[go: up one dir, main page]

CN201057037Y - One-time lifted fracturing string of horizontal well - Google Patents

One-time lifted fracturing string of horizontal well Download PDF

Info

Publication number
CN201057037Y
CN201057037Y CNU2007201694532U CN200720169453U CN201057037Y CN 201057037 Y CN201057037 Y CN 201057037Y CN U2007201694532 U CNU2007201694532 U CN U2007201694532U CN 200720169453 U CN200720169453 U CN 200720169453U CN 201057037 Y CN201057037 Y CN 201057037Y
Authority
CN
China
Prior art keywords
packer
oil pipe
horizontal well
well
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNU2007201694532U
Other languages
Chinese (zh)
Inventor
宫秀坤
王中伟
蒋子龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Downhole Operation Engineering Co Of Jilin Petroleum Refco Group Ltd
Jilin Petroleum Group Co Ltd
Original Assignee
Downhole Operation Engineering Co Of Jilin Petroleum Refco Group Ltd
Jilin Petroleum Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Downhole Operation Engineering Co Of Jilin Petroleum Refco Group Ltd, Jilin Petroleum Group Co Ltd filed Critical Downhole Operation Engineering Co Of Jilin Petroleum Refco Group Ltd
Priority to CNU2007201694532U priority Critical patent/CN201057037Y/en
Application granted granted Critical
Publication of CN201057037Y publication Critical patent/CN201057037Y/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a horizontal well once lifting fractured tubular column, which is applied in the staged fracturing of an oil field horizontal well. The utility model is characterized in that the connection of the horizontal well once lifting fracture tubular column from up to down adopts a guide head, the guide head is connected with a compulsive desterilizing packer, 20 to 100 meters oil pipes is connected at the upper part of the compulsive desterilizing packer, an one-way valve is connected between the 20 to 100 meters oil pipes, a back washing well packer is connected at the upper part of the oil pipe, a hydraulic anchor is connected at the upper part of the back washing well packer, a safety joint is connected at the upper part of the hydraulic anchor, and a heavy weight oil pipe is connected from the upper part of the safety joint to a well mouth. A check valve and a sand blower are connected on the oil pipe between the two packers. The effect of the utility model is that the two packers respectively lock a section of stratus required to be fractured, and different pressure is used to perform construction, and the success ratio is high; the utility model has a back washing function, and has a sand back washing function and a jam release measure, and the working construction is safe; a trip of working tubular column finishes various sections of fracture, the working time is saved, the working cost can be reduced, and the working efficiency is improved.

Description

Horizontal well is once gone up pressure-raising and is split tubing string
Technical field
The utility model relates to oil well fracturing technique field, and particularly a kind of horizontal well in segments fracturing string is carried the tubular column structure that mode realizes a tubing string pressure break multistage stratum on a kind of can the utilization.
Background technology
At present, the oilfield horizontal well pressure break mainly adopts limited entry fracture treatment technology, pitching limited entry fracture treatment technology, liquid gum plug staged fracturing technology and mechanical type staged fracturing technology both at home and abroad.The tubular column structure of mechanical type staged fracturing technology mainly is made up of packer and bridging plug etc.Mechanical type staged fracturing technology is a kind of segmentation reforming techniques method.Adopt mechanical type staged fracturing technology can realize staged fracturing, but this job practices has deficiency, long as the engineering time, complex procedures, operation often, the construction cost height, efficiency of construction is lower, is unfavorable for that carrying out staged fracturing at horizontal well constructs.
The utility model content
The purpose of this utility model is: provide a kind of horizontal well once to go up pressure-raising and split tubing string, realize putting forward on a tubing string purpose on pressure break multistage horizontal well stratum.Satisfy the fractured horizontal well transformation by this tubing string, reduce the fracturing work time, reduce operating cost, improve construction effect.
The technical solution adopted in the utility model is: horizontal well is once gone up pressure-raising and is split tubing string, comprise oil pipe, hydraulic anchor, packer, ball-and-seat and centralizer, it is characterized in that: horizontal well is once gone up pressure-raising, and to split tubing string connection from bottom to top be guide head, guide head connects forces deblocking packer, force deblocking packer, top is connected with the oil pipe of 20-100 rice, in the middle of the oil pipe of this 20-100 rice, be connected with ball-and-seat, the top of oil pipe connects the anti-flushing well packer, the top of anti-flushing well packer connects hydraulic anchor, the top attachment security joint of hydraulic anchor, what the top of safety joint to well head connected is heavy wall tubing.
Split tubing string realization recoil sand technology in order to utilize this horizontal well once to go up pressure-raising, on the oil pipe between anti-flushing well packer and the pressure deblocking packer, be connected with sandblaster.Promptly on the oil pipe between two packers, not only be connected with ball-and-seat, also be connected with sandblaster.
Basic functional principle is: utilize upper and lower two packer single deck tape-recorder pressure break stratum, adopt the liquid filling pressure set packer, stop to annotate the automatic deblocking of fracturing fluid packer; Go up pressure-raising and split tubing string and set another stratum again after finishing a formation breakdown, realize separate stratum fracfturing, one time the utility model tubing string can be finished the job execution of multistage formation breakdown.
The beneficial effects of the utility model: the utility model horizontal well is once gone up pressure-raising and is split tubing string, the specific aim of the well staged fracturing of improving the standard, and twin packer blocks one section stratum that needs pressure break respectively, adopts the different pressures job practices to construct the success rate height.This fracturing string has the backwash function, recoil sand function and unfreezing measure is arranged, job execution safety.One time working string is finished the multistage pressure break, saves activity duration and operation intensity, can lower operating cost, increases work efficiency.
Description of drawings
Fig. 1 is the utility model structural profile schematic diagram.
Among the figure, 1. oil pipe, 2. safety joint, 3. hydraulic anchor, 4. anti-flushing well packer, 5. ball-and-seat, 6. sandblaster is 7. forced deblocking packer, 8. centralizer, 9. guide head, 10. sleeve pipe.
The specific embodiment
Below in conjunction with the drawings and specific embodiments the utility model is described in further detail.
Embodiment 1: consult Fig. 1.The utility model horizontal well is once gone up pressure-raising and is split tubing string, connection from bottom to top, the bottom be a guide head 9, the top of guide head 9 centralizer 8 that is threaded, centralizer 8 tops are threaded one and force deblocking packer 7, force be threaded 80 meters oil pipe of deblocking packer 7 tops.On this oil pipe of 80 meters, be connected with 3 ball-and-seats 5, the top of the oil pipe anti-flushing well packer 4 that is threaded, the top of anti-flushing well packer 4 hydraulic anchor 3 that is threaded, the safety joint 2 that is threaded of the top of hydraulic anchor 3, what the top of safety joint 2 to well head was threaded is that diameter is 62 millimeters a heavy wall tubing 1.Horizontal well is once gone up pressure-raising to be split tubing string and is lowered in the sleeve pipe 10.Anti-flushing well packer 4 and pressure deblocking packer 7 set by of the fracturing fluid pressure.Safety joint 2 is when tubing string is met card, can in time break away from, and prevents pernicious card tubing string accident.
Embodiment 2: consult Fig. 1.Substantially the same manner as Example 1.Difference is to split tubing string realization recoil sand technology in order to utilize this horizontal well once to go up pressure-raising, also is connected with a sandblaster 6 on the oil pipe between anti-flushing well packer 4 and the pressure deblocking packer 7.

Claims (2)

1. a horizontal well is once gone up pressure-raising and is split tubing string, comprise oil pipe (1), hydraulic anchor (3), packer (4), ball-and-seat (5) and centralizer, it is characterized in that: horizontal well is once gone up pressure-raising, and to split tubing string connection from bottom to top be guide head (9), guide head (9) connects forces deblocking packer (8), force deblocking packer (8), top is connected with the oil pipe of 20-100 rice, be connected with ball-and-seat (5) in the centre of this 20-100 rice bran oil pipe, the top of oil pipe connects anti-flushing well packer (4), the top of anti-flushing well packer (4) connects hydraulic anchor (3), the top attachment security joint (2) of hydraulic anchor (3), what the top of safety joint (2) to well head connected is heavy wall tubing (1).
2. horizontal well according to claim 1 is once gone up pressure-raising and is split tubing string, it is characterized in that: be connected with sandblaster (6) on the oil pipe between anti-flushing well packer (4) and the pressure deblocking packer (8).
CNU2007201694532U 2007-06-27 2007-06-27 One-time lifted fracturing string of horizontal well Expired - Fee Related CN201057037Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNU2007201694532U CN201057037Y (en) 2007-06-27 2007-06-27 One-time lifted fracturing string of horizontal well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNU2007201694532U CN201057037Y (en) 2007-06-27 2007-06-27 One-time lifted fracturing string of horizontal well

Publications (1)

Publication Number Publication Date
CN201057037Y true CN201057037Y (en) 2008-05-07

Family

ID=39425878

Family Applications (1)

Application Number Title Priority Date Filing Date
CNU2007201694532U Expired - Fee Related CN201057037Y (en) 2007-06-27 2007-06-27 One-time lifted fracturing string of horizontal well

Country Status (1)

Country Link
CN (1) CN201057037Y (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102884277A (en) * 2010-03-01 2013-01-16 哈里伯顿能源服务公司 Fracturing a stress-altered subterranean formation
CN103857877A (en) * 2011-08-05 2014-06-11 普拉德研究及开发股份有限公司 Method of fracturing multiple zones within a well
CN105178905A (en) * 2015-09-11 2015-12-23 中国石油天然气股份有限公司 A horizontal well bridge plug setting and channeling inspection integrated process string and method
US9915137B2 (en) 2011-08-05 2018-03-13 Schlumberger Technology Corporation Method of fracturing multiple zones within a well using propellant pre-fracturing

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102884277A (en) * 2010-03-01 2013-01-16 哈里伯顿能源服务公司 Fracturing a stress-altered subterranean formation
CN102884277B (en) * 2010-03-01 2016-03-09 哈里伯顿能源服务公司 The method of pressure break subsurface formations and the system for pressure break subsurface formations
CN103857877A (en) * 2011-08-05 2014-06-11 普拉德研究及开发股份有限公司 Method of fracturing multiple zones within a well
CN103857877B (en) * 2011-08-05 2016-06-29 普拉德研究及开发股份有限公司 Method of fracturing multiple zones in a well
US9915137B2 (en) 2011-08-05 2018-03-13 Schlumberger Technology Corporation Method of fracturing multiple zones within a well using propellant pre-fracturing
CN105178905A (en) * 2015-09-11 2015-12-23 中国石油天然气股份有限公司 A horizontal well bridge plug setting and channeling inspection integrated process string and method

Similar Documents

Publication Publication Date Title
CN201802376U (en) Hydraulic sand blasting and non-moving string staged fracturing string for open hole completion
CN103883293B (en) Hydraulic jet radial drilling and fracturing integrating method
CN104373103B (en) A temporary plugging and repeated fracturing pipe string in old well fractures capable of large displacement construction and its method
CN201412133Y (en) Multi-section dragging fracturing process pipe column of horizontal well
CN101560877A (en) Horizontal well packer staged fracturing technology tube pillar
CN201057037Y (en) One-time lifted fracturing string of horizontal well
CN103899264A (en) Lift prestress ground anchor device for well cementation and completion on top of screen pipe of oil-gas well and application method
CN105178910A (en) A horizontal well water plugging process string and method
CN203961938U (en) Packer staged fracturing technology tube pillar in a kind of horizontal well tube
CN201386510Y (en) Hydraumatic self- sealed self-locking window-opening integrated whipstock
CN201301694Y (en) Hydraulic jet pump separate zone oil production process pipe string
CN202707024U (en) Immovable separate stratum fracture technology pipe column
CN105178909A (en) A continuous water plugging process string and method for horizontal wells
CN203614088U (en) Gas-well two-layer fracturing tool
CN204371286U (en) A temporary plugging refracturing string in old well fractures that can be constructed with large displacement
CN204041042U (en) A kind of coiled tubing drag fracturing tubing string
CN201013255Y (en) Releasing joint
CN203081367U (en) Large drift diameter hollow ground anchor for oil and gas well cementation and completion practice
CN216588708U (en) Hydraulic top cutting device
CN204851208U (en) Sliding sleeve packer staged fracturing device
CN204591240U (en) Natural gas well pressure break or acidifying foam return comb post
CN201358744Y (en) Well head pressing and sealing device of oil-water well
CN201037387Y (en) Hydraulic pipe pulling equipment
CN202745799U (en) Large-diameter self-locking packer
CN201943623U (en) Oil pipe hydraulic jacking struck releasing device for ocean oil gas producing platform well repairing

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20080507

Termination date: 20120627