[go: up one dir, main page]

CN111997058B - Construction method for preventing pile top concrete from chiseling and over-grouting - Google Patents

Construction method for preventing pile top concrete from chiseling and over-grouting Download PDF

Info

Publication number
CN111997058B
CN111997058B CN202010769666.9A CN202010769666A CN111997058B CN 111997058 B CN111997058 B CN 111997058B CN 202010769666 A CN202010769666 A CN 202010769666A CN 111997058 B CN111997058 B CN 111997058B
Authority
CN
China
Prior art keywords
concrete
pile
vibrating rod
fixing ring
cast
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010769666.9A
Other languages
Chinese (zh)
Other versions
CN111997058A (en
Inventor
徐晨旭
张卫东
吴昊
李晓倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Original Assignee
Sinohydro Bureau 11 Co Ltd
PowerChina 11th Bureau Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 11 Co Ltd, PowerChina 11th Bureau Engineering Co Ltd filed Critical Sinohydro Bureau 11 Co Ltd
Priority to CN202010769666.9A priority Critical patent/CN111997058B/en
Publication of CN111997058A publication Critical patent/CN111997058A/en
Application granted granted Critical
Publication of CN111997058B publication Critical patent/CN111997058B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

本发明属于工程施工领域,尤其是涉及桩基工程的桩顶混凝土免凿除、防超灌的施工方法。本发明优化混凝土灌注桩浇筑工艺,减少混凝土浇筑量,避免后期凿桩头工序的发生:在混凝土灌注桩浇筑过程中,利用现浇灌注桩桩顶混凝土强度提升设备,把上涌的沉渣排除同时增加桩顶混凝土的密实度,形成能够符合设计要求的桩顶标高和设计强度的桩顶混凝土,无需超灌混凝土。本发明在满足桩顶混凝土符合设计强度的前提下,该施工方法可减少人工、机械投入,降低混凝土用量,减少施工工期,减少对环境的污染,具有一定的推广应用价值。

Figure 202010769666

The invention belongs to the field of engineering construction, in particular to a construction method for pile top concrete free from chiseling and overfill prevention for pile foundation engineering. The invention optimizes the pouring process of the cast-in-place concrete pile, reduces the amount of concrete pouring, and avoids the occurrence of the pile head chisel process in the later stage. Increase the density of the pile top concrete to form pile top concrete that can meet the design requirements of the pile top elevation and design strength, without over-filling concrete. On the premise that the pile top concrete meets the design strength, the construction method can reduce labor and mechanical input, reduce the consumption of concrete, reduce the construction period, and reduce the pollution to the environment, and has certain popularization and application value.

Figure 202010769666

Description

Construction method for preventing pile top concrete from chiseling and over-grouting
Technical Field
The invention belongs to the field of engineering construction, and particularly relates to a construction method for pile top concrete chiseling-free and over-irrigation-prevention of pile foundation engineering.
Background
In order to ensure the concrete strength of the pile top in the concrete pile foundation engineering, the concrete pouring surface is usually specified to be higher than the designed elevation of the pile top by 0.5-1m in the construction, and the concrete of the over-poured part of the pile top is chiseled after the concrete strength of the pile body reaches the design requirement.
The prior method for removing pile top super-poured concrete comprises the following steps: manual chiseling method, mechanical cutting method, physical separation method, chemical spalling method and the like. The common construction method is that the pile top concrete is chiseled by a manual air blowing pick, in the process of chiseling the pile top concrete, because part of the main reinforcement of the reinforcement cage extends into the concrete at the part beyond the pouring of the pile top, the construction difficulty is increased, in order to separate the reinforcement from the concrete to be chiseled, and in some new processes, the main reinforcement of the reinforcement cage is separated from the concrete by adopting a partition plate method or a reinforcement sleeve method before the concrete is poured.
According to the construction idea of early concrete super-irrigation and later-stage concrete chiseling super-irrigation, the chiseling work of the pile top super-irrigation is an important construction process, and mechanical equipment and constructors need to be reasonably arranged.
For the construction of chiseling the concrete on the pile top, the prior construction method has the following problems:
(1) the construction efficiency is low: taking a small foundation pit with 50 piles as an example, pile heads are manually broken for 2-3 piles per day, and pile heads are mechanically broken for 5-8 piles per machine team. If 3 people are selected to perform manual chiseling at the same time, all chiseling needs 6-8 days; 6.25-10 shifts are needed for mechanical removal.
(2) The construction cost is high: in order to reduce the construction period of pile head chiseling and provide a working surface for subsequent work, the investment of personnel and mechanical equipment needs to be increased, and the management cost is relatively increased. The super-poured concrete also increases the construction cost, and the cost of the concrete with the pile diameter of 1m is about 300 yuan for the super-poured concrete with the diameter of 1 m.
(3) There is a security risk: pile top concrete chiseling construction belongs to high strength construction operation, and the work progress needs man-machine cooperation, the concrete fragment of chiseling can splash all around, and the safety risk in the construction has been increased to complicated environment.
(4) The environmental protection problem exists: dust, cement paste and noise are generated in the pile top concrete chiseling construction, and dust prevention and noise reduction measures need to be made in the construction process.
Disclosure of Invention
In order to solve the problems in the prior art, the invention provides a construction method for preventing pile top concrete from chiseling and over-irrigation.
In order to achieve the purpose, the invention adopts the following technical scheme: a construction method for preventing pile top concrete from chiseling and over-filling comprises the following steps:
(1) the installation preparation work of the cast-in-place bored concrete pile top concrete strength hoisting equipment: sealing the pressure sensing piece and the connecting circuit, wherein the pressure sensing piece is adhered to the end head of the vibrating rod, the connecting circuit is fixed along the vibrating rod, and the end part of the slurry pump is 1-1.3 m higher than the end part of the vibrating rod;
(2) scale position preparation work: calculating the difference between the elevation delta h2 of the designed pile top of the concrete cast-in-place pile and the actual elevation delta h1 of the ground to obtain the depth of the empty concrete cast-in-place pile, ensuring that the lower end part of the vibrating rod is 1 meter lower than the designed elevation delta h2 of the pile top by controlling the lowering length of a rope with length scales, and pouring concrete to the elevation delta h2 of the designed pile top without over-pouring concrete;
(3) the equipment is in place: after pile hole excavation is finished and hole inspection is passed, installing a blanking guide pipe, fixing the lantern ring on the steel wire rope along the direction of the guide pipe, and putting the lantern ring to the scale position calculated in the step (2);
(4) pouring concrete: installing a hopper and pouring concrete;
(5) pumping and discharging sediments: along with the elevation delta h2 of the pouring top surface of the concrete, when sediment at the bottom contacts a pressure sensing piece adhered to the end part of the vibrating rod, the display reading of the pressure sensing piece has a mutation phenomenon, and at the moment, a mud pump is started to pump upwelling sediment out of the hole;
(6) concrete vibrating: when the display reading of the pressure sensing piece is changed suddenly again, the concrete is shown to be in contact with the pressure sensing piece, the vibrating rod is started, and sediment on the upper portion is vibrated during vibrating to be beneficial to pumping and discharging of the mud pump;
(7) and (4) observation: when the display reading of the pressure sensing piece does not change any more;
(8) lifting equipment: closing a slurry pump, keeping the vibrating rod to continue vibrating, and slowly pulling out the cast-in-place bored concrete pile top concrete strength lifting equipment;
(9) ending work: cleaning the vibrating rod, checking whether the pressure sensing sheet is damaged or not, and timely replacing the vibrating rod if the pressure sensing sheet cannot be used again;
(10) and (3) post-processing: after the concrete cast-in-place pile reaches the design strength, the pile head part of the concrete cast-in-place pile is only required to be chiseled and cleaned up, and then the subsequent construction can be carried out.
This pile bolck concrete intensity lifting means is annotated in preferred watering includes the stick that vibrates, pressure sensing piece, slush pump and rope, vibrates the fixed pressure sensing dish that sets up in stick bottom that vibrates, and the rope sets up in stick one side that vibrates, and the rope passes through the staple bolt and vibrates stick and slush pump looks fixed connection, and the slush pump sets up in stick one side that vibrates.
The side wall of the upper portion of the preferable blanking guide pipe is fixed with a fixing ring, the fixing ring comprises a first fixing ring and a second fixing ring, the first fixing ring is arranged on the upper portion of the second fixing ring, a steel wire rope is fixed between the first fixing ring and the second fixing ring, the steel wire rope is arranged between the first fixing ring and the second fixing ring in an overhead mode, the outer side of the rope is fixedly connected with a lantern ring, the steel wire rope penetrates through the lantern ring, and the lantern ring can slide up and down on the steel wire rope.
Preferably, the upper part of the blanking conduit is provided with a hopper which is communicated with the blanking conduit.
Compared with the prior art, the invention has the beneficial effects that: compared with the conventional cast-in-place pile pouring method, the construction method which adopts the pile top concrete and avoids chiseling and over-pouring has the advantages that:
(1) the labor, material and equipment investment is reduced, and the cost is saved. Taking a small foundation pit with the diameter of 50 piles being 1m as an example, the mixed concrete cost is about 1.5 ten thousand yuan (3.14 × 0.5 × 1 × 50 × 400), and the manpower cost is about 1.6 ten thousand yuan (3 × 800 × 7).
(2) The progress is accelerated, and the construction period is shortened. Taking a small foundation pit with 50 piles as an example, the construction period can be shortened by 5-8 days.
(3) Reducing the environmental pollution. The dust, cement paste and noise generated in the pile top concrete chiseling are reduced.
On the premise of meeting the requirement that the pile top concrete meets the design strength, the construction method can reduce the labor and mechanical investment, reduce the concrete consumption, shorten the construction period and reduce the pollution to the environment, and has certain popularization and application values.
Drawings
Other features, objects and advantages of the present invention will become more apparent upon reading of the following detailed description of non-limiting embodiments thereof, with reference to the accompanying drawings.
FIG. 1 is a schematic diagram of the present invention.
Fig. 2 is a schematic diagram of the structure at a in fig. 1.
Detailed Description
The present invention will be described in further detail with reference to the following examples, which are provided only for illustrating the present invention and are not intended to limit the scope of the present invention.
Referring to fig. 1-2, a construction method for preventing pile top concrete from chiseling and over-irrigation includes the following steps:
(1) the installation preparation work of the cast-in-place bored concrete pile top concrete strength hoisting equipment: sealing the pressure sensing piece 2 and a connecting circuit, wherein the pressure sensing piece 2 is adhered to the end head of the vibrating rod 1, the connecting circuit is fixed along the vibrating rod 1, and the end part of the slurry pump 4 is 1-1.3 m higher than the end part of the vibrating rod 1;
(2) scale position preparation work: calculating the difference between the elevation delta h2 of the designed pile top of the concrete cast-in-place pile 11 and the actual elevation delta h1 of the ground to obtain the depth of the empty concrete cast-in-place pile, ensuring that the lower end part of the vibrating rod 1 is 1 meter lower than the designed elevation delta h2 of the pile top by controlling the lowering length of the rope 5 with length scales, and pouring concrete to the elevation delta h2 of the designed pile top without over-pouring concrete;
(3) the equipment is in place: after pile hole excavation is finished and hole inspection is passed, installing a blanking guide pipe 9, fixing a lantern ring 6 on a steel wire rope 7 along the direction of the guide pipe 9, and lowering to a scale position obtained through calculation in the step (2);
(4) pouring concrete: installing a hopper 10 and beginning to pour concrete;
(5) pumping and discharging sediments: along with the elevation delta h2 of the top surface of the concrete, when sediment at the bottom contacts the pressure sensing piece 2 adhered to the end part of the vibrating rod 1, the display reading of the pressure sensing piece 2 has a sudden change phenomenon, and at the moment, a mud pump 4 is started to pump and discharge upwelling sediment out of the hole;
(6) concrete vibrating: when the display reading of the pressure sensing piece 2 is changed suddenly again, the concrete is contacted with the pressure sensing piece 2, the vibrating rod 1 is started, and sediment on the upper part is vibrated to be beneficial to pumping and discharging of the mud pump 4;
(7) and (4) observation: when the display reading of the pressure sensing sheet 2 does not change any more, the vibrating compaction is indicated;
(8) lifting equipment: the slurry pump 4 is closed, the vibrating rod 1 is kept vibrating continuously, and the cast-in-place bored concrete pile top concrete strength lifting equipment is slowly pulled out;
(9) ending work: cleaning the vibrating rod 1, checking whether the pressure sensing sheet 2 is damaged or not, and replacing the vibrating rod in time if the vibrating rod cannot be used again;
(10) and (3) post-processing: after the concrete cast-in-place pile 11 reaches the design strength, the pile head part of the concrete cast-in-place pile 11 is only required to be chiseled and cleaned up, and the subsequent construction can be carried out.
Pouring pile top concrete intensity lifting equipment comprises a vibrating rod 1, a pressure sensing piece 2, a slurry pump 4 and a rope 5, wherein a pressure sensing disc 2 is fixedly arranged at the bottom of the vibrating rod 1, the rope 5 is arranged on one side of the vibrating rod 1, the rope 5 is fixedly connected with the vibrating rod 1 and the slurry pump 4 through a hoop 3, and the slurry pump 4 is arranged on one side of the vibrating rod 1; the vibrating rod 1 is an insertion type vibrating rod, the diameter of the vibrating rod is 50-80mm, and the vibrating frequency of the vibrating rod is an intermediate frequency type 83-133 HZ (5000-8000 times/min). The pressure sensing piece 2 is a film type flexible pressure sensing piece. The slurry pump 4 has low lift and a pipe diameter of 100 mm. The rope 5 is for taking length scale, tightly fixes the staple bolt for vibrating spear and slush pump pipe on rope 5, and the lantern ring 6 through fixing on rope 5 is followed wire rope 7 on the pipe and is transferred downwards, ensures that the pipeline of the in-process vibrating spear 1 of descending and slush pump 4 is near the stake center.
A fixing ring 8 is fixed on the side wall of the upper part of the blanking guide pipe 9, the fixing ring 8 comprises a first fixing ring 81 and a second fixing ring 82, the first fixing ring 81 is arranged on the upper part of the second fixing ring 82, a steel wire rope 7 is fixed between the first fixing ring 81 and the second fixing ring 82, the steel wire rope 7 is arranged between the first fixing ring 81 and the second fixing ring 82 in an overhead mode, the outer side of the rope 5 is fixedly connected with a lantern ring 6, the steel wire rope 7 penetrates through the lantern ring 6, and the lantern ring 6 can slide up and down on the steel wire rope 7;
the upper part of the blanking conduit 9 is provided with a hopper 10, and the hopper 10 is communicated with the blanking conduit 9.
The invention achieves the following effects:
(1) the cast-in-place concrete pile casting process is optimized, the concrete casting amount is reduced, and the later pile head chiseling procedure is avoided: in the pouring process of the cast-in-place pile, upwelling sediments are removed by utilizing cast-in-place pile top concrete strength lifting equipment, the compactness of the pile top concrete is increased, the pile top concrete which can meet the pile top elevation and the design strength of the design requirement is formed, and super-pouring concrete is not needed.
(2) The concrete consumption is saved: and by controlling the concrete pouring elevation, the super-pouring of concrete is avoided, the using amount of concrete is reduced, and the concept of green and environment-friendly construction is met.
(3) Shortening the construction period: due to the fact that pile head chiseling construction is omitted, subsequent construction is advanced, and the whole construction period is shortened.
(4) The quality of the concrete is ensured: the strength of the concrete pile head part is ensured by vibrating the vibrating rod in the cast-in-place bored concrete pile top concrete strength lifting equipment.
The foregoing is directed to preferred embodiments of the present invention, other and further embodiments of the invention may be devised without departing from the basic scope thereof, and the scope thereof is determined by the claims that follow. However, any simple modification, equivalent change and modification of the above embodiments according to the technical essence of the present invention are within the protection scope of the technical solution of the present invention.

Claims (1)

1.一种桩顶混凝土免凿除、防超灌的施工方法,其特征在于,包括如下步骤:1. a construction method of pile top concrete exempt from chiseling, preventing overfilling, is characterized in that, comprises the steps: (1)现浇灌注桩桩顶混凝土强度提升设备的安装准备工作:将压力传感片及连接线路密封,压力传感片粘贴在振捣棒的端头,连接线路沿振捣棒固定,泥浆泵端部比振捣棒的端部高出1-1.3米;(1) Installation preparation of the concrete strength lifting equipment on the top of the cast-in-place pile: seal the pressure sensor sheet and the connecting line, paste the pressure sensor sheet on the end of the vibrating rod, and fix the connecting line along the vibrating rod. The end of the pump is 1-1.3 meters higher than the end of the vibrator; (2)刻度位置准备工作:计算混凝土灌注桩桩顶的设计标高△h2和地面实际标高△h1之差得出空混凝土灌注桩深度,通过控制带长度刻度的绳子的下放长度的方式,保证振捣棒的下端部比桩顶的设计标高△h2低1米,将混凝土浇筑至桩顶的设计标高△h2,无需超浇混凝土;(2) Preparatory work for the scale position: Calculate the difference between the design elevation Δh2 of the top of the concrete cast-in-place pile and the actual ground elevation Δh1 to obtain the depth of the empty concrete cast-in-place pile. The lower end of the tamping rod is 1 meter lower than the design elevation Δh2 of the pile top, and the concrete is poured to the design elevation Δh2 of the pile top without over-pouring concrete; (3)设备就位:桩孔开挖完成并通过验孔后,安装下料导管,将套环固定在沿导管方向的钢丝绳上,下放至通过步骤(2)计算得出的刻度位置;(3) The equipment is in place: after the excavation of the pile hole is completed and the hole inspection is completed, the blanking guide tube is installed, and the collar is fixed on the wire rope along the direction of the guide tube, and lowered to the scale position calculated by step (2); (4)混凝土浇筑:安装料斗,开始浇筑混凝土;(4) Concrete pouring: install the hopper and start pouring concrete; (5)沉渣抽排:随着混凝土的浇筑顶面的标高上升,当底部沉渣接触到粘贴在振捣棒端部的压力传感片时,压力传感片的显示读数会发生突变,此时开启泥浆泵将上涌沉渣抽排到孔外;(5) Sediment extraction: As the elevation of the top surface of the concrete pouring rises, when the bottom sediment contacts the pressure sensor sheet attached to the end of the vibrator, the display reading of the pressure sensor sheet will change abruptly. Turn on the mud pump to pump the upwelling sediment out of the hole; (6)混凝土振捣:当压力传感片的显示读数再次突变时说明混凝土已接触到压力传感片,此时开启振捣棒,振捣时将上部的沉渣振动有助于泥浆泵的抽排;(6) Vibration of concrete: when the displayed reading of the pressure sensor sheet suddenly changes again, it means that the concrete has contacted the pressure sensor sheet. At this time, the vibrating rod is turned on, and the upper part of the slag is vibrated during the vibration, which is helpful for the pumping of the mud pump. Row; (7)观察:当压力传感片的显示读数不再有明细变化时;(7) Observation: when the displayed reading of the pressure sensor sheet no longer changes in detail; (8)提升设备:关闭泥浆泵,保持振动棒继续振捣,缓慢拔出现浇灌注桩桩顶混凝土强度提升设备;(8) Lifting equipment: turn off the mud pump, keep the vibrating rod vibrating continuously, and slowly pull out the concrete strength lifting equipment on the top of the cast-in-place pile; (9)收尾工作:清洗振动棒、检查压力传感片是否受损,若无法再次使用则及时更换;(9) Finishing work: clean the vibrating rod, check whether the pressure sensor is damaged, and replace it in time if it cannot be used again; (10)后期处理:待混凝土灌注桩达到设计强度后,只需将混凝土灌注桩的桩头部位凿毛清理干净,即可进入后序施工;(10) Post-processing: After the concrete cast-in-place pile reaches the design strength, it is only necessary to clean up the pile head of the concrete cast-in-place pile, and then the subsequent construction can be started; 该现浇灌注桩桩顶混凝土强度提升设备包括振捣棒、压力传感片、泥浆泵和绳子,振捣棒底部固定设置压力传感片,绳子设置于振捣棒一侧,绳子通过抱箍与振捣棒和泥浆泵相固定连接,泥浆泵设置于振捣棒一侧;The equipment for improving the concrete strength of the cast-in-place pile top includes a vibrating rod, a pressure sensing piece, a mud pump and a rope. The pressure sensing piece is fixed at the bottom of the vibrating rod, the rope is set on one side of the vibrating rod, and the rope passes through the hoop It is fixedly connected with the vibrating rod and the mud pump, and the mud pump is arranged on one side of the vibrating rod; 该下料导管上部侧壁固定有固定环,固定环包括固定环一和固定环二,固定环一设置于固定环二上部,固定环一和固定环二之间固定钢丝绳,钢丝绳架空设置于固定环一和固定环二之间,绳子外侧与套环相固定连接,钢丝绳穿过套环,套环可在钢丝绳上进行上下滑动;A fixing ring is fixed on the upper side wall of the feeding guide. The fixing ring includes a fixing ring 1 and a fixing ring 2. The fixing ring 1 is arranged on the upper part of the fixing ring 2. A steel wire rope is fixed between the fixing ring 1 and the fixing ring 2. Between the first ring and the second fixed ring, the outer side of the rope is fixedly connected with the collar, the wire rope passes through the collar, and the collar can slide up and down on the wire rope; 该下料导管上部设置料斗,料斗与下料导管相连通。A hopper is arranged on the upper part of the feeding duct, and the hopper is communicated with the feeding duct.
CN202010769666.9A 2020-08-04 2020-08-04 Construction method for preventing pile top concrete from chiseling and over-grouting Active CN111997058B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010769666.9A CN111997058B (en) 2020-08-04 2020-08-04 Construction method for preventing pile top concrete from chiseling and over-grouting

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010769666.9A CN111997058B (en) 2020-08-04 2020-08-04 Construction method for preventing pile top concrete from chiseling and over-grouting

Publications (2)

Publication Number Publication Date
CN111997058A CN111997058A (en) 2020-11-27
CN111997058B true CN111997058B (en) 2021-11-23

Family

ID=73462686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010769666.9A Active CN111997058B (en) 2020-08-04 2020-08-04 Construction method for preventing pile top concrete from chiseling and over-grouting

Country Status (1)

Country Link
CN (1) CN111997058B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120099960B (en) * 2025-05-07 2025-07-22 中铁上海工程局集团第五工程有限公司 Method for rapid separation of sediment and sediment control in deep holes under pebble cover

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102304915A (en) * 2011-06-29 2012-01-04 中铁四局集团第一工程有限公司 New method for controlling top quality of drilled pile
GB2525315A (en) * 2014-04-15 2015-10-21 Adbury Electronics Ltd Monitoring of cementitious material
CN105350777A (en) * 2015-11-27 2016-02-24 中国一冶集团有限公司 Device and method for one-time pouring molding of ultra-high concrete column
CN208251108U (en) * 2018-04-25 2018-12-18 深圳市工勘岩土集团有限公司 Caisson pile concrete elevation measurement and superfilled control structure
CN208701771U (en) * 2018-07-10 2019-04-05 长江岩土工程总公司(武汉) The superfilled height detecting device of drill-pouring pile concrete
CN111395323A (en) * 2020-04-13 2020-07-10 中北大学 An anti-overfill control device based on a pressure sensor and a method of using the same

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US10577767B2 (en) * 2018-02-20 2020-03-03 Petram Technologies, Inc. In-situ piling and anchor shaping using plasma blasting

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102304915A (en) * 2011-06-29 2012-01-04 中铁四局集团第一工程有限公司 New method for controlling top quality of drilled pile
GB2525315A (en) * 2014-04-15 2015-10-21 Adbury Electronics Ltd Monitoring of cementitious material
CN105350777A (en) * 2015-11-27 2016-02-24 中国一冶集团有限公司 Device and method for one-time pouring molding of ultra-high concrete column
CN208251108U (en) * 2018-04-25 2018-12-18 深圳市工勘岩土集团有限公司 Caisson pile concrete elevation measurement and superfilled control structure
CN208701771U (en) * 2018-07-10 2019-04-05 长江岩土工程总公司(武汉) The superfilled height detecting device of drill-pouring pile concrete
CN111395323A (en) * 2020-04-13 2020-07-10 中北大学 An anti-overfill control device based on a pressure sensor and a method of using the same

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
低标高桩顶水下钻孔灌注桩混凝土超灌高度控制装置研制;李亮亮等;《施工技术》;20170131;第36-38页 *

Also Published As

Publication number Publication date
CN111997058A (en) 2020-11-27

Similar Documents

Publication Publication Date Title
CN111441374B (en) Quick plugging construction method for high-water-pressure deep foundation pit dewatering well
CN105569560A (en) Full casing type long auger drilled pile driver and construction method using the pile driver
CN104563118B (en) The pre-poured built pile construction method of full-sleeve vibration soil taking
CN106337391A (en) Long piled wharf panel bottom large-area damage repairing construction method
CN111997058B (en) Construction method for preventing pile top concrete from chiseling and over-grouting
CN110144887A (en) Construction method of long empty pile bored pile
CN115749654A (en) Hole cleaning equipment for cast-in-place pile and cast-in-place pile hole forming method using same
CN107083932A (en) Drilling cleaning circulation equipment and installation method of steel pipe columns in pilot tunnels
CN111910622A (en) Construction method of bored pile without pile head
CN100523389C (en) Ballastless track steel reinforced concrete pile-net construction method
CN105649010A (en) Grouting pile construction technology
CN111456091B (en) Pressure sewage pipe diversion method
CN114961336A (en) Protective demolition construction method for basement pile foundation next to existing subway line
CN113152436A (en) Low-clearance MJS pile construction method
CN111424651A (en) Backfill method and structure of ultra-deep large-diameter pile hole
CN111928014A (en) Pipe jacking engineering construction method
CN113187243B (en) A vibrating device for cast-in-place pile concrete
CN109930602A (en) A kind of Water Cutting vibration immersed tube pile pulling device
CN111996923B (en) Closed type in-column concrete pouring method
CN210066752U (en) Water cutting vibrations immersed tube pile pulling device
CN114892648A (en) Construction method for upright post pile and uplift pile
CN111456143A (en) Open excavation construction equipment for comprehensive pipe gallery and construction method thereof
CN120990100B (en) Bridge underwater construction device with protection function
CN114482049B (en) Construction method and device for pulling out small-diameter pile foundation
CN223880355U (en) Supporting structure for steel sheet pile of large-scale slope toe of deep foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant