CN111287896A - Protective components for tower crane foundations for tower construction - Google Patents

Protective components for tower crane foundations for tower construction Download PDF

Info

Publication number
CN111287896A
CN111287896A CN201811488965.4A CN201811488965A CN111287896A CN 111287896 A CN111287896 A CN 111287896A CN 201811488965 A CN201811488965 A CN 201811488965A CN 111287896 A CN111287896 A CN 111287896A
Authority
CN
China
Prior art keywords
tower
foundation
bolt
tower crane
bearing platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811488965.4A
Other languages
Chinese (zh)
Inventor
孙阳
李沐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Fengling new energy Co.,Ltd.
Original Assignee
Shenzhen Jingchuang Heavy Industry Special Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Jingchuang Heavy Industry Special Engineering Co ltd filed Critical Shenzhen Jingchuang Heavy Industry Special Engineering Co ltd
Priority to CN201811488965.4A priority Critical patent/CN111287896A/en
Publication of CN111287896A publication Critical patent/CN111287896A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B10/00Integration of renewable energy sources in buildings
    • Y02B10/30Wind power
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/728Onshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a protective assembly of a tower crane foundation for building a tower drum, wherein the tower drum comprises a tower drum foundation and a concrete tower drum arranged on the tower drum foundation, the tower crane foundation is arranged on one side of the outer side surface of the tower drum foundation along the radial direction, and the tower crane foundation comprises a bottom bearing platform which is integrally cast with the tower drum foundation; the connecting flange is arranged on the upper surface of the bottom bearing platform; the high-strength bolt is partially embedded in the bottom bearing platform and is connected with the connecting flange; the protection assembly is arranged above the bottom bearing platform and connected with the high-strength bolt, the protection assembly comprises a plurality of bolt caps, the bolt caps are sleeved at the upper end of the high-strength bolt and abut against the upper surface of the connecting flange, and the bolt caps and the high-strength bolt are arranged in a one-to-one correspondence manner; and the top cover plate is arranged at the tops of the bolt caps, and the relative positions of the top cover plate and the bolt caps are fixed. According to the protective component for the tower crane foundation for tower drum construction, the high-strength bolt can be protected.

Description

用于塔筒建造的塔机基础的防护组件Protective components for tower crane foundations for tower construction

技术领域technical field

本发明涉及风力发电技术领域,尤其是涉及一种用于塔筒建造的塔机基础的防护组件。The present invention relates to the technical field of wind power generation, in particular to a protection component for a tower crane foundation used for tower construction.

背景技术Background technique

相关技术中,随着风机发电效率的增加,叶片长度越来越长,与之匹配的风机塔筒的高度和截面尺寸也不断增加。钢结构塔筒由于成本较高、运输困难,因此难以满足大截面高塔筒的建造要求。而预制混凝土塔筒能够经济地建造大型风力发电机组。混凝土塔筒建造过程中通过由下往上依次吊装单个塔筒,最终建造成完整的混凝土塔筒。In the related art, with the increase of the power generation efficiency of the wind turbine, the length of the blade is getting longer and longer, and the height and cross-sectional size of the matching wind turbine tower are also increasing. Due to the high cost and difficult transportation of steel structure towers, it is difficult to meet the construction requirements of large cross-section and high towers. Precast concrete towers, on the other hand, enable the economical construction of large wind turbines. During the construction of the concrete tower, the individual towers are hoisted sequentially from bottom to top, and finally a complete concrete tower is constructed.

发明内容SUMMARY OF THE INVENTION

本发明旨在至少解决现有技术中存在的技术问题之一。为此,本发明的一个目的在于提出一种用于塔筒建造的塔机基础的防护组件,所述用于塔筒建造的塔机基础的防护组件可以对塔基础进行一定的防护。The present invention aims to solve at least one of the technical problems existing in the prior art. Therefore, an object of the present invention is to provide a tower crane foundation protection assembly for tower construction, which can protect the tower foundation to a certain extent.

根据本发明实施例的用于塔筒建造的塔机基础的防护组件,所述塔筒包括塔筒基础以及设在所述塔筒基础上的混凝土塔筒,所述塔机基础设在所述塔筒基础的外侧面沿径向的一侧,所述塔机基础包括:底部承台,所述底部承台与所述塔筒基础一体浇筑成型;连接法兰,所述连接法兰设在所述底部承台的上表面以连接塔机;高强螺栓,所述高强螺栓的一部分预埋在所述底部承台内,所述高强螺栓与所述连接法兰相连,且所述高强螺栓包括多个,多个所述高强螺栓间隔开布置;所述防护组件设于所述底部承台的上方并与所述高强螺栓相连以保护所述高强螺栓,所述防护组件包括:多个螺栓帽,所述螺栓帽外套在所述高强螺栓的上端且止抵所述连接法兰的上表面,所述螺栓帽与所述高强螺栓一一对应设置;顶盖板,所述顶盖板设在所述多个螺栓帽的顶部,且所述顶盖板与所述多个螺栓帽的相对位置固定。According to an embodiment of the present invention, a tower crane foundation protection assembly for tower construction, the tower includes a tower foundation and a concrete tower provided on the tower foundation, and the tower foundation is set on the The outer side of the tower foundation is on one side along the radial direction, and the tower foundation includes: a bottom cap, which is integrally cast with the tower foundation; a connecting flange, which is provided on the The upper surface of the bottom cap is used to connect the tower crane; high-strength bolts, a part of the high-strength bolts are pre-buried in the bottom cap, the high-strength bolts are connected with the connecting flange, and the high-strength bolts include A plurality of the high-strength bolts are arranged at intervals; the protective assembly is arranged above the bottom platform and connected with the high-strength bolts to protect the high-strength bolts, and the protective assembly includes: a plurality of bolt caps , the bolt cap covers the upper end of the high-strength bolt and stops against the upper surface of the connecting flange, and the bolt cap and the high-strength bolt are arranged in one-to-one correspondence; the tops of the plurality of bolt caps, and the relative positions of the top cover plate and the plurality of bolt caps are fixed.

根据本发明实施例的用于塔筒建造的塔机基础的防护组件,通过将塔机基础设置在塔筒基础的外侧面沿径向的一侧,并使底部承台与塔筒基础一体浇筑成型,由此,可以保证塔机基础的整体性,提高塔机基础承载能力,从而保证塔机的安全可靠。另外,当塔机由塔机基础上拆卸之后,通过防护组件还可以保护高强螺栓。According to the protective assembly of the tower crane foundation for tower construction according to the embodiment of the present invention, the tower crane foundation is arranged on one side of the outer side of the tower foundation along the radial direction, and the bottom cap and the tower foundation are integrally casted Forming, thus, the integrity of the tower crane foundation can be ensured, the bearing capacity of the tower crane foundation can be improved, and the safety and reliability of the tower crane can be ensured. In addition, after the tower crane is disassembled from the tower crane foundation, the high-strength bolts can also be protected by the protective components.

另外,根据本发明上述实施例的用于塔筒建造的塔机基础的防护组件还具有如下附加的技术特征:In addition, the protective assembly for the tower crane foundation for tower construction according to the above embodiments of the present invention also has the following additional technical features:

根据本发明的一些实施例,所述螺栓帽为橡胶件或塑料件,且所述螺栓帽与所述高强螺栓过盈配合。According to some embodiments of the present invention, the bolt cap is a rubber part or a plastic part, and the bolt cap is an interference fit with the high-strength bolt.

可选地,所述顶盖板被构造成中部向上凸起的伞状,以使所述顶盖板在填充土壤后能突出于地面,所述顶盖板包括:板体;凸部,所述凸部设于所述板体的上表面且向上凸出。Optionally, the top cover plate is configured in an umbrella shape with a middle part protruding upward, so that the top cover plate can protrude from the ground after being filled with soil, and the top cover plate includes: a plate body; The protruding portion is arranged on the upper surface of the plate body and protrudes upward.

根据本发明的一些实施例,所述高强螺栓预埋至所述底部承台内的部分还连接有加强件,所述加强件垂直于所述高强螺栓设置以提高所述塔机基础的锚固能力。According to some embodiments of the present invention, the part of the high-strength bolts pre-embedded into the bottom cap is also connected with a reinforcing member, and the reinforcing member is arranged perpendicular to the high-strength bolt to improve the anchoring capacity of the tower crane foundation .

进一步地,所述加强件为预埋至所述底部承台内的钢筋,所述钢筋与所述高强螺栓焊接,所述高强螺栓的直径为D,所述钢筋的长度L在4D-10D的范围内。Further, the reinforcing member is a steel bar pre-buried in the bottom platform, the steel bar is welded with the high-strength bolt, the diameter of the high-strength bolt is D, and the length L of the steel bar is 4D-10D. within the range.

可选地,所述底部承台的上表面低于所述塔筒基础的上表面的距离为200-300mm。Optionally, the distance that the upper surface of the bottom cap is lower than the upper surface of the tower foundation is 200-300 mm.

进一步地,所述塔筒基础的外侧面沿径向的一侧还设有散热器基础,所述散热器基础邻近所述塔机基础设置,且所述散热器基础的上表面与所述塔筒基础的上表面平齐。Further, a radiator foundation is also provided on one side of the outer side of the tower foundation along the radial direction, the radiator foundation is arranged adjacent to the tower crane foundation, and the upper surface of the radiator foundation is connected to the tower. The upper surface of the barrel foundation is flush.

更进一步地,在所述塔筒的纵向截面上,所述塔机基础被构造成梯形,所述散热器基础被构造成三角形。Further, in the longitudinal section of the tower, the tower base is configured as a trapezoid, and the radiator base is configured as a triangle.

可选地,所述混凝土塔筒由多段呈圆弧片状的混凝土塔筒段相互拼接构成。Optionally, the concrete tower is formed by splicing a plurality of arc-shaped concrete tower sections with each other.

本发明的附加方面和优点将在下面的描述中部分给出,部分将从下面的描述中变得明显,或通过本发明的实践了解到。Additional aspects and advantages of the present invention will be set forth, in part, from the following description, and in part will be apparent from the following description, or may be learned by practice of the invention.

附图说明Description of drawings

本发明的上述和/或附加的方面和优点从结合下面附图对实施例的描述中将变得明显和容易理解,其中:The above and/or additional aspects and advantages of the present invention will become apparent and readily understood from the following description of embodiments taken in conjunction with the accompanying drawings, wherein:

图1是根据本发明实施例的用于塔筒建造的塔机基础的一个示意图;1 is a schematic diagram of a tower crane foundation for tower construction according to an embodiment of the present invention;

图2是根据本发明实施例的用于塔筒建造的塔机基础的另一个示意图;2 is another schematic diagram of a tower crane foundation for tower construction according to an embodiment of the present invention;

图3是图2中圈示部分的局部放大图;Fig. 3 is a partial enlarged view of the part circled in Fig. 2;

图4是根据本发明实施例的用于塔筒建造的塔机基础的防护组件的一个示意图,其中图示位置塔机已由所述塔机基础上拆卸;4 is a schematic diagram of a protective assembly for a tower crane foundation for tower construction according to an embodiment of the present invention, wherein the tower crane has been disassembled from the tower crane foundation in the illustrated position;

图5是图4中圈示部分的局部放大图。FIG. 5 is a partial enlarged view of the portion circled in FIG. 4 .

附图标记:Reference number:

用于塔筒建造的塔机基础100,Tower Crane Foundation 100 for Tower Construction,

底部承台1,底部承台1的上表面11,底部承台1的外侧面12,连接法兰2,高强螺栓3,加强件4,散热器基础5,散热器基础5的上表面51,Bottom cap 1, the upper surface 11 of the bottom cap 1, the outer side 12 of the bottom cap 1, the connecting flange 2, the high-strength bolts 3, the reinforcement 4, the radiator foundation 5, the upper surface 51 of the radiator foundation 5,

基础底座210,塔筒基础220,塔筒基础220的外侧面221,塔筒基础220的外周面222,塔筒基础220的上表面223,The foundation base 210, the tower foundation 220, the outer side surface 221 of the tower foundation 220, the outer peripheral surface 222 of the tower foundation 220, the upper surface 223 of the tower foundation 220,

防护组件300,guard assembly 300,

螺栓帽310,顶盖板320,板体321,凸部322。Bolt cap 310 , top cover plate 320 , plate body 321 , convex portion 322 .

具体实施方式Detailed ways

下面详细描述本发明的实施例,所述实施例的示例在附图中示出,其中自始至终相同或类似的标号表示相同或类似的元件或具有相同或类似功能的元件。下面通过参考附图描述的实施例是示例性的,仅用于解释本发明,而不能理解为对本发明的限制。The following describes in detail the embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein the same or similar reference numerals refer to the same or similar elements or elements having the same or similar functions throughout. The embodiments described below with reference to the accompanying drawings are exemplary, only used to explain the present invention, and should not be construed as a limitation of the present invention.

下面参考图1-图5描述根据本发明实施例的用于塔筒建造的塔机基础的防护组件300。塔机即塔式起重机械,简称塔吊。The following describes a protective assembly 300 for a tower crane foundation for tower construction according to an embodiment of the present invention with reference to FIGS. 1-5 . Tower crane is tower crane, referred to as tower crane.

具体而言,根据本发明实施例的用于塔筒建造的塔机基础的防护组件300,所述塔筒包括塔筒基础220以及混凝土塔筒,所述混凝土塔筒设在塔筒基础220上。Specifically, a tower crane foundation protection assembly 300 for tower construction according to an embodiment of the present invention, the tower includes a tower foundation 220 and a concrete tower, and the concrete tower is provided on the tower foundation 220 .

例如,在一些实施例中,塔筒基础220可以为实心结构体,可选地,塔筒基础220的内部也可以为中空的锥台形结构,本申请对塔筒基础220的具体结构形式不作限定,实际应用中可以根据需要适应性设置。For example, in some embodiments, the tower foundation 220 may be a solid structure. Optionally, the interior of the tower foundation 220 may also be a hollow frustum-shaped structure, and the specific structural form of the tower foundation 220 is not limited in this application. , which can be adaptively set as required in practical applications.

所述混凝土塔筒的横截面可以呈圆形或多边形,当所述混凝土塔筒的横截面为多边形时,所述混凝土塔筒的径向尺寸指的是所述混凝土塔筒的最大外接圆的直径,这对本领域的技术人员来说是可以理解的。The cross section of the concrete tower can be circular or polygonal. When the cross section of the concrete tower is a polygon, the radial dimension of the concrete tower refers to the maximum circumscribed circle of the concrete tower. diameter, which will be understood by those skilled in the art.

塔机基础100可以设在塔筒基础220的外侧面221沿径向的一侧。示意性且不限制地,图2的中示出了塔机基础100设在塔筒基础220的外侧面221沿径向的左侧中的实施例。The tower crane foundation 100 may be provided on one side of the outer side surface 221 of the tower base 220 in the radial direction. Schematically and without limitation, FIG. 2 shows an embodiment in which the tower base 100 is provided in the left side of the outer side surface 221 of the tower base 220 in the radial direction.

塔机基础100包括:底部承台1、连接法兰2以及高强螺栓3。具体地,底部承台1与塔筒基础220可以一体浇筑成型,这样有利于减少塔机基础100的施工操作工作量,从而能够缩短工期。连接法兰2可以设在底部承台1的上表面11处,这样可以进一步在塔机基础100上连接塔机101。高强螺栓3的一部分预埋在底部承台1内,高强螺栓3与连接法兰2相连,且高强螺栓3包括多个,多个高强螺栓3间隔开布置。由此,通过塔机基础101不仅便于塔机101的安装和拆卸,还有利于提高塔机101的安装稳定性,使用可靠性好。The tower crane foundation 100 includes: a bottom cap 1 , a connecting flange 2 and high-strength bolts 3 . Specifically, the bottom cap 1 and the tower base 220 can be casted integrally, which is beneficial to reduce the construction workload of the tower crane base 100, thereby shortening the construction period. The connecting flange 2 can be provided on the upper surface 11 of the bottom platform 1 , so that the tower crane 101 can be further connected to the tower crane foundation 100 . A part of the high-strength bolts 3 are pre-buried in the bottom cap 1, and the high-strength bolts 3 are connected with the connecting flange 2, and the high-strength bolts 3 include a plurality of high-strength bolts 3 arranged at intervals. Therefore, the tower crane 101 is not only convenient for the installation and disassembly of the tower crane 101, but also helps to improve the installation stability of the tower crane 101, and the use reliability is good.

根据本发明实施例的用于塔筒建造的塔机基础100,通过将塔机基础100设置在塔筒基础220的外侧面221沿径向的一侧,并使底部承台1与塔筒基础220一体浇筑成型,由此,可以保证塔机基础100的整体性,提高塔机基础100承载能力,从而保证塔机101的安全可靠。According to the tower crane foundation 100 for tower construction according to the embodiment of the present invention, the tower crane foundation 100 is arranged on one side of the outer side surface 221 of the tower foundation 220 along the radial direction, and the bottom cap 1 is connected to the tower foundation. 220 is integrally cast and formed, thus, the integrity of the tower crane foundation 100 can be ensured, the bearing capacity of the tower crane foundation 100 can be improved, and the safety and reliability of the tower crane 101 can be ensured.

参照图4和图5,根据本发明实施例的用于塔筒建造的塔机基础的防护组件300,防护组件300设于底部承台1的上方,并且防护组件300可以与高强螺栓3相连,这样可以通过防护组件300保护高强螺栓3。4 and 5 , according to the protective assembly 300 of the tower crane foundation for tower construction according to the embodiment of the present invention, the protective assembly 300 is arranged above the bottom platform 1, and the protective assembly 300 can be connected with the high-strength bolts 3, In this way, the high-strength bolt 3 can be protected by the guard assembly 300 .

根据本发明实施例的用于塔筒建造的塔机基础的防护组件300,当塔机101由塔筒基础100上拆卸之后,通过防护组件300能够避免预埋在底部承台1内的高强螺栓3锈蚀和被碰撞等,从而可以保护高强螺栓3,由此,当所述塔筒正常使用时,通过防护组件300可以实现对高强螺栓3的保护。According to the protection assembly 300 of the tower crane foundation for tower construction according to the embodiment of the present invention, after the tower crane 101 is disassembled from the tower foundation 100, the protection assembly 300 can avoid high-strength bolts pre-buried in the bottom cap 1 3. Corrosion and collision, etc., so that the high-strength bolts 3 can be protected. Therefore, when the tower is in normal use, the protection components 300 can be used to protect the high-strength bolts 3.

结合图4和图5,根据本发明的一些实施例,防护组件300可以包括多组,每组防护组件300均包括:顶盖板320以及多个螺栓帽310。具体地,螺栓帽310可以外套在高强螺栓3的上端,并且螺栓帽310的下端可以止抵连接法兰2的上表面,螺栓帽310与高强螺栓3一一对应设置。顶盖板320设在多个螺栓帽310的顶部,并且顶盖板320与多个螺栓帽310的相对位置固定。由此,通过防护组件300可以实现对塔机基础100的保护。4 and 5 , according to some embodiments of the present invention, the guard assembly 300 may include multiple groups, and each group of guard assemblies 300 includes: a top cover plate 320 and a plurality of bolt caps 310 . Specifically, the bolt caps 310 can be fitted over the upper ends of the high-strength bolts 3 , and the lower ends of the bolt caps 310 can abut against the upper surface of the connecting flange 2 . The top cover plate 320 is provided on top of the plurality of bolt caps 310 , and the relative positions of the top cover plate 320 and the plurality of bolt caps 310 are fixed. Thus, the protection of the tower crane foundation 100 can be achieved by the protection assembly 300 .

进一步地,螺栓帽310可以为橡胶件或塑料件,并且螺栓帽310与高强螺栓3过盈配合。由此,通过螺栓帽310与高强螺栓3的配合,便于实现螺栓帽310与高强螺栓3之间的可靠连接,从而能够更好地实现对高强螺栓3的保护。Further, the bolt cap 310 may be a rubber part or a plastic part, and the bolt cap 310 is in an interference fit with the high-strength bolt 3 . Therefore, through the cooperation between the bolt cap 310 and the high-strength bolt 3 , it is convenient to realize a reliable connection between the bolt cap 310 and the high-strength bolt 3 , so that the protection of the high-strength bolt 3 can be better achieved.

可选地,参照图5,顶盖板320可以被构造成中部向上凸起的伞状,以使顶盖板320在填充土壤后能突出于地面,顶盖板320包括:板体321以及凸部322,凸部322设于板体321的上表面且向上凸出。由此,当在塔机基础100上填充土壤后,顶盖板320的顶部可以凸出于地面,从而可以起到一定的标识作用,方便施工人员快速找到塔机基础100的位置,易于施工。Optionally, referring to FIG. 5 , the top cover plate 320 may be configured into an umbrella shape with a central upwardly protruding upwards, so that the top cover plate 320 can protrude from the ground after filling with soil, and the top cover plate 320 includes: a plate body 321 and a convex The protruding portion 322 is provided on the upper surface of the plate body 321 and protrudes upward. Therefore, when the tower crane foundation 100 is filled with soil, the top of the top cover plate 320 can protrude from the ground, so as to play a certain identification role, which is convenient for construction personnel to quickly find the position of the tower crane foundation 100 and facilitate construction.

由于塔机101的荷载较大,需保证塔机101安全可靠。根据本发明的一些实施例,高强螺栓3预埋至底部承台1内的部分还连接有加强件4,加强件4垂直于高强螺栓3设置以提高塔机基础100的锚固能力。由此,通过在高强螺栓3上设置加强件4,有利于提高塔机基础100的锚固能力,从而提高塔机101的安全性。Due to the large load of the tower crane 101, it is necessary to ensure the safety and reliability of the tower crane 101. According to some embodiments of the present invention, the part of the high-strength bolts 3 pre-embedded in the bottom cap 1 is also connected with reinforcements 4, and the reinforcements 4 are arranged perpendicular to the high-strength bolts 3 to improve the anchoring capacity of the tower crane foundation 100. Therefore, by arranging the reinforcement 4 on the high-strength bolts 3 , it is beneficial to improve the anchoring capacity of the tower crane foundation 100 , thereby improving the safety of the tower crane 101 .

进一步地,加强件4为预埋至底部承台1内的钢筋,所述钢筋可以与高强螺栓3焊接。所述钢筋可以为短钢筋,这样有利于降低成本。更进一步地,高强螺栓3的直径为D,所述钢筋的长度L在4D-10D的范围内。由此通过设置加强件4例如钢筋等,不仅可以提高塔机基础100的承载能力,还有利于降低成本。Further, the reinforcing member 4 is a steel bar pre-embedded in the bottom platform 1 , and the steel bar can be welded with the high-strength bolt 3 . The steel bars can be short steel bars, which is beneficial to reduce costs. Further, the diameter of the high-strength bolt 3 is D, and the length L of the steel bar is in the range of 4D-10D. Therefore, by providing reinforcements 4 such as steel bars, not only the bearing capacity of the tower crane foundation 100 can be improved, but also the cost can be reduced.

其中,所述钢筋的长度L可以为4D、6D、8D或10D等,本发明对此不作具体限定。当然,在不考虑成本的情况下,所述钢筋的长度可以适当增加,在一些实施例中,加强件4也可以为其他的结构形式等,这对本领域的技术人员来说是可以理解的。Wherein, the length L of the steel bar may be 4D, 6D, 8D or 10D, etc., which is not specifically limited in the present invention. Of course, without considering the cost, the length of the reinforcing bar can be appropriately increased, and in some embodiments, the reinforcing member 4 can also be in other structural forms, etc., which can be understood by those skilled in the art.

参照图2和图3,根据本发明的一些实施例,在所述塔筒的轴向上(例如图3中所示的上下方向),底部承台1的外侧面12与塔筒基础220的外周面222可以平齐。由此,使得塔机基础100与塔筒基础220的一致性好,且外形美观。2 and 3 , according to some embodiments of the present invention, in the axial direction of the tower (for example, the vertical direction shown in FIG. 3 ), the outer surface 12 of the bottom platform 1 and the tower foundation 220 are The outer peripheral surface 222 may be flush. As a result, the tower crane foundation 100 and the tower base 220 have good consistency, and the appearance is beautiful.

根据本发明的一些实施例,底部承台1的上表面11可以低于塔筒基础220的上表面223设置;底部承台1的上表面11低于塔筒基础220的上表面223的距离为200-300mm。由此,当塔机101安装在塔机基础100上时,可以用土壤将塔机基础100掩盖,从而能够通过土壤将塔机基础100隐藏,外形美观。According to some embodiments of the present invention, the upper surface 11 of the bottom platform 1 may be set lower than the upper surface 223 of the tower foundation 220; the distance between the upper surface 11 of the bottom platform 1 and the upper surface 223 of the tower foundation 220 is 200-300mm. Therefore, when the tower crane 101 is installed on the tower crane foundation 100, the tower crane foundation 100 can be covered with soil, so that the tower crane foundation 100 can be hidden by the soil, and the appearance is beautiful.

其中,底部承台1的上表面11低于塔筒基础220的上表面223的距离可以为200mm、230mm、250mm、280mm或300mm等,本发明对此不作具体限定。The distance between the upper surface 11 of the bottom platform 1 and the upper surface 223 of the tower foundation 220 may be 200mm, 230mm, 250mm, 280mm or 300mm, etc., which is not specifically limited in the present invention.

另外,在一些可选地实施例中,底部承台1的上表面11也可以与塔筒基础220的上表面223平齐。In addition, in some optional embodiments, the upper surface 11 of the bottom platform 1 may also be flush with the upper surface 223 of the tower foundation 220 .

进一步地,参照图3,塔筒基础220的外侧面221沿径向的一侧还可以设有散热器基础5,散热器基础5上可以安装散热器,散热器基础5可以邻近塔机基础100设置,散热器基础5的上表面51可以高于底部承台1的上表面11设置,并且散热器基础5的上表面51可以与塔筒基础220的上表面223平齐。由此,使得塔机基础100和散热器基础5在塔筒基础220上的布置更加紧凑且美观。Further, referring to FIG. 3 , the outer side surface 221 of the tower base 220 can also be provided with a radiator base 5 on one side in the radial direction, a radiator can be installed on the radiator base 5, and the radiator base 5 can be adjacent to the tower crane base 100 The upper surface 51 of the radiator base 5 can be set higher than the upper surface 11 of the bottom platform 1 , and the upper surface 51 of the radiator base 5 can be flush with the upper surface 223 of the tower base 220 . Therefore, the arrangement of the tower base 100 and the radiator base 5 on the tower base 220 is more compact and beautiful.

更进一步地,参照图3,在所述塔筒的纵向截面上,塔机基础100被构造成梯形,散热器基础5被构造成三角形。由此,使得塔机基础100和散热器基础5在塔筒基础220上的布置更加紧凑。Further, referring to FIG. 3 , in the longitudinal section of the tower, the tower base 100 is configured as a trapezoid, and the radiator base 5 is configured as a triangle. Therefore, the arrangement of the tower base 100 and the radiator base 5 on the tower base 220 is made more compact.

在本发明的一些实施例中,参照图2和图3,塔筒基础220的底部还可以设有基础底座210,基础底座210与塔筒基础220可以一体浇筑成型。基础底座210被构造成在由上至下的方向上向内收缩的锥形,基础底座210沿横向的最大尺寸可以大于塔筒基础220沿横向的最大尺寸,这样有利于在一定程度上提高塔筒基础220的平稳性,从而有利于进一步提高所述混凝土塔筒的使用可靠性。In some embodiments of the present invention, referring to FIGS. 2 and 3 , the bottom of the tower foundation 220 may further be provided with a foundation base 210 , and the foundation base 210 and the tower foundation 220 may be integrally cast. The foundation base 210 is configured as a conical shape that shrinks inward in the top-to-bottom direction, and the maximum lateral dimension of the base base 210 may be greater than the lateral maximum dimension of the tower base 220, which is beneficial to improve the tower to a certain extent. The stability of the cylinder foundation 220 is beneficial to further improve the reliability of the concrete tower.

根据本发明的一些实施例,连接法兰2包括至少四个,至少四个连接法兰2布置成四边形例如矩形等。由此,通过连接法兰2易于实现塔机基础100与塔机101之间的可靠连接。According to some embodiments of the present invention, the connecting flanges 2 include at least four, and the at least four connecting flanges 2 are arranged in a quadrangle such as a rectangle or the like. Therefore, the reliable connection between the tower crane foundation 100 and the tower crane 101 is easily achieved through the connection flange 2 .

根据本发明的一些实施例,所述混凝土塔筒可以由多段呈圆弧片状的混凝土塔筒段相互拼接构成。由此,便于所述混凝土塔筒的建造,且有利于降低成本。According to some embodiments of the present invention, the concrete tower may be formed by splicing a plurality of arc-shaped concrete tower sections with each other. Therefore, the construction of the concrete tower is facilitated, and the cost is reduced.

其中,所述混凝土塔筒可以通过连接件例如强度较高的螺栓等与塔筒基础220相连。在一些可选地实施例中,所述混凝土塔筒也可以为分段直塔筒等。Wherein, the concrete tower can be connected with the tower foundation 220 by connecting parts such as bolts with higher strength. In some optional embodiments, the concrete tower can also be a segmented straight tower or the like.

根据本发明实施例的用于塔筒建造的塔机基础100,通过将塔机基础100设置在塔筒基础220上,可以保证塔机基础100的整体性,减少塔机基础100的施工工作量,提高塔机基础100的承载能力。According to the tower crane foundation 100 for tower construction according to the embodiment of the present invention, by disposing the tower crane foundation 100 on the tower base 220, the integrity of the tower crane foundation 100 can be ensured, and the construction workload of the tower crane foundation 100 can be reduced. , to improve the bearing capacity of the tower crane foundation 100.

根据本发明实施例的用于塔筒建造的塔机基础100以及防护组件300的其他构成以及操作对于本领域普通技术人员而言都是已知的,这里不再详细描述。Other structures and operations of the tower crane foundation 100 for tower construction and the shield assembly 300 according to the embodiments of the present invention are known to those of ordinary skill in the art and will not be described in detail here.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”、“轴向”、“径向”、“周向”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "upper", "lower", "front", "rear", "left", " The orientation or position relationship indicated by "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "axial", "radial", "circumferential", etc. is Based on the orientation or positional relationship shown in the drawings, it is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood to limit the present invention.

在本说明书的描述中,参考术语“一个实施例”、“一些实施例”、“示意性实施例”、“示例”、“具体示例”、或“一些示例”等的描述意指结合该实施例或示例描述的具体特征、结构、材料或者特点包含于本发明的至少一个实施例或示例中。在本说明书中,对上述术语的示意性表述不一定指的是相同的实施例或示例。而且,描述的具体特征、结构、材料或者特点可以在任何的一个或多个实施例或示例中以合适的方式结合。In the description of this specification, reference to the terms "one embodiment," "some embodiments," "exemplary embodiment," "example," "specific example," or "some examples", etc., is meant to incorporate the embodiments A particular feature, structure, material, or characteristic described by an example or example is included in at least one embodiment or example of the present invention. In this specification, schematic representations of the above terms do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.

尽管已经示出和描述了本发明的实施例,本领域的普通技术人员可以理解:在不脱离本发明的原理和宗旨的情况下可以对这些实施例进行多种变化、修改、替换和变型,本发明的范围由权利要求及其等同物限定。Although embodiments of the present invention have been shown and described, it will be understood by those of ordinary skill in the art that various changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, The scope of the invention is defined by the claims and their equivalents.

Claims (9)

1. A protection component for tower crane foundation that tower section of thick bamboo was built, its characterized in that, a tower section of thick bamboo includes tower section of thick bamboo basis and establishes the concrete tower section of thick bamboo on tower section of thick bamboo basis, tower crane foundation establishes in the radial one side of the lateral surface of tower section of thick bamboo basis, tower crane foundation includes:
the bottom bearing platform and the tower drum foundation are integrally cast;
the connecting flange is arranged on the upper surface of the bottom bearing platform and is used for connecting the tower crane;
the high-strength bolts are partially embedded in the bottom bearing platform, are connected with the connecting flange and comprise a plurality of high-strength bolts, and the high-strength bolts are arranged at intervals;
protection component locates the top of bottom cushion cap and with the bolt that excels in links to each other in order to protect the bolt that excels in, protection component includes:
the bolt caps are sleeved at the upper ends of the high-strength bolts and abut against the upper surfaces of the connecting flanges, and the bolt caps and the high-strength bolts are arranged in a one-to-one correspondence manner;
and the top cover plate is arranged at the tops of the bolt caps, and the relative positions of the top cover plate and the bolt caps are fixed.
2. The tower foundation protection assembly for tower construction according to claim 1, wherein the bolt cap is made of rubber or plastic and is in interference fit with the high-strength bolt.
3. The shielding assembly of a tower foundation for tower construction according to claim 1, wherein said top cover plate is configured as an umbrella with a middle portion protruding upward so that said top cover plate can protrude out of the ground after being filled with soil, said top cover plate comprising:
a plate body;
and the convex part is arranged on the upper surface of the plate body and protrudes upwards.
4. The tower crane foundation protection assembly for tower construction as claimed in any one of claims 1-3, wherein the portion of the high-strength bolt embedded in the bottom bearing platform is further connected with a reinforcement member, and the reinforcement member is arranged perpendicular to the high-strength bolt to improve the anchoring capability of the tower crane foundation.
5. The tower crane foundation protection assembly for tower construction according to claim 4, wherein the reinforcement is a steel bar pre-embedded into the bottom bearing platform, the steel bar is welded to the high-strength bolt, the diameter of the high-strength bolt is D, and the length L of the steel bar is within the range of 4D-10D.
6. The tower foundation protection assembly for tower construction as claimed in claim 4, wherein the upper surface of the bottom bearing platform is arranged lower than the upper surface of the tower foundation, and the distance between the upper surface of the bottom bearing platform and the upper surface of the tower foundation is 200mm and 300 mm.
7. The tower crane foundation protection assembly for tower construction as claimed in claim 6, wherein a heat sink foundation is further provided on the outer side surface of the tower crane foundation along one radial side, the heat sink foundation is disposed adjacent to the tower crane foundation, and the upper surface of the heat sink foundation is flush with the upper surface of the tower crane foundation.
8. The shielding assembly of a tower foundation for tower construction according to claim 7, wherein said tower foundation is configured as a trapezoid and said heat sink foundation is configured as a triangle in a longitudinal cross-section of said tower.
9. The tower foundation protection assembly for tower construction according to claim 4, wherein the concrete tower drum is formed by mutually splicing a plurality of arc-shaped concrete tower drum sections.
CN201811488965.4A 2018-12-06 2018-12-06 Protective components for tower crane foundations for tower construction Pending CN111287896A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811488965.4A CN111287896A (en) 2018-12-06 2018-12-06 Protective components for tower crane foundations for tower construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811488965.4A CN111287896A (en) 2018-12-06 2018-12-06 Protective components for tower crane foundations for tower construction

Publications (1)

Publication Number Publication Date
CN111287896A true CN111287896A (en) 2020-06-16

Family

ID=71031266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811488965.4A Pending CN111287896A (en) 2018-12-06 2018-12-06 Protective components for tower crane foundations for tower construction

Country Status (1)

Country Link
CN (1) CN111287896A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201297323Y (en) * 2008-11-19 2009-08-26 咸阳供电局 An anti-corrosive cover for bolt
WO2012163906A1 (en) * 2011-05-27 2012-12-06 Max Bögl Wind AG Method for constructing a wind turbine
CN203585040U (en) * 2013-11-18 2014-05-07 国家电网公司 Foundation bolt protective cover
CN104674837A (en) * 2015-02-26 2015-06-03 石健 Connection structure and connection method of draught fan foundation and draught fan tower barrel
CN108050019A (en) * 2017-10-23 2018-05-18 南京律智诚专利技术开发有限公司 It is a kind of height-adjustable wind power generation stepped
CN209908667U (en) * 2018-12-06 2020-01-07 深圳京创重工特种工程有限公司 A protection component for tower machine basis that tower section of thick bamboo was built

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201297323Y (en) * 2008-11-19 2009-08-26 咸阳供电局 An anti-corrosive cover for bolt
WO2012163906A1 (en) * 2011-05-27 2012-12-06 Max Bögl Wind AG Method for constructing a wind turbine
CN203585040U (en) * 2013-11-18 2014-05-07 国家电网公司 Foundation bolt protective cover
CN104674837A (en) * 2015-02-26 2015-06-03 石健 Connection structure and connection method of draught fan foundation and draught fan tower barrel
CN108050019A (en) * 2017-10-23 2018-05-18 南京律智诚专利技术开发有限公司 It is a kind of height-adjustable wind power generation stepped
CN209908667U (en) * 2018-12-06 2020-01-07 深圳京创重工特种工程有限公司 A protection component for tower machine basis that tower section of thick bamboo was built

Similar Documents

Publication Publication Date Title
ES2796475T3 (en) Foundation for a windmill
ES2784000T3 (en) Foundation for a windmill
US7805895B2 (en) Foundation for enabling anchoring of a wind turbine tower thereto by means of replaceable through-bolts
US8555600B2 (en) Method for mounting in sections an annular tower for wind power generator, heliostatic power generator or chimney composed from three concrete segments or more
JP4488745B2 (en) Wind turbine
JP5748744B2 (en) Wind turbine tower
CN211446991U (en) Center cylinder of tower cylinder foundation, tower cylinder foundation and tower cylinder
FI3516121T3 (en) Foundation for a wind turbine
CN102482892A (en) Telescopic tower assembly and method
WO2008031912A1 (en) Wind turbine tower mounted with pre-fabricated elements
KR101575789B1 (en) Reinforcing bar assembly for concrete pile reinforcement and concrete pile assembly including the same
CN107849864A (en) The tower of wind power plant
CN210766856U (en) Prefabricated spliced center cylinder and tower cylinder foundation with same
CN210194671U (en) Tower crane foundation for tower drum construction
CN204163095U (en) A kind of foundation structure of building and combined member thereof
CN111287896A (en) Protective components for tower crane foundations for tower construction
CN209908667U (en) A protection component for tower machine basis that tower section of thick bamboo was built
CN111287211A (en) Tower Crane Foundation for Tower Construction
KR101358435B1 (en) Complex section tower combination assembly for wind power generator
JP6324165B2 (en) Photovoltaic generator and its basics
JP7073517B2 (en) Semi-finished parts for the foundation of a tower building, semi-finished parts-foundation segments, foundations, methods for manufacturing semi-finished parts, and methods for manufacturing foundations.
CN208430522U (en) The blower foundation of steel truss structure
ES2662926B1 (en) EOLIC TOWER PEDESTAL
CN103981881A (en) Building foundation structure, construction method of building foundation structure and combined members
CN102852138B (en) Concrete pile

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20211214

Address after: 200021 room 1001, 10th floor, 138 Huaihai Middle Road, Huangpu District, Shanghai

Applicant after: Shanghai Fengling new energy Co.,Ltd.

Address before: Room 305, building 4, Nanyou fourth industrial zone, 1124 Nanshan Avenue, Nanshan street, Nanshan District, Shenzhen, Guangdong 518000

Applicant before: SHENZHEN JINGCHUANG HEAVY INDUSTRY SPECIAL ENGINEERING Co.,Ltd.