CN111894026A - Tunnel type pile foundation bearing platform combined anchorage structure and installation method thereof - Google Patents
Tunnel type pile foundation bearing platform combined anchorage structure and installation method thereof Download PDFInfo
- Publication number
- CN111894026A CN111894026A CN202010976553.6A CN202010976553A CN111894026A CN 111894026 A CN111894026 A CN 111894026A CN 202010976553 A CN202010976553 A CN 202010976553A CN 111894026 A CN111894026 A CN 111894026A
- Authority
- CN
- China
- Prior art keywords
- tunnel
- pile foundation
- pile
- bearing platform
- tunnel type
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A10/00—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
- Y02A10/23—Dune restoration or creation; Cliff stabilisation
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明提供了一种隧洞式桩基承台组合锚碇结构,锚碇结构设置在斜向的坡体内,坡体沿横向设有隧洞,锚碇结构包括隧洞式承台和桩基,隧洞式承台沿水平方向嵌入隧洞设置,从隧洞的下端竖直向下开挖形成桩孔,桩孔内设置桩基,桩基与隧洞式承台连接,隧洞式承台前端包括上下依次连接斜面段和竖直段,斜面段埋设有若干锚索;本发明的优点在于:在陡峭坡体上开挖隧洞提供锚碇施工空间,有效地减小了放坡开挖施工桩基承台的土石方开挖量,节约施工成本;利用桩基深入较好的地质层以提供水平抗力,结构安全可靠;适用于地形陡峭、地质不良的恶劣条件,施工工艺简单、结构安全可靠、成本相对经济。
The invention provides a tunnel-type pile foundation bearing platform combined anchorage structure. The anchorage structure is arranged in an oblique slope body, and the slope body is provided with a tunnel along the transverse direction. The anchorage structure includes a tunnel-type bearing platform and a pile foundation. The cap is embedded in the tunnel along the horizontal direction, and the pile hole is excavated vertically downward from the lower end of the tunnel. The pile foundation is arranged in the pile hole, and the pile foundation is connected with the tunnel-type cap. There are several anchor cables buried in the slope section and the vertical section; the advantages of the invention are: excavating the tunnel on the steep slope body provides the anchorage construction space, effectively reducing the earth and stone opening of the pile foundation bearing platform in the grading excavation construction. The amount of excavation can save the construction cost; the pile foundation is used to penetrate into the better geological layer to provide horizontal resistance, and the structure is safe and reliable; it is suitable for harsh conditions with steep terrain and poor geological conditions, with simple construction technology, safe and reliable structure, and relatively economical cost.
Description
技术领域technical field
本发明涉及基础工程领域,尤其涉及一种隧洞式桩基承台组合锚碇结构及其安装方法。The invention relates to the field of foundation engineering, in particular to a tunnel-type pile foundation bearing platform combined anchor structure and an installation method thereof.
背景技术Background technique
在基础工程中,以承受水平力为主的锚碇结构是一种重要的基础类型,其常见结构形式有重力式锚碇、桩基承台锚碇、岩锚等。重力式锚碇一般用于地势较平坦、表层地质良好的区域,当表层地质不良时,可增设桩基提供水平抗力,由此衍生出桩基承台锚碇形式;而对于陡峭山坡地带、不适于大面积开挖坡体,若地质条件良好,则可采用岩锚,将锚索打入硬质岩层以提供水平抗力。但对于地形陡峭、地质不良的山区恶劣条件下,常规的锚碇结构形式均表现出适用性不强的缺点。针对此类问题,一般在设计选址时尽量避免在如此恶劣的区域建造锚碇,但确因工程需要无法避免时,则仍需对其进行探索研究。In foundation engineering, the anchor structure that mainly bears horizontal force is an important foundation type. Its common structural forms include gravity anchors, pile foundation anchors, rock anchors, etc. Gravity anchors are generally used in areas with relatively flat terrain and good surface geology. When the surface geology is poor, a pile foundation can be added to provide horizontal resistance, which derives the form of pile foundation caps. For excavating slopes in large areas, if the geological conditions are good, rock anchors can be used to drive the anchor cables into hard rock layers to provide horizontal resistance. However, under the harsh conditions of mountainous areas with steep terrain and bad geology, the conventional anchorage structures all show the shortcomings of poor applicability. In response to such problems, the construction of anchorages in such poor areas is generally avoided in the design and site selection. However, when it is unavoidable due to engineering needs, it is still necessary to explore and study them.
发明内容SUMMARY OF THE INVENTION
本发明的目的是提供一种隧洞式桩基承台组合锚碇结构及其安装方法。The purpose of the present invention is to provide a tunnel-type pile foundation bearing platform combined anchor structure and its installation method.
为了实现上述目的,本发明的技术方案是:In order to achieve the above object, the technical scheme of the present invention is:
一种隧洞式桩基承台组合锚碇结构,其特征在于,所述锚碇结构设置在斜向的坡体内,所述坡体沿横向设有隧洞,所述锚碇结构包括一隧洞式承台和若干桩基,所述隧洞式承台沿水平方向嵌入隧洞设置,所述隧洞的下端低于隧洞入口处的坡体,所述隧洞的下端与坡体之间形成一台阶,从所述隧洞的下端竖直向下开挖形成若干圆柱状的桩孔,每一所述桩孔内设置一桩基,所述桩基的上端与隧洞式承台的下端连接,A tunnel-type pile foundation bearing platform combined anchoring structure is characterized in that the anchoring structure is arranged in an oblique slope body, the slope body is provided with a tunnel along the lateral direction, and the anchoring structure comprises a tunnel-type bearing The tunnel-type cap is embedded in the tunnel along the horizontal direction, the lower end of the tunnel is lower than the slope body at the entrance of the tunnel, and a step is formed between the lower end of the tunnel and the slope body. The lower end of the tunnel is excavated vertically downward to form a number of cylindrical pile holes, and a pile foundation is arranged in each of the pile holes, and the upper end of the pile foundation is connected with the lower end of the tunnel-type cap.
所述隧洞式承台的上端呈弧形,所述隧洞式承台的上端由两侧至中央逐渐升高,所述隧洞式承台的上端由前至后向下倾斜设置,所述隧洞式承台的前端包括上下依次连接的斜面段和竖直段,所述斜面段由上至下向前倾斜设置,所述斜面段埋设有若干锚索。The upper end of the tunnel-type bearing platform is arc-shaped, the upper end of the tunnel-type bearing platform is gradually raised from both sides to the center, and the upper end of the tunnel-type bearing platform is inclined downward from front to back. The front end of the bearing platform includes an inclined plane section and a vertical section connected up and down in sequence, the inclined plane section is inclined forward from top to bottom, and several anchor cables are embedded in the inclined plane section.
一种隧洞式桩基承台组合锚碇结构的安装方法,其特征在于,包括以下步骤:A method for installing a tunnel-type pile foundation bearing platform combined anchor structure, characterized in that it comprises the following steps:
步骤1)根据设计图纸,放样隧洞位置,进行隧洞开挖;Step 1) According to the design drawings, stake out the location of the tunnel and excavate the tunnel;
步骤2)开挖过程按要求施作拱架、锚杆和喷护,使得拱顶、边墙、仰拱结构满足施工安全需求,仰拱施工喷护时留出桩基的桩口位置;Step 2) Arch frame, anchor rod and spray protection are applied as required in the excavation process, so that the vault, side wall and inverted arch structure meet the construction safety requirements, and the position of the pile opening of the pile foundation is reserved during the construction of the inverted arch spray protection;
步骤3)完成隧洞开挖支护,修筑锁口,并人工开挖桩孔和桩基;Step 3) Complete the tunnel excavation and support, build the lock, and manually excavate the pile hole and pile foundation;
步骤4)桩基完成后,安装钢筋笼、浇注混凝土,按要求留出桩基的桩头钢筋,与隧洞式承台连接锚固;Step 4) After the pile foundation is completed, install the reinforcement cage, pour concrete, and leave the pile head reinforcement of the pile foundation as required to connect and anchor with the tunnel cap;
步骤5)凿除桩头,修整桩头外伸钢筋,进行隧洞式承台的钢筋绑扎安装;Step 5) Chisel off the pile head, trim the overhanging steel bars of the pile head, and install the steel bar binding of the tunnel-type cap;
步骤6)根据设计要求的数量及位置安装锚索,安装隧洞端口模板后,对隧洞式承台浇筑混凝土,使桩基和锚索通过隧洞式承台连接形成整体。Step 6) Install the anchor cables according to the quantity and position required by the design. After installing the tunnel port formwork, pour concrete on the tunnel cap, so that the pile foundation and the anchor cables are connected through the tunnel cap to form a whole.
本发明的优点在于:在陡峭坡体上开挖隧洞提供锚碇施工空间,有效地减小了放坡开挖施工桩基承台的土石方开挖量,节约施工成本;利用桩基深入较好的地质层以提供水平抗力,结构安全可靠;适用于地形陡峭、地质不良的恶劣条件,施工工艺简单、结构安全可靠、成本相对经济。The advantages of the invention are: excavating a tunnel on a steep slope body provides an anchorage construction space, effectively reducing the amount of earth and stone excavation for the pile foundation cap of the grading excavation construction, and saving the construction cost; it is better to use the pile foundation to penetrate deeply. It is suitable for the harsh conditions of steep terrain and bad geology, with simple construction technology, safe and reliable structure, and relatively economical cost.
附图说明Description of drawings
图1为本发明的侧面结构示意图;Fig. 1 is the side structure schematic diagram of the present invention;
图2为本发明中隧洞式承台的正面结构示意图。FIG. 2 is a schematic view of the front structure of the tunnel-type cap in the present invention.
附图标记:Reference number:
1桩基2隧洞式承台21斜面段22竖直段1
3锚索4坡体5隧洞。3
具体实施方式Detailed ways
下面将结合附图对本发明的技术方案进行清楚、完整地描述,显然,所描述的实施例是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
本发明公开了一种隧洞式桩基承台组合锚碇结构,如图1所示,所述锚碇结构设置在斜向的坡体4内,所述坡体4沿横向设有隧洞5,所述锚碇结构包括一隧洞式承台2和若干桩基1,所述隧洞式承台2沿水平方向嵌入隧洞5设置,所述隧洞5的下端低于隧洞5入口处的坡体4,所述隧洞5的下端与坡体4之间形成一台阶,从所述隧洞5的下端竖直向下开挖形成若干圆柱状的桩孔,每一所述桩孔内设置一桩基1,所述桩基1的上端与隧洞式承台2的下端连接,所述桩基1竖直向下深入下层良好的地质层,以抵抗锚碇结构所承受的水平力。The present invention discloses a tunnel-type pile foundation bearing platform combined anchorage structure. As shown in FIG. 1 , the anchorage structure is arranged in an
如图1和图2所示,所述隧洞式承台2的上端呈弧形,所述隧洞式承台2的上端由两侧至中央逐渐升高,所述隧洞式承台2的上端由前至后向下倾斜设置,所述隧洞式承台2的前端包括上下依次连接的斜面段21和竖直段22,所述斜面段21由上至下向前倾斜设置,所述斜面段21埋设有若干锚索3。As shown in FIG. 1 and FIG. 2 , the upper end of the tunnel-
本发明还公开了一种隧洞式桩基承台组合锚碇结构的安装方法,包括以下步骤:The invention also discloses an installation method of the tunnel-type pile foundation cap combined anchorage structure, comprising the following steps:
步骤1)根据设计图纸,放样隧洞5位置,进行隧洞5开挖;Step 1) According to the design drawings, stake out the position of the tunnel 5 and excavate the tunnel 5;
步骤2)开挖过程按要求施作拱架、锚杆和喷护,使得拱顶、边墙、仰拱结构满足施工安全需求,仰拱施工喷护时留出桩基1的桩口位置;Step 2) Arch frame, anchor rod and spray protection are applied in the excavation process as required, so that the vault, side wall and inverted arch structure meet the construction safety requirements, and the position of the pile mouth of
步骤3)完成隧洞5开挖支护,修筑锁口,并人工开挖桩孔和桩基1;Step 3) Complete the excavation and support of the tunnel 5, build the lock, and manually excavate the pile hole and the
步骤4)桩基1完成后,安装钢筋笼、浇注混凝土,按要求留出桩基1的桩头钢筋,桩头钢筋与隧洞式承台2连接锚固;Step 4) After the
步骤5)凿除桩头,修整桩头外伸钢筋,进行隧洞式承台2的钢筋绑扎安装;Step 5) Chisel off the pile head, trim the overhanging steel bars of the pile head, and install the steel bar binding of the tunnel-
步骤6)根据设计要求的数量及位置安装锚索3,安装隧洞5端口模板后,对隧洞式承台2浇筑混凝土,使桩基1和锚索3通过隧洞式承台2连接形成整体。Step 6) Install the anchor cables 3 according to the quantity and position required by the design. After installing the tunnel 5 port formwork, pour concrete on the
具体实施时,某山区大跨度拱桥所处地形条件恶劣,横跨河流、两岸山坡陡峭,桥梁两端直接与隧道相连,桥址附近基本无良好的施工场地,采用缆索吊进行拱肋斜拉扣挂悬拼安装,由于山坡陡峭且附近有多条民用电缆架空穿过,迁改拆除困难、费用巨大,导致临时施工锚碇只能布置在隧道洞口两侧。During the specific implementation, the terrain conditions of a large-span arch bridge in a mountainous area are harsh, spanning a river and the slopes on both sides are steep, both ends of the bridge are directly connected to the tunnel, and there is basically no good construction site near the bridge site. Due to the steep hillside and the overhead crossing of several civil cables nearby, the relocation and demolition are difficult and the cost is huge, so the temporary construction anchors can only be arranged on both sides of the tunnel entrance.
考虑山体表层风化严重,表层50m范围内地质条件差,存在溶洞、且裂隙较发育,不适于应用岩锚结构,故采用本发明涉及的一种隧洞式桩基承台组合锚碇结构进行施工。Considering the serious weathering of the mountain surface, poor geological conditions within 50m of the surface layer, there are karst caves, and cracks are relatively developed, which is not suitable for the application of the rock anchor structure, so the tunnel-type pile foundation bearing platform combination anchor anchor structure involved in the present invention is used for construction.
根据锚碇需要承受的外荷载、坡体4的坡度、地质情况等,所述锚碇结构包含四根直径φ2m的桩基1,四根桩基1由一个隧洞式承台2连成整体,所述隧洞式承台2的平面尺寸为8×8m,隧洞式承台2外露的斜面段21上根据受力情况布置数组锚索3。According to the external load that the anchorage needs to bear, the slope of the
最后应说明的是:以上各实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述各实施例对本发明进行了详细的说明,本领域的普通技术人员应当理解:其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分或者全部技术特征进行等同替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的范围。Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, but not to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those of ordinary skill in the art should understand that: The technical solutions described in the foregoing embodiments can still be modified, or some or all of the technical features thereof can be equivalently replaced; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the technical solutions of the embodiments of the present invention. scope.
Claims (2)
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202010280373.4A CN111608196A (en) | 2020-04-10 | 2020-04-10 | A tunnel-type pile foundation bearing platform combined anchor structure and its installation method |
| CN2020102803734 | 2020-04-10 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN111894026A true CN111894026A (en) | 2020-11-06 |
| CN111894026B CN111894026B (en) | 2024-09-13 |
Family
ID=72203742
Family Applications (2)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010280373.4A Pending CN111608196A (en) | 2020-04-10 | 2020-04-10 | A tunnel-type pile foundation bearing platform combined anchor structure and its installation method |
| CN202010976553.6A Active CN111894026B (en) | 2020-04-10 | 2020-09-16 | A construction method for a tunnel type pile foundation cap combined anchor structure |
Family Applications Before (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202010280373.4A Pending CN111608196A (en) | 2020-04-10 | 2020-04-10 | A tunnel-type pile foundation bearing platform combined anchor structure and its installation method |
Country Status (1)
| Country | Link |
|---|---|
| CN (2) | CN111608196A (en) |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112482225B (en) * | 2020-11-16 | 2022-08-26 | 贵州路桥集团有限公司 | Arch bridge arch center excavation construction method |
| CN115094849B (en) * | 2022-07-05 | 2023-09-08 | 中铁建大桥工程局集团第五工程有限公司 | An anchor cable support method for the cross section of the diversion tunnel |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101864737A (en) * | 2010-06-11 | 2010-10-20 | 中铁大桥局集团有限公司 | Construction Method of Secondary Vertical Rotation of Arch Rib of Long-span Steel Arch Bridge |
| CN204266121U (en) * | 2014-11-12 | 2015-04-15 | 中铁十八局集团有限公司 | Button anchor system combinations formula pile foundation support table anchorage |
| WO2015152826A1 (en) * | 2014-04-03 | 2015-10-08 | Nanyang Technological University | Method for installing a multi-section suction caisson |
| CN206173990U (en) * | 2016-11-18 | 2017-05-17 | 江苏交科交通设计研究院有限公司 | Asymmetric clump of piles cushion cap formula anchorage structure suitable for suspension bridge |
| CN107059617A (en) * | 2016-12-24 | 2017-08-18 | 中铁十八局集团有限公司 | A kind of interim anchorage of combined type |
| CN108867376A (en) * | 2018-06-14 | 2018-11-23 | 张学武 | Face anchor system and its construction method after mating type forever |
-
2020
- 2020-04-10 CN CN202010280373.4A patent/CN111608196A/en active Pending
- 2020-09-16 CN CN202010976553.6A patent/CN111894026B/en active Active
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101864737A (en) * | 2010-06-11 | 2010-10-20 | 中铁大桥局集团有限公司 | Construction Method of Secondary Vertical Rotation of Arch Rib of Long-span Steel Arch Bridge |
| WO2015152826A1 (en) * | 2014-04-03 | 2015-10-08 | Nanyang Technological University | Method for installing a multi-section suction caisson |
| CN204266121U (en) * | 2014-11-12 | 2015-04-15 | 中铁十八局集团有限公司 | Button anchor system combinations formula pile foundation support table anchorage |
| CN206173990U (en) * | 2016-11-18 | 2017-05-17 | 江苏交科交通设计研究院有限公司 | Asymmetric clump of piles cushion cap formula anchorage structure suitable for suspension bridge |
| CN107059617A (en) * | 2016-12-24 | 2017-08-18 | 中铁十八局集团有限公司 | A kind of interim anchorage of combined type |
| CN108867376A (en) * | 2018-06-14 | 2018-11-23 | 张学武 | Face anchor system and its construction method after mating type forever |
Also Published As
| Publication number | Publication date |
|---|---|
| CN111894026B (en) | 2024-09-13 |
| CN111608196A (en) | 2020-09-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN113622956B (en) | Construction method for high-speed railway double-track tunnel to penetrate through vertical mud gushing karst cave | |
| CN102758632B (en) | Rock stratum double initial support layering method for establishing large-scale underground structure | |
| CN101338678B (en) | Supporting arch hidden digging top-down construction method | |
| CN105064397B (en) | Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation | |
| CN101215815B (en) | Method for building integrated cantilever structure composite road adapted for precipitous mountainous area | |
| CN106337686A (en) | Rock stratum underground excavation three-story subway station umbrella cover structure and construction method thereof | |
| CN107130613A (en) | Large span tunnel is just wearing the retaining structure and its construction method of existing barricade | |
| CN111622251A (en) | Assembly type open caisson structure and construction method thereof | |
| US12123157B1 (en) | Delaminated subway station structure in sea-land connection region and construction method thereof | |
| CN109441456A (en) | A kind of the tunnel structure and its construction method of weakness Facility-sliding strata | |
| CN111305219A (en) | Existing tunnel spanning system and construction method based on foundation pit jumping and arch cover conversion | |
| CN110017149A (en) | A kind of underground structure and construction method of underground excavation and construction of arch cover | |
| CN112095656A (en) | A tension-compression composite prestressed anchor cable retaining wall structure | |
| CN111254966A (en) | Bridge abutment and pier-column foundation structure in mountainous area and its construction method | |
| CN101838957B (en) | Integral type T-shaped outer cantilever roads and construction method thereof | |
| CN107653886A (en) | A kind of building supporting construction and its implementation applied to foundation ditch landform | |
| CN219410378U (en) | Rock slope overhanging type road structure | |
| CN111894026B (en) | A construction method for a tunnel type pile foundation cap combined anchor structure | |
| CN211816326U (en) | Combined retaining structure of half H-shaped anti-slide pile and retaining plate | |
| CN206888990U (en) | A kind of Shallow Covered Metro Station separates open type structure | |
| CN105386779A (en) | Arch column method for building large-scale underground structure in shallow buried rock stratums | |
| CN216765941U (en) | Tunnel decompression load shedding structure under bias voltage state | |
| CN101368388B (en) | Anchor pipe skeleton support method | |
| CN100513705C (en) | Underground Beam-Pile Frame Structure for Slope Reinforcement | |
| CN115506382A (en) | Construction method for pile plate wall of island building platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| OL01 | Intention to license declared | ||
| OL01 | Intention to license declared | ||
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20201106 Assignee: SHANGHAI URBAN CONSTRUCTION RILI SPECIAL ASPHALT Co.,Ltd. Assignor: THE CIVIL CONSTRUCTION ENGINEERING CO., LTD. OF CRECSH Group Contract record no.: X2025980019582 Denomination of invention: A construction method of a tunnel-type pile foundation cap combined anchor structure Granted publication date: 20240913 License type: Open License Record date: 20250829 |
|
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20201106 Assignee: Shanghai Jikezhu Technology Co.,Ltd. Assignor: SHANGHAI CIVIL ENGINEERING Co.,Ltd. OF CREC|THE CIVIL CONSTRUCTION ENGINEERING CO., LTD. OF CRECSH Group Contract record no.: X2025980023609 Denomination of invention: A construction method of a tunnel-type pile foundation cap combined anchor structure Granted publication date: 20240913 License type: Open License Record date: 20250923 |