The preparation method of assembling reinforcement concreting building facilities behind elder generation's system facing
(1) technical field:
The present invention relates to the preparation method of a class building facilities, specifically the preparation method of the building facilities of assembling reinforcement concreting behind elder generation's system facing.Be applicable to the kitchen range top, chopping board, operating desk, the Xi Chi in kitchen, the washstand of washroom, the lavatory cuts off, dining room dinner shopping table, laboratory operation platform etc.
(2) background technology:
In the present construction work, facilities such as the washstand of the kitchen range top in kitchen, chopping board, operating desk, Xi Chi, washroom, lavatory partition, dining room dinner shopping table, laboratory operation platform all are constructions of carrying out structure earlier, use brick support, precast rc slab is installed, carry out the construction of architectural surface after plastering again, less expensive, ornamental and practicality is relatively poor, be a kind of low-grade product.The work progress more complicated, and can not construct continuously, need expend a large amount of stand-by period, operating efficiency is not high.
What have then is the finished product kitchen cabinet, use woodwork or stone material to do frame construction, stone material is done the cabinet face, wood product structure surface spary paint or paste PLASTIC LAMINATED, or be: 94207453.x as application number, the utility model patent that is called " a kind of kitchen kitchen cabinet " is disclosed, by casing, building stones sheet material, tack coat constitutes, casing is by side plate, chamber door, the case pin, cover plate constitutes, and on the cover plate face, is coated with the last layer tack coat, building stones sheet material is placed on it, cover plate and building stones sheet material are bonded into one, play the effect of decoration, increase attractive in appearance, the effect of nature, simultaneously, building stones sheet material has solid sense, firmly, can carry out operation firmly thereon, and easy to clean, be not afraid of boiling hot, but this class kitchen cabinet price generally all compares expensive, and adopts the surface of wooden structure not water-fast, is subjected to cargo sweat easily.
(3) summary of the invention:
The present invention will provide simple, the ornamental and practicality of a kind of manufacture craft better and can accomplish the preparation method of the building facilities of assembling reinforcement concreting behind the facing of system earlier of construction continuously.
The preparation method of the building facilities of assembling reinforcement concreting behind elder generation's system facing, its fabrication and installation step is as follows:
1) according to the building facilities real size cutting of design, the finish material that processing is used for facing; And then be ready to materials such as reinforcing bar, cement, sand, rubble;
2) according to the building facilities that designs, the finish material that will be used for facing is adhered to one another with cementing agent, builds the framework of building facilities;
3) assembling reinforcement in the framework that builds, and concreting;
4) be pasted on the concrete of building with the end face sheet material of plain cement mortar building facilities;
5) other members such as cabinet door, drawer, natural curing concrete are installed.
The preparation method of the building facilities of assembling reinforcement concreting behind elder generation's system facing, the job practices uniqueness that is adopted, the work progress advantages of simple, take the finish material of first fabrication and installation building facilities, assembling reinforcement again, and poured in place concrete, simple in structure, both save a large amount of templates, saved cost of labor again.When facilities such as the washstand of the kitchen range top, the operating desk in building kitchen, washroom, lavatory partition, dining room dinner shopping table, laboratory operation platform, finish material should adopt materials such as stone material or glazed ceramic wall tile as far as possible, it is elegant in appearance so not only to seem, can also prevent fire, prevent damaging by worms and can prevent that the surface is out of shape owing to making moist, and be easy to clean.In when construction,, should be earlier the finish material of fritter be bonded to an integral body securely with cementing agent when decorative cover during greater than the dimensions of finish material, cut by the size that designs again, so both can reduce construction sequence, save time, and make integral body seem attractive in appearance again; If certainly with the bulk stone material of monoblock or ceramic tile then better effects if.For example can make the stone slab or the ceramic tile (or claiming ceramic materials) of different size and shape in advance according to different designs, the framework that direct bonding one-tenth designs when using like this gets final product.Formerly make in the work progress of the preparation method of the building facilities of assembling reinforcement concreting behind the facing, the finish material that adopted cementing agent directly will be used to decorate is before this pasted mutually according to the structure that designs, because cementing agent is that Pasting is firm in the very short time, can carry out next step operation thereafter, saved the engineering time so significantly, can accomplish to construct rapidly, continuously; And after concreting is good, need not treat that it ties firmly fully, just available water mud is pasted the top decoration panel thereon.In whole construction course, can compact the connection between each construction sequence and needn't rest on a construction sequence and wait as long for, more need not as former construction technology, after building up frame construction, need to wait for its dry and hard fully after, just can carry out decorative faced layer and other operation, this new technology had both realized and can construct continuously, save the engineering time, improved operating efficiency significantly.The force structure of facility adopts steel concrete, and the configuration of reinforcing bar and concrete intensity, thickness design according to the structure stress feature, and load-carrying members meet mechanics principle more, and structure is more sturdy and durable.Can also install thereon cabinet door, drawer, etc. other members, mounting method can be laid the fixing method of expansion glue self-tapping screw with getting into the cave, as the continuity that will guarantee to construct, should be in advance at the finish material upper drill hole and lay expansion glue.
(4) description of drawings
Fig. 1 for build kitchen range, chopping board with the method for the invention, when washing the pond, the stickup schematic diagram of ground and wall coverings sheet material;
Fig. 2 is the finish material of a vertical direction supporting member structural representation adhered to one another;
At the bottom of Fig. 3 is the plate of horizontal direction force member, the structural representation of plate side and hole to be provided oral-lateral edging flooring bonding;
Fig. 4 is the structural representation behind the assembling reinforcement concreting in the framework that builds.
(5) specific embodiment:
Below with the building kitchen range, chopping board, wash the pond be example in conjunction with the accompanying drawings, specify technical scheme of the present invention.The used finish material 1 of present embodiment is stone slab or glazed ceramic wall tile, with the stone material cementing agent that finish material 1 is adhered to one another firm earlier, build the structural framing of facility, and the cementing agent that adopts can be selected the cementing agent of any bonding stone material, ceramic tile for use, strong man's board cloud stone glue as the production of Shanghai strong man's cementing agent Co., Ltd, if need more firm bonding, the strong man's board AB glue that then can select for use the said firm to produce, certainly also can select other cementing agent for use, but so that each panel bonding firmly is advisable.
At first carry out architectural design, can design voluntarily, also can select for use or reference country and the local building structure that designs the building standard atlas of publishing picture, change brick support into concrete 2, all the other structures all can adopt national standard atlas, as the general building standard design of ALFISOL IN CENTRAL " building fittings atlas ".Real size by design is cut, is processed the stone slab or the glazed ceramic wall tile that are used for the facility decoration, is ready to materials such as reinforcing bar, cement, sand, rubble again.
To be used at the bottom of ground or the cabinet and the finish material 1 usefulness cement paste of metope or cement mortar and ground and metope are pasted, when requiring certain discrepancy in elevation is arranged at the bottom of the cabinet, can spread a layer concrete 2 on the ground, on concrete 2, paste again with ground; Metope finish material 1 can adopt the method for directly pasting or adopt extension subsides cement injection mortar with cement paste.
With stone material cementing agent secure bond, needn't wait the cement mortar on metope and ground to harden fully during bonding between the finish material 1 that the finish material 1 of vertical direction supporting member surface layer and ground and metope have been pasted, can adopt the method for continuous construction.
The decorative cover of the finish material 1 at the bottom of the horizontal primary structure member plate is firm with the finish material 1 mutual bonding of mounted vertical direction down, this plate pavcilion flooring 1 adds will reserve the reservation hole 4 that pond or other members are installed man-hour, with the finish material 1 of horizontal primary structure member plate side and finish material 1 at the bottom of the plate mutually bonding firmly, bonding is firmly mutually will to be used to install finish material 1 and the finish material 1 at the bottom of the plate on hole to be provided limit of pond or other members.
The reinforcing bar of colligation primary structure member, concreting 2 in the framework that builds, present embodiment adopts magma or cement screed, on 2 of concrete after the levelling, paste finish material 1 surface layer at top with cement paste, for constructing continuously, concrete 2 should be selected harsh concrete for use, so that carry out the construction of end face finish material 1.The configuration of the intensity of reinforcing bar 3, concrete 2, thickness and reinforcing bar 3 is designed and constructed according to building structural design specification or the reference standard atlas.
Install cabinet door, drawer, etc. other component and fittings, mounting method is: get into the cave in the corresponding position at finish material 1, lays expansion glue, with self-tapping screw the member of installing fixed.As the continuity that will guarantee to construct, should on finish material 1, get into the cave like clockwork in advance and lay expansion glue.