CN1215233C - Method and apparatus for controlling verticality of steel pile - Google Patents

Method and apparatus for controlling verticality of steel pile Download PDF

Info

Publication number
CN1215233C
CN1215233C CN02136613.6A CN02136613A CN1215233C CN 1215233 C CN1215233 C CN 1215233C CN 02136613 A CN02136613 A CN 02136613A CN 1215233 C CN1215233 C CN 1215233C
Authority
CN
China
Prior art keywords
verticality
steel pipe
pipe post
mould
present
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN02136613.6A
Other languages
Chinese (zh)
Other versions
CN1424469A (en
Inventor
龚剑
顾华
袁家余
胡西焕
杨旭
黄路遥
阮则成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai First Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai First Construction Co Ltd filed Critical Shanghai First Construction Co Ltd
Priority to CN02136613.6A priority Critical patent/CN1215233C/en
Publication of CN1424469A publication Critical patent/CN1424469A/en
Application granted granted Critical
Publication of CN1215233C publication Critical patent/CN1215233C/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Placing Or Removing Of Piles Or Sheet Piles, Or Accessories Thereof (AREA)
  • Foundations (AREA)

Abstract

The present invention provides a method and a device for exactly completing adjusting and controlling the verticality of a steel pile in direct viewing. According to the method and the device of the present invention, because all operation can be completed above the ground, the operation condition is good, and the present invention can be matched with a computer to carry out synchronous monitoring direction; thus, the whole process of adjusting and controlling the steel pile can be true reflected in direct viewing, the problem existing in the prior art is better solved, and reliable technique assurance is provided for wide use of a reverse-making method; in addition, the operation of the present invention is rather convenient, and operators can master the operation after being trained for short time.

Description

The controlling verticality of steel pile method
Technical field
The present invention relates to building construction technology, particularly controlling verticality of steel pile method in the reverse construction.
Background technology
At present, growing along with building construction technology, institute's project of building is to the super Shenzhen Development Bank of super large, and reverse construction is employed more and more.The contrary sequence method and the advantages such as duration weak point, cost savings of having compared along the practice, but its construction technology content and difficulty increase greatly.Therefore, constantly carrying out the technological innovation invention, improve construction technology, strengthen management, is the reverse construction key of success.
In numerous technical barriers that reverse construction ran into, the location of piling bar post, verticality and absolute altitude control are particularly crucial, are the problems that reverse construction must solve.At present, few to the control method of piling bar post, these method construction control are not directly perceived, and Shi Gong composition is more by rule of thumb, and operation is complicated, the difficult control of precision, and effect is undesirable.
Summary of the invention
The present invention is directed to the problems referred to above, a kind of controlling verticality of steel pile method is provided, it can intuitively, accurately finish the adjustment control to piling bar post verticality.
According to controlling verticality of steel pile method of the present invention, may further comprise the steps:
1) steel pipe post is fixedlyed connected with connecting rod with mould, and fix one and survey straight tube on the steel pipe post outer wall, the length of connecting rod is set to when steel pipe post arrives its absolute altitude position mould still on terrace;
2) bury the base of a plurality of absolute altitude unanimities underground around in the stake position, and on base, be fixed for the pedestal of mounting support steel pipe post and mould;
3) mould is installed on the pedestal, and between mould and pedestal, many telescopic vertical adjusting bars is installed;
4) sensor probe of measuring vertical degree is put into the survey straight tube to measure the verticality of steel pipe post;
5) by sensor with survey being connected of straight instrument, the verticality data that measure are passed to are surveyed straight instrument, according to the verticality data adjustment adjusting rod that measures, make the verticality of steel pipe post reach preset value by it.
Controlling verticality of steel pile method of the present invention, all operate in more than the ground and finish, operating condition is good, and can be equipped with computer and carry out synchronization monitoring commander, the overall process that can reflect the regulation and control of piling bar post truly, intuitively, solved the difficult problem that prior art exists well, for contrary sequence method widely-used provides the reliable technique assurance.
Description of drawings
Fig. 1 is the principle schematic according to controlling verticality of steel pile method of the present invention;
Fig. 2 is the flow chart according to controlling verticality of steel pile method of the present invention.
The specific embodiment
Below by accompanying drawing preferred embodiment of the present invention is described.
Controlling verticality of steel pile device of the present invention comprises verticality monitoring system and verticality Adjustment System two parts.Wherein, the verticality monitoring system comprises mould, surveys straight tube and surveys straight instrument.The verticality Adjustment System comprises a plurality of bases, be installed in levelling device, pedestal on the base, be installed in level(l)ing device and discrepancy in elevation adjusting device and many verticality adjusting rods on the pedestal.
As shown in Figure 1, because steel pipe post top mark height below natural terrace, therefore needs to use connecting rod spreading steel pipe post, mould is basseted.Steel pipe post and mould are adjusted to concentric then installing and fixing with connecting rod.
Survey straight unit by surveying straight instrument and surveying straight tube and form.Survey straight tube and be installed in the steel pipe post outer wall, length decide with steel pipe post length, reasonablely is, its lower end is near bottom the steel pipe post, and the upper end exceeds the nature terrace.Survey straight instrument and select the common special-purpose straight instrument of surveying for use, sensor probe slips into along surveying straight tube during use, and the data of its collection are delivered to computer and carried out the data processing, to determine the deviation situation of steel pipe post verticality.Thus, the verticality Adjustment System can determine to adjust direction and size according to the deviation situation.
A plurality of bases are fixed on the terrace, are used for supporting pedestal, and have disposed levelling device, the absolute altitude that pedestal leveling to calculated in advance can be gone out, thereby the absolute altitude of control steel pipe post.
The pedestal that is installed on the base indicates the center control line, and has disposed level(l)ing device and discrepancy in elevation adjusting device, is used to adjust and control the plan-position and the absolute altitude of steel pipe post.
Many verticality adjusting rods are set connect moulds and pedestal, its length can telescopic adjustment, is used to adjust the direction and the size of steel pipe post verticality.
Below by Fig. 2 the technological process utilize controlling verticality of steel pile method construction of the present invention is described.Whether as shown in Figure 2, at first measure stake position, base embedded part position, it is accurate to check the stake position then, with its adjust to the position accurately till.Then lift the piling bar post, and carry out centering and check, adjust to centrally aligned.Utilize controlling verticality of steel pile method of the present invention that the verticality of piling bar post is tested subsequently, and adjust verticality, till adhering to specification according to test result.The adjustment of piling bar post verticality gets final product placing of concrete after finishing.In the process of placing of concrete, must monitor the verticality of piling bar post at any time, finely tuned, guarantee precision.
The present invention compares with conventional control method, and following characteristics are arranged:
At first, operation is carried out on ground fully, and working condition is stable, not restricted by the hole wall situation, more can guarantee construction quality.
Secondly, the present invention has utilized advanced Computerized monitor system to monitor, and can reflect the overall process of regulation and control, and is directly perceived, effective, can guarantee construction quality.
Once more, all movable parts of verticality regulator control system can be recycled the economic benefit height.
In addition, operation of the present invention is quite easy, and operating personnel just can be competent at through the short period training.

Claims (1)

1. a controlling verticality of steel pile method is characterized in that, may further comprise the steps:
1) steel pipe post is fixedlyed connected with connecting rod with mould, and fix one and survey straight tube on the steel pipe post outer wall, the length of connecting rod is set to when steel pipe post arrives its absolute altitude position mould still on terrace;
2) bury the base of a plurality of absolute altitude unanimities underground around in the stake position, and on base, be fixed for the pedestal of mounting support steel pipe post and mould;
3) mould is installed on the pedestal, and between mould and pedestal, many telescopic vertical adjusting bars is installed;
4) sensor probe of measuring vertical degree is put into the survey straight tube to measure the verticality of steel pipe post; And
5) by sensor with survey being connected of straight instrument, the verticality data that measure are passed to are surveyed straight instrument, according to the verticality data adjustment adjusting rod that measures, make the verticality of steel pipe post reach preset value by it.
CN02136613.6A 2002-08-23 2002-08-23 Method and apparatus for controlling verticality of steel pile Expired - Lifetime CN1215233C (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN02136613.6A CN1215233C (en) 2002-08-23 2002-08-23 Method and apparatus for controlling verticality of steel pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN02136613.6A CN1215233C (en) 2002-08-23 2002-08-23 Method and apparatus for controlling verticality of steel pile

Publications (2)

Publication Number Publication Date
CN1424469A CN1424469A (en) 2003-06-18
CN1215233C true CN1215233C (en) 2005-08-17

Family

ID=4748712

Family Applications (1)

Application Number Title Priority Date Filing Date
CN02136613.6A Expired - Lifetime CN1215233C (en) 2002-08-23 2002-08-23 Method and apparatus for controlling verticality of steel pile

Country Status (1)

Country Link
CN (1) CN1215233C (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100585098C (en) * 2006-02-21 2010-01-27 上海建工(集团)总公司 High-precision intelligent vertical adjustment system for underground pre-buried columns and its installation and construction method
NL2006477C2 (en) * 2011-03-28 2012-10-01 Ihc Holland Ie Bv Measurement system for a pile.
CN102653947B (en) * 2012-05-08 2015-02-18 上海市基础工程集团有限公司 Underground embedded steel component limiting straightening construction method
CN102653943B (en) * 2012-05-08 2015-02-18 上海市基础工程集团有限公司 Underground embedded steel column straightening limiting device
CN102888865B (en) * 2012-05-29 2015-08-12 中国建筑第四工程局有限公司 The bearing calibration of steel beam column verticality and device in stand column pile construction
CN112551395B (en) * 2020-11-30 2023-03-31 中天建设集团有限公司 Method for correcting installation inclination of tower crane installation structure caused by foundation inclination

Also Published As

Publication number Publication date
CN1424469A (en) 2003-06-18

Similar Documents

Publication Publication Date Title
CN201065533Y (en) Steel pile column perpendicularity regulating and controlling device
CN208533586U (en) One-thousandth vertical-adjustment device for one-column, one-pile, and one-thousandth-level vertical adjustment with a five-story underground reverse method
CN112378381B (en) Slope gradient measuring device
CN1215233C (en) Method and apparatus for controlling verticality of steel pile
CN108507526A (en) A kind of foundation pit deformation measuring device and its measurement method
CN104535045A (en) Wall-hanging hydrostatic level mounting device and wall-hanging hydrostatic level mounting method
CN204495333U (en) A kind of erecting device of wall-hanging hydrostatic level
CN206457859U (en) A kind of detachable apparatus for facilitating open caisson to observe skew and absolute altitude
CN108517872A (en) A kind of measurement method of foundation pit deformation
CN220206691U (en) Composite observation pier structure suitable for machine vision deformation monitoring
CN217150251U (en) Digital verticality adjusting system for reverse steel stand column
CN216159888U (en) A kind of fixed bracket for observation ruler of subgrade and pavement settlement
CN210460637U (en) A but, rotation of shaft orientation is accurate appearance support that hangs down
CN111322996B (en) Column template gradient control structure by laser pointing method and use method thereof
CN223780813U (en) A soil subgrade settlement monitoring device
CN117005473B (en) A method for detecting the verticality of precast piles
CN216621210U (en) Accurate measuring instrument bed frame of self-control cylinder type
CN219890448U (en) Civil engineering wall straightness check out test set that hangs down
CN120537508B (en) A tool for positioning and drilling manhole steps in inspection wells
CN215368789U (en) Slope finding tool for concrete surface inside circular sedimentation tank
CN116518251B (en) High-efficient auxiliary device is used in survey and drawing engineering
CN221402339U (en) Surveying instrument for engineering cost
CN213296447U (en) Be used for major diameter steel-pipe pile straightness detection device that hangs down
CN220184008U (en) Anchor rod construction device
CN219675111U (en) Bridge abutment straightness detection device that hangs down

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 25-27 Floor, 33 Fushan Road, China (Shanghai) Free Trade Pilot Area, 200120

Patentee after: SHANGHAI CONSTRUCTION NO.1 (Group) Co.,Ltd.

Address before: 200082 No. 1198 Zhongshan North Second Road, Shanghai

Patentee before: Shanghai No.1 Construction Co.,Ltd.

CP03 Change of name, title or address