CN111411980A - A water conveyance tunnel lining structure and construction method capable of withstanding high internal and external water pressure - Google Patents

A water conveyance tunnel lining structure and construction method capable of withstanding high internal and external water pressure Download PDF

Info

Publication number
CN111411980A
CN111411980A CN202010327605.7A CN202010327605A CN111411980A CN 111411980 A CN111411980 A CN 111411980A CN 202010327605 A CN202010327605 A CN 202010327605A CN 111411980 A CN111411980 A CN 111411980A
Authority
CN
China
Prior art keywords
lining
layer
water
wall
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010327605.7A
Other languages
Chinese (zh)
Other versions
CN111411980B (en
Inventor
李炳奇
李泽阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010327605.7A priority Critical patent/CN111411980B/en
Publication of CN111411980A publication Critical patent/CN111411980A/en
Application granted granted Critical
Publication of CN111411980B publication Critical patent/CN111411980B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03BMACHINES OR ENGINES FOR LIQUIDS
    • F03B13/00Adaptations of machines or engines for special use; Combinations of machines or engines with driving or driven apparatus; Power stations or aggregates
    • F03B13/06Stations or aggregates of water-storage type, e.g. comprising a turbine and a pump
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/16Mechanical energy storage, e.g. flywheels or pressurised fluids

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides a water-conveying tunnel lining structure capable of bearing high internal and external water pressure and a construction method, wherein the structure comprises an outer lining layer and an inner lining layer, wherein the inner lining layer consists of a first lining, a high-strength force-transmission water-permeable grid and a second lining; wherein, the outer lining layer is arranged on the inner wall of the water delivery tunnel; the inner wall of the outer lining layer is provided with the first inner lining, and grouting is carried out between the outer lining layer and the first inner lining to form a grouting layer, and the grouting layer and the outer lining layer form an integrated outer lining layer; the high-strength force transmission water permeable grating is arranged on the inner wall of the first lining; and a second lining is arranged on the inner wall of the high-strength force-transmission water-permeable grid. The water delivery tunnel lining structure provided by the invention strictly controls the overhigh internal and external water pressure which can be possibly born by the lining within an allowable range, avoids the risk of internal water leakage caused by tensile cracking of the lining, simultaneously eliminates the hidden trouble of buckling, deformation and instability of the lining caused by high external water pressure in the emptying period, and fundamentally solves the safety problem of operation of the high internal and external water pressure tunnel lining structure.

Description

一种可承受高内外水压的输水隧洞衬砌结构及施工方法A water conveyance tunnel lining structure and construction method capable of withstanding high internal and external water pressure

技术领域technical field

本发明属于水利水电领域,涉及一种输水隧洞衬砌结构及施工方法,具体涉及一种可承受高内外水压的输水隧洞衬砌结构及施工方法。The invention belongs to the field of water conservancy and hydropower, and relates to a water conveyance tunnel lining structure and a construction method, in particular to a water conveyance tunnel lining structure and a construction method that can withstand high internal and external water pressures.

背景技术Background technique

随着我国的经济社会发展,用电需求和用电峰谷差持续加强,用户对供电质量要求不断提高,随机性、间歇性新能源大规模开发以及事故备用及调相等需求加大,对水电站的发展提出了更高要求。近些年,抽水蓄能电站作为灵活性较高的发电站,既具备常规发电站的调峰、调相和备用的功能,同时又能把低成本的电能,转换为高收益的峰荷电能,从而达到能源的有效利用。With my country's economic and social development, the demand for electricity and the peak-to-valley difference in electricity consumption continue to increase, users' requirements for power supply quality continue to increase, and the large-scale development of random and intermittent new energy sources, as well as the increasing demand for emergency backup and adjustment, have increased the demand for hydropower stations. development has put forward higher requirements. In recent years, pumped storage power station, as a power station with high flexibility, not only has the functions of peak regulation, phase regulation and backup of conventional power stations, but also converts low-cost electric energy into high-yield peak load energy. , so as to achieve the efficient use of energy.

水力发电的机理是通过隧洞管道把大坝储水引导至发电机,如图1所示,将势能转化为动能再转化为电能,通常这种隧洞具有高内外水压的特点。特别是在抽水蓄能发电站工程中,运行水头已经从500m已发展至800m甚至更高,高内外水压导水隧洞作为抽水蓄能电站的关键性控制“咽喉”工程,其安全运行关乎整个工程建设乃至周边人民生命财产安全。导水隧洞一般是在隧洞内部贴设薄壁钢管,该钢管不仅需承受充水期的高内水压力、和放空期的山体水高外水压力、以及围岩变形荷载作用等。目前,传统薄壁钢管在内水放空时,由于山体外水压作用可能导致薄壁钢管发生屈曲变形破坏,这给抽水蓄能电站的建造以及安全运营造成了很大困扰。因此,在设计导水钢管时,在考虑内水压力的同时还需考虑在放空时候的外水压作用下的破坏,并且为了防止山体滑坡等灾害还需考虑避免内水外渗的结构型式。为了提高导水隧洞抵抗外水压能力的方法,一方面可以考虑通过加筋高度及间距影响设计增大承受外水压能力;另外一方面通过增加钢管厚度增大承受外压能力,但是相对于内压而言会产生过剩设计,不经济,产生浪费。The mechanism of hydroelectric power generation is to guide the water stored in the dam to the generator through the tunnel pipeline, as shown in Figure 1, to convert the potential energy into kinetic energy and then into electrical energy. Usually, this kind of tunnel has the characteristics of high internal and external water pressure. Especially in the pumped storage power station project, the operating water head has grown from 500m to 800m or even higher. The high internal and external water pressure diversion tunnel is the key control "throat" project of the pumped storage power station, and its safe operation is related to the whole Project construction and the safety of life and property of the surrounding people. Generally, thin-walled steel pipes are installed inside the tunnels for water diversion tunnels. The steel pipes not only need to withstand the high internal water pressure during the water filling period, the high external water pressure of the mountain water during the venting period, and the deformation load of the surrounding rock, etc. At present, when the traditional thin-walled steel pipe is emptied in the internal water, the thin-walled steel pipe may be buckling and deformed due to the water pressure outside the mountain, which has caused great difficulties in the construction and safe operation of the pumped storage power station. Therefore, when designing the water-conducting steel pipe, it is necessary to consider the damage under the action of the external water pressure when venting while considering the internal water pressure, and in order to prevent landslides and other disasters, it is also necessary to consider the structure type that avoids the external seepage of the internal water. In order to improve the ability of water-conducting tunnels to resist external water pressure, on the one hand, it can be considered to increase the ability to withstand external water pressure by affecting the design by the height and spacing of reinforcement; In terms of internal pressure, there will be excess design, which is uneconomical and wasteful.

因此,需根据实际地质构造及结构力学机理,研发一种经济适用的、可承受高内外水压的新型抽水蓄能电站导水隧洞的衬砌结构型式,实现合理承受内外水压的结构设计,将衬砌可能承受的过高内外水压严格控制在允许范围内,避免衬砌受拉开裂产生内水外渗的风险,同时消除放空期高外水压导致衬砌屈曲变形失稳的隐患,从根本上解决高内外水压隧洞衬砌结构运行的安全问题,为突破抽水蓄能电站行业技术瓶颈、推动行业健康快速发展提供科技支撑。Therefore, according to the actual geological structure and structural mechanics mechanism, it is necessary to develop an economical and applicable new type of lining structure type for the water conduction tunnel of the pumped storage power station that can withstand high internal and external water pressures, so as to realize the structural design that reasonably withstands the internal and external water pressures. The excessive internal and external water pressure that the lining may bear is strictly controlled within the allowable range to avoid the risk of internal water seepage caused by the lining cracking under tension, and at the same time eliminate the hidden danger of buckling deformation and instability of the lining caused by high external water pressure during the venting period, and fundamentally solve the problem. The safety of the operation of the tunnel lining structure with high internal and external water pressure provides scientific and technological support for breaking through the technical bottleneck of the pumped storage power station industry and promoting the healthy and rapid development of the industry.

发明内容SUMMARY OF THE INVENTION

为了解决上述问题,本发明的目的在于提供一种可承受高内外水压的输水隧洞衬砌结构,该输水隧洞衬砌结构将衬砌可能承受的过高内外水压严格控制在允许范围内,避免衬砌受拉开裂产生内水外渗的风险,同时消除放空期高外水压导致衬砌屈曲变形失稳的隐患,从根本上解决高内外水压隧洞衬砌结构运行的安全问题。In order to solve the above problems, the purpose of the present invention is to provide a water conveyance tunnel lining structure that can withstand high internal and external water pressure. The risk of internal water seepage caused by the lining cracking under tension, at the same time, eliminates the hidden danger of buckling deformation and instability of the lining caused by high external water pressure during the venting period, and fundamentally solves the safety problem of the operation of the tunnel lining structure with high internal and external water pressure.

本发明的另一目的在于提供一种上述可承受高内外水压的输水隧洞衬砌结构的施工方法。Another object of the present invention is to provide a construction method for the above-mentioned water conveyance tunnel lining structure that can withstand high internal and external water pressure.

为了实现上述目的,本发明提供一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层和内衬砌层,该内衬砌层由第一内衬、高强传力透水格栅和第二内衬构成;In order to achieve the above purpose, the present invention provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure, comprising an outer lining layer and an inner lining layer, the inner lining layer is composed of a first inner lining, a high-strength force-transmitting permeable grille and a second lining layer. Two inner linings;

其中,该外衬砌层设置于输水隧洞内壁;Wherein, the outer lining layer is arranged on the inner wall of the water conveyance tunnel;

该外衬砌层的内壁设置该第一内衬,并在该外衬砌层和该第一内衬之间灌浆,形成一灌浆层,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer is provided with the first inner lining, and grouting is performed between the outer lining layer and the first inner lining to form a grouting layer, and the grouting layer and the outer lining layer form an integrated outer lining layer;

在该第一内衬内壁设置该高强传力透水格栅;The high-strength force-transmitting water-permeable grille is arranged on the inner wall of the first lining;

在该高强传力透水格栅内壁设置第二内衬。A second lining is arranged on the inner wall of the high-strength force-transmitting permeable grille.

优选地,所述外衬砌层为混凝土或混凝土管片。Preferably, the outer lining layer is concrete or concrete segments.

优选地,所述第一内衬为钢衬筒、加劲肋钢筒、PVC管、加筋环钢筒或碳纤维复合钢筒。Preferably, the first inner lining is a steel lining cylinder, a stiffening rib steel cylinder, a PVC pipe, a reinforced ring steel cylinder or a carbon fiber composite steel cylinder.

优选地,所述第二内衬为素混凝土、预应力混凝土、钢筋混凝土、或混凝土管片。Preferably, the second lining is plain concrete, prestressed concrete, reinforced concrete, or concrete segment.

优选地,所述高强传力透水格栅为玻璃钢格栅、或高强钢塑土工格栅。Preferably, the high-strength force-transmitting water-permeable grid is a glass fiber reinforced plastic grid or a high-strength steel-plastic geogrid.

优选地,所述第二内衬穿设复数个水阀。Preferably, a plurality of water valves are pierced through the second inner liner.

优选地,该第二内衬的内壁设有一降糙率涂层,在该第二内衬和该降糙率涂层穿设复数个水阀,该降糙率涂层为有机硅涂层或氟碳漆涂料。Preferably, the inner wall of the second inner liner is provided with a roughness reduction coating, and a plurality of water valves are passed through the second inner liner and the roughness reduction coating, and the roughness reduction coating is a silicone coating or Fluorocarbon paint coating.

优选地,所述第二内衬内壁设有一防渗涂层,所述防渗涂层为聚脲弹性体涂层。Preferably, the inner wall of the second inner liner is provided with an impermeable coating, and the impermeable coating is a polyurea elastomer coating.

本发明还提供上述的可承受高内外水压的输水隧洞衬砌结构的施工方法,包括以下步骤:The present invention also provides the above-mentioned construction method for the lining structure of a water conveyance tunnel that can withstand high internal and external water pressure, comprising the following steps:

1)通过TBM或者NATM爆破掘出隧洞,然后在隧洞围岩上打入锚杆加固围岩;1) The tunnel is excavated by TBM or NATM blasting, and then bolts are driven into the surrounding rock of the tunnel to reinforce the surrounding rock;

在输水隧洞工程当中,施工前先对输水隧洞围岩打锚杆加固,然后再进行后续衬砌结构的施工。将锚杆打得深入一点,可起到加固隧洞围岩的作用。In the water conveyance tunnel project, the surrounding rock of the water conveyance tunnel is reinforced with bolts before construction, and then the subsequent construction of the lining structure is carried out. Drilling the bolt deeper can play a role in strengthening the surrounding rock of the tunnel.

2)在围岩上浇筑或者喷射混凝土,或安装混凝土管片,形成外衬砌层;2) Pouring or spraying concrete on the surrounding rock, or installing concrete segments to form an outer lining layer;

3)安装第一内衬,然后在该第一内衬和该外衬砌层之间进行灌浆,将外衬砌层与灌浆层粘合成一体化外衬砌;3) Install the first inner lining, then grouting between the first inner lining and the outer lining layer, and bonding the outer lining layer and the grouting layer to form an integrated outer lining;

4)在第一内衬内壁上铺设高强传力透水格栅;4) Lay high-strength force-transmitting permeable grille on the inner wall of the first lining;

5)在高强传力透水格栅内壁铺设第二内衬。5) Lay a second lining on the inner wall of the high-strength force-transmitting permeable grille.

更进一步地,增加步骤6)在所述第二内衬设置或预制复数个水阀;Further, adding step 6) setting or prefabricating multiple water valves on the second lining;

或,步骤6)在该内衬砌层的内壁涂覆一降糙率涂层,然后在所述第二内衬和该降糙率涂层设置或预制复数个水阀;Or, step 6) coating a roughness reduction coating on the inner wall of the inner lining layer, and then setting or prefabricating a plurality of water valves on the second inner lining and the roughness reduction coating;

或,步骤6)在所述第二内衬内壁涂覆一防渗层。Or, step 6) coating an impermeable layer on the inner wall of the second liner.

本发明的特点在于:The characteristics of the present invention are:

本发明在第一内衬安装后,在外衬砌层与第一内衬之间灌浆,使得将外衬砌层与灌浆形成的灌浆层粘合为一体化衬砌,从而可以避免第一内衬与外衬之间产生空隙从而导致内衬砌移动。In the present invention, after the first inner lining is installed, grouting is performed between the outer lining layer and the first inner lining, so that the outer lining layer and the grouting layer formed by grouting are bonded into an integrated lining, so that the first inner lining and the outer lining can be avoided. A gap is created between the linings causing movement of the lining.

当第二内衬为浇筑较好的混凝土结构时,表面光滑,无坑洼的情况,可以选择不涂覆降糙率涂层;当内衬砌层选用管片或喷射的混凝土时,由于表面光滑度不高,会有坑洼出现,比如管片接缝处,则需要涂覆降糙率涂层,以防高速水流下的冲蚀作用会破坏混凝土或者管片的结构。When the second lining is a well-cast concrete structure, the surface is smooth and there are no pits, and the roughness reduction coating can be chosen not to be applied; If the degree is not high, there will be potholes. For example, at the joints of the segments, a roughness reduction coating needs to be applied to prevent the erosion under the high-speed water flow from damaging the structure of the concrete or segment.

现有技术为了解决由于高内外水压造成输水隧洞衬砌结构的屈曲变形破坏,在使用钢材料(钢管)作为内衬的情况下,需要将钢管壁厚度增加到40-80mm,其中40mm位于高程较高的部位(近蓄水大坝端,外水压较低),80mm位于高程较低的部位(近发电机端,外水压较高),使得钢材料可以承受高内外水压,但是当内外水压不平衡时,巨大的水压差仍然会造成钢材料的屈曲变形,进而影响内衬砌层混凝土结构的安全稳定。而本发明通过设置高强传力透水格栅将第二内衬的支撑作用传到钢管上,防止钢管屈曲变形,从而可以降低钢衬筒的厚度。In the prior art, in order to solve the buckling deformation damage of the lining structure of the water conveyance tunnel caused by high internal and external water pressure, in the case of using steel material (steel pipe) as the lining, the thickness of the steel pipe wall needs to be increased to 40-80mm, of which 40mm is located at the elevation. The higher part (near the water storage dam end, the external water pressure is low), 80mm is located in the lower elevation part (near the generator end, the external water pressure is high), so that the steel material can withstand high internal and external water pressure, but When the internal and external water pressure is unbalanced, the huge water pressure difference will still cause the buckling deformation of the steel material, thereby affecting the safety and stability of the inner lining concrete structure. In the present invention, the supporting action of the second inner lining is transmitted to the steel pipe by arranging a high-strength force-transmitting permeable grille, so as to prevent the steel pipe from buckling and deforming, thereby reducing the thickness of the steel lining cylinder.

本发明还可以进一步在第二内衬砌层设置可双向通水的水阀,使得内外水压产生水压差时,可以让内部水通过水阀流入到高强传力透水格栅中或从高强传力透水格栅中流入到内衬砌层内,从而使得第二内衬内部水压和外部水压是几乎平衡的状态,能够避免较大压差破坏第二内衬的混凝土。In the present invention, a water valve that can pass water in both directions can be further arranged on the second inner lining layer, so that when a water pressure difference occurs between the internal and external water pressure, the internal water can flow into the high-strength transmission permeable grille through the water valve or from the high-strength transmission. The force permeable grid flows into the inner lining layer, so that the inner water pressure and the outer water pressure of the second inner lining are almost in a balanced state, which can prevent the concrete of the second inner lining from being damaged by a large pressure difference.

在本发明的结构中,因为混凝土通过高强传力格栅支撑着钢管,防止钢管产生变形屈曲。In the structure of the present invention, because the concrete supports the steel pipe through the high-strength force transmission grid, the steel pipe is prevented from being deformed and buckled.

本发明的有益效果在于:The beneficial effects of the present invention are:

本发明提供一种可承受高内外水压的输水隧洞衬砌结构,该输水隧洞衬砌结构将衬砌可能承受的高内外水压严格控制在允许范围内,避免衬砌受拉开裂产生内水外渗的风险,同时消除放空期高外水压导致衬砌屈曲变形失稳的隐患,从根本上解决高内外水压隧洞衬砌结构运行的安全问题。同时采用上述结构可以减少内衬钢管的厚度(40-80mm减少到10-40mm),减少了钢材的用量,降低了原料成本,运输成本,同时降低了施工的难度。The invention provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure. The water conveyance tunnel lining structure strictly controls the high internal and external water pressure that the lining may bear within an allowable range, and prevents the lining from being stretched and cracked to cause internal water seepage. At the same time, it eliminates the hidden danger of buckling deformation and instability of the lining caused by high external water pressure during the venting period, and fundamentally solves the safety problem of the operation of the high internal and external water pressure tunnel lining structure. At the same time, the above structure can reduce the thickness of the lined steel pipe (40-80mm to 10-40mm), reduce the amount of steel, reduce the cost of raw materials, transportation costs, and reduce the difficulty of construction.

附图说明Description of drawings

图1为现有通过隧洞管道把蓄水大坝储水引导至发电机的示意图。FIG. 1 is a schematic diagram of the existing water storage dam guiding the water storage dam to the generator through the tunnel pipeline.

图2为本发明提供的一优选实施例的可承受高内外水压的输水隧洞衬砌结构示意图。FIG. 2 is a schematic diagram of a lining structure of a water conveyance tunnel that can withstand high internal and external water pressure according to a preferred embodiment of the present invention.

图3为本发明提供的另一优选实施例的可承受高内外水压的输水隧洞衬砌结构示意图。3 is a schematic diagram of the lining structure of a water conveyance tunnel that can withstand high internal and external water pressure according to another preferred embodiment of the present invention.

图4为本发明提供的第三优选实施例的可承受高内外水压的输水隧洞衬砌结构示意图。FIG. 4 is a schematic diagram of the lining structure of a water conveyance tunnel that can withstand high internal and external water pressure according to a third preferred embodiment of the present invention.

图5为本发明提供的第四优选实施例的可承受高内外水压的输水隧洞衬砌结构示意图。FIG. 5 is a schematic diagram of the lining structure of a water conveyance tunnel that can withstand high internal and external water pressure according to the fourth preferred embodiment of the present invention.

附图标记reference number

1:外衬砌层;2:第一内衬;3:高强传力透水格栅;4:第二内衬;5:灌浆层;6:围岩;7:锚杆;8:水阀;9:降糙率涂层;10:防渗涂层。1: Outer lining layer; 2: First lining; 3: High-strength force-transmitting permeable grille; 4: Second lining; 5: Grouting layer; 6: Surrounding rock; 7: Anchor rod; 8: Water valve; 9 : Roughness reduction coating; 10: Anti-seepage coating.

具体实施方式Detailed ways

下面将对本发明的实施例进行详细、完善的描述,以使本发明的优点和特征能更易于被本领域技术人员理解,从而对本发明的保护范围做出更为清楚明确的界定。The embodiments of the present invention will be described in detail and complete below, so that the advantages and features of the present invention can be more easily understood by those skilled in the art, and the protection scope of the present invention can be more clearly defined.

设置是指在如果是浇筑的混凝的情况下,可在浇筑之后通过工具打通混凝土,安装上水阀;预制是指如果内衬是在施工现场以外的工厂等地方预制而成,那可提前预留水阀。Setting means that in the case of poured concrete, the concrete can be opened by tools after pouring, and the water valve can be installed; prefabrication means that if the lining is prefabricated in a factory other than the construction site, it can be prefabricated in advance. Reserve the water valve.

TBM为全断面隧道掘进机,硬岩TBM是利用旋转刀盘上的滚刀挤压剪切破岩,通过旋转刀盘上的铲斗齿拾起石渣,落入主机皮带机上向后输送,再通过牵引矿渣车或隧洞连续皮带机运渣到洞外。TBM is a full-section tunnel boring machine. The hard rock TBM uses the hob on the rotary cutter head to squeeze and shear the rock, pick up the gravel through the bucket teeth on the rotary cutter head, and fall on the main belt conveyor to transport it backwards. Then, the slag is transported to the outside of the tunnel by the traction slag truck or the tunnel continuous belt conveyor.

NATM为新奥法的英文简称。新奥法是以隧道工程经验和岩体力学的理论为基础,将锚杆和喷射混凝土组合在一起,作为主要支护手段的一种施工方法,经过一些国家的许多实践和理论研究,于60年代取得专利权并正式命名。在地下工程中都离不开NATM,新奥法几乎成为在软弱破碎围岩地段修筑隧道的一种基本方法。NATM is the English abbreviation of New Austrian Law. The new Austrian method is a construction method based on the experience of tunnel engineering and the theory of rock mechanics, combining bolts and shotcrete as the main supporting means. Obtained the patent right and officially named it. NATM is inseparable from underground engineering, and the new Austrian method has almost become a basic method for building tunnels in areas with weak and broken surrounding rock.

由于不同标号的混凝土的的抗压强度也不同,在工程上的适用范围也不相同,在水利工程中多使用标号在C25-C50的混凝土,但是标号不同混凝土也会影响工程造价。而为了输水隧洞衬砌结构安全,在选用混凝土时不同标号混凝土在衬砌施工上也会对衬砌结构产生影响,同时施工方法对于衬砌结构也会带来影响。Because the compressive strength of concrete with different grades is also different, the scope of application in engineering is also different. In hydraulic engineering, concrete with the grade of C25-C50 is mostly used, but the concrete with different grades will also affect the project cost. In order to ensure the safety of the lining structure of the water conveyance tunnel, different grades of concrete will also have an impact on the lining structure when selecting concrete, and the construction method will also have an impact on the lining structure.

本发明所用原料都为市场化商品,未详细说明的工艺都为本领域常规工艺。The raw materials used in the present invention are all marketed commodities, and the processes not described in detail are all conventional processes in the field.

实施例1Example 1

本实施例提供一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层1、内衬砌层;This embodiment provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure, including an outer lining layer 1 and an inner lining layer;

该内衬砌层由第一内衬2、高强传力透水格栅3和第二内衬4构成;The inner lining layer is composed of a first inner lining 2, a high-strength force-transmitting permeable grille 3 and a second inner lining 4;

其中,该外衬砌层1设置于输水隧洞内壁;Wherein, the outer lining layer 1 is arranged on the inner wall of the water conveyance tunnel;

该外衬砌层1的内壁设置该第一内衬2,并在该外衬砌层1和该第一内衬2之间灌浆,形成一灌浆层5,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer 1 is provided with the first inner lining 2, and grouting is performed between the outer lining layer 1 and the first inner lining 2 to form a grouting layer 5. The grouting layer and the outer lining layer form an integrated outer lining layer. lining;

在该第一内衬2内壁设置该高强传力透水格栅3;The high-strength force-transmitting permeable grille 3 is arranged on the inner wall of the first lining 2;

在该高强传力透水格栅3内壁设置第二内衬4。A second lining 4 is arranged on the inner wall of the high-strength force-transmitting permeable grille 3 .

在本实施例中外衬砌层使用喷射混凝土,第一内衬使用钢衬筒,高强传力透水格栅使用玻璃钢格栅,第二内衬使用预应力混凝土。In this embodiment, shotcrete is used for the outer lining layer, steel lining cylinder is used for the first inner lining, glass fiber reinforced plastic grating is used for the high-strength force-transmitting permeable grid, and prestressed concrete is used for the second inner lining.

施工方法为:The construction method is:

1)通过TBM掘出隧洞,然后在隧洞围岩6上打入锚杆7加固围岩6;1) The tunnel is excavated by TBM, and then bolts 7 are driven into the surrounding rock 6 of the tunnel to reinforce the surrounding rock 6;

在输水隧洞工程当中,常规需要施工前先对输水隧洞围岩打锚杆加固,然后再进行后续衬砌结构的施工。In the water conveyance tunnel project, it is conventionally necessary to reinforce the surrounding rock of the water conveyance tunnel with bolts before construction, and then carry out the subsequent construction of the lining structure.

2)在围岩上浇筑或者喷射混凝土,形成外衬砌层1;2) Pour or spray concrete on the surrounding rock to form the outer lining layer 1;

3)安装第一内衬2,然后在该第一内衬2和该外衬砌层1之间进行灌浆,将外衬砌层1与灌浆层5粘合成一体化外衬砌;3) install the first inner lining 2, then grouting is performed between the first inner lining 2 and the outer lining layer 1, and the outer lining layer 1 and the grouting layer 5 are bonded to form an integrated outer lining;

4)在第一内衬2内壁上铺设高强传力透水格栅3;4) Lay high-strength force-transmitting permeable grille 3 on the inner wall of the first lining 2;

5)在高强传力透水格栅3内壁铺设第二内衬4。5) Lay a second lining 4 on the inner wall of the high-strength force-transmitting permeable grille 3 .

当第二内衬使用施工性特好的预应力混凝土的时候,可以实现良好的防屈曲变形和防渗的效果。When the second inner lining is made of prestressed concrete with good workability, good buckling deformation and anti-seepage effects can be achieved.

当采用本实施例的结构时,由第二内衬直接承受内水压,第一内衬不直接承受内水压,同时由于第一内衬被第二内衬通过高强传力透水格栅支撑着,此时第一内衬为钢衬筒时可以减小厚度,约为20mm-40mm。When the structure of this embodiment is adopted, the second inner lining directly bears the internal water pressure, and the first inner lining does not directly bear the inner water pressure. At the same time, because the first inner lining is supported by the second inner lining through the high-strength force-transmitting permeable grille At this time, when the first liner is a steel liner, the thickness can be reduced, about 20mm-40mm.

实施例2Example 2

本实施例提供一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层1、内衬砌层;This embodiment provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure, including an outer lining layer 1 and an inner lining layer;

该内衬砌层由第一内衬2、高强传力透水格栅3和第二内衬4构成;The inner lining layer is composed of a first inner lining 2, a high-strength force-transmitting permeable grille 3 and a second inner lining 4;

其中,该外衬砌层1设置于输水隧洞内壁;Wherein, the outer lining layer 1 is arranged on the inner wall of the water conveyance tunnel;

该外衬砌层1的内壁设置该第一内衬2,并在该外衬砌层1和该第一内衬2之间灌浆,形成一灌浆层5,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer 1 is provided with the first inner lining 2, and grouting is performed between the outer lining layer 1 and the first inner lining 2 to form a grouting layer 5. The grouting layer and the outer lining layer form an integrated outer lining layer. lining;

在该第一内衬2内壁设置该高强传力透水格栅3;The high-strength force-transmitting permeable grille 3 is arranged on the inner wall of the first lining 2;

在该高强传力透水格栅3内壁设置第二内衬4;A second lining 4 is arranged on the inner wall of the high-strength force-transmitting permeable grille 3;

在该第二内衬4穿设复数个水阀8。A plurality of water valves 8 are passed through the second lining 4 .

在本实施例中外衬砌层为贴设的管片,第一内衬为加筋钢筒环,高强传力透水格栅为玻璃钢格栅,第二内衬为钢筋混凝土。In this embodiment, the outer lining layer is the attached segment, the first inner lining is a reinforced steel cylinder ring, the high-strength force-transmitting permeable grid is a glass fiber reinforced plastic grid, and the second inner lining is a reinforced concrete.

施工方法为:The construction method is:

1)通过NATM爆破掘出隧洞,然后在隧洞围岩6上打入锚杆7加固围岩6;1) The tunnel is excavated by NATM blasting, and then bolts 7 are driven into the surrounding rock 6 of the tunnel to reinforce the surrounding rock 6;

在输水隧洞工程当中,常规需要施工前先对输水隧洞围岩打锚杆加固,然后再进行后续衬砌结构的施工。In the water conveyance tunnel project, it is conventionally necessary to reinforce the surrounding rock of the water conveyance tunnel with bolts before construction, and then carry out the subsequent construction of the lining structure.

2)在围岩上浇筑或者喷射混凝土,形成外衬砌层1;2) Pour or spray concrete on the surrounding rock to form the outer lining layer 1;

3)安装第一内衬2,然后在该第一内衬2和该外衬砌层1之间进行灌浆,将外衬砌层1与灌浆层5粘合成一体化外衬砌;3) install the first inner lining 2, then grouting is performed between the first inner lining 2 and the outer lining layer 1, and the outer lining layer 1 and the grouting layer 5 are bonded to form an integrated outer lining;

4)在第一内衬2内壁上铺设高强传力透水格栅3;4) Lay high-strength force-transmitting permeable grille 3 on the inner wall of the first lining 2;

5)在高强传力透水格栅3内壁铺设第二内衬4;5) Lay the second lining 4 on the inner wall of the high-strength force-transmitting permeable grille 3;

6)在所述第二内衬4设置复数个水阀86) A plurality of water valves 8 are provided on the second lining 4

在本实施例中,当第一内衬为钢筒材质时,由于钢筒被第二内衬通过高强传力透水格栅支撑着,可以避免钢筒屈曲;同时,水在高强传力透水格栅和第二内衬内形成动态平衡,即:当第二内衬处于充水状态时,第二内衬内部的水流入透水格栅中,保护第二内衬不受内水压破坏;当第二内衬处于未充水状态时,高强传力透水格栅中的水流入内衬内,高强传力透水格栅中不必一直处于储水状态。这种设置使得当第二内衬为素混凝土等强度较低的材质时,可以通过水压平衡保护第二内衬。In this embodiment, when the first lining is made of steel cylinder, since the steel cylinder is supported by the second lining through the high-strength force-transmitting permeable grid, the buckling of the steel cylinder can be avoided; The grid and the second lining form a dynamic balance, that is: when the second lining is in a water-filled state, the water inside the second lining flows into the permeable grille to protect the second lining from being damaged by the inner water pressure; When the second inner lining is not filled with water, the water in the high-strength force-transmitting permeable grid flows into the inner lining, and the high-strength force-transmitting permeable grid does not have to be in a water storage state all the time. This arrangement makes it possible to protect the second inner lining through the balance of water pressure when the second inner lining is made of a material with lower strength such as plain concrete.

水阀门数量根据实际的管道的受力情况进行设计,一般是在管道受拉应力较大的地方设置即内衬顶部和下部设置。The number of water valves is designed according to the actual stress of the pipeline. Generally, it is set in the place where the tensile stress of the pipeline is large, that is, the top and bottom of the lining.

当采用本实施例的结构时,由于第二内衬两侧水压平衡,使得第二内衬安全性提高,而被第二内衬通过高强传力透水格栅支撑着的钢筒也可以减少厚度至10-30mm。When the structure of this embodiment is adopted, due to the balance of water pressure on both sides of the second lining, the safety of the second lining is improved, and the number of steel cylinders supported by the second lining through the high-strength force-transmitting permeable grille can also be reduced. Thickness to 10-30mm.

实施例3Example 3

本实施例提供一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层1、内衬砌层;This embodiment provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure, including an outer lining layer 1 and an inner lining layer;

该内衬砌层由第一内衬2、高强传力透水格栅3和第二内衬4构成;The inner lining layer is composed of a first inner lining 2, a high-strength force-transmitting permeable grille 3 and a second inner lining 4;

其中,该外衬砌层1设置于输水隧洞内壁;Wherein, the outer lining layer 1 is arranged on the inner wall of the water conveyance tunnel;

该外衬砌层1的内壁设置该第一内衬2,并在该外衬砌层1和该第一内衬2之间灌浆,形成一灌浆层5,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer 1 is provided with the first inner lining 2, and grouting is performed between the outer lining layer 1 and the first inner lining 2 to form a grouting layer 5. The grouting layer and the outer lining layer form an integrated outer lining layer. lining;

在该第一内衬2内壁设置该高强传力透水格栅3;The high-strength force-transmitting permeable grille 3 is arranged on the inner wall of the first lining 2;

在该高强传力透水格栅3内壁设置第二内衬4。A second lining 4 is arranged on the inner wall of the high-strength force-transmitting permeable grille 3 .

该第二内衬的内壁设有一降糙率涂层9,在该第二内衬4和该降糙率涂层9穿设复数个水阀8The inner wall of the second inner liner is provided with a roughness reduction coating 9 , and a plurality of water valves 8 are passed through the second inner lining 4 and the roughness reduction coating 9

在本实施例中外衬砌层为喷射的混凝土,第一内衬砌层为加劲肋钢筒,高强传力透水格栅为高强钢塑土工格栅,第二内衬为素混凝土,降糙率涂层为有机硅涂层。In this embodiment, the outer lining layer is sprayed concrete, the first inner lining layer is a stiffening rib steel cylinder, the high-strength force-transmitting water-permeable grid is a high-strength steel-plastic geogrid, the second lining layer is plain concrete, and the roughness reduction coating is used. For silicone coating.

施工方法为:The construction method is:

1)通过NATM爆破掘出隧洞,然后在隧洞围岩6上打入锚杆7加固围岩6;1) The tunnel is excavated by NATM blasting, and then bolts 7 are driven into the surrounding rock 6 of the tunnel to reinforce the surrounding rock 6;

在输水隧洞工程当中,常规需要施工前先对输水隧洞围岩打锚杆加固,然后再进行后续衬砌结构的施工。In the water conveyance tunnel project, it is conventionally necessary to reinforce the surrounding rock of the water conveyance tunnel with bolts before construction, and then carry out the subsequent construction of the lining structure.

2)在围岩上浇筑或者喷射混凝土,形成外衬砌层1;2) Pour or spray concrete on the surrounding rock to form the outer lining layer 1;

3)安装第一内衬2,然后在该第一内衬2和该外衬砌层1之间进行灌浆,将外衬砌层1与灌浆层5粘合成一体化外衬砌;3) install the first inner lining 2, then grouting is performed between the first inner lining 2 and the outer lining layer 1, and the outer lining layer 1 and the grouting layer 5 are bonded to form an integrated outer lining;

4)在第一内衬2内壁上铺设高强传力透水格栅3;4) Lay high-strength force-transmitting permeable grille 3 on the inner wall of the first lining 2;

5)在高强传力透水格栅3内壁铺设第二内衬4;5) Lay the second lining 4 on the inner wall of the high-strength force-transmitting permeable grille 3;

6)在该内衬砌层的内壁涂覆一降糙率涂层9,然后在所述第二内衬砌层和该降糙率涂层预制复数个水阀8。6) Coating a roughness reduction coating 9 on the inner wall of the inner lining layer, and then prefabricating a plurality of water valves 8 on the second inner lining layer and the roughness reduction coating.

本实施例比实施例2增加一降糙率涂层,以解决由于采用喷射混凝土或铺设混凝土管片施工时第二内衬内壁不光滑的问题。内壁不光滑会使水流受阻,而受阻处水流压力增大,对于第二内衬产生冲刷破坏。影响整个衬砌结构的安全。同时与实施例2相同,本实施例在第一内衬为钢筒时可以将钢筒厚度减少至10-30mm。In this embodiment, a roughness-reducing coating is added compared with Embodiment 2 to solve the problem that the inner wall of the second lining is not smooth due to the use of shotcrete or the laying of concrete segments. If the inner wall is not smooth, the water flow will be blocked, and the pressure of the water flow at the blocked place will increase, which will cause erosion damage to the second lining. Affect the safety of the entire lining structure. At the same time, as in Embodiment 2, in this embodiment, when the first inner lining is a steel cylinder, the thickness of the steel cylinder can be reduced to 10-30 mm.

实施例4Example 4

本实施例提供一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层1、内衬砌层;This embodiment provides a water conveyance tunnel lining structure that can withstand high internal and external water pressure, including an outer lining layer 1 and an inner lining layer;

该内衬砌层由第一内衬2、高强传力透水格栅3和第二内衬4构成;The inner lining layer is composed of a first inner lining 2, a high-strength force-transmitting permeable grille 3 and a second inner lining 4;

其中,该外衬砌层1设置于输水隧洞内壁;Wherein, the outer lining layer 1 is arranged on the inner wall of the water conveyance tunnel;

该外衬砌层1的内壁设置该第一内衬2,并在该外衬砌层1和该第一内衬2之间灌浆,形成一灌浆层5,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer 1 is provided with the first inner lining 2, and grouting is performed between the outer lining layer 1 and the first inner lining 2 to form a grouting layer 5. The grouting layer and the outer lining layer form an integrated outer lining layer. lining;

在该第一内衬2内壁设置该高强传力透水格栅3;The high-strength force-transmitting permeable grille 3 is arranged on the inner wall of the first lining 2;

在该高强传力透水格栅3内壁设置第二内衬4。A second lining 4 is arranged on the inner wall of the high-strength force-transmitting permeable grille 3 .

在该第二内衬4内壁设有一防渗涂层10。An impermeable coating 10 is provided on the inner wall of the second inner liner 4 .

在本实施例中所述外衬砌层为喷射的混凝土,第一内衬砌层为钢衬筒,高强传力透水格栅为玻璃钢格栅,第二内衬为预应力混凝土,防渗涂层为聚脲弹性体涂层。In this embodiment, the outer lining layer is sprayed concrete, the first inner lining layer is a steel lining cylinder, the high-strength force-transmitting permeable grid is a glass fiber reinforced plastic grid, the second inner lining is prestressed concrete, and the impermeable coating is Polyurea elastomer coating.

施工方法为:The construction method is:

1)通过NATM爆破掘出隧洞,然后在隧洞围岩6上打入锚杆7加固围岩6;1) The tunnel is excavated by NATM blasting, and then bolts 7 are driven into the surrounding rock 6 of the tunnel to reinforce the surrounding rock 6;

在输水隧洞工程当中,常规需要施工前先对输水隧洞围岩打锚杆加固,然后再进行后续衬砌结构的施工。In the water conveyance tunnel project, it is conventionally necessary to reinforce the surrounding rock of the water conveyance tunnel with bolts before construction, and then carry out the subsequent construction of the lining structure.

2)在围岩上浇筑或者喷射混凝土,形成外衬砌层1;2) Pour or spray concrete on the surrounding rock to form the outer lining layer 1;

3)安装第一内衬2,然后在该第一内衬2和该外衬砌层1之间进行灌浆,将外衬砌层1与灌浆层5粘合成一体化外衬砌;3) install the first inner lining 2, then grouting is performed between the first inner lining 2 and the outer lining layer 1, and the outer lining layer 1 and the grouting layer 5 are bonded to form an integrated outer lining;

4)在第一内衬2内壁上铺设高强传力透水格栅3;4) Lay high-strength force-transmitting permeable grille 3 on the inner wall of the first lining 2;

5)在高强传力透水格栅3内壁铺设第二内衬4;5) Lay the second lining 4 on the inner wall of the high-strength force-transmitting permeable grille 3;

6)在第二内衬内壁涂覆一防渗层。6) Coating an impermeable layer on the inner wall of the second liner.

当采用本实施例的结构时,由第二内衬直接承受内水压,不设置水阀,第一内衬不直接承受内水压,同时由于钢筒被第二内衬通过高强传力透水格栅支撑着,此时第一内衬为钢衬筒时可以减小厚度,约为1mm-20mm。When the structure of this embodiment is adopted, the second inner lining directly bears the internal water pressure without a water valve, and the first inner lining does not directly bear the inner water pressure. The grid is supported, and the thickness of the first lining can be reduced to about 1mm-20mm when the first lining is a steel lining.

从上述实施例可以看出,本发明提供一种可承受高内外水压的输水隧洞衬砌结构,该输水隧洞衬砌结构将衬砌可能承受的过高内外水压严格控制在允许范围内,避免衬砌受拉开裂产生内水外渗的风险,同时消除放空期高外水压导致衬砌屈曲变形失稳的隐患,从根本上解决高内外水压隧洞衬砌结构运行的安全问题。It can be seen from the above embodiments that the present invention provides a water conveyance tunnel lining structure that can withstand high internal and external water pressures. The risk of internal water seepage caused by the lining cracking under tension, at the same time, eliminates the hidden danger of buckling deformation and instability of the lining caused by high external water pressure during the venting period, and fundamentally solves the safety problem of the operation of the tunnel lining structure with high internal and external water pressure.

Claims (10)

1.一种可承受高内外水压的输水隧洞衬砌结构,包括外衬砌层和内衬砌层,其特征在于:该内衬砌层由第一内衬、高强传力透水格栅和第二内衬构成;1. A water-conveying tunnel lining structure that can withstand high internal and external water pressures, comprising an outer lining layer and an inner lining layer, is characterized in that: the inner lining layer is composed of a first inner lining, a high-strength force-transmitting permeable grille and a second inner lining. lining composition; 其中,该外衬砌层设置于输水隧洞内壁;Wherein, the outer lining layer is arranged on the inner wall of the water conveyance tunnel; 该外衬砌层的内壁设置该第一内衬,并在该外衬砌层和该第一内衬之间灌浆,形成一灌浆层,该灌浆层与外衬砌层形成一体化外衬层;The inner wall of the outer lining layer is provided with the first inner lining, and grouting is performed between the outer lining layer and the first inner lining to form a grouting layer, and the grouting layer and the outer lining layer form an integrated outer lining layer; 在该第一内衬内壁设置该高强传力透水格栅;The high-strength force-transmitting water-permeable grille is arranged on the inner wall of the first lining; 在该高强传力透水格栅内壁设置第二内衬。A second lining is arranged on the inner wall of the high-strength force-transmitting permeable grille. 2.如权利要求1所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述外衬砌层为混凝土或混凝土管片。2 . The lining structure of a water conveyance tunnel capable of withstanding high internal and external water pressures according to claim 1 , wherein the outer lining layer is concrete or concrete segments. 3 . 3.如权利要求1所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述第一内衬为钢衬筒、加劲肋钢筒、PVC管、加筋环钢筒或碳纤维复合钢筒。3. The water conveyance tunnel lining structure capable of withstanding high internal and external water pressure as claimed in claim 1, wherein the first lining is a steel lining cylinder, a stiffening rib steel cylinder, a PVC pipe, and a reinforced ring steel cylinder Or carbon fiber composite steel drum. 4.如权利要求1所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述第二内衬为素混凝土、预应力混凝土、钢筋混凝土、或混凝土管片。4 . The lining structure of a water conveyance tunnel capable of withstanding high internal and external water pressures according to claim 1 , wherein the second lining is plain concrete, prestressed concrete, reinforced concrete, or concrete segment. 5 . 5.如权利要求1所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述高强传力透水格栅为玻璃钢格栅、或高强钢塑土工格栅。5 . The lining structure of a water conveyance tunnel capable of withstanding high internal and external water pressures as claimed in claim 1 , wherein the high-strength force-transmitting water-permeable grille is a glass fiber reinforced plastic grille or a high-strength steel-plastic geogrid. 6 . 6.如权利要求1至5任一项所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述第二内衬穿设复数个水阀。6. The lining structure of a water conveyance tunnel capable of withstanding high internal and external water pressures according to any one of claims 1 to 5, wherein the second lining is provided with a plurality of water valves. 7.如权利要求1至5任一项所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,该第二内衬的内壁设有一降糙率涂层,在该第二内衬和该降糙率涂层穿设复数个水阀,该降糙率涂层为有机硅涂层或氟碳漆涂料。7. The water conveyance tunnel lining structure capable of withstanding high internal and external water pressures according to any one of claims 1 to 5, wherein the inner wall of the second lining is provided with a roughness reduction coating, and the second The inner lining and the roughness reduction coating pass through a plurality of water valves, and the roughness reduction coating is an organic silicon coating or a fluorocarbon paint. 8.如权利要求1至5任一项所述的可承受高内外水压的输水隧洞衬砌结构,其特征在于,所述第二内衬内壁设有一防渗涂层,所述防渗涂层为聚脲弹性体涂层。8. The water conveyance tunnel lining structure capable of withstanding high internal and external water pressures according to any one of claims 1 to 5, wherein the inner wall of the second lining is provided with an anti-seepage coating, and the anti-seepage coating is provided with an anti-seepage coating. The layer is a polyurea elastomer coating. 9.如权利要求1-5任一项所述的可承受高内外水压的输水隧洞衬砌结构的施工方法,其特征在于,包括以下步骤:9. The construction method of the water conveyance tunnel lining structure that can withstand high internal and external water pressure as claimed in any one of claims 1-5, is characterized in that, comprises the following steps: 1)通过TBM或者NATM爆破掘出隧洞,然后在隧洞围岩上打入锚杆加固围岩;1) The tunnel is excavated by TBM or NATM blasting, and then bolts are driven into the surrounding rock of the tunnel to reinforce the surrounding rock; 2)在围岩上浇筑或者喷射混凝土,或安装混凝土管片,形成外衬砌层;2) Pouring or spraying concrete on the surrounding rock, or installing concrete segments to form an outer lining layer; 3)安装第一内衬,然后在该第一内衬和该外衬砌层之间进行灌浆,将外衬砌层与灌浆层粘合成一体化外衬砌;3) Install the first inner lining, then grouting between the first inner lining and the outer lining layer, and bonding the outer lining layer and the grouting layer to form an integrated outer lining; 4)在第一内衬内壁上铺设高强传力透水格栅;4) Lay high-strength force-transmitting permeable grille on the inner wall of the first lining; 5)在高强传力透水格栅内壁铺设第二内衬。5) Lay a second lining on the inner wall of the high-strength force-transmitting permeable grille. 10.如权利要求9所述的可承受高内外水压的输水隧洞衬砌结构的施工方法,其特征在于,对于权利要求6的输水隧洞衬砌结构增加:步骤6)在所述第二内衬设置或预制复数个水阀;10. The construction method of the lining structure of a water conveyance tunnel that can withstand high internal and external water pressure as claimed in claim 9 is characterized in that, for the lining structure of the water conveyance tunnel of claim 6, step 6) is added in the second inner Lining or prefabricating multiple water valves; 或,对于权利要求7的输水隧洞衬砌结构增加:步骤6)在该内衬砌层的内壁涂覆一降糙率涂层,然后在所述第二内衬和该降糙率涂层设置或预制复数个水阀;Or, for the water conveyance tunnel lining structure of claim 7: step 6) coating a roughness reduction coating on the inner wall of the inner lining layer, and then setting the second inner lining and the roughness reduction coating or Prefabricated multiple water valves; 或,对于权利要求8的输水隧洞衬砌结构增加:步骤6)在所述第二内衬内壁涂覆一防渗层。Or, for the water conveyance tunnel lining structure of claim 8, step 6) coating an anti-seepage layer on the inner wall of the second inner lining.
CN202010327605.7A 2020-04-23 2020-04-23 A water conveyance tunnel lining structure capable of withstanding high internal and external water pressure and a construction method thereof Active CN111411980B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010327605.7A CN111411980B (en) 2020-04-23 2020-04-23 A water conveyance tunnel lining structure capable of withstanding high internal and external water pressure and a construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010327605.7A CN111411980B (en) 2020-04-23 2020-04-23 A water conveyance tunnel lining structure capable of withstanding high internal and external water pressure and a construction method thereof

Publications (2)

Publication Number Publication Date
CN111411980A true CN111411980A (en) 2020-07-14
CN111411980B CN111411980B (en) 2025-03-25

Family

ID=71492082

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010327605.7A Active CN111411980B (en) 2020-04-23 2020-04-23 A water conveyance tunnel lining structure capable of withstanding high internal and external water pressure and a construction method thereof

Country Status (1)

Country Link
CN (1) CN111411980B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627072A (en) * 2021-02-02 2021-04-09 河南省水利勘测设计研究有限公司 Reinforcing structure of hole body under earth and rockfill dam and construction method thereof
CN112943308A (en) * 2021-04-13 2021-06-11 李泽阳 High pressure water delivery tunnel composite lining structure
CN113776952A (en) * 2021-09-01 2021-12-10 武汉市政工程设计研究院有限责任公司 Functional test method for long-distance large-caliber deep drainage tunnel and application
CN115773136A (en) * 2022-12-07 2023-03-10 国网新源控股有限公司 Composite lining structure and construction method of hydraulic water delivery tunnel
CN116006887A (en) * 2022-12-23 2023-04-25 安徽建筑大学 A prestressed pressure regulating lining structure of roadway air energy storage tank
CN116044438A (en) * 2023-02-17 2023-05-02 中国电建集团昆明勘测设计研究院有限公司 Composite seepage control structure and method for non-drainage tunnel section of tunnel with water head of more than 50m
CN117003524A (en) * 2023-07-18 2023-11-07 中国水利水电第六工程局有限公司 TBM excavation tunnel sudden water blocking grouting material and construction method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07324595A (en) * 1994-05-31 1995-12-12 Fujita Corp Inner formwork and secondary lining method of shield tunnel for internal water pressure
JPH11200465A (en) * 1998-01-14 1999-07-27 Ohbayashi Corp Method for forming anticorrosion lining layer inside aqueduct tunnel
KR100610556B1 (en) * 2005-03-09 2006-08-08 한국건설기술연구원 Filling PC panel tunnel lining system and construction method
CN201096232Y (en) * 2007-10-10 2008-08-06 天津万联管道工程有限公司 Steel wire netting longitudinal rib prestressing force steel cylinder concrete pipe
CN203067974U (en) * 2013-02-25 2013-07-17 安徽邦尼新材料有限公司 Reinforcing structure of PVC (polyvinyl chloride) pipe
CN104806843A (en) * 2015-03-12 2015-07-29 武汉中地管通非开挖科技有限公司 Steel cylinder mesh suspended mortar spray compound lining and pressure pipe non-excavation repair method
CN204827469U (en) * 2015-07-15 2015-12-02 北京市水利规划设计研究院 A tunnel for transmission fluid
CN204920975U (en) * 2015-06-29 2015-12-30 中铁隧道股份有限公司 Tunnel supporting construction
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel
CN110939459A (en) * 2019-12-13 2020-03-31 华南理工大学 Shield water delivery tunnel composite lining structure and construction method thereof
CN212054722U (en) * 2020-04-23 2020-12-01 李泽阳 Can bear water delivery tunnel lining cutting structure of high inside and outside water pressure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07324595A (en) * 1994-05-31 1995-12-12 Fujita Corp Inner formwork and secondary lining method of shield tunnel for internal water pressure
JPH11200465A (en) * 1998-01-14 1999-07-27 Ohbayashi Corp Method for forming anticorrosion lining layer inside aqueduct tunnel
KR100610556B1 (en) * 2005-03-09 2006-08-08 한국건설기술연구원 Filling PC panel tunnel lining system and construction method
CN201096232Y (en) * 2007-10-10 2008-08-06 天津万联管道工程有限公司 Steel wire netting longitudinal rib prestressing force steel cylinder concrete pipe
CN203067974U (en) * 2013-02-25 2013-07-17 安徽邦尼新材料有限公司 Reinforcing structure of PVC (polyvinyl chloride) pipe
CN104806843A (en) * 2015-03-12 2015-07-29 武汉中地管通非开挖科技有限公司 Steel cylinder mesh suspended mortar spray compound lining and pressure pipe non-excavation repair method
CN204920975U (en) * 2015-06-29 2015-12-30 中铁隧道股份有限公司 Tunnel supporting construction
CN204827469U (en) * 2015-07-15 2015-12-02 北京市水利规划设计研究院 A tunnel for transmission fluid
CN106320296A (en) * 2016-11-02 2017-01-11 广西大学 Basalt fiber grid reinforced lining structure for high ground temperature high-pressure hydraulic tunnel
CN110939459A (en) * 2019-12-13 2020-03-31 华南理工大学 Shield water delivery tunnel composite lining structure and construction method thereof
CN212054722U (en) * 2020-04-23 2020-12-01 李泽阳 Can bear water delivery tunnel lining cutting structure of high inside and outside water pressure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
蒋奇;姜思华;石维新;杨进新;: "全防水复合衬砌隧洞结构设计", 水利水电技术, no. 12, 20 December 2015 (2015-12-20), pages 12 - 16 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627072A (en) * 2021-02-02 2021-04-09 河南省水利勘测设计研究有限公司 Reinforcing structure of hole body under earth and rockfill dam and construction method thereof
CN112943308A (en) * 2021-04-13 2021-06-11 李泽阳 High pressure water delivery tunnel composite lining structure
CN113776952A (en) * 2021-09-01 2021-12-10 武汉市政工程设计研究院有限责任公司 Functional test method for long-distance large-caliber deep drainage tunnel and application
CN113776952B (en) * 2021-09-01 2024-06-11 武汉市政工程设计研究院有限责任公司 Functional test method for long-distance large-caliber deep drainage tunnel and application
CN115773136A (en) * 2022-12-07 2023-03-10 国网新源控股有限公司 Composite lining structure and construction method of hydraulic water delivery tunnel
CN116006887A (en) * 2022-12-23 2023-04-25 安徽建筑大学 A prestressed pressure regulating lining structure of roadway air energy storage tank
CN116006887B (en) * 2022-12-23 2024-04-26 安徽建筑大学 Prestress pressure regulating lining structure of roadway air energy storage tank
CN116044438A (en) * 2023-02-17 2023-05-02 中国电建集团昆明勘测设计研究院有限公司 Composite seepage control structure and method for non-drainage tunnel section of tunnel with water head of more than 50m
CN117003524A (en) * 2023-07-18 2023-11-07 中国水利水电第六工程局有限公司 TBM excavation tunnel sudden water blocking grouting material and construction method
CN117003524B (en) * 2023-07-18 2025-07-22 中国水利水电第六工程局有限公司 TBM tunneling tunnel gushing water blocking grouting material and construction method

Also Published As

Publication number Publication date
CN111411980B (en) 2025-03-25

Similar Documents

Publication Publication Date Title
CN111411980A (en) A water conveyance tunnel lining structure and construction method capable of withstanding high internal and external water pressure
CN110700857B (en) A composite tunnel support system and construction method
CN101967984B (en) Deep well tunnel cable anchor rigid-flexible coupling support and surrounding rock overall reinforced support method
CN110159314A (en) A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN105673040A (en) Bearing system of deep well high-stress roadway surrounding rock enhanced support and application of bearing system
CN110030014B (en) Yielding arc-shaped shell treatment method for floor heave of soft rock roadway
CN107806349B (en) A kind of steel-FRP complex wave card tunnel secondary liner structure and its apply method
CN105401955A (en) Seepage-proofing bearing structure of soft soil pressure tunnel
CN117418900A (en) A compressed air energy storage bearing sealing structure and construction method for soft rock tunnels in shallow coal mines
CN114776323A (en) Method for controlling double compensation of stratum and stress loss of shield tunnel
CN210977516U (en) A scour protection energy release composite support structure for rock burst mine tunnel
CN102296617A (en) Post-grouting reinforcement construction method of flexible joints of diaphragm walls
CN116816387A (en) Design method of functional gradient composite lining structure of hard rock compressed air energy storage chamber
CN116771382B (en) Composite lining structure of high-pressure underground gas storage tunnel
CN114526093A (en) Method for repairing floor heave roadway by FRP (fiber reinforced Plastic) grid fiber reinforced cement-based composite material
CN115978311A (en) Double-steel-lining-reinforced concrete prefabricated combined structure pressure pipe and construction method thereof
JP3240417B2 (en) Construction method of headrace tunnel and headrace tunnel
CN212054722U (en) Can bear water delivery tunnel lining cutting structure of high inside and outside water pressure
CN101487279A (en) Segmented water-holding automatic water delivery control method in water delivery engineering
CN215718801U (en) High pressure water delivery tunnel composite lining structure
CN220319571U (en) Composite lining structure of high-pressure underground gas storage tunnel
CN111305093A (en) Self-unloading steel corrugated plate arch culvert
CN214836395U (en) Tunnel lining structure suitable for strong corrosive environment
CN110173276A (en) A kind of tunnel constant limit resistance buffer structure and its construction method
CN115839083A (en) Construction method for reinforcing single prestressed anchor rod combined foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant