[go: up one dir, main page]

CN201125479Y - Ceiling structure for personnel to walking maintaining - Google Patents

Ceiling structure for personnel to walking maintaining Download PDF

Info

Publication number
CN201125479Y
CN201125479Y CNU200720075590XU CN200720075590U CN201125479Y CN 201125479 Y CN201125479 Y CN 201125479Y CN U200720075590X U CNU200720075590X U CN U200720075590XU CN 200720075590 U CN200720075590 U CN 200720075590U CN 201125479 Y CN201125479 Y CN 201125479Y
Authority
CN
China
Prior art keywords
plate
ceiling structure
perforate
receive
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU200720075590XU
Other languages
Chinese (zh)
Inventor
黄建德
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI DERUI METAL PRODUCTS CO Ltd
Original Assignee
SHANGHAI DERUI METAL PRODUCTS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI DERUI METAL PRODUCTS CO Ltd filed Critical SHANGHAI DERUI METAL PRODUCTS CO Ltd
Priority to CNU200720075590XU priority Critical patent/CN201125479Y/en
Application granted granted Critical
Publication of CN201125479Y publication Critical patent/CN201125479Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Floor Finish (AREA)

Abstract

A shockproof fixed structure of the ceiling structure, the closed-edge structure and the suspension structure, is available to the staff for walk and maintenance and comprises an upper plate fixed between the frame and the truss, a median plate vertically positioned at the end of the upper plate, and a bottom plate vertically positioned at the end of the median plate and fixed to a gauge plate of the closed-edge structure, so as to reduce shaking of the ceiling structure which is then fixed firmly on the closed-edge structure to avoid staff falling.

Description

The ceiling structure that can supply personnel to walk and keep in repair
Technical field
The utility model system relevant for a kind of for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, be meant especially a kind ofly be located at toilet's ceiling structure, receive limit structure and overhung construction between, can prevent the ceiling structure vibrations, improve its stability, and Gong the personnel that avoid personnel to drop walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction.
Background technology
As shown in Figure 3, the ceiling 1 of commonly using the toilet comprises: a ceiling structure 7, can be for personnel's maintenance of walking thereon, system is made up of many frameworks 70, comprising: several truss 8a, generally form square, be located at 82 of the flat boards of the bottom of these dividing plate 81 2 sides by a dividing plate 81 and two and form, dividing plate 81 upper and lower parts are provided with the upper and lower slide rail 83,85 that a cross section generally is the T type respectively, and biend is respectively equipped with a screw 84; And several Connection Blocks 9, be connected with in the junction between each truss 8a, formed by the keeper 92 that a base plate 91 and four is fixedly arranged on respectively on the base plate 91; Keeper 92 is provided with a hole 94; And several spiral shell spares 96, be to pass the screw 84 that hole 94 back spiral shells are located at truss 8a; And several overhung constructions 2, comprising: a framework 20 is provided with upper and lower hole 21,22; An and tooth bar 23, the top is fixedly arranged on structure ceiling or upper strata shaped steel (not shown), end is provided with the Safety nut 25 that external screw thread 24 and a spiral shell are located at external screw thread 24, external screw thread 24 pass framework 20 on behind the hole 21, utilize upper cap nut 26 to cooperate Safety nut 25 lockings, use the truss 8a top that framework 20 is suspended in ceiling structure 7; And a fixed screw 27, the top is fixing block 28, terminal pass the following hole 22 of framework 20 by the below after, utilizing down, nut 29 locks; Fixedly block 28 is the last slide rail 83 that is arranged in truss 8a, uses location ceiling structure 7 in predetermined altitude; And several receive limit structure 4, comprising: a plate body 40, generally be the L type, formed by fixed head 41 and generally vertical location-plate 42 with fixed head 41, its fixed head 41 is to utilize screw 43 to be fixedly arranged on predetermined set ceiling structure 7 places on toilet's interseptal board 11, makes location-plate 42 can support ceiling structure 7; Wherein, the truss 8a that is located at the marginal portion has only an end to be provided with bindiny mechanism 6 to be fixedly arranged on Connection Block 9, and the other end system of truss 8a directly is positioned on the location-plate 42 of receiving limit structure 4.
But the overhung construction 2 that is used to locate ceiling structure 7 all positively is not fixed together ceiling structure 7 with receiving limit structure 4, makes that ceiling structure 7 stability are not enough, rocks easily, has a strong impact on personnel's craftmanship; And ceiling structure 7 is not installed in really receives limit structure 4, causes this to locate easy avalanche, and personnel easily drop from here, have a strong impact on the safety of life and property.
In view of this utility model designer is to think hard funiculus, and active research is engaged in the experience that Related product is studied for many years, and the utility model through constantly testing and improvement, developing finally.
The utility model content
The purpose of this utility model provide a kind of reduce Gong personnel that ceiling structure rocks walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction.
Another purpose of the present utility model is providing a kind of ceiling structure can being installed in really to receive on the structure of limit, with the walk shockproof fixed structure of ceiling structure, receipts limit structure and overhung construction of maintenance of Gong the personnel that avoid personnel to drop from here.
One side of the present utility model provide a kind of for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, it is connected with fixture, connector, fixing hole, truss, dividing plate in this ceiling structure, and framework, the fixed screw of overhung construction, and receive between the location-plate of limit structure, comprising:
One top board has first perforate, and the fixed screw of this overhung construction of mat is fixedly arranged between the truss of framework and ceiling structure; And
Plate in one generally vertically is located at this top board end; And
One base plate generally vertically is located in this plate end with respect to this top board
Opposite side, it is to be fixedly arranged on the location-plate of this receipts limit structure.
In specific embodiment of the utility model, provide a kind of for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, should have one second perforate by middle plate, after the connector of this ceiling structure ties up to and passes second perforate, be fixedly arranged on the fixing hole of fixture.
In specific embodiment of the utility model, provide a kind of for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, this base plate has one the 3rd perforate, and one screw rod is set in the precalculated position of the location-plate of this receipts limit structure, after the 3rd perforate is sheathed on screw rod, utilize the positioning screw cap locking again.
In specific embodiment of the utility model, provide a kind of for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, two ends of this truss are respectively equipped with several bindiny mechanisms, it has: a fixture, have a fixing hole that is provided with internal screw thread, be fixedly arranged on dividing plate two ends; And a connection piece, have external screw teeth, after passing keeper, spiral shell is located at the internal screw thread of the fixing hole of fixture.
The beneficial effects of the utility model are: utilize shockproof fixed structure to connect ceiling structure, receive limit structure and overhung construction, use the minimizing ceiling structure and rock, and ceiling structure is installed on the structure of receipts limit really, drop to avoid personnel.
The utility model is for reaching above-mentioned and other purpose, and its technological means of taking, assembly and effect thereof are adopted a preferred embodiment now and cooperated illustration as follows.
Description of drawings
Stereogram when Fig. 1 is assembled in ceiling structure, receipts limit structure and overhung construction for the utility model.
Fig. 2 is an exploded view shown in Figure 1.
Fig. 3 is the schematic diagram of commonly using ceiling structure, receiving limit structure and overhung construction.
[primary clustering symbol description]
1....... ceiling 11...... toilet, toilet interseptal board
2....... overhung construction 20...... framework
21...... hole under the last hole 22......
23...... tooth bar 24...... external screw thread
25...... Safety nut 26...... upper cap nut
27...... fixed screw 28...... is block fixedly
29...... following nut
3....... shockproof fixed structure 33...... top board
34...... plate among the first perforate 35......
36...... the second perforate 37...... base plate
38...... the 3rd perforate
4....... receive limit structure 40...... plate body
41...... fixed head 42...... location-plate
43...... screw
51...... screw rod 52...... positioning screw cap
6....... the 61...... of bindiny mechanism fixture
62...... connector 63...... fixing hole
7....... ceiling structure 70...... framework
8,8a....... truss 81...... dividing plate
82...... dull and stereotyped 83...... goes up slide rail
85...... glidepath 84...... screw
9....... Connection Block 91...... base plate
92...... keeper 94...... hole
96...... spiral shell spare
The specific embodiment
Shown in Fig. 1~2, the shockproof fixed structure 3 of the utility model comprises: a top board 33; And plate 35 in, generally vertically be located at top board 33 ends; And a base plate 37, plate 35 ends are with respect to the opposite side of top board 33 in generally vertically being located at; The shockproof fixed structure 3 of mat connects ceiling structure 7, receives limit structure 4 and overhung construction 2, uses minimizing ceiling structure 7 and rocks, and ceiling structure 7 is installed on the receipts limit structure 4 really, drops to avoid personnel.Hereinafter will know clearly and give explanation.
Top board 33 has one first perforate 34, when assembling, after the fixed screw 27 of overhung construction 2 ties up to the following hole 22 of passing first perforate 34 and framework 20, utilize nut 29 lockings down, so that fixing block 28 be arranged in truss 8 on during slide rail 83, top board 33 can be fixedly arranged between the truss 8 of framework 20 and ceiling structure 7.
In order to improve and the constant intensity of receiving limit structure 4, two ends of truss 8 are respectively equipped with several bindiny mechanisms 6, and it has: a fixture 61, have a fixing hole 63 that is provided with internal screw thread, and be fixedly arranged on dividing plate 81 2 ends; And a connection piece 62, have external screw teeth, after passing keeper, spiral shell is located at the internal screw thread of the fixing hole 63 of fixture 61.
Middle plate 35 has one second perforate 36, in when assembling, after the connector 62 of ceiling structure 7 ties up to and passes second perforate 36, be fixedly arranged on the fixing hole 63 of the fixture 61 that an end and truss 8 fix, wherein these connector 62 1 ends have external screw teeth, can be locked in the internal screw thread of fixing hole 63.
Base plate 37 has one the 3rd perforate 38, when assembling, the precalculated position that lies in the location-plate 42 of receiving limit structure 4 is provided with a screw rod 51, after the 3rd perforate 38 is sheathed on screw rod 51, utilize positioning screw cap 52 lockings again, use that base plate 37 is fixedly arranged on the location-plate 42 of receiving limit structure 4.
In sum, the utility model utilizes top board 33, middle plate 35 and base plate 37 to connect ceiling structure 7 really, receive limit structure 4 and overhung construction 2, can effectively utilize and receive rocking of limit structure 4 minimizing ceiling structures 7, use the craftmanship of increase personnel and facility; And also can avoid personnel to drop, ensure the safety of life and property effectively by receiving structure 4 places, limit.

Claims (4)

  1. One kind can for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, it is characterized in that, it is connected with fixture, connector, fixing hole, truss, dividing plate in this ceiling structure, and framework, the fixed screw of overhung construction, and receive between the location-plate of limit structure, comprising:
    One top board has first perforate, and the fixed screw of this overhung construction of mat is fixedly arranged between the truss of framework and ceiling structure; And
    Plate in one generally vertically is located at this top board end; And
    One base plate generally is located at vertically that plate end is with respect to the opposite side of this top board in this, and it is to be fixedly arranged on the location-plate of this receipts limit structure.
  2. As 1 of claim the described for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, it is characterized in that, should have one second perforate by middle plate, after the connector of this ceiling structure ties up to and passes second perforate, be fixedly arranged on the fixing hole of fixture.
  3. As 1 of claim the described for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, it is characterized in that, this base plate has one the 3rd perforate, and one screw rod is set in the precalculated position of the location-plate of this receipts limit structure, after the 3rd perforate is sheathed on screw rod, utilize the positioning screw cap locking again.
  4. As 1 of claim the described for personnel walk maintenance ceiling structure, receive the shockproof fixed structure of limit structure and overhung construction, it is characterized in that, two ends of this truss are respectively equipped with several bindiny mechanisms, it has: a fixture, have a fixing hole that is provided with internal screw thread, be fixedly arranged on dividing plate two ends; And a connection piece, have external screw teeth, after passing keeper, spiral shell is located at the internal screw thread of the fixing hole of fixture.
CNU200720075590XU 2007-10-19 2007-10-19 Ceiling structure for personnel to walking maintaining Expired - Fee Related CN201125479Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU200720075590XU CN201125479Y (en) 2007-10-19 2007-10-19 Ceiling structure for personnel to walking maintaining

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU200720075590XU CN201125479Y (en) 2007-10-19 2007-10-19 Ceiling structure for personnel to walking maintaining

Publications (1)

Publication Number Publication Date
CN201125479Y true CN201125479Y (en) 2008-10-01

Family

ID=39998900

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU200720075590XU Expired - Fee Related CN201125479Y (en) 2007-10-19 2007-10-19 Ceiling structure for personnel to walking maintaining

Country Status (1)

Country Link
CN (1) CN201125479Y (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI408301B (en) * 2009-07-30 2013-09-11 Chiuho Engineering Co Ltd The improved structure atop a combination between

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TWI408301B (en) * 2009-07-30 2013-09-11 Chiuho Engineering Co Ltd The improved structure atop a combination between

Similar Documents

Publication Publication Date Title
CN201125479Y (en) Ceiling structure for personnel to walking maintaining
CN214839423U (en) Adjustable urban rail transponder mounting bracket set
CN202899051U (en) Acoustic barrier
CN204475978U (en) A kind of assembling column of Assembled surrounding wall
CN212316747U (en) Rail guard of town road construction usefulness
CN203038587U (en) Light-emitting diode (LED) display screen mounting support and ground seats thereof
CN107687282B (en) A kind of assembling type steel structure Self-resetting energy dissipation brace device
CN206753006U (en) A kind of construction scaffold
CN207646599U (en) A kind of queen post steel bridge pier
CN217464349U (en) Solar panel with anti-falling function
CN205688828U (en) A kind of net sheet type foundation ditch guard rail
CN210032540U (en) Steel column installation operation platform
CN210567051U (en) An outrigger leveling mechanism
CN213705109U (en) Adjustable compressor support
CN216042567U (en) Shaping foot baffle of building scaffold
CN207047757U (en) New town road isolation strip device
CN202838845U (en) Light emitting diode (LED) display screen installation device
CN207293227U (en) The fixed structure of shelf rail
CN2893062Y (en) Dismounting bedding course for swimming pool
CN205548107U (en) Two -berth bed accessory that high school used in bedroom
CN221682995U (en) Impact-pressure-resistant combined anchor net rope
CN205822763U (en) A kind of bowl fastening type steel pipe scaffold being easy to assemble
CN217419416U (en) Transmission line buffer stop
CN208137614U (en) A kind of construction protective fence with lighting device
CN211548043U (en) Steel construction anti-wind post

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Huiya Aluminium Alloy Products Co Ltd. Shanghai

Assignor: Shanghai Derui Metal Products Co., Ltd.

Contract record no.: 2010310000087

Denomination of utility model: Ceiling structure for personnel to walking maintaining

Granted publication date: 20081001

License type: Exclusive License

Record date: 20100623

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20081001

Termination date: 20161019

CF01 Termination of patent right due to non-payment of annual fee