Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator Download PDF

Info

Publication number
CN111908322A
CN111908322A CN202010851385.8A CN202010851385A CN111908322A CN 111908322 A CN111908322 A CN 111908322A CN 202010851385 A CN202010851385 A CN 202010851385A CN 111908322 A CN111908322 A CN 111908322A
Authority
CN
China
Prior art keywords
hoisting
main shaft
belt
hoisting belt
shackle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010851385.8A
Other languages
Chinese (zh)
Inventor
覃方强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Guiguan Electric Power Co ltd
Dahua General Hydropower Plant Of Guangxi Guiguan Electric Power Co ltd
Original Assignee
Guangxi Guiguan Electric Power Co ltd
Dahua General Hydropower Plant Of Guangxi Guiguan Electric Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Guiguan Electric Power Co ltd, Dahua General Hydropower Plant Of Guangxi Guiguan Electric Power Co ltd filed Critical Guangxi Guiguan Electric Power Co ltd
Priority to CN202010851385.8A priority Critical patent/CN111908322A/en
Publication of CN111908322A publication Critical patent/CN111908322A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/18Band-type slings

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

本发明揭示了一种灯泡贯流式水轮发电机主轴吊装带及吊装方法。该吊装带一端设置有悬挂部、另一端设置有连接部,悬挂部用于悬挂在桥机主钩上,连接部连接有卸扣,卸扣在连接部环绕主轴后与吊装带连接。本发明的吊装方法采用两根吊装带代替原来的一根钢丝绳,在拆挂吊装带的作业过程中,作业人员不需要站到主轴上方进行拆装绳头的高空作业,可以直接站在主轴两侧完成两根吊装带套锁工作,方便省力,避免了高空作业人员坠落风险。

Figure 202010851385

The invention discloses a main shaft hoisting belt and a hoisting method of a bulb tubular hydro-generator. One end of the hoisting belt is provided with a hanging part and the other end is provided with a connecting part, the hanging part is used to hang on the main hook of the bridge machine, the connecting part is connected with a shackle, and the shackle is connected with the hoisting belt after the connecting part surrounds the main shaft. The hoisting method of the present invention uses two hoisting belts to replace the original wire rope. During the operation of removing and hanging the hoisting belt, the operator does not need to stand above the main shaft to perform the aerial work of disassembling and assembling the rope head, and can directly stand on the two sides of the main shaft. The two slings are locked on the side, which is convenient and labor-saving, and avoids the risk of falling for high-altitude workers.

Figure 202010851385

Description

灯泡贯流式水轮发电机主轴吊装带及吊装方法Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator

技术领域technical field

本发明涉及一种灯泡贯流式水轮发电机主轴吊装带及吊装方法。The invention relates to a main shaft hoisting belt and a hoisting method of a bulb tubular hydro-generator.

背景技术Background technique

水轮发电机组A修时需要将主轴吊出机坑,在机组主轴水平拉出至专用支墩后,使用电动葫芦将钢丝绳的一个绳头从主轴下方拉起后,再通过手拉葫芦辅助挂上桥机吊钩,整个作业过程需要作业人员爬上主轴或组合轴承在高空完成,而且吊装定子的钢丝绳本身重量大,弯曲扭矩大,不易控制钢丝绳,作业难度和风险大,挂装过程费时费力;而且钢丝绳在挂装好后调整受力时容易出现钢丝绳滑动移位、受力点偏移的情况,因此在起吊过程中为防止钢丝绳滑动移位,还需要用手拉葫芦在上下游方向对钢丝绳进行固定,过程十分繁琐。When repairing the hydro-generator set A, the main shaft needs to be hoisted out of the machine pit. After the main shaft of the unit is pulled horizontally to the special support pier, an electric hoist is used to pull up one end of the wire rope from the bottom of the main shaft, and then the hand hoist is used to assist the hanging. For the hook of the bridge machine, the whole operation process requires the operator to climb on the main shaft or the combined bearing to complete at high altitude, and the wire rope for hoisting the stator itself is heavy, the bending torque is large, it is difficult to control the wire rope, the operation is difficult and risky, and the hanging process is time-consuming and laborious ; And the wire rope is prone to sliding and shifting of the wire rope and the displacement of the force point when the wire rope is adjusted after it is hung and installed. Therefore, in order to prevent the wire rope from sliding and shifting during the lifting process, it is necessary to use a hand hoist in the upstream and downstream directions. The wire rope is fixed, the process is very cumbersome.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于针对现有技术中的上述缺陷,提供一种灯泡贯流式水轮发电机主轴吊装带及吊装方法,用于解决作业时需爬上主轴或组合轴承、使用钢丝绳点状容易出现钢丝绳移位、受力点偏移的问题。The purpose of the present invention is to aim at the above-mentioned defects in the prior art, to provide a bulb tubular hydro-generator main shaft hoisting belt and a hoisting method, which are used to solve the problem of needing to climb up the main shaft or the combined bearing during operation, and it is easy to use a steel wire rope in a point-like manner. There are problems of wire rope displacement and force point offset.

为实现上述发明目的,本发明采用了如下技术方案:In order to realize the above-mentioned purpose of the invention, the present invention has adopted the following technical solutions:

一种灯泡贯流式水轮发电机主轴吊装带,所述吊装带一端设置有悬挂部、另一端设置有连接部,悬挂部用于悬挂在桥机主钩上,连接部连接有卸扣,卸扣在连接部环绕主轴后与吊装带连接。A bulb tubular water turbine generator main shaft hoisting belt, one end of the hoisting belt is provided with a hanging part, the other end is provided with a connecting part, the hanging part is used for hanging on the main hook of a bridge machine, and the connecting part is connected with a shackle, The shackle is connected with the sling after the connecting part surrounds the main shaft.

作为上述技术方案的进一步改进:As a further improvement of the above technical solution:

所述悬挂部和吊装带下半部上设置有耐磨套,耐磨套的两端分别设有固定于悬挂部和吊装带上,吊装带吊装主轴时卸扣与吊装带上的耐磨套连接。The suspension part and the lower half of the hoisting belt are provided with wear-resistant sleeves, and both ends of the wear-resistant sleeves are respectively provided with wear-resistant sleeves fixed on the suspension part and the hoisting belt. connect.

所述吊装带由纤维制成。The sling is made of fibers.

所述卸扣外设置有软质包层。A soft cladding layer is provided outside the shackle.

所述吊装带的连接部的下端设置有连接孔,所述卸扣穿过连接孔与吊装带连接。The lower end of the connecting portion of the sling is provided with a connecting hole, and the shackle is connected to the sling through the connecting hole.

另一方面,本发明还提供了一种灯泡贯流式水轮发电机主轴吊装方法,该吊装方法包括以下步骤:1)准备吊装装置,该吊装装置包括两根吊装带和两台手拉葫芦,吊装带一端设置有悬挂部、另一端设置有连接部;2)将两根吊装带的悬挂部分别挂在桥机主钩的左右两侧的挂钩上,当主轴水平拉出至专用支墩后,将主钩左侧的吊装带连接部从主轴的左下侧绕到右上侧后将卸扣与吊装带连接,使吊装带套锁在主轴的受力点位置,然后再将主钩右侧的吊装带以同样的方式套锁在主轴的受力点位置;3)调整主钩,使主钩对准主轴的重心位置;4)将两台手拉葫芦与主轴发电机端专用吊环连接,调整并使两根吊装带和两台手拉葫芦受力均匀;5)将主轴吊离专用支墩,调整位置吊出机坑。On the other hand, the present invention also provides a method for hoisting the main shaft of a bulb tubular hydro-generator, the hoisting method comprising the following steps: 1) preparing a hoisting device, the hoisting device comprising two hoisting belts and two chain hoists , One end of the hoisting belt is provided with a hanging part, and the other end is provided with a connecting part; 2) Hang the hanging parts of the two hoisting belts on the hooks on the left and right sides of the main hook of the bridge machine, when the main shaft is horizontally pulled out to the special support pier Then, wind the connecting part of the sling on the left side of the main hook from the lower left side of the main shaft to the upper right side, and then connect the shackle to the sling, so that the sling sleeve is locked at the stress point of the main shaft, and then put the right side of the main hook. 3) Adjust the main hook so that the main hook is aligned with the center of gravity of the main shaft; 4) Connect the two chain hoists to the special lifting ring at the generator end of the main shaft, Adjust and make the two hoisting belts and the two chain hoists evenly stressed; 5) Lift the main shaft away from the special support pier, and adjust the position to lift it out of the machine pit.

进一步地,所述步骤2)中的受力点位置距离组合轴承侧650mm-750mm。Further, the position of the force bearing point in the step 2) is 650mm-750mm away from the combined bearing side.

进一步地,所述步骤4)中,使两根吊装带和两台手拉葫芦受力均匀的过程中,利用两台手拉葫芦受力转换调整,使主轴大部分重量由桥机主钩承载。Further, in the step 4), in the process of making the two hoisting belts and the two chain hoists evenly stressed, the force conversion adjustment of the two chain hoists is utilized, so that most of the weight of the main shaft is carried by the main hook of the bridge machine. .

相比于现有技术,本发明的优势在于:Compared with the prior art, the advantages of the present invention are:

本发明的吊装带一端设置有悬挂部、另一端设置有连接部,吊装带的悬挂部挂在桥机主钩上,连接部绕过主轴后用卸扣套锁在吊装带上。吊装方法采用两根吊装带代替一根钢丝绳,在吊装带拆挂作业过程中,不需要作业人员站到主轴上方以进行拆装绳头等高空作业,作业人员可以直接站在主轴两侧就能轻松完成两根吊装带套锁工作,既方便又省力,且避免高空作业人员坠落风险,同时又省去用桥机电动葫芦辅助拆挂绳头工序;而且采用套锁式的连接方式,连接后的吊装带不易发生滑移和受力点偏移的情况。The sling of the present invention is provided with a hanging part at one end and a connecting part at the other end; The hoisting method uses two hoisting belts instead of one steel wire rope. During the dismantling and hanging operation of the hoisting belt, the operator does not need to stand above the main shaft to perform high-altitude operations such as disassembling and assembling the rope head. The operator can directly stand on both sides of the main shaft and easily It is convenient and labor-saving to complete the locking work of two hoisting belts, and avoids the risk of falling for high-altitude workers, and at the same time saves the process of using the bridge motor electric hoist to assist in removing the hanging rope head; The sling is not prone to slippage and deflection of the force point.

附图说明Description of drawings

为了更清楚地说明本发明实施例的技术方案,下面将对实施例或相关技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅涉及本发明的一些实施例,并非对本发明的限制。In order to illustrate the technical solutions of the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings required in the description of the embodiments or related technologies. Obviously, the drawings in the following description only relate to some implementations of the present invention. example, and not limitation of the present invention.

图1是现有技术的主轴吊装示意图。FIG. 1 is a schematic diagram of a prior art spindle hoisting.

图2是本发明的吊装带的结构示意图。FIG. 2 is a schematic view of the structure of the hoisting belt of the present invention.

图3是本发明的卸扣的剖视图。3 is a cross-sectional view of the shackle of the present invention.

图4是本发明的主轴吊装示意图。FIG. 4 is a schematic diagram of the main shaft hoisting of the present invention.

图中标号:1、吊装带;2、手拉葫芦;3、连接部;4、悬挂部;5、卸扣;6、软质包层;7、耐磨套;8、主钩;9、主轴;10、组合轴承;11、钢丝绳。Labels in the figure: 1. Lifting belt; 2. Chain hoist; 3. Connecting part; 4. Suspension part; 5. Shackle; 6. Soft cladding; 7. Wear-resistant sleeve; 8. Main hook; 9. Main shaft; 10. Combined bearing; 11. Steel wire rope.

具体实施方式Detailed ways

为了能够更清楚地理解本发明的上述目的、特征和优点,下面结合附图和具体实施方式对本发明技术方案作进一步非限制性的详细描述。In order to more clearly understand the above objects, features and advantages of the present invention, the technical solutions of the present invention are further described in non-limiting detail below with reference to the accompanying drawings and specific embodiments.

如图2所示,本实施例的灯泡贯流式水轮发电机主轴吊装带1一端设置悬挂部1,另一端设置有连接部3,悬挂部4与连接部3与吊装带1一体制成,均由纤维材质制成,规格为50t×10m,该吊装带相对于钢丝绳而言,具有较好的防滑效果,吊装带1与主轴9连接后不易发生滑动移位的情况。悬挂部4呈挂环状,用于挂在桥机主钩上。连接部3的下端设置有连接孔,卸扣5通过连接孔与连接部3连接,卸扣5在连接部3环绕主轴9后与吊装带1连接。如图3所示,在卸扣5外设置有软质包层6,可以防止吊装过程中卸扣5对主轴造成挤压变形。在悬挂部4以及吊装带1的中下部设置有耐磨套7,耐磨套7的两端分别固定于悬挂部4和吊装带1上,吊装主轴9时卸扣5与吊装带1上的耐磨套7连接。耐磨套提高了悬挂部4和吊装带1的耐磨性能,延长吊装带1的使用寿命。As shown in FIG. 2 , the main shaft hoisting belt 1 of the bulb tubular hydro-generator of this embodiment is provided with a hanging part 1 at one end and a connecting part 3 on the other end. The hanging part 4 and the connecting part 3 are integrally formed with the hoisting belt 1 , are made of fiber material, the specification is 50t×10m, the sling has better anti-slip effect than the wire rope, and the sling 1 is not easy to slide and shift after connecting with the main shaft 9. The hanging part 4 is in the form of a hanging ring, which is used for hanging on the main hook of the bridge machine. The lower end of the connecting portion 3 is provided with a connecting hole, and the shackle 5 is connected to the connecting portion 3 through the connecting hole. The shackle 5 is connected to the sling 1 after the connecting portion 3 surrounds the main shaft 9 . As shown in FIG. 3 , a soft cladding 6 is provided outside the shackle 5 , which can prevent the shackle 5 from causing extrusion deformation to the main shaft during the hoisting process. A wear-resistant sleeve 7 is provided at the middle and lower parts of the suspension part 4 and the hoisting belt 1 , and both ends of the wear-resistant sleeve 7 are respectively fixed on the hanging part 4 and the hoisting belt 1 . Wear sleeve 7 connection. The wear-resistant sleeve improves the wear resistance of the suspension portion 4 and the sling 1 and prolongs the service life of the sling 1 .

如图4所示,本实施例的灯泡贯流式水轮发电机主轴吊装方法包括以下步骤:As shown in FIG. 4 , the method for hoisting the main shaft of a bulb tubular hydro-generator in this embodiment includes the following steps:

1)准备吊装装置,该吊装装置包括两根吊装带1和两台30t手拉葫芦2,吊装带1一端设置有悬挂部4、另一端连接有连接部3;1) Prepare a hoisting device, the hoisting device includes two hoisting belts 1 and two 30t chain hoists 2, one end of the hoisting belt 1 is provided with a hanging part 4, and the other end is connected with a connecting part 3;

2)将两根吊装带1的悬挂部4挂在桥机主钩8的左右两侧的挂钩上,当主轴9水平拉出至专用支墩后,将主钩8左侧的吊装带1的连接部3从主轴9的左下侧绕到右上侧后将卸扣5与吊装带1连接,使吊装带1套锁在主轴9的受力点位置,然后再将主钩8右侧的吊装带1以同样的方式套锁在主轴9的受力点位置;受力点位置距离组合轴承10侧650mm-750mm。2) Hang the suspension parts 4 of the two slings 1 on the hooks on the left and right sides of the main hook 8 of the bridge machine. The connecting part 3 is wound from the lower left side of the main shaft 9 to the upper right side, and then the shackle 5 is connected to the sling 1, so that the sling 1 is locked at the stress point position of the main shaft 9, and then the sling on the right side of the main hook 8 is locked. 1. In the same way, lock it on the force point position of the main shaft 9; the force point position is 650mm-750mm away from the combined bearing 10 side.

3)调整主钩8,使主钩8对准主轴的重心位置;3) Adjust the main hook 8 so that the main hook 8 is aligned with the center of gravity of the main shaft;

4)将两台手拉葫芦2与主轴发电机端专用吊环连接,调整并使两根吊装带1和两台手拉葫芦2受力均匀,同时利用两台手拉葫芦受力转换调整,使主轴大部分重量由桥机主钩承载;4) Connect the two chain hoists 2 with the special lifting ring at the main generator end, adjust and make the two lifting belts 1 and the two chain hoists 2 evenly stressed, and at the same time use the force conversion adjustment of the two chain hoists to make the Most of the weight of the main shaft is carried by the main hook of the bridge machine;

5)将主轴9吊离专用支墩,调整位置吊出机坑。5) Lift the main shaft 9 away from the special support pier, adjust the position and lift it out of the machine pit.

本发明采用两根吊装带代替原来的一根钢丝绳,将两根吊装分别从主轴受力位置的两侧绕过主轴将卸扣连接在吊装带上,在拆挂该吊装带的作业过程中,作业人员不需要站到主轴上方进行拆装绳头的高空作业,作业人员可以直接站在主轴两侧完成两根吊装带套锁工作,方便省力,避免了高空作业人员坠落风险。吊装带本身是防滑的,省去了在主轴上下游方向加装手拉葫芦进行固定工序,减少了作业时间,提高了作业效率。In the present invention, two slings are used to replace the original steel wire rope, and the two slings respectively bypass the main shaft from both sides of the main shaft where the main shaft is stressed, and connect the shackle to the sling. During the operation of disassembling and hanging the sling, The operator does not need to stand above the main shaft to perform aerial work of disassembling and assembling the rope head. The operator can directly stand on both sides of the main shaft to complete the work of locking the two slings, which is convenient and labor-saving, and avoids the risk of falling for aerial workers. The hoisting belt itself is non-slip, eliminating the need to install chain hoists in the upstream and downstream directions of the main shaft to fix the process, reducing the operation time and improving the operation efficiency.

需要指出的是,上述较佳实施例仅为说明本发明的技术构思及特点,其目的在于让熟悉此项技术的人士能够了解本发明的内容并据以实施,并不能以此限制本发明的保护范围。凡根据本发明精神实质所作的等效变化或修饰,都应涵盖在本发明的保护范围之内。It should be pointed out that the above-mentioned preferred embodiment is only to illustrate the technical concept and characteristics of the present invention, and its purpose is to enable those who are familiar with the technology to understand the content of the present invention and implement it accordingly, and cannot limit the present invention. protected range. All equivalent changes or modifications made according to the spirit of the present invention should be included within the protection scope of the present invention.

Claims (8)

1. The bulb through-flow type hydraulic generator spindle hoisting belt is characterized in that one end of the hoisting belt (1) is provided with a hanging part (4), the other end of the hoisting belt is provided with a connecting part (3), the hanging part (4) is used for hanging on a bridge crane main hook, the connecting part (3) is connected with a shackle (5), and the shackle (5) is connected with the hoisting belt (1) after the connecting part (3) surrounds a spindle (9).
2. The bulb through-flow type hydraulic generator main shaft hoisting belt according to claim 1, characterized in that wear-resistant sleeves (7) are arranged at the middle lower parts of the hanging part (4) and the hoisting belt (1), two ends of each wear-resistant sleeve (7) are respectively fixed on the hanging part (4) and the hoisting belt (1), and the shackle (5) is connected with the wear-resistant sleeves (7) on the hoisting belt (1) when the hoisting belt (1) hoists the main shaft (9).
3. The main shaft hoisting belt of the bulb through-flow type hydraulic generator according to claim 1, wherein the hoisting belt (1) is made of a fiber material.
4. The main shaft hoisting belt of a bulb through-flow type hydraulic generator according to claim 1, wherein a soft coating (6) is arranged outside the shackle (5).
5. The bulb through-flow type hydraulic generator spindle hoisting belt according to claim 1, wherein a connecting hole is formed in the lower end of the connecting portion (3) of the hoisting belt (1), and the shackle (5) penetrates through the connecting hole to be connected with the hoisting belt (1).
6. The method for hoisting the main shaft of the bulb tubular hydraulic generator is characterized by comprising the following steps of:
1) preparing a hoisting device, wherein the hoisting device comprises two hoisting belts and two chain blocks, one end of each hoisting belt is provided with a suspension part, and the other end of each hoisting belt is provided with a connecting part;
2) hanging the hanging parts of the two hoisting belts on the hooks on the left side and the right side of the main hook of the bridge crane respectively, after the main shaft is horizontally pulled out to a special buttress, winding the hoisting belt connecting part on the left side of the main hook from the left lower side to the right upper side of the main shaft, connecting the shackle with the hoisting belts, enabling the hoisting belts to be locked at the stress point position of the main shaft in a sleeved mode, and then locking the hoisting belts on the right side of the main hook at the stress point position of the main shaft in a sleeved mode in the same mode;
3) adjusting the main hook to align the main hook to the gravity center position of the main shaft;
4) connecting the two chain blocks with a special lifting ring at the end of the main shaft generator, and adjusting and enabling the two lifting belts and the two chain blocks to be stressed uniformly;
5) the main shaft is lifted away from the special buttress, and the position is adjusted to be lifted out of the pit.
7. Hoisting method according to claim 6, characterized in that the location of the force point in step 2) is 650-750 mm from the combined bearing side.
8. The hoisting method according to claim 6, wherein in the step 4), in the process of uniformly stressing the two hoisting belts and the two chain blocks, the two chain blocks are utilized for stress conversion and adjustment, so that most of the weight of the main shaft is borne by the main hook of the bridge crane.
CN202010851385.8A 2020-08-21 2020-08-21 Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator Pending CN111908322A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010851385.8A CN111908322A (en) 2020-08-21 2020-08-21 Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010851385.8A CN111908322A (en) 2020-08-21 2020-08-21 Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator

Publications (1)

Publication Number Publication Date
CN111908322A true CN111908322A (en) 2020-11-10

Family

ID=73279744

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010851385.8A Pending CN111908322A (en) 2020-08-21 2020-08-21 Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator

Country Status (1)

Country Link
CN (1) CN111908322A (en)

Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1508588A (en) * 1975-04-01 1978-04-26 Fisons Ltd Slings
GB1511251A (en) * 1975-06-12 1978-05-17 Fisons Ltd Sling assembly
BR6301393U (en) * 1983-09-27 1985-04-30 Kef Administracao E Participac SELF-TIGHTENING BELT FOR HANDLING SACKS AND VOLUMES
JP2004026412A (en) * 2002-06-26 2004-01-29 Wako Engineering Corp Cylinder carrying tool
CN200967703Y (en) * 2006-10-16 2007-10-31 天津港第一港埠公司 Chain binding rigging
CN201102856Y (en) * 2007-08-15 2008-08-20 巨力索具股份有限公司 Hanging strip and hanging ring device
CN201280384Y (en) * 2008-04-16 2009-07-29 程前进 Polyurethane composite steel wire rope hanging strip
CN101565090A (en) * 2008-10-28 2009-10-28 广州文冲船厂有限责任公司 Method for binding ship-launching steel beams
US20100200143A1 (en) * 2008-03-14 2010-08-12 Sumitomo Electric Tochigi Co., Ltd. Annular concentric stranded bead cord, method for manufacturing the same, and vehicle tire
US20100327615A1 (en) * 2009-06-24 2010-12-30 Dongguan Ponsa Textile Limited Textile sling and method of manufacturing same
CN201849269U (en) * 2010-11-12 2011-06-01 边晓霞 Trailer rope with shackles
CN103708338A (en) * 2012-09-28 2014-04-09 侯天章 Wear resistant synthetic fiber lifting belt
CN104444763A (en) * 2014-11-17 2015-03-25 常熟市永固起重设备安装工程有限公司 Adjustable binding hoisting sling
CN104649130A (en) * 2014-12-10 2015-05-27 泰兴晨光索具有限公司 Guy tackle rigging for high-strength environment-resistant ship
ES2539554A1 (en) * 2013-10-28 2015-07-01 Francisco GÓMEZ TRUNSER Pull and pull device for motorcycles
CN205709468U (en) * 2016-06-24 2016-11-23 中国石油集团西部钻探工程有限公司 Radial bearing suspender belt
CN205874823U (en) * 2016-06-23 2017-01-11 山东鲁普科技有限公司 Hollow volume chemical fibre rope flexibility is broken out
CN207597141U (en) * 2017-08-15 2018-07-10 江门市新会区会城远洋绳缆厂 A kind of single point mooring's Hawser
CN112645208A (en) * 2021-01-13 2021-04-13 扬州华谊绳带有限公司 Tow rope or sling with adjustable length and openable button hole
CN213865049U (en) * 2020-08-21 2021-08-03 广西桂冠电力股份有限公司大化水力发电总厂 Bulb tubular hydraulic generator spindle hoisting belt

Patent Citations (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1508588A (en) * 1975-04-01 1978-04-26 Fisons Ltd Slings
GB1511251A (en) * 1975-06-12 1978-05-17 Fisons Ltd Sling assembly
BR6301393U (en) * 1983-09-27 1985-04-30 Kef Administracao E Participac SELF-TIGHTENING BELT FOR HANDLING SACKS AND VOLUMES
JP2004026412A (en) * 2002-06-26 2004-01-29 Wako Engineering Corp Cylinder carrying tool
CN200967703Y (en) * 2006-10-16 2007-10-31 天津港第一港埠公司 Chain binding rigging
CN201102856Y (en) * 2007-08-15 2008-08-20 巨力索具股份有限公司 Hanging strip and hanging ring device
US20100200143A1 (en) * 2008-03-14 2010-08-12 Sumitomo Electric Tochigi Co., Ltd. Annular concentric stranded bead cord, method for manufacturing the same, and vehicle tire
CN201280384Y (en) * 2008-04-16 2009-07-29 程前进 Polyurethane composite steel wire rope hanging strip
CN101565090A (en) * 2008-10-28 2009-10-28 广州文冲船厂有限责任公司 Method for binding ship-launching steel beams
US20100327615A1 (en) * 2009-06-24 2010-12-30 Dongguan Ponsa Textile Limited Textile sling and method of manufacturing same
CN201849269U (en) * 2010-11-12 2011-06-01 边晓霞 Trailer rope with shackles
CN103708338A (en) * 2012-09-28 2014-04-09 侯天章 Wear resistant synthetic fiber lifting belt
ES2539554A1 (en) * 2013-10-28 2015-07-01 Francisco GÓMEZ TRUNSER Pull and pull device for motorcycles
CN104444763A (en) * 2014-11-17 2015-03-25 常熟市永固起重设备安装工程有限公司 Adjustable binding hoisting sling
CN104649130A (en) * 2014-12-10 2015-05-27 泰兴晨光索具有限公司 Guy tackle rigging for high-strength environment-resistant ship
CN205874823U (en) * 2016-06-23 2017-01-11 山东鲁普科技有限公司 Hollow volume chemical fibre rope flexibility is broken out
CN205709468U (en) * 2016-06-24 2016-11-23 中国石油集团西部钻探工程有限公司 Radial bearing suspender belt
CN207597141U (en) * 2017-08-15 2018-07-10 江门市新会区会城远洋绳缆厂 A kind of single point mooring's Hawser
CN213865049U (en) * 2020-08-21 2021-08-03 广西桂冠电力股份有限公司大化水力发电总厂 Bulb tubular hydraulic generator spindle hoisting belt
CN112645208A (en) * 2021-01-13 2021-04-13 扬州华谊绳带有限公司 Tow rope or sling with adjustable length and openable button hole

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
吕明伟,李英武: "大树移植前各环节技术分析", 中国园艺文摘, no. 8, 26 August 2012 (2012-08-26), pages 63 - 64 *
尹志,魏忠明,张培飞: "高压套管吊装的改进方法", 云南电力技术, no. 2, 15 April 2008 (2008-04-15), pages 59 *
杨文渊: "起重吊装技术手册 下", vol. 1, 31 December 1981, 人民交通出版社, pages: 197 *
黄健,周洪元,奚健,曹云勇: "船体总段吊带吊装新工艺研究与应用", 船舶与海洋工程, no. 3, 14 August 2018 (2018-08-14), pages 68 - 74 *

Similar Documents

Publication Publication Date Title
CN203806941U (en) Hoisting overturning device of direct-drive wind power generator
CN205222445U (en) A hoist device for wind generating set blade
CN106415005A (en) Method and system for de-erection and re-erection of a blade of a wind turbine
CN110104571B (en) Wire rope pre-tightening method for offshore engineering cranes
CN209702171U (en) A wire rope anti-twisting rope fixing device
CN111908322A (en) Main shaft hoisting belt and hoisting method of bulb tubular hydro-generator
CN213865049U (en) Bulb tubular hydraulic generator spindle hoisting belt
CN105735629A (en) Lifting device for building-attached lifting scaffold
CN207599140U (en) A kind of descending pipelines into ditch device
CN110143531A (en) Self-climbing cranes and wind power maintenance equipment
CN204980974U (en) Pulley gear is used to drilling rod hoisting cable direction of geological drilling rig
CN205132977U (en) Movable swing arm tower machine installation wire rope
CN206278860U (en) The safe reel wire rope winding device of steel wire rope winding type ship lift
CN206735620U (en) A kind of nuclear steam turbine low pressure rotor boom hoisting
CN104176660B (en) Tower crane amplitude variation maintenance, replacing options
CN206692201U (en) A kind of nuclear steam turbine high pressure rotor boom hoisting
CN205590182U (en) Tower crane dismantles part and puts from hoist and mount
CN222947932U (en) Sectional hoisting equipment
CN214935549U (en) Underwater structural part hoisting device for ocean platform
CN107445064B (en) Balance pulley and pulley block of crane for hoisting molten metal
CN206427917U (en) A kind of diesel locomotive cylinder jacket lifting device
CN205204713U (en) Crane equipped with travelable counterweight unit
CN104386598A (en) Dismantling method for tower crane jib
CN206016704U (en) A kind of drilling rod location structure and the rotary drilling rig with which of rotary drilling rig
CN206438402U (en) A kind of suspension bridge sling replacing system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20201110

RJ01 Rejection of invention patent application after publication