孔沿管子轴线方向间隔分布,在出浆孔11前后两侧的管壁上分别套置有3个环形止浆塞9,止浆塞9为皮碗式结构,止浆塞的碗口方向均朝向出浆孔11,在出浆孔8前后两侧分别构成三道密封。注浆芯管4后端连接进浆管1并通过进浆管与注浆泵连通;进浆管路上具有进浆阀2和泄压阀3。

Claims (1)

1、一种小导管分段反复注浆装置,其特征是:主要由注浆泵、进浆管(1)和小导管(6)、注浆芯管(4)构成,其中小导管(6)前端为尖锥状结构且封闭,在其管壁上沿管子轴线方向间隔开置有多个溢浆孔(8),在溢浆孔(8)处套置环形橡胶套(7)将溢浆孔封闭,橡胶套(7)位于小导管(6)外壁上开置的环向凹槽内;注浆芯管(4)位于小导管(6)内其前端也为封闭结构,在注浆芯管(4)前段的管壁上具有多个沿管子圆周分布的出浆孔(11),在出浆孔(11)前后两侧的管壁上套置有多个环形止浆塞(9),止浆塞(9)为皮碗式结构,位于管壁上的止浆塞(9)其碗口方向朝向出浆孔(11),注浆芯管(4)后端通过进浆管(1)与注浆泵连通。
CNU2007201911676U 2007-12-29 2007-12-29 小导管分段反复注浆装置 Expired - Fee Related CN201129183Y (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201911676U CN201129183Y (zh) 2007-12-29 2007-12-29 小导管分段反复注浆装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201911676U CN201129183Y (zh) 2007-12-29 2007-12-29 小导管分段反复注浆装置

Publications (1)

Publication Number Publication Date
CN201129183Y true CN201129183Y (zh) 2008-10-08

Family

ID=40017024

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201911676U Expired - Fee Related CN201129183Y (zh) 2007-12-29 2007-12-29 小导管分段反复注浆装置

Country Status (1)

Country Link
CN (1) CN201129183Y (zh)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644469A (zh) * 2012-05-10 2012-08-22 中国矿业大学 一种裂隙发育围岩超深孔超前注浆管及注浆方法
CN103089274A (zh) * 2013-01-15 2013-05-08 河南理工大学 一种可重复注浆加固巷道围岩的方法
CN104653209A (zh) * 2015-01-23 2015-05-27 山东大学 一种多级增阻锚杆及施工方法
CN105731978A (zh) * 2016-01-28 2016-07-06 中铁第四勘察设计院集团有限公司 一种用于细砂层顶进涵掌子面加固的注浆浆液及注浆方法
CN108506027A (zh) * 2018-05-08 2018-09-07 大同煤矿集团有限责任公司 一种煤矿水害防治装置
CN109594951A (zh) * 2019-01-23 2019-04-09 石家庄铁道大学 一种小导管注浆孔口封堵装置及封堵方法
CN110241821A (zh) * 2019-06-17 2019-09-17 中国十七冶集团有限公司 一种倒刺式土层锚杆及其施工方法
CN111733822A (zh) * 2020-07-23 2020-10-02 天津建岩岩土工程有限公司 钻注两用型袖阀管、袖阀管施工结构及施工方法
CN112081107A (zh) * 2020-08-28 2020-12-15 浙大城市学院 降排水定位注浆导管及其使用方法

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102644469A (zh) * 2012-05-10 2012-08-22 中国矿业大学 一种裂隙发育围岩超深孔超前注浆管及注浆方法
CN102644469B (zh) * 2012-05-10 2014-07-16 中国矿业大学 一种裂隙发育围岩超深孔超前注浆管及注浆方法
CN103089274A (zh) * 2013-01-15 2013-05-08 河南理工大学 一种可重复注浆加固巷道围岩的方法
CN104653209A (zh) * 2015-01-23 2015-05-27 山东大学 一种多级增阻锚杆及施工方法
CN105731978A (zh) * 2016-01-28 2016-07-06 中铁第四勘察设计院集团有限公司 一种用于细砂层顶进涵掌子面加固的注浆浆液及注浆方法
CN105731978B (zh) * 2016-01-28 2018-07-31 中铁四院集团岩土工程有限责任公司 一种用于细砂层顶进涵掌子面加固的注浆浆液及注浆方法
CN108506027A (zh) * 2018-05-08 2018-09-07 大同煤矿集团有限责任公司 一种煤矿水害防治装置
CN108506027B (zh) * 2018-05-08 2024-01-05 晋能控股煤业集团有限公司 一种煤矿水害防治装置
CN109594951A (zh) * 2019-01-23 2019-04-09 石家庄铁道大学 一种小导管注浆孔口封堵装置及封堵方法
CN109594951B (zh) * 2019-01-23 2024-04-09 石家庄铁道大学 一种小导管注浆孔口封堵的方法
CN110241821A (zh) * 2019-06-17 2019-09-17 中国十七冶集团有限公司 一种倒刺式土层锚杆及其施工方法
CN111733822A (zh) * 2020-07-23 2020-10-02 天津建岩岩土工程有限公司 钻注两用型袖阀管、袖阀管施工结构及施工方法
CN111733822B (zh) * 2020-07-23 2024-10-29 天津建岩岩土工程有限公司 钻注两用型袖阀管、袖阀管施工结构及施工方法
CN112081107A (zh) * 2020-08-28 2020-12-15 浙大城市学院 降排水定位注浆导管及其使用方法

Similar Documents

Publication Publication Date Title
CN201129183Y (zh) 小导管分段反复注浆装置
CN101251017B (zh) 孔口止浆钻杆分段后退式注浆方法
CN101251019B (zh) 孔口止浆管内混合双管分段后退式注浆方法
CN201133248Y (zh) 孔口密封双管后退式注浆装置
CN105200978B (zh) 一种前进式定域双液注浆装置及施工方法
CN101251018B (zh) 孔口止浆管外混合双管分段后退式注浆方法
CN105507940B (zh) 一种割封压一体化强化瓦斯抽采装置及方法
CN107605498B (zh) 富水砂卵石地层盾构隧道端头水平注浆加固结构施工方法
CN105350519A (zh) 一种适用于砂土层浅埋隧道超前预注浆装置及施工工艺
CN201129184Y (zh) 小导管外阀单向式分段后退注浆装置
CN102003189A (zh) 一种快速均匀加固软弱地层的模袋注浆方法和装置
CN110424892A (zh) 一种矿井近水平定向钻孔的突水治理方法
CN101793154A (zh) 利用隧道围岩地质参数和设置分流孔的注浆堵水方法
CN105649655B (zh) 一种用于从盾构机内往周边地层注浆加固装置
CN205918368U (zh) 钻注一体后退式注浆钻杆
CN202644538U (zh) 一种在富水流砂地层中使用的注浆装置
CN106437612A (zh) 顺层瓦斯抽采钻孔封孔方法及其封孔结构
CN201129177Y (zh) 钻杆后退分段注浆装置
CN116624157A (zh) 一种高水压强渗透地层中水下对接加固方法
CN105443098A (zh) 一种煤矿井下钻孔分段定点水力压裂固孔装置及方法
CN101864968B (zh) 一种用于隧道底地层加固的防喷涌装置及其施工方法
CN204436413U (zh) 一种结合隧道管片对不良地层加固的注浆装置
CN110344784A (zh) 一种矿井近水平定向钻孔的突水治理装置
CN205445634U (zh) 一种用于从盾构机内往周边地层注浆加固装置
CN204551481U (zh) 用于软土地层加固的分段注浆管

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA RAILWAY TUNNEL GROUP TECHNOLOGY RESEARCH CO.

Free format text: FORMER OWNER: ZHONGTIE TUNNEL GROUP CO., LTD.

Effective date: 20140626

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20140626

Address after: 471009 Luoyang City, the old town of Henan champion Red Road, No. 3

Patentee after: China Railway Tunnel Group Technology Research Co., Ltd.

Address before: 471009 Henan province Luoyang Xigong Cemetery Road No. 3

Patentee before: Zhongtie Tunnel Group Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081008

Termination date: 20151229

EXPY Termination of patent right or utility model