[go: up one dir, main page]

CN1239796C - Building structural element - Google Patents

Building structural element Download PDF

Info

Publication number
CN1239796C
CN1239796C CNB028112539A CN02811253A CN1239796C CN 1239796 C CN1239796 C CN 1239796C CN B028112539 A CNB028112539 A CN B028112539A CN 02811253 A CN02811253 A CN 02811253A CN 1239796 C CN1239796 C CN 1239796C
Authority
CN
China
Prior art keywords
flange portion
building
beams
pair
cementitious material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CNB028112539A
Other languages
Chinese (zh)
Other versions
CN1524149A (en
Inventor
N·包那西
S·G·罗西特
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BONACCI GROUP Pty Ltd
Original Assignee
BONACCI GROUP Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AUPR5481A external-priority patent/AUPR548101A0/en
Application filed by BONACCI GROUP Pty Ltd filed Critical BONACCI GROUP Pty Ltd
Publication of CN1524149A publication Critical patent/CN1524149A/en
Application granted granted Critical
Publication of CN1239796C publication Critical patent/CN1239796C/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/29Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures
    • E04C3/293Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces built-up from parts of different material, i.e. composite structures the materials being steel and concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B5/00Floors; Floor construction with regard to insulation; Connections specially adapted therefor
    • E04B5/16Load-carrying floor structures wholly or partly cast or similarly formed in situ
    • E04B5/17Floor structures partly formed in situ
    • E04B5/23Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated
    • E04B5/29Floor structures partly formed in situ with stiffening ribs or other beam-like formations wholly or partly prefabricated the prefabricated parts of the beams consisting wholly of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • E04C3/20Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
    • E04C3/26Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Chemical & Material Sciences (AREA)
  • Composite Materials (AREA)
  • Building Environments (AREA)
  • Rod-Shaped Construction Members (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

A building structural element (1) having a pair of beams (5) joined by a plate member (13) or alternatively a generally U-shaped channel having a pair of opposed side walls (33, 34) joined by a further portion (35). In either case an interior space (57) is defined by either the pair of beams (5) and plate member (13) or by the pair of side walls (33, 34) and the further portion (35). A cementitious material, such as concrete, occupies a substantial volume of the interior space (57) and the building structural element (1) has a post-tensioned pre-stressing force applied thereto.

Description

建筑物的结构构件及其制作方法Structural components of buildings and methods of making the same

技术领域technical field

本发明涉及一建筑物的结构构件和制作建筑物结构构件的方法。具体来说,本发明涉及用于建筑物楼板系统内的建筑物的结构构件和制作这样构件的方法。The invention relates to a structural element of a building and a method of making a structural element of a building. More particularly, the present invention relates to structural elements for use in buildings within building floor systems and methods of making such elements.

本发明还可用于许多其它建筑用途,例如,在公路隧道、铁路轨道等上方的顶棚盖。它可用于大型多跨楼板空间,特别是层与层之间的尺寸高、和/或沿一个或两个方向的大跨度、和/或诸如用于零售业、娱乐业或其它用途的楼板上的楼板载荷高的楼板空间。它还可用于桥面和大跨度和/或在支承之间必须承载高载荷的任何其它的用途。The invention can also be used in many other construction applications, eg roof coverings over road tunnels, railway tracks and the like. It can be used for large multi-span floor spaces, especially with high floor-to-story dimensions, and/or large spans in one or two directions, and/or on floors such as those used for retail, entertainment, or other uses. Floor spaces with high floor loads. It can also be used for bridge decks and large spans and/or any other application where high loads must be carried between supports.

本发明的一特殊的方面涉及用于建筑物楼板系统的建造中的楼板梁,并且较佳地由两种部件组合件制成,较佳地由钢材和诸如混凝土之类的水泥质材料制成。A particular aspect of the invention relates to floor beams for use in the construction of building floor systems and is preferably made from an assembly of two components, preferably steel and a cementitious material such as concrete .

背景技术Background technique

对于跨度超过8至10米的建筑物的楼板系统,通常要求有梁。上述跨度一般是对于结构支承可不需使用梁而延伸楼板的上界范围或限值。支承柱通常间隔6至9米,其中普通的间距是8.4米。这是一种合适的办公楼模块,其容纳一柱加上三个空间的宽度,所述空间可用于车辆停放在两个相邻柱之间,并可用作建筑物的办公室楼板(或零售业楼层楼板、机构楼层楼板或其它楼板)下面的任何停放层。要求诸梁在四柱的网格之间或在建筑物和一多层建筑物的核芯或中心部分外面的一对外柱之间,来横跨一矩形楼板的较大的尺度。核芯通常用来容纳电梯井和各层面上的人们可进入的其它的公共空间。横跨在这些梁之间的楼板系统可以并确实可呈许多种形式,其取决于就地的取材、经济性和业主、工程师或建造者的偏好,或上述三方中任何一方偏好的一种组合。Beams are usually required for floor slab systems in buildings spanning more than 8 to 10 metres. The above spans are generally upper bounds or limits on how far a floor can be extended for structural support without the use of beams. The support columns are usually spaced 6 to 9 meters apart, with a common spacing of 8.4 meters. This is a suitable module for an office building that accommodates one column plus the width of three spaces that can be used for vehicle parking between two adjacent columns and can be used as the building's office floor (or retail any parking level below the commercial floor, institutional floor, or other floor). Beams are required to span the larger dimension of a rectangular floor between a grid of four columns or between a building and a pair of outer columns outside the core or central portion of a multistory building. The core is typically used to accommodate elevator shafts and other public spaces accessible to people on all levels. The slab system spanning these beams can and does take many forms, depending on site availability, economics, and the preferences of the owner, engineer, or builder, or a combination of the preferences of any of these three parties .

沿一个方向在支承梁之间的跨度约为8米的楼板系统,其各种变化的形式有:在传统的模板上或大的平台模上形成的混凝土板,在金属托架上的混凝土板,这些金属托架临时支持在支承、靠近中心(2.1至3.0米)的钢次梁上,次梁在无支持的金属托架模板上支承相对薄的板。还有一些诸如各种预应力厚板系统的其它的专用系统,它们能跨越7至8米无支承的距离。Floor system spanning about 8 meters in one direction between supporting beams in various variations: concrete slabs formed on conventional formwork or large platform forms, concrete slabs on metal brackets , these metal brackets are temporarily supported on supported, near-centre (2.1 to 3.0 m) steel secondary beams that support relatively thin slabs on unsupported metal bracket formwork. There are also other specialized systems such as various prestressed slab systems which can span unsupported distances of 7 to 8 meters.

对于支承梁来说,适合于钢筋混凝土浅箍梁的上限范围约为10至12米。对于预应力的浅箍梁(通常是后张拉的),适用性的上限范围通常为12至14米。然而,对于超过12至14米的跨度,则需要特别的关注和留心细节,普通的解决方案是钢楼板梁或预应力混凝土楼板梁。For supporting beams, the upper range suitable for reinforced concrete shallow hooped beams is about 10 to 12 meters. For prestressed shallow hooped beams (usually post-tensioned), the upper limit of applicability is usually in the range of 12 to 14 metres. However, for spans longer than 12 to 14 metres, special attention and attention to detail are required and common solutions are steel or prestressed concrete floor beams.

在钢楼板梁系统中,有一系列中心间距为2.1至3.0米的钢梁,它们跨越矩形楼板平面布置图的较大的距离,并由跨越支承柱之间较短距离的“主”梁支承。大多数工程师或设计师所面临的特殊问题是,在使用楼板梁的系统中,要求减小各梁由于静载或活载或两者的组合引起的挠度量。楼板系统的不必要的大挠度和振动会影响楼板的适宜性。In a steel floor beam system, there are a series of steel beams spaced 2.1 to 3.0 meters on center that span the larger distances of a rectangular floor plan and are supported by 'main' beams that span the shorter distances between supporting columns. A particular problem faced by most engineers or designers is the need to reduce the amount of deflection of each beam due to dead or live loads, or a combination of the two, in systems using floor beams. Unnecessarily large deflections and vibrations of the floor system can affect the suitability of the floor.

采用目前使用的钢楼板梁系统,不利的是,各梁在其支承处需要坚固的连接。梁和连接处通常要求涂覆保护性的涂层以使其能防火。尽管可使这种钢楼板梁与用剪切短柱进行支承的相对薄的楼板组合起作用,但由于混凝土和剪切短柱分界面处的蠕变,存在着静载挠度的一个小的、不断发展的分量。由静载引起的钢梁的挠度大多数在载荷一作用时就发生,并可允许梁的预起拱来抵消。然而,由于瞬态的活载引起的挠度和振动仍然是一固有的问题,尤其是对于较大跨度的梁,因为组合钢梁的刚度比用于相同跨度的钢筋混凝土梁或预应力混凝土梁的刚度小。A disadvantage of the currently used steel floor beam systems is that the individual beams require strong connections at their supports. Beams and joints often require a protective coating to make them fire resistant. Although such steel floor beams can be made to function in combination with relatively thin slabs supported by shear studs, there is a small, small amount of static deflection due to creep at the concrete and shear stud interface. Evolving heft. Most of the deflection of the steel beam caused by the static load occurs as soon as the load is applied, and can be offset by the pre-arching of the beam. However, deflection and vibration due to transient live loads remain an inherent problem, especially for longer-span beams, since composite steel beams are stiffer than those used for reinforced or prestressed concrete beams of the same span The stiffness is small.

目前一般使用的其它类型的楼板梁系统有后张拉的、预应力混凝土楼板梁系统。它们包括具有深的高宽比的混凝土梁,换句话说,混凝土梁的尺寸是其高度大于其宽度,并且对于跨度超过10米的梁,这些混凝土梁通常为预应力的。混凝土梁与它们所支承的板是现浇。然后,通过在混凝土通常在浇注3至6天内已达到足够的强度时施加应力的后张拉钢筋束(tendon)来实现预应力。混凝土梁和相邻的板通常在大的平台模板上形成,这些平台模板由吊车从一个楼板提升到另一楼板。通常采用两组平台,来保持较佳的约一周的楼板的循环,在一半楼板区域浇注的同时,提供其它各种作业的工作连续性。除了梁的钢筋骨架(它可以包括或不包括预应力钢筋)之外,很少有预制件的可能。任何预制的钢筋骨架需要很好地撑牢和放在支架上,以便能被吊车吊到梁的模板内。一般来说,当混凝土将梁连接到支承柱上时,在梁的支承处不存在困难的连接。当一现浇的混凝土梁支承在已在主楼板前“跳过形成”的混凝土核芯时,该连接可以是一在混凝土核芯的壁面内的简单的凹凸榫,在梁的顶部和底部的钢筋旋入到锚固在混凝土核芯内的箍中。或者,梁可坐落在留在混凝土心壁内的凹穴中。Other types of floor beam systems in general use today are post-tensioned, prestressed concrete floor beam systems. They include concrete beams with a deep aspect ratio, in other words concrete beams sized such that their height is greater than their width, and for beams spanning over 10 metres, these concrete beams are usually prestressed. The concrete beams and the slabs they support are cast in situ. Prestressing is then achieved by post-tensioning tendons that apply stress when the concrete has reached sufficient strength, usually within 3 to 6 days of pouring. Concrete beams and adjacent slabs are usually formed on large deck forms that are lifted from one slab to the other by cranes. Two sets of platforms are usually used to maintain a good cycle of the slab for about one week, and to provide continuity of work for various other operations while pouring half of the slab area. Apart from the reinforced skeleton of the beams (which may or may not include prestressing reinforcement), there is little possibility of prefabrication. Any prefabricated steel skeleton needs to be well braced and resting on supports so that it can be hoisted into the beam formwork by a crane. In general, when concrete joins beams to support columns, there are no difficult connections at the supports of the beams. When a cast-in-place concrete beam is supported on a concrete core that has been "jump formed" before the main floor slab, the connection can be a simple tenon and tenon in the walls of the concrete core, with reinforcement at the top and bottom of the beam Screwed into hoops anchored in the concrete core. Alternatively, the beams may sit in pockets left in the concrete core.

预应力混凝土楼板系统的刚度比跨越同样距离所需的钢楼板梁系统的刚度大,因此,不易发生因瞬时载荷所引起的楼板振动和挠曲。然而,当混凝土在持续载荷作用下发生蠕变时,楼板被占用之后楼板系统所发生挠曲增加,其原因不仅在于活载和轻质的隔断,而且在于因蠕变分量由静载引起的显著的挠度份额。预应力可平衡只是静载引起的大部分的挠度。然而,由于轴向预应力赋予梁永久的轴向力,因随时间而形成的缩短,会引起预应力的丧失,这将导致梁的进一步挠曲增大。Prestressed concrete floor systems are stiffer than steel floor beam systems required to span the same distance and are therefore less prone to floor vibration and deflection due to transient loads. However, when the concrete creeps under sustained load, the deflection of the slab system increases after the slab is occupied, not only because of live loads and light partitions, but also because the creep component is significantly increased by static loads. deflection share. Prestressing balances most of the deflection due to static loads only. However, since the axial prestress imparts a permanent axial force to the beam, the shortening over time causes a loss of the prestress, which leads to further increased deflection of the beam.

发明内容Contents of the invention

本发明的一个目的是提供一建筑物的结构构件,其基本上克服上述的一个或多个缺点。具体来说,本发明提供一建筑物的结构构件,其具有最小的挠度,并基本上保持其中的轴向的预应力,且减小由于如现有技术中系统的使梁缩短的轴向蠕变引起的这种预应力的丧失。It is an object of the present invention to provide a structural element of a building which substantially overcomes one or more of the aforementioned disadvantages. Specifically, the present invention provides a structural member of a building that has minimal deflection and substantially maintains axial prestress therein and reduces axial creep due to beam shortening as in prior art systems. The loss of this prestress caused by the change.

根据本发明的第一方面,提供一建筑物的结构构件,其包括:According to a first aspect of the present invention there is provided a structural element of a building comprising:

一对梁,在所述成对梁中的各个梁具有一第一翼缘部分、一第二翼缘部分、以及一在所述第一翼缘部分和所述第二翼缘部分之间延伸的腹板部分;a pair of beams, each beam in the pair having a first flange portion, a second flange portion, and a flange extending between the first flange portion and the second flange portion the web part;

一板件,其适于与各梁的所述第一翼缘部分或所述第二翼缘部分中一个部分接合,这样,在所述成对梁中的各梁和所述板件内形成一内部的空间;a plate adapted to engage with one of said first flange portion or said second flange portion of each beam such that a an internal space;

其中,水泥似的材料占据所述内部空间的主要容积,以形成一非整体的建筑物结构构件,且在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。Wherein, the cement-like material occupies the main volume of the interior space to form a non-integral building structural member, and after post-tensioning prestress is applied, under static load, the structural member of the building With residual deflection or no deflection.

建筑物的结构构件还可包括沿内部空间的长度延伸的一根或多根钢筋,所述空间形成在各梁和可以是金属托架形式拱腹的所述板件之间。各一根或多根钢筋可以施加预应力,以提供一抵消一部分静载的向上方向的力。在结构构件在各端固定之后,各梁的第一翼缘部分可支承楼板跨度的一部分。通常地,结构构件可在一柱和一建筑物的核芯之间延伸。结构构件可在离核芯一短距离和离柱一短距离处终止,或者在各端离一柱的一短距离出终止,并在其端部、也可以还在跨中处暂时地支承在脚手架上。The structural members of the building may also include one or more steel bars extending the length of the interior space formed between the beams and the panels which may be metal bracket form soffits. Each of the one or more bars may be prestressed to provide an upwardly directed force which counteracts a portion of the dead load. The first flange portion of each beam may support a portion of the floor span after the structural member is secured at each end. Generally, structural members may extend between a column and the core of a building. Structural members may terminate at a short distance from the core and a short distance from the columns, or at each end a short distance from a column, and be temporarily supported at their ends, and possibly also at mid-span on scaffolding.

各梁较佳地由诸如钢材之类的金属构成,而水泥质材料较佳地是混凝土。The beams are preferably constructed of metal such as steel and the cementitious material is preferably concrete.

根据本发明的第二方面,提供一建筑物的结构构件,其包括:According to a second aspect of the present invention, there is provided a structural member of a building comprising:

一对梁,在所述成对梁中的各个梁具有一顶部翼缘部分、一底部翼缘部分、以及在所述顶部翼缘部分和所述底部翼缘部分之间延伸的一腹板部分;a pair of beams, each beam in the pair having a top flange portion, a bottom flange portion, and a web portion extending between the top flange portion and the bottom flange portion ;

一板件,其适于与所述成对梁中的各梁的对应的底部翼缘部分接合,这样,在所述成对梁中的各梁和所述板件内形成一内部的空间;a plate adapted to engage a corresponding bottom flange portion of each of said pair of beams such that an interior space is formed within each of said pair of beams and said plate;

其中,水泥质材料占据所述内部空间的主要容积,以形成一非整体的建筑物结构构件,在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。Wherein, the cementitious material occupies the main volume of the inner space to form a non-integral building structural member, and after applying post-tension prestress, the structural member of the building has residual deflection or no deflection.

板件可以是金属托架形式拱腹,或其它合适的水平拱腹表面。The panels may be metal bracket form soffits, or other suitable horizontal soffit surfaces.

根据本发明的第三方面,提供一建筑物的结构构件,其包括:According to a third aspect of the present invention, there is provided a structural member of a building comprising:

一大致呈U形的槽装置,其具有一对相对的侧壁以及另一连接各侧壁的部分;a generally U-shaped trough means having a pair of opposing side walls and another portion connecting the side walls;

其中,所述成对的相对的侧壁和另一部分形成一内部空间;以及wherein the pair of opposite side walls and the other portion form an interior space; and

其中,水泥质材料占据所述内部空间的主要容积,以在该槽装置内形成一非整体的建筑物结构构件,在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。wherein the cementitious material occupies the main volume of said interior space to form a non-integral building structural element within the trough device, said building being under static load after application of a post-tensioned prestress of structural members have residual deflection or no deflection.

根据本发明的第四方面,提供一制作建筑物结构构件的方法,其包括如下诸步骤:According to a fourth aspect of the present invention, there is provided a method of making a building structural member, which includes the following steps:

构造一对梁,在所述成对梁中的各个梁包括一第一翼缘部分、一第二翼缘部分、以及在所述第一翼缘部分和所述第二翼缘部分之间延伸的一腹板部分;constructing a pair of beams, each beam in the pair comprising a first flange portion, a second flange portion, and extending between the first flange portion and the second flange portion a web portion of;

形成和组装一板件,以使板件与各梁的所述第一翼缘部分或所述第二翼缘部分中一个部分接合,这样,由所述成对梁和板件形成一内部的空间;以及forming and assembling a panel so that the panel engages one of said first flange portion or said second flange portion of each beam such that an internal space; and

将水泥质材料浇注到所述内部空间,以形成一非整体的建筑物结构构件,这样,在所述水泥质材料硬化和施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件基本上无挠度。pouring cementitious material into said interior space to form a non-integral building structural member such that, after said cementitious material has hardened and post-tensioned prestressed, said building The structural members of the object are basically deflection-free.

浇注的步骤可以单独地进行,或作为浇注结构构件所支承的相邻的楼板跨度的一部分。结构构件可沿跨度利用可能的额外的支承,使其端部起初支承在邻近梁的永久端部支承的暂时的支承结构上。The pouring step may be performed separately, or as part of pouring the adjacent floor spans supported by the structural member. Structural members may utilize possible additional support along the span with their ends initially supported on temporary support structures adjacent to the permanent end supports of the beams.

附图说明Description of drawings

下面将参照附图以例子的方式来描述本发明的优选的实施例,诸附图中:Preferred embodiments of the present invention will be described below by way of example with reference to the accompanying drawings, in which:

图1是在一建筑物的核芯墙和建筑物的一边缘之间延伸的一建筑物楼板系统的部分的平面图;1 is a plan view of a portion of a building floor system extending between a core wall of a building and an edge of the building;

图2分解成图2A和2B,是沿图1的线A-A截取的侧视截面图;FIG. 2 is exploded into FIGS. 2A and 2B and is a side sectional view taken along line A-A of FIG. 1;

图3是沿图2的线B-B截取的、根据本发明一实施例的在使用中的结构构件的截面图;Figure 3 is a cross-sectional view of a structural member in use according to an embodiment of the present invention, taken along line B-B of Figure 2;

图4是沿图2的线C-C截取的、在使用中的结构构件的截面图;Figure 4 is a cross-sectional view of the structural member in use, taken along line C-C of Figure 2;

图5是类似于图3且根据另一实施例的在使用中的结构构件的截面图;Figure 5 is a cross-sectional view of a structural member in use similar to Figure 3 and according to another embodiment;

图5(a)至5(d)是图5中结构构件的侧视图,示出结构构件的单独的各种情况;Figures 5(a) to 5(d) are side views of the structural member in Figure 5, showing individual instances of the structural member;

图6是类似于图4在使用中的结构构件的另一实施例的截面图;Figure 6 is a cross-sectional view similar to Figure 4 of another embodiment of a structural member in use;

图7是示出应用于一隧道盖板的结构构件的侧视截面图;7 is a side sectional view showing a structural member applied to a tunnel cover;

图8是一现有技术的预制的结构构件的侧视图;以及Figure 8 is a side view of a prior art prefabricated structural member; and

图9示出带有次支承梁的横贯一楼板跨度的结构构件的平面图和侧视图。Figure 9 shows a plan view and a side view of a structural member across a floor span with secondary support beams.

具体实施方式Detailed ways

图1所示是一对结构构件1的平面图,各结构构件从建筑物一外边缘上的边柱2延伸到建筑物中心部分内的核芯墙3。各结构构件的跨度延伸的长度可长达18米和超过18米,且各构件1之间的间距取决于各边柱之间的距离,如先前所讨论的,该间距相当于适应三个在办公室楼板下面的停车层内用于车辆的空间,该间距通常可在为6至9米中的任一距离。在边柱2之间延伸一边梁16,而楼板4在相邻的两个构件1之间延伸。边梁16可包含一内部的钢梁,其就终止在不到边柱2的侧边上,这样,不需与柱2有任何实质的连接,并支承在该支承主结构构件1的同一外支承框架19上。边梁16的钢部分预先成拱形以承受静载,以使沿建筑物的边缘的挠度最小,这种挠度可影响任何立面的玻璃装配。应当注意到,在图1中,尽管只示出两根梁,但可使用支承一指定楼板区域所需要的任何数量的梁。Figure 1 shows a plan view of a pair of structural members 1, each extending from side columns 2 on an outer edge of a building to a core wall 3 in the central part of the building. The span of each structural member can extend up to and beyond 18 meters in length, and the spacing between the members 1 depends on the distance between the side columns, which, as previously discussed, is equivalent to accommodating three in The space used for vehicles in the parking level below the office floor, the distance can usually be anywhere from 6 to 9 meters. A side beam 16 extends between the side columns 2 , while a floor slab 4 extends between two adjacent elements 1 . The side beams 16 may comprise an internal steel beam which terminates short of the side of the side columns 2, so that it does not require any substantial connection to the columns 2, and is supported on the same outer surface of the supporting main structural member 1. On the support frame 19. The steel portions of the edge beams 16 are pre-arched to withstand static loads to minimize deflection along the edges of the building which could affect the glazing of any façade. It should be noted that in Figure 1, although only two beams are shown, any number of beams required to support a given floor area may be used.

参照图3和4,构件1基本上由一外壳构成,外壳通常由钢材制成,它包括第一和第二(侧壳)梁5,其呈工字梁形状,具有一腹板部分30,在腹板部分30的两端有第一和第二翼缘部分31和32。在构件1的下部延伸的是一板件13(或形成托架形式拱腹),其通常由金属制成,具体来说,由钢材制成,由此,其在各底部或侧壳梁5的第二翼缘部分32之间延伸,并附着或以其它方式与翼缘部分32接合。从侧壳梁5的腹板部分30延伸出的剪切短柱12被用来获得与浇注入由各梁5和板件13形成的壳的内部空间57内的水泥材料的整体作用。大致呈U形形式的绑扎物23从楼板4内向下延伸到内部空间57内,并通过板件13的高起的肋。这也可用作对浇注入壳内部的水泥质材料的额外的支承。此外,钢筋24也设置在构件1内。一闭合件或间隔件15也定位在楼板4内,以将笼架结构绑扎到侧壳梁5上。预应力钢筋束构件10在数量上有若干根,将在下面参照图2予以介绍。Referring to Figures 3 and 4, the structure 1 basically consists of a shell, usually made of steel, comprising first and second (side shell) beams 5, which are in the shape of I-beams, having a web portion 30, At both ends of the web portion 30 there are first and second flange portions 31 and 32 . Extending from the lower part of the member 1 is a plate 13 (or forming a bracket-like soffit), usually made of metal, more specifically steel, whereby it rests on each bottom or side shell girder 5 The second flange portion 32 extends between, and is attached or otherwise engaged with the flange portion 32 . The shear stubs 12 extending from the web portions 30 of the side shell beams 5 are used to obtain integral action with the cementitious material poured into the interior space 57 of the shell formed by the beams 5 and plates 13 . A binding 23 of generally U-shaped form extends from within the floor 4 down into the interior space 57 and passes through the raised ribs of the panel 13 . This also serves as additional support for the cementitious material poured into the interior of the shell. Furthermore, reinforcement bars 24 are also provided in the component 1 . A closure or spacer 15 is also positioned within the floor 4 to tie the cage structure to the side shell beams 5 . There are several prestressed tendon members 10 in number, which will be introduced below with reference to FIG. 2 .

应当注意的是,成对的梁5和用于梁的各种钢筋可在现场外的一控制的生产线环境内进行预制,并与其钢筋24和绑扎物23、预应力钢筋束构件6、8和10和将诸钢钢筋束构件保持在一定位置上的支撑15一起运输到现场。钢筋束构件6是用于钢筋束10中之一的死端锚固,而钢筋束构件8是包含一活动端锚固凹陷的加压金属形式。与用于搬运和传送的支架25连接的两个钢侧壳梁5,能使通常约为4.5吨的18米的梁的整个组件提供到工地上,且用一简单的提升方法,其两端就位在预设的支承框架上,支承框架用标号18和19表示,且在跨中设有支承框架20。It should be noted that the pairs of beams 5 and the various reinforcements for the beams can be prefabricated off-site in a controlled production line environment with their reinforcements 24 and ties 23, prestressed tendon members 6, 8 and 10 are transported to the site together with supports 15 which hold the steel tendon members in position. Tendon member 6 is for dead-end anchoring of one of the tendons 10, while tendon member 8 is a pressed metal form comprising a free-end anchoring recess. Two steel side shell girders 5 connected to brackets 25 for handling and conveyance enable the entire assembly of an 18 m beam, typically about 4.5 tonnes, to be delivered to the site and with a simple lifting method, its ends In place on pre-set support frames, referenced 18 and 19, with a support frame 20 in the mid-span.

参照图2,在建筑物的核芯墙3处,构件1可被容纳成邻接于墙3内的凹凸榫22,而单个的钢筋14和17旋入到箍21内,箍21为顶部和底部配筋连接部已预埋在跳出形式(jump form)的核芯墙3内,以便分别连接钢筋14和17。在梁的另一端,与外柱2的连接所要求的是,连接的钢筋14和17延伸过通过柱2的表面要求的长度。这些钢筋14和17连同在构件1的端部处的梁绑扎物11,是构件1的仅有的需要现场固定的钢筋。Referring to Figure 2, at the core wall 3 of a building, the member 1 may be received adjacent to a tenon and tenon 22 in the wall 3, while the individual bars 14 and 17 are screwed into hoops 21, which are the top and bottom The reinforcement connection has been pre-embedded in the jump form (jump form) core wall 3, so as to connect the steel bars 14 and 17 respectively. At the other end of the beam, all that is required for the connection to the outer column 2 is that the connecting bars 14 and 17 extend the required length through the surface of the column 2 . These bars 14 and 17, together with the beam ties 11 at the ends of the member 1, are the only bars of the member 1 that need to be fixed on site.

尽管穿过构件1的腹板可包含用于消防喷淋管、污水管等的小的(直径达150mm)贯穿孔,但各梁的各端可被成台阶状,只需抬高各钢侧壳梁5的底部翼缘部分32,即可容纳任何主要的公共管道网,而不会撞击到天花板的高度。这可在图2中更清楚地示出,其中,图中示出台阶7,致使台阶和核芯墙3或柱2之间的空间9提供一用于这样的公共管道网(如果需要的话)的空间。该台阶还允许容纳用于一个或多个预应力钢筋束10的活动或张拉端。所述钢筋束10在是在现场进行后张拉的,并可按要求包括任何的数量,以位于各钢侧壳梁5之间的内部空间内。示于图2中的一预应力钢筋束在台阶7之间底部翼缘部分32中延伸,所示的另外的预应力钢筋束10在梁的全长上延伸,并具有一悬垂,换句话说,以凹下的方式施加预应力,这样做的目的是提供一向上提的力或分量,它抵消总的静载的50%至100%的力,对于这些梁通常大约50-60%已足够,由预制梁的钢壳和水泥质材料来提供的其余的静载和瞬时载荷的能力。静载被认为是包括楼板本身、梁的重量,以及诸如天花板表面和楼板面层之类的永久叠加的载荷。两个钢侧壳梁5通常预起拱,这样,一旦移去临时支撑,则已经包容由静载引起的所有的挠度。实际上,钢侧壳梁5、预应力钢筋束和填充到成对梁5的内部空间内的混凝土芯,一起互相作用来承担总载荷。然而,梁5和预应力钢筋束基本上防止配钢筋束构件承受任何重要份额的载荷,并在梁已经挠曲到水平之前,由于预应力钢筋束加上其间预先拱起的钢侧壳梁5能够承受总的静载,所以,决然不会允许混凝土发生蠕变。Each end of each beam can be stepped, although the web passing through member 1 may contain small (up to 150mm diameter) through-holes for fire sprinkler pipes, sewage pipes, etc. The bottom flange portion 32 of the shell beam 5 can accommodate any major utility piping network without hitting the ceiling height. This can be seen more clearly in Figure 2, where the step 7 is shown so that the space 9 between the step and the core wall 3 or column 2 provides a network for such common piping (if required) Space. The step also allows to accommodate the active or tensioned ends for one or more prestressing tendons 10 . The tendons 10 are post-tensioned in situ and may comprise any number as required to be located in the interior space between the steel side shell girders 5 . One prestressing tendon shown in Figure 2 extends in the bottom flange portion 32 between the steps 7 and a further prestressing tendon 10 is shown extending the full length of the beam with an overhang, in other words , prestressed in a concave manner, the purpose of this is to provide an upward force or component that counteracts the force of 50% to 100% of the total static load, for these beams usually about 50-60% is sufficient , the remaining static and transient load capacity is provided by the steel shell and cementitious materials of the prefabricated beams. Dead loads are considered to include the slab itself, the weight of the beams, and permanently superimposed loads such as ceiling surfaces and slab finishes. The two steel side shell girders 5 are usually pre-arched so that, once the temporary support is removed, all deflections due to dead loads are accommodated. In fact, the steel side shell girders 5, the prestressed tendons and the concrete core filling the inner space of the paired beams 5, interact together to bear the total load. However, the beams 5 and tendons substantially prevent the tendon member from carrying any significant share of the load, and before the beam has deflected horizontally, due to the prestressed tendons plus the pre-arched steel side shell beams 5 in between Capable of bearing the total static load, therefore, the concrete will never be allowed to creep.

在使用中,如上所述,在构造钢侧壳梁5之前,剪切短柱和预应力钢筋束10和大部分梁的钢筋在现场外制作,而钢筋14、17和连接到端部的绑扎物11则在现场制作。然后,构件1放置在其临时的支承上,刚好不到核芯墙内的凹凸榫22,在另一端处则刚好不到柱。然后将钢筋14和17放置到各自的箍内,且连同现场放置的绑扎物11,此后,进行楼板的浇注,以使水泥质材料或一般的混凝土被浇注入楼板结构,允许填充在钢侧壳梁5内的内部空间57的主要容积中。通过将混凝土浇注在钢梁之间和钢梁之上,还通过已在工厂里焊接到梁5的各腹板30的内侧上的剪切短柱12,两个钢侧壳梁5和水泥性(混凝土)材料的组合首先一体地作用。In use, prior to construction of the steel side shell girder 5, shear stubs and prestress tendons 10 and most of the beam reinforcement are fabricated off-site, while the reinforcement 14, 17 and lashings connected to the ends Object 11 was produced on site. The element 1 is then placed on its temporary support just short of the tenon 22 in the core wall and just short of the column at the other end. The bars 14 and 17 are then placed in their respective hoops, together with the lashings 11 placed on site, after which the pouring of the slab is carried out so that cementitious material or concrete in general is poured into the slab structure, allowing filling in the steel side shell In the main volume of the interior space 57 inside the beam 5 . The two steel side shell girders 5 and the cementitious The combination of (concrete) materials first acts integrally.

因此,两个钢侧壳梁5显著地增加组合梁的轴向钢的含量,在预应力载荷的作用下,组合梁起作一压缩件,这样,由于使梁缩短的轴向蠕变而引起的任何预应力损失将是最小的。然后,这种混合梁结构还可不具有由静载引起的总挠度,或者,在瞬时载荷之前,它可设置有略微向上的残余拱起。作为未开裂部分的其余坚固的混凝土梁可协助其它两个组成部分,且其挠度由于活载和任何其它的瞬时载荷而增加。Therefore, the two steel side shell girders 5 significantly increase the axial steel content of the composite beam, which acts as a compressive member under the action of the prestressed load, so that the axial creep due to shortening of the beam causes Any loss of prestress will be minimal. Such a hybrid beam structure may then also have no total deflection due to static loading, or it may be provided with a slight upward residual camber before transient loading. The remaining solid concrete beams as uncracked sections assist the other two components and their deflection increases due to live loads and any other transient loads.

由于外柱起初不支承任何的楼板4和构件1,所以,楼板4和构件1和柱2可在同一天浇注。柱2可进行浇注,而同时安装楼板模板和混合构件1之间的楼板4的配筋。可以想像,具备精心组织好的劳动力,通过第一天浇注一半的楼板,第二天浇注另一半,第三天准备柱和提升周界的挡板等,即使是大的楼板区域,三天或甚至不到的楼板循环可以按部就班地实现。Since the outer column initially does not support any floor 4 and element 1, the floor 4 and element 1 and column 2 can be poured on the same day. The columns 2 can be poured while at the same time the reinforcement of the floor 4 between the floor formwork and the composite element 1 is installed. As you can imagine, with a well-organized workforce, even for large slab areas, three days or Even less than slab circulation can be achieved step-by-step.

构件1的混凝土部分分摊到,在澳大利亚采取简化的防火设计,受荷状态是静载的1.1倍加上活载的0.4倍,在其它国家采用类似的数字。因此,如果实际上这可提供一解决方案,则不需进行抗火保护或复杂的抗火工程分析。钢和预应力混凝土梁的组合能力更足以承载工作载荷,在澳大利亚,工作载荷通常是静载的1.25倍加上活载的1.5倍,在其它国家采用类似的数字。The concrete portion of member 1 is apportioned, with a simplified fire design in Australia, to a load condition of 1.1 times the dead load plus 0.4 times the live load, and similar figures in other countries. Therefore, no fire protection or complex fire engineering analysis is required if this actually provides a solution. The combined capacity of steel and prestressed concrete beams is more than sufficient to carry the working load, which is typically 1.25 times the dead load plus 1.5 times the live load in Australia and similar figures are used in other countries.

大部分规范设定对应增加的挠度的挠度限值设为跨度的1/500,该增加的挠度指由于静载的任何的蠕变分量加上由于活载加上隔断的重量引起的挠度。因此,对于18米跨度,该限值是36毫米。对于具有平行于和邻近于建筑物边上的大的内部跨度的任何的建筑物,这个邻近在建筑物边上的柱的楼板(其中挠度为零)和在靠近内部梁处(对于钢梁楼板系统内部梁可接近为2.5米)的跨中的挠度之间的挠度相差量显然太大。比规范更严厉的挠度标准是必要的。本发明通过其混合的钢和混凝土梁可实现,对于18米的跨度,最大的递增的挠度约在20毫米以下。Most codes set the deflection limit at 1/500 of the span for the added deflection due to any creep component of the dead load plus the deflection due to the live load plus the weight of the partition. Therefore, for a span of 18 meters, the limit is 36 mm. For any building with large internal spans parallel to and adjacent to the building sides, the slab adjacent to the column on the building side (where the deflection is zero) and near the internal beams (for steel girder slabs The amount of deflection difference between the mid-span deflections of the internal beams of the system (approximately 2.5 meters) is obviously too large. A more stringent deflection standard than the code is necessary. The present invention achieves, with its hybrid steel and concrete beams, a maximum incremental deflection of about 20mm or less for a span of 18m.

参照图5和6,示出本发明的另一实施例,其中,结构构件1由一单一的整体结构或结合结构制成。具体来说,代替如第一实施例那样地由一板件连接的一对相对的梁,在诸附图中的本实施例具有一大致U行的槽,其由一对侧壁33和34及连接各侧壁33和34的底部35形成。较佳地,该结构由钢材制成。侧壁33和34的上部分别具有翼缘部分36和37,用于支承部分的楼板4。Referring to Figures 5 and 6, another embodiment of the invention is shown in which the structural member 1 is made of a single unitary or combined structure. Specifically, instead of a pair of opposing beams connected by a plate as in the first embodiment, the present embodiment in the drawings has a generally U-row channel defined by a pair of side walls 33 and 34 And the bottom 35 connecting the respective side walls 33 and 34 is formed. Preferably, the structure is made of steel. The upper portions of the side walls 33 and 34 have flange portions 36 and 37, respectively, for supporting the floor 4 of the portion.

参照图5(a)、(b)、(c)和(d),结构构件可由单件的钢板制成,例如,利用如图5(a)所示的38、39、40和41处的四个折角(不采用焊接)。或者,如图5(b)所示,给出两板结构,该结构可在点42处进行焊接,并保持38至41的四个折角。在图5(c)中,示出结构构件的一变化的结构,保持折角38和41,但在点43和44处进行焊接,提供一三板结构。最后,在图5(d)中,可使用五片钢板,没有折角,如图所示在点45、46、47和48处有四个焊缝。Referring to Figures 5(a), (b), (c) and (d), structural members may be made from a single piece of steel plate, for example, using the Four corners (not welded). Alternatively, as shown in Figure 5(b), given a two-plate structure, the structure can be welded at point 42 and the four knuckles 38 to 41 maintained. In Figure 5(c) an alternate configuration of the structural member is shown, retaining the knuckles 38 and 41 but welding at points 43 and 44 to provide a three-plate structure. Finally, in Figure 5(d), five sheets of steel can be used, with no knuckles, and four welds at points 45, 46, 47 and 48 as shown.

采用较浅的侧壳钢梁,利用或不利用预应力钢筋束,以及在梁的端部的底部处具有或不具有凹口来容纳主公共管道网,本发明还可用于较短的跨度。The invention can also be used for shorter spans with shallower side shell steel beams, with or without prestressed tendons, and with or without notches at the bottom of the beam ends to accommodate the main utility piping network.

对于不具有公共管道台阶(双应力锚固点)的这样浅的梁,采用预应力的钢筋束的情形中,则可在钢筋束施加预应力和灌浆之后,锚固可在其后浇注的楼板的顶部内的凹凸榫穴内施加预应力。In the case of prestressed tendons for such shallow beams that do not have a common pipe step (double stress anchor point), then after the tendons have been prestressed and grouted, the anchorage can be placed on top of the slab that can be poured afterwards Prestressing is applied to the concave and convex mortise holes inside.

参照图7,如上所述,采用“切割和覆盖”方法,本发明适用于公路隧道。这涉及到各结构构件提升到位的问题,这些结构构件已经在一定位置上设有钢筋和预制件,并采用相对低载荷的能力的吊车。这与用于现有技术系统的极其重的预浇预应力的混凝土梁49形成对比,其示于图8中。重型预浇预应力梁49需要使用极其大的吊车来提升这样的构件。参照图8,梁49具有用于这种应用的相对薄的翼缘50和顶板51。通常需要防水层或在全范围板上采用防水的薄膜52,其又要求一保护磨损的板53。采用本发明,可使用水密的整体浇注,则省去所有这些。回过来参照图7,这涉及到采用流体阻挡装置,具体来说,配装止水片58和局部的防水层54(或采用防水的薄膜),以确保隧道顶棚的水密性。在结构构件1之间的楼板的跨度可以足够地厚,并以合适的尺寸分段浇注,如有必要的话,在控制接头56之间施加预应力。止水片53和局部的防水层或薄膜54配装到各个控制接头56。Referring to Figure 7, the present invention is applicable to road tunnels using the "cut and cover" approach as described above. This involves lifting into position the structural elements, which are already reinforced and prefabricated in position, using cranes of relatively low load capacity. This is in contrast to the extremely heavy precast prestressed concrete beam 49 used in the prior art system, which is shown in FIG. 8 . Heavy precast prestressed beams 49 require the use of extremely large cranes to lift such members. Referring to Figure 8, the beam 49 has a relatively thin flange 50 and top plate 51 for this application. Usually a waterproof layer or membrane 52 for waterproofing is required over the full extent of the board, which in turn requires a board 53 to protect it from wear. With the present invention, a watertight monolithic casting can be used and all this is dispensed with. Referring back to FIG. 7 , this involves the use of fluid blocking devices, specifically, the fitting of a water-stop sheet 58 and a partial waterproof layer 54 (or a waterproof film) to ensure the watertightness of the tunnel roof. The span of the floor slab between the structural elements 1 can be sufficiently thick and poured in sections with suitable dimensions, prestressed if necessary between the control joints 56 . A waterstop 53 and a partial waterproof layer or membrane 54 are fitted to each control joint 56 .

参照图9,如上所述,本发明也可适用于大型的多跨楼板空间,尤其是高的楼层与楼层尺度、和/或沿一个或两个方向的大跨度、和/或诸如用于零售业、娱乐业或其它用途的楼板上的高的楼板载荷的情况。建筑物构件1可用来跨在次梁60栓接的柱59之间,以支承结构构件1之间的楼板4。Referring to Figure 9, as noted above, the present invention is also applicable to large multi-span floor spaces, particularly high floor-to-floor dimensions, and/or large spans in one or two directions, and/or such as for retail High floor loads on floors for commercial, recreational or other uses. The building elements 1 may be used to span between the columns 59 to which the secondary beams 60 are bolted to support the floor slab 4 between the structural elements 1 .

在建造过程中,只需简单地支承在柱之间,该结构构件就可制作来跨越楼板结构的自重加上建造时的活载。Simply supported between columns during construction, the structural member can be fabricated to span the self-weight of the floor structure plus the live load during construction.

然后,结构构件形成一钢筋混凝土或预应力混凝土构件,其对于需由楼板支承的载荷是连续多跨的。The structural members then form a reinforced concrete or prestressed concrete member which is continuous over multiple spans for the loads to be supported by the floor slab.

Claims (40)

1.一种建筑物的结构构件,其包括:1. A structural member of a building comprising: 一对梁,在所述成对梁中的各个梁具有一第一翼缘部分、一第二翼缘部分、以及在所述第一翼缘部分和所述第二翼缘部分之间延伸的一腹板部分;a pair of beams, each beam in the pair having a first flange portion, a second flange portion, and extending between the first flange portion and the second flange portion a web portion; 一板件,其适于与各梁的所述第一翼缘部分或所述第二翼缘部分中一个部分接合,这样,在所述成对梁中的各梁和所述板件内形成一内部的空间;a plate adapted to engage with one of said first flange portion or said second flange portion of each beam such that a an internal space; 其中,水泥质材料占据所述内部空间的主要容积,以形成一非整体的建筑物结构构件,且在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。Wherein, the cementitious material occupies the main volume of the internal space to form a non-integral building structural member, and after applying post-tensioning prestress, under static load, the structural member of the building has Residual deflection or no deflection. 2.如权利要求1所述的构件,其特征在于,还包括一根或多根沿所述内部空间的长度延伸的钢筋。2. The member of claim 1, further comprising one or more steel bars extending along the length of the interior space. 3.如权利要求2所述的构件,其特征在于,所述一根或多根钢筋各施加预应力,以提供一抵消所述静载的一部分的向上方向的力。3. A member as claimed in claim 2, wherein said one or more reinforcing bars are each prestressed to provide an upwardly directed force which counteracts a portion of said dead load. 4.如权利要求1所述的构件,其特征在于,其用来支承一建筑物内的大跨度楼板区域。4. The element of claim 1 for supporting a long-span floor area in a building. 5.如权利要求4所述的构件,其特征在于,各梁的所述第一翼缘部分支承所述建筑物内的楼板跨度的一部分。5. The member of claim 4, wherein the first flange portion of each beam supports a portion of a floor span in the building. 6.如权利要求5所述的构件,其特征在于,所述构件的一端固定在所述建筑物的一柱上,而所述构件的另一端固定在所述建筑物的核芯上。6. A member as claimed in claim 5, wherein one end of the member is fixed to a column of the building and the other end of the member is fixed to the core of the building. 7.如权利要求6所述的构件,其特征在于,在固定所述构件的各端之前,所述构件暂时地支承在所述构件的所述各端处的脚手架上。7. A structure as claimed in claim 6, wherein said structure is temporarily supported on scaffolding at said ends of said structure prior to securing said ends of said structure. 8.如权利要求1所述的构件,其特征在于,构件具有一个或多个从各所述梁内的所述腹板部分延伸到所述内部空间中的剪切短柱,以与所述水泥质材料成整体。8. The member of claim 1, wherein the member has one or more shear studs extending from said web portion in each said beam into said interior space to communicate with said The cementitious material forms a whole. 9.如权利要求1所述的构件,其特征在于,呈绑扎物形式的支承装置延伸到所述内部空间,以支承所述的水泥质材料。9. The structure of claim 1 wherein support means in the form of a lashing extends into said interior space to support said cementitious material. 10.如权利要求1所述的构件,其特征在于,还包括多根沿所述构件的一部分延伸的钢筋。10. The member of claim 1, further comprising a plurality of steel bars extending along a portion of the member. 11.如权利要求10所述的构件,其特征在于,所述构件的所述另一端容纳邻接在所述建筑物的所述核芯内的凹凸榫内。11. A member as claimed in claim 10, wherein said other end of said member is received within a tenon and tenon abutting within said core of said building. 12.如权利要求11所述的构件,其特征在于,形成在所述核芯内的个别的箍装置固定到所述多根钢筋的个别钢筋上。12. A member as claimed in claim 11, wherein individual hoop means formed in said core are secured to individual bars of said plurality of bars. 13.如权利要求1所述的构件,其特征在于,所述各个梁的各端成台阶状以容纳公共管道。13. The member of claim 1 wherein each end of each beam is stepped to accommodate a common conduit. 14.如权利要求1所述的构件,其特征在于,在所述成对梁中的各梁用金属构造。14. The structure of claim 1 wherein each beam in said pair of beams is constructed of metal. 15.如权利要求1所述的构件,其特征在于,所述水泥质材料是混凝土。15. The member of claim 1, wherein the cementitious material is concrete. 16.一种建筑物结构构件,其包括:16. A building structural member comprising: 一大致呈U形的槽装置,其具有一对相对的侧壁和连接各侧壁的另一部分;a generally U-shaped trough means having a pair of opposing side walls and a further portion connecting the side walls; 其中,所述成对的相对的侧壁和所述另一部分形成一内部空间;以及wherein said pair of opposite side walls and said other portion form an interior space; and 其中,水泥质材料占据所述内部空间的主要容积,以在该槽装置中形成一非整体的建筑物结构构件,且在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。wherein the cementitious material occupies the main volume of the interior space to form a non-integral building structural member in the trough device, and the building is under static load after post-tensioning prestressing The structural members of the object have residual deflection or no deflection. 17.如权利要求16所述的构件,其特征在于,构件具有一个或多个从各所述侧壁之一延伸到所述内部空间的剪切短柱,以与所述水泥质材料成整体。17. A member as claimed in claim 16, wherein the member has one or more shear stubs extending from each of said side walls into said interior space to be integral with said cementitious material . 18.如权利要求16所述的构件,其特征在于,呈绑扎物形式的支承装置延伸到所述内部空间,以支承所述水泥质材料。18. A structure as claimed in claim 16 wherein support means in the form of a lashing extends into the interior space to support the cementitious material. 19.如权利要求16所述的构件,其特征在于,还包括一根或多根沿所述内部空间的长度延伸的钢筋。19. The member of claim 16, further comprising one or more steel bars extending along the length of the interior space. 20.如权利要求19所述的构件,其特征在于,所述一根或多根钢筋各是预应力的,以提供一抵消所述静载的一部分的向上方向的力。20. A member as claimed in claim 19, wherein said one or more steel bars are each prestressed to provide an upwardly directed force which counteracts a portion of said dead load. 21.如权利要求16所述的构件,其特征在于,各个所述侧壁具有一从各侧壁的自由端延伸的翼缘部分,所述翼缘部分支承楼板的一部分。21. The structure of claim 16 wherein each of said side walls has a flange portion extending from a free end of each side wall, said flange portion supporting a portion of the floor. 22.如权利要求16所述的构件,其特征在于,所述构件的各端固定到一支承结构上。22. The member of claim 16, wherein each end of the member is secured to a support structure. 23.如权利要求22所述的构件,其特征在于,在将所述构件的各端固定到所述支承结构之前,所述构件暂时地支承在所述构件的所述各端处的脚手架上。23. A member as claimed in claim 22, wherein the member is temporarily supported on scaffolding at each end of the member prior to securing each end of the member to the support structure . 24.如权利要求16所述的构件,其特征在于,还包括多根沿所述构件的一部分延伸的钢筋。24. The member of claim 16, further comprising a plurality of reinforcing bars extending along a portion of the member. 25.如权利要求24所述的构件,其特征在于,所述构件的两端中的至少一端容纳邻接在所述支承结构内的凹凸榫内。25. A member as claimed in claim 24, wherein at least one of the two ends of the member is received within a rebate abutting within the support structure. 26.如权利要求25所述的构件,其特征在于,形成在所述支承结构内的个别的箍装置固定到所述多根钢筋的个别钢筋上。26. A member as claimed in claim 25, wherein individual hoop means formed within the support structure are secured to individual bars of the plurality of bars. 27.如权利要求16所述的构件,其特征在于,所述各个梁的各端成台阶状以容纳公共管道。27. The member of claim 16 wherein each end of each beam is stepped to accommodate a common conduit. 28.如权利要求16所述的构件,其特征在于,所述槽在构造上是整体的。28. The member of claim 16, wherein the groove is unitary in construction. 29.如权利要求16所述的构件,其特征在于,所述槽装置由一个或多个连接邻近部分的接头构成。29. A component as claimed in claim 16, wherein the channel means is formed by one or more joints connecting adjacent parts. 30.如权利要求16所述的构件,其特征在于,所述槽装置由金属构成。30. The component of claim 16, wherein the channel means is constructed of metal. 31.如权利要求16所述的构件,其特征在于,所述水泥质材料是混凝土。31. The structure of claim 16, wherein the cementitious material is concrete. 32.如权利要求16所述的构件,其特征在于,所述楼板具有流体阻挡装置,以确保所述构件是流体密封的。32. A structure as claimed in claim 16, wherein the floor has fluid blocking means to ensure that the structure is fluid tight. 33.如权利要求32所述的构件,其特征在于,所述流体阻挡装置包括一流体阻挡件和一防流体薄膜。33. A member as claimed in claim 32, wherein said fluid blocking means comprises a fluid blocking member and a fluid resistant membrane. 34.一种建筑物结构构件,其包括:34. A building structural member comprising: 一对梁,在所述成对梁中的各个梁具有一顶部翼缘部分、一底部翼缘部分、以及在所述顶部翼缘部分和所述底部翼缘部分之间延伸的一腹板部分;a pair of beams, each beam in the pair having a top flange portion, a bottom flange portion, and a web portion extending between the top flange portion and the bottom flange portion ; 一板件,其适于与所述成对梁中的各梁的对应的底部翼缘部分接合,这样,在所述成对梁中的各梁和所述板件内形成一内部的空间;以及a plate adapted to engage a corresponding bottom flange portion of each of said pair of beams such that an interior space is formed within each of said pair of beams and said plate; as well as 其中,水泥质材料占据所述内部空间的主要容积,以形成一非整体的建筑物结构构件,且在施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件具有残余的挠度或无挠度。Wherein, the cementitious material occupies the main volume of the internal space to form a non-integral building structural member, and after applying post-tensioning prestress, under static load, the structural member of the building has Residual deflection or no deflection. 35.如权利要求34所述的结构构件,其特征在于,所述板件是一拱腹。35. The structural member of claim 34, wherein said panel is a soffit. 36.如权利要求35所述的结构构件,其特征在于,所述拱腹是一金属托架形式的拱腹。36. A structural member as claimed in claim 35 wherein said soffit is a soffit in the form of a metal bracket. 37.一种制作建筑物结构构件的方法,其包括以下诸步骤:37. A method of making a structural member of a building, comprising the steps of: 构造一对梁,在所述成对梁中的各个梁包括一第一翼缘部分、一第二翼缘部分、以及在所述第一翼缘部分和所述第二翼缘部分之间延伸的一腹板部分;constructing a pair of beams, each beam in the pair comprising a first flange portion, a second flange portion, and extending between the first flange portion and the second flange portion a web portion of; 形成和组装一板件,以使板件与各梁的所述第一翼缘部分或所述第二翼缘部分中一个部分接合,这样,由所述成对梁和所述板件形成一内部的空间;以及forming and assembling a panel so that the panel engages one of said first flange portion or said second flange portion of each beam such that a pair of beams and said panel form a interior space; and 将水泥质材料浇注到所述内部空间,以形成一非整体的建筑物结构构件,这样,在所述水泥质材料硬化和施加后张拉的预应力之后,在静载作用下,所述建筑物的结构构件基本上无挠度。pouring cementitious material into said interior space to form a non-integral building structural member such that, after said cementitious material has hardened and post-tensioned prestressed, said building The structural members of the object are basically deflection-free. 38.如权利要求37所述的方法,其特征在于,所述浇注步骤包括浇注作为楼板的一部分的所述水泥质材料,在与相邻楼板的同一步骤中,浇注到所述内部空间。38. The method of claim 37, wherein the pouring step includes pouring the cementitious material as part of a slab into the interior space in the same step as an adjacent slab. 39.如权利要求37所述的方法,其特征在于,所述浇注步骤包括浇注所述水泥质材料以构造一楼板,且所述浇注对于在构造所述楼板中的浇注步骤是分开进行的。39. The method of claim 37, wherein said pouring step includes pouring said cementitious material to construct a floor, and said pouring is performed separately from the pouring step in constructing said floor. 40.如权利要求37至39中任何一项所述的方法,其特征在于,还包括开始时将所述结构构件的端部支承在邻近所述结构构件的永久端部支承的暂时支承结构上。40. A method as claimed in any one of claims 37 to 39, further comprising initially supporting the end of the structural member on a temporary support structure adjacent to the permanent end support of the structural member .
CNB028112539A 2001-06-05 2002-06-04 Building structural element Expired - Fee Related CN1239796C (en)

Applications Claiming Priority (5)

Application Number Priority Date Filing Date Title
AUPR5481A AUPR548101A0 (en) 2001-06-05 2001-06-05 Building structural element
AUPR5481 2001-06-05
AU11941/02 2002-01-18
AU11941/2002 2002-01-18
AU11941/02A AU754130B1 (en) 2001-06-05 2002-01-18 Building structural element

Publications (2)

Publication Number Publication Date
CN1524149A CN1524149A (en) 2004-08-25
CN1239796C true CN1239796C (en) 2006-02-01

Family

ID=25614666

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB028112539A Expired - Fee Related CN1239796C (en) 2001-06-05 2002-06-04 Building structural element

Country Status (7)

Country Link
US (1) US20040182027A1 (en)
CN (1) CN1239796C (en)
AU (1) AU754130B1 (en)
BR (1) BR0210182A (en)
CA (1) CA2448629A1 (en)
NZ (1) NZ529942A (en)
WO (1) WO2002099215A1 (en)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2002951787A0 (en) * 2002-10-02 2002-10-17 University Of Western Sydney A composite beam
KR20060024850A (en) * 2004-09-15 2006-03-20 삼성물산 주식회사 Steel-concrete sandwich composite beam and high rigid composite structure system
US20070028541A1 (en) * 2005-08-02 2007-02-08 Mark Joseph Pasek Prefabricated shell concrete structural components
US20100242403A1 (en) * 2007-10-24 2010-09-30 Western Forms, Inc. Multiple dimension beam, deck and column system
FR2925088B1 (en) * 2007-12-18 2014-12-26 Soc Civ D Brevets Matiere METHOD FOR PRODUCING AN ARMED CONCRETE BUILDING ELEMENT AND CONSTRUCTION ELEMENT THUS PRODUCED
CN101899877B (en) * 2009-05-19 2014-07-16 柳忠林 Small simulate framework structure of long-span prestress concrete girder slab
CN102061770A (en) * 2010-03-03 2011-05-18 柳忠林 Construction method for imitated frame structure of long-span prestressed concrete beam slab
FI20145669A7 (en) * 2014-07-11 2016-01-12 Peikko Group Oy Steel beam
KR101567741B1 (en) * 2015-02-16 2015-11-09 권용근 Composite beam having truss reinforcement embedded in concrete
DE202015104628U1 (en) 2015-09-01 2016-12-05 Pfeifer Holding Gmbh & Co. Kg Support beam for ceiling systems and ceiling system
US10337196B2 (en) * 2017-04-04 2019-07-02 Reigstad & Associates, Inc. Load-carrying concrete floor structure and method for building the load-carrying concrete floor structure
CN107327020A (en) * 2017-07-06 2017-11-07 能诚集团有限公司 A kind of concrete component attachment structure
DE102018212750A1 (en) * 2018-07-31 2020-02-06 Pfeifer Holding Gmbh & Co. Kg Support beams for ceiling systems, ceiling system and process for their production
CN109359343B (en) * 2018-09-20 2023-06-20 北京电子工程总体研究所 Design method of high-speed large-span flexible sliding rail
CN109057152B (en) * 2018-09-21 2024-05-31 苏州光彩建筑钢品有限公司 Beam structure of integrated steel type house
US11732428B2 (en) * 2018-11-30 2023-08-22 Vellaisamy Thavamani Pandi System for construction of double u and single u steel concrete composite structure for bridges
CN110255208B (en) * 2019-06-27 2024-04-26 中国能源建设集团安徽省电力设计院有限公司 Transfer station crossing original coal conveying trestle and construction method
CA3050000A1 (en) * 2019-07-16 2021-01-16 Invent To Build Inc. Concrete fillable steel joist
CN111914369B (en) * 2020-07-30 2022-12-20 中铁二院工程集团有限责任公司 Automatic design method of U-shaped groove
CN112487678B (en) * 2020-11-20 2024-07-16 合肥工业大学 Performance evaluation method of frame structure after impact
CN113123513A (en) * 2021-05-12 2021-07-16 多维联合集团有限公司 Lapping type bottom-wrapping connecting assembly and steel bar truss floor bearing plate
CN215888960U (en) * 2021-09-06 2022-02-22 昊恒(福建)建材科技有限公司 Steel structure beam
CN114837447B (en) * 2022-04-29 2024-09-06 中建二局安装工程有限公司 Push-type overhanging horizontal protection device and construction method thereof
CN115142602B (en) * 2022-07-21 2024-02-13 黑龙江华装清配建筑科技有限公司 Fully assembled prestress string building cover system
CN115928558B (en) * 2023-02-21 2023-06-02 湖南大学 A UHPC composite box girder transverse joint structure and its construction method
CN117846217B (en) * 2024-01-11 2025-03-21 江苏开放大学(江苏城市职业学院) A mold-free component of a ring beam and a method of using the same

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1398562A (en) * 1972-08-09 1975-06-25 Taylor R Composite and reinforced concrete structures
US4580380A (en) * 1983-11-07 1986-04-08 Ballard Derryl R Composite filled interior structural box beams
EP0350139A3 (en) * 1983-11-07 1990-10-17 Harumoto Iron Works Co., Ltd. A method for forming a composite structural member
US5425152A (en) * 1992-08-14 1995-06-20 Teron International Building Technologies Ltd. Bridge construction

Also Published As

Publication number Publication date
US20040182027A1 (en) 2004-09-23
CN1524149A (en) 2004-08-25
AU754130B1 (en) 2002-11-07
BR0210182A (en) 2004-04-27
NZ529942A (en) 2004-09-24
CA2448629A1 (en) 2002-12-12
WO2002099215A1 (en) 2002-12-12

Similar Documents

Publication Publication Date Title
CN1239796C (en) Building structural element
EP0656085B1 (en) Bridge construction
US20160340855A1 (en) Modular construction mold apparatus and method for constructing concrete buildings and structures
CN100570065C (en) Construction methods for PSC girder bridges
US6543195B2 (en) Composite structural framing system
CN110820928B (en) Connection node between wall panel and beam and construction method thereof
CA2023198C (en) Composite girder construction and method of making same
AU2009204645B2 (en) Precast concrete panel
JPS6282147A (en) Novel prestressed synthetic beam and its construction
JP7479547B1 (en) Concrete Structures
WO2020194205A1 (en) Construction method of providing prefabricated post-tensioned superstructure system
CN117626786A (en) Prefabricated steel-concrete composite beam and its construction method
CN216446283U (en) An assembled folding line top cover
JP2024151537A (en) Bridges and their construction methods
CN217175198U (en) Connecting structure of steel bar truss floor bearing plate and reinforced concrete wall
RU2194127C2 (en) Reinforced-concrete frame of building or structure
KR101387232B1 (en) Moment framework system
CN119434513A (en) A kind of local prestressed support-free prefabricated floor and construction method thereof
JP2000087313A (en) Construction method of composite slab bridge and composite slab bridge
JP2000356041A (en) Concrete casting method
HK40112208A (en) A concrete module of integrating prefabricated shear walls and assembly method
HK40112208B (en) A concrete module of integrating prefabricated shear walls and assembly method
CN114232789A (en) Connecting structure of steel bar truss floor bearing plate and reinforced concrete wall and construction method
EP1404930A1 (en) Building structural element
CN117027260A (en) Vehicle section cover plate assembly type connection structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C19 Lapse of patent right due to non-payment of the annual fee
CF01 Termination of patent right due to non-payment of annual fee