CN111186011A - Factory prefabricated automatic assembly line layout structure and production method of laminated slab beam - Google Patents

Factory prefabricated automatic assembly line layout structure and production method of laminated slab beam Download PDF

Info

Publication number
CN111186011A
CN111186011A CN202010027564.XA CN202010027564A CN111186011A CN 111186011 A CN111186011 A CN 111186011A CN 202010027564 A CN202010027564 A CN 202010027564A CN 111186011 A CN111186011 A CN 111186011A
Authority
CN
China
Prior art keywords
area
mold
pouring
standard
tamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010027564.XA
Other languages
Chinese (zh)
Other versions
CN111186011B (en
Inventor
顾建明
李柱宾
尹海
罗慧龙
梁龙昇
文光勇
方迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Lanlv Zhi zao Jiancai Co., Ltd.
Original Assignee
Hangzhou Lin'an Zhongmin Zhuyou Intelligent Manufacturing Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Lin'an Zhongmin Zhuyou Intelligent Manufacturing Technology Co Ltd filed Critical Hangzhou Lin'an Zhongmin Zhuyou Intelligent Manufacturing Technology Co Ltd
Priority to CN202010027564.XA priority Critical patent/CN111186011B/en
Publication of CN111186011A publication Critical patent/CN111186011A/en
Application granted granted Critical
Publication of CN111186011B publication Critical patent/CN111186011B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/04Discharging the shaped articles
    • B28B13/06Removing the shaped articles from moulds
    • B28B13/065Removing the shaped articles from moulds by applying electric current or other means of discharging, e.g. pneumatic or hydraulic discharging means
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/38Treating surfaces of moulds, cores, or mandrels to prevent sticking
    • B28B7/386Cleaning

Landscapes

  • Engineering & Computer Science (AREA)
  • Ceramic Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明涉及一种叠合板梁工厂预制自动流水线布置结构,包括:标准模台、搅拌站、浇捣区、养护区、脱模清理区、支模区、钢筋安装区、拉毛区、围护栏、模板堆放区和材料堆放区;循环流水线依次为浇捣区、养护区、脱模清理区、支模区、钢筋安装区和浇捣区;标准模台通过模台移动系统移动至各功能区,标准模台下方设有模台驱动装置和模台流水导向装置。本发明的有益效果是:本发明对叠合板梁工厂化预制设计了一套自动生产流水线,实现预制构件的功能分区流水线施工,是一种充分利用空间、工序顺接的高效生产组织方式,成本降低,节能明显。同时也促进了装配式建筑质量、品质的不断提升,绿色环保水平明显提高。

Figure 202010027564

The invention relates to a prefabricated automatic assembly line layout structure of a laminated slab beam factory, comprising: a standard mold table, a mixing station, a pouring and tamping area, a maintenance area, a demoulding cleaning area, a mold support area, a steel bar installation area, a roughening area, a fence, The formwork stacking area and the material stacking area; the circulation line is the pouring and tamping area, the curing area, the demoulding cleaning area, the formwork area, the steel bar installation area and the pouring and tamping area; the standard mold table is moved to each functional area through the mold table moving system, Below the standard die table is a die table drive device and a die table flow guide device. The beneficial effects of the present invention are as follows: the present invention designs a set of automatic production lines for the factory prefabrication of laminated slab beams, realizes the construction of functional sub-assembly lines of prefabricated components, and is an efficient production organization method that makes full use of space and processes in succession. Reduced, the energy saving is obvious. At the same time, it has also promoted the continuous improvement of the quality and quality of prefabricated buildings, and the level of green environmental protection has been significantly improved.

Figure 202010027564

Description

Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams and production method
Technical Field
The invention relates to a factory-prefabricated automatic assembly line arrangement structure and a production method of a laminated slab beam, and belongs to the technical field of assembly type building engineering.
Background
The assembly type buildings are one of the important directions of green buildings and building industrialization, the novel building industrialization is greatly promoted all over the country, and the proportion of the assembly type buildings in the novel buildings is gradually increased through the construction of industrial bases. The factory prefabrication of the composite plate beam is the most common process in the assembly type building, but the specification and the size of the composite plate beam are more, and when a fixed pedestal is adopted for production, the investment is large, the work efficiency is low, and the space utilization rate is low.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provides an automatic assembly line arrangement structure and a production method for factory prefabrication of a laminated slab beam.
The automatic assembly line arrangement structure for factory prefabrication of the laminated slab beam comprises a standard die table, a stirring station, a pouring and tamping area, a maintenance area, a demolding and cleaning area, a formwork supporting area, a steel bar installation area, a napping area, a surrounding guardrail, a template stacking area and a material stacking area; the circulating assembly line sequentially comprises a pouring and tamping area, a maintenance area, a demolding and cleaning area, a formwork supporting area, a steel bar mounting area and a pouring and tamping area; the standard mould platform moves to each functional area through a mould platform moving system, and a mould platform driving device and a mould platform flowing water guiding device are arranged below the standard mould platform; the pouring and tamping area mainly comprises a vibration system, a feeding hopper system and an automatic distributing machine; the stirring station is positioned outside the pouring and tamping area and is connected to the hopper system through a concrete conveying belt; a vertical curing kiln, a lifter and a control console are arranged in the curing area; the template of the laminated plate beam mainly comprises an L-shaped side die and a bottom die of the laminated plate beam; surrounding guardrails are arranged around the production line.
Preferably, the method comprises the following steps: the mould platform moving system comprises a mould platform driving device, a mould platform flowing water guiding device, a roller conveyor, a guide wheel and a double-machine lifting type ferry vehicle.
Preferably, the method comprises the following steps: the L-shaped side mold of the laminated plate beam is provided with a pre-buried steel bar preformed hole, a laminated plate beam top truss pre-buried steel bar is arranged in the pre-buried steel bar preformed hole, a slurry leakage prevention device is inserted into the pre-buried steel bar preformed hole, and the L-shaped side mold of the laminated plate beam is reinforced with the bottom mold through a strong magnetic fixer.
The automatic flow line production method for factory prefabrication of the laminated slab beam comprises the following steps of:
designing and arranging an automatic production line; the circulating assembly line is functionally partitioned according to a pouring area, a maintenance area, a demolding cleaning area, a formwork supporting area, a steel bar installation area, a napping area, a template stacking area and a material stacking area and is arranged in a rectangular shape; along the long side direction of a flow line, a mould platform driving device is arranged below each standard mould platform, and mould platform flow guiding devices are arranged below longitudinal beams on two sides of the standard mould platform and used for longitudinal movement of the standard mould platform; two lifting type ferry vehicles are arranged in the direction of two short edges of the production line and are used for transversely moving a standard die table on the production line to realize a square circulation production line; wherein the stirring station is positioned outside the pouring and tamping area, and the mixed concrete is conveyed to a hopper system right above the standard mould platform through a concrete conveying belt; enclosing the guardrail around the production line;
step two, mounting a side die; the method comprises the following steps that a bottom die is manufactured on a laminated slab beam by using a standard die table, a side die is customized according to the structural size of the laminated slab beam, an L-shaped steel plate structure is adopted, and pre-buried steel bar preformed holes are formed in the L-shaped side die of the laminated slab beam according to the distance between pre-buried steel bars; the side die is fixedly formed with the bottom die through a strong magnetic fixer;
step three, installing a steel bar framework; uniformly processing the semi-finished products of the reinforcement cage of the laminated slab beam in a reinforcement processing factory, and transporting the semi-finished products to a site at the inner side of a production line of a reinforcement installation area for use; the steel bars, the steel bar framework and the steel bar mesh which are put into the die are checked and accepted; after the reinforcing steel bars enter the die, arranging a protective layer cushion block according to a quincunx shape; before pouring, inserting slurry leakage prevention devices one by one on the preformed holes of the embedded steel bars;
step four, pouring concrete; concrete is intensively mixed by a mixing station, is conveyed to a feeding hopper system right above a to-be-delivered mould table through a concrete conveying belt, is fed by an automatic material distributor and is compactly vibrated by a vibration system below the mould table, and the top surface is leveled by manual assistance;
fifthly, maintaining the component in a vertical curing kiln; after the concrete pouring molding and the surface layer treatment of the laminated slab beam, the standard die platform travels to the vertical curing kiln, and the laminated slab beam and the standard die platform are conveyed to the curing kiln for high-temperature curing through a lifter; the vertical curing kiln is maintained by automatically controlling the temperature through an instrument, and the maintenance is carried out in four stages of standing, heating, constant temperature and cooling; standing at normal temperature for 2-4 hours before steaming; the temperature rising speed is not more than 20 ℃/h; the temperature in the constant temperature heating stage is not more than 60 ℃; the cooling speed is not more than 20 ℃/h; demolding when the temperature difference between the surface of the component and the external environment is not more than 20 ℃;
step six, demoulding; the member is taken out of the kiln when being cured in the curing kiln until reaching the specified hoisting and demolding strength; before the member is demoulded and lifted, a group of test blocks maintained under the same condition are pressed; when the strength of the test block group reaches over 75 percent of the design strength or meets the design requirement, demoulding and hoisting; when the mold is removed, the strong magnetic fixer is removed, and then the L-shaped side mold of the laminated plate beam is removed; after the component is demoulded, checking and accepting, spraying the engineering part, the component model and the production date according to the specification, and stacking and maintaining;
seventhly, cleaning the template; and cleaning the grout skin on the mould by using a putty shovel, then cleaning the bottom mould, and performing the flow construction of the next circulation superposed plate beam prefabrication.
The invention has the beneficial effects that: the invention designs a set of automatic production line for the factory prefabrication of the laminated plate girder, realizes the function partition assembly line construction of the prefabricated part, is an efficient production organization mode which fully utilizes space and has sequential working procedures, reduces the cost and obviously saves energy. Meanwhile, the quality and quality of the fabricated building are promoted to be improved continuously, and the level of environmental protection is obviously improved.
Drawings
FIG. 1 is a plan view of an automatic production line for factory prefabrication of composite slabs;
FIG. 2 is a perspective view of an automatic production line for factory prefabrication of composite slabs;
FIG. 3 is a detailed view of a prefabricated formwork system;
FIG. 4 is a layout view of a standard die table drive;
FIG. 5 is a flow chart of the construction process of the present invention.
Description of reference numerals: the system comprises a standard mould platform 1, a stirring station 2, a pouring and tamping area 3, a concrete conveying belt 3-1, a vibration system 3-2, a maintenance area 4, a vertical maintenance kiln 4-1, a lifter 4-2, a control console 4-3, a demoulding and cleaning area 5, a laminated plate beam 5-1, a template 5-2, a strong magnetic fixer 5-3, a mould supporting area 6, a laminated plate beam L-shaped side mould 6-1, a pre-embedded steel bar preformed hole 6-2, a steel bar mounting area 7, a laminated plate beam top truss pre-embedded steel bar 7-1, a slurry leakage prevention device 7-2, a mould platform moving system 8, a mould platform driving device 8-1, a mould platform water guiding device 8-2, a napping area 9, a surrounding guardrail 10, a mould plate stacking area 11 and a material stacking area 12.
Detailed Description
The present invention will be further described with reference to the following examples. The following examples are set forth merely to aid in the understanding of the invention. It should be noted that, for those skilled in the art, it is possible to make various improvements and modifications to the present invention without departing from the principle of the present invention, and those improvements and modifications also fall within the scope of the claims of the present invention.
The automatic assembly line arrangement structure for the prefabricated superimposed sheet beam factory realizes the circulation assembly line of the functional partitions such as the pouring area, the maintenance area, the demolding cleaning area, the formwork supporting area and the steel bar installation area by setting the movable standard platform formwork system, achieves the efficient production organization mode of fully utilizing the space and the procedure in order, reduces the cost and obviously saves energy.
Aiming at the characteristics of the plane component of the laminated slab beam, according to the technological processes of prefabricated slab beam formwork erection, steel bar installation, concrete pouring, maintenance and demolding, a standard formwork table 1 (with the length of 9.0m and the width of 3.5m, serving as a prefabricated bottom formwork of the laminated slab beam) is arranged as a functional partition (an operation platform), and a plurality of standard formwork tables 1 form a circulating assembly line. The standard die table 1 moves to each functional area through a die table moving system 8 which is composed of a roller conveyer, a guide wheel, a double-machine lifting ferry vehicle and the like and is arranged below the die table. Wherein, the pouring and pounding area 3 mainly comprises a vibration system 3-2, a feeding hopper system and an automatic distributing machine. The mixed concrete in the mixing station 2 is transported to a hopper system through a concrete conveying belt 3-1, and the concrete is poured by an automatic distributing machine. Considering that the top surface of the composite beam is often provided with the embedded ribs 7-1 of the truss on the top of the composite beam, the leveling of the concrete surface on the top of the plate is completed by manual assistance. After the laminated plate beam 5-1 is poured, the laminated plate beam travels from the standard die table 1 to enter a vertical curing kiln 4-1 for high-temperature curing, and then sequentially enters a demolding cleaning area 5, a formwork supporting area 6, a steel bar mounting area 7 and a pouring and tamping area 3 to form a circulating production line.
As shown in fig. 1-4, the automatic assembly line layout structure for the factory prefabrication of the composite slab beam comprises a standard die table 1, a stirring station 2, a pouring area 3, a maintenance area 4, a demolding cleaning area 5, a formwork supporting area 6, a steel bar installation area 7, a napping area 9, a guardrail 10, a template stacking area 11 and a material stacking area 12. The circulating production line sequentially comprises a pouring and tamping area 3, a maintenance area 4, a demoulding and cleaning area 5, a formwork supporting area 6, a reinforcing steel bar mounting area 7 and a pouring and tamping area 3. The standard mould platform 1 moves to each functional area through a mould platform moving system 8, the mould platform moving system 8 comprises a mould platform driving device 8-1, a mould platform flowing water guiding device 8-2, a roller conveyor, a guide wheel and a double-machine lifting type ferry vehicle, and the mould platform driving device 8-1 and the mould platform flowing water guiding device 8-2 are arranged below the standard mould platform 1. The mixing station 2 is located outside the casting and tamping zone 3, and the mixing station 2 is connected to the casting and tamping zone 3 by a concrete conveyor belt 3-1. The curing area 4 comprises a vertical curing kiln 4-1, a lifter 4-2 and a console 4-3. The template 5-2 mainly comprises an L-shaped side mold 6-1 of the laminated slab beam and a bottom mold, the L-shaped side mold 6-1 of the laminated slab beam is provided with a pre-buried steel bar preformed hole 6-2, a top truss pre-buried steel bar 7-1 of the laminated slab beam is arranged in the pre-buried steel bar preformed hole 6-2, a slurry leakage prevention device 7-2 is inserted into the pre-buried steel bar preformed hole 6-2, and the L-shaped side mold 6-1 of the laminated slab beam is reinforced with the bottom mold through a strong magnetic fixer 5-3. Surrounding guardrails 10 are arranged around the production line.
As shown in fig. 5, the automatic flow line production method for the factory prefabrication of the laminated slab beam comprises the following steps:
the method comprises the step one of automatically designing and arranging the production line. The occupied area length multiplied by the width of the single laminated plate beam automatic production line is 105m multiplied by 28m, the length multiplied by the width of a standard mould table 1 is 9.0m multiplied by 3.5m, and the circulating production line is functionally partitioned according to a pouring region 3, a maintenance region 4, a demoulding cleaning region 5, a formwork supporting region 6, a reinforcing steel bar installation region 7, a galling region 9, a template stacking region 11 and a material stacking region 12 and is arranged in a rectangular shape. Along the long side direction of a flow line, a mould platform driving device 8-1 is arranged below each standard mould platform 1 (4 mould platforms are arranged, the distance from the end is about 1m), and meanwhile, mould platform flow water guide devices 8-2 (the distance is 2m) are usually arranged below longitudinal beams on two sides of the mould platform so as to ensure that the standard mould platform 1 moves longitudinally; and two lifting type ferry vehicles are arranged in the direction of two short edges of the production line and are used for transversely moving the standard die table 1 on the production line to realize a square circulation production line. Wherein the mixing station 2 is positioned outside the pouring and pounding area 3, and the mixed concrete is conveyed to a hopper system right above the mould platform through a concrete conveying belt 3-1. The periphery of the whole production line (except the demoulding area component delivery area) is protected by yellow steel bar net enclosure guardrails (people enter and exit channels are arranged as required).
And step two, mounting the side die. The bottom die is manufactured by the aid of the standard die table 1 for the composite slab beam, the side die is customized according to the structural size of the composite slab beam, an L-shaped steel plate structure is adopted, and pre-buried steel bar preformed holes 6-2 are formed in the L-shaped side die 6-1 of the composite slab beam according to pre-buried steel bar intervals. The side die system is fixedly formed with the bottom die through a strong magnetic fixer 5-3. The quality of the formwork should be accurate in geometric dimension of each part, square in four corners, free of twisting deformation, free of slurry leakage of abutted seams and clean in the formwork. The side die used for the first time is self-checked after the first part is supported, and the side die can be used after being checked and accepted by a production supervisor, inspectors and technicians in a combined mode. The template used in the turnover must be self-checked.
And step three, installing the steel reinforcement framework. The semi-finished products (including the plate top truss type embedded ribs) of the reinforcement frameworks of the composite slabs are processed in a reinforcing steel bar processing factory in a unified mode and are transported to a site on the inner side of a 7-assembly line of a reinforcement installation area for use. The steel bars, the steel bar framework and the steel bar mesh which are put into the die must be checked and accepted; after the reinforcing steel bars enter the die, arranging a protective layer cushion block according to a quincunx shape, and strictly prohibiting walking and treading on the reinforcing steel bars; tools or other sundries for brushing the release agent cannot be put on the steel bars. Before pouring, inserting the slurry leakage prevention devices 7-2 one by one on the preformed holes 6-2 of the embedded steel bars.
And step four, pouring concrete. The concrete is intensively mixed by a mixing station 2, is transported to a feeding hopper system right above a die table to be delivered by a concrete conveying belt 3-1, is compacted by the blanking of an automatic distributing machine and the vibration of a vibration system 3-2 below the die table, and adopts the manual assistance for top surface leveling.
And step five, maintaining the component in a vertical curing kiln. After the concrete pouring forming and the surface layer processing of the composite slab beam, the mold platform travels to the vertical curing kiln 4-1 and is sent to the curing kiln for high-temperature curing together with the mold platform through the hoister 4-2. The vertical curing kiln 4-1 is used for automatic temperature control curing through an instrument, and curing is carried out in four stages of standing, temperature rising, constant temperature and temperature lowering. Standing at normal temperature for 2-4 hours before steaming; the temperature rising speed is not more than 20 ℃/h; the temperature in the constant temperature heating stage is not more than 60 ℃; the cooling speed is not more than 20 ℃/h; when the temperature difference between the surface of the component and the external environment is not more than 20 ℃, the component can be demoulded.
And step six, demolding. And (5) curing the member in a curing kiln until the member reaches the specified hoisting and demolding strength, and taking out the member from the kiln. Before the member is demoulded and lifted, a group of test blocks with the same condition must be maintained by pressing; only when the strength of the test block group reaches over 75 percent of the design strength or meets the design requirement, the test block group can be demolded and lifted. When the mould is disassembled, the strong magnetic fixer 5-3 is disassembled, and then the L-shaped side mould 6-1 of the laminated plate beam is disassembled. When the form is removed, the form is forbidden to be hammered by a sledge hammer, and the component can not be directly impacted. And (4) after the component is demoulded, checking and accepting in time, spraying the engineering part, the component model and the production date according to the specification, and stacking and maintaining.
And seventhly, cleaning the template. And cleaning the grout skin on the mould by using a putty shovel, then cleaning the bottom mould, and performing the flow construction of the next circulation superposed plate beam prefabrication.

Claims (4)

1.一种叠合板梁工厂预制自动流水线布置结构,其特征在于:包括标准模台(1)、搅拌站(2)、浇捣区(3)、养护区(4)、脱模清理区(5)、支模区(6)、钢筋安装区(7)、拉毛区(9)、围护栏(10)、模板堆放区(11)和材料堆放区(12);循环流水线依次为浇捣区(3)、养护区(4)、脱模清理区(5)、支模区(6)、钢筋安装区(7)和浇捣区(3);标准模台(1)通过模台移动系统(8)移动至各功能区,标准模台(1)下方设有模台驱动装置(8-1)和模台流水导向装置(8-2);浇捣区(3)主要由振动系统(3-2)、送料斗系统和自动布料机组成;搅拌站(2)位于浇捣区(3)外侧,搅拌站(2)通过混凝土传输带(3-1)连接至送料斗系统;养护区(4)内设有立式养护窑(4-1)、提升机(4-2)和控制台(4-3);叠合板梁(5-1)的模板(5-2)主要由叠合板梁L型侧模(6-1)和底模组成;生产流水线周围设有围护栏(10)。1. A prefabricated automatic assembly line layout structure of a laminated plate beam factory is characterized in that: comprising a standard die table (1), a mixing station (2), a pouring and tamping area (3), a maintenance area (4), a demoulding cleaning area ( 5), the formwork area (6), the reinforcement installation area (7), the pulling area (9), the fence (10), the formwork stacking area (11) and the material stacking area (12); the circulation line is the pouring and tamping area in turn (3), maintenance area (4), demoulding cleaning area (5), form support area (6), reinforcement installation area (7) and pouring and tamping area (3); standard die table (1) moves through the die table moving system (8) Move to each functional area, the standard die table (1) is provided with a die table driving device (8-1) and a die table flow guide device (8-2); the pouring and tamping area (3) is mainly composed of a vibration system ( 3-2), a feeding hopper system and an automatic distributing machine; the mixing station (2) is located outside the pouring and tamping area (3), and the mixing station (2) is connected to the feeding hopper system through the concrete conveyor belt (3-1); the curing area (4) There is a vertical curing kiln (4-1), a hoist (4-2) and a console (4-3) inside; the formwork (5-2) of the laminated beam (5-1) is mainly composed of laminated The plywood beam is composed of an L-shaped side mold (6-1) and a bottom mold; a fence (10) is arranged around the production line. 2.根据权利要求1所述的叠合板梁工厂预制自动流水线布置结构,其特征在于:模台移动系统(8)包括模台驱动装置(8-1)、模台流水导向装置(8-2)、滚轴传送机、导向轮和双机升降式摆渡车。2. The prefabricated automatic assembly line layout structure of the laminated slab beam factory according to claim 1, characterized in that: the mold table moving system (8) comprises a mold table driving device (8-1), a mold table flow guide device (8-2) ), roller conveyors, guide wheels and double lift shuttles. 3.根据权利要求1所述的叠合板梁工厂预制自动流水线布置结构,其特征在于:叠合板梁L型侧模(6-1)设有预埋钢筋预留孔(6-2),预埋钢筋预留孔(6-2)内设有叠合板梁顶桁架预埋筋(7-1),预埋钢筋预留孔(6-2)上插设防漏浆装置(7-2),叠合板梁L型侧模(6-1)通过强磁固定器(5-3)与底模加固。3. The factory prefabricated automatic assembly line layout structure of the laminated plate beam according to claim 1, is characterized in that: the L-shaped side mold (6-1) of the laminated plate beam is provided with pre-embedded steel bar reserved holes (6-2), The pre-embedded reinforcement (7-1) of the top truss of the superimposed slab beam is arranged in the reserved hole (6-2) for the embedded steel bar, and the slurry leakage prevention device (7-2) is inserted into the reserved hole (6-2) of the pre-embedded steel bar. The L-shaped side mold (6-1) of the laminated plate beam is reinforced with the bottom mold by a strong magnetic fastener (5-3). 4.一种叠合板梁工厂预制自动流水线生产方法,其特征在于,包括以下步骤:4. a factory prefabricated automatic assembly line production method of laminated plate beam, is characterized in that, comprises the following steps: 步骤一:自动化生产流水线设计和布置;循环流水线按浇捣区(3)、养护区(4)、脱模清理区(5)、支模区(6)、钢筋安装区(7)、拉毛区(9)、模板堆放区(11)和材料堆放区(12)进行功能分区,呈长方形布置;沿流水线长边方向,每个标准模台(1)下方设置模台驱动装置(8-1),同时在标准模台(1)两侧纵梁下方设置模台流水导向装置(8-2),用于标准模台(1)纵向移行;在流水线两短边方向,设置双机升降式摆渡车,用于流水线上标准模台的横移,实现口字形循环流水线;其中搅拌站(2)位于浇捣区(3)外侧,拌和好的混凝土经混凝土传输带(3-1)输送至标准模台(1)正上方的送料斗系统;生产流水线周围围护栏(10)围护;Step 1: Design and layout of the automated production line; the circulation line is divided into the pouring and tamping area (3), the maintenance area (4), the demoulding cleaning area (5), the formwork support area (6), the reinforcing bar installation area (7), and the roughening area. (9) The template stacking area (11) and the material stacking area (12) are functionally partitioned and arranged in a rectangular shape; along the long side of the assembly line, a die table driving device (8-1) is provided below each standard die table (1). At the same time, mold table flow guide devices (8-2) are installed under the longitudinal beams on both sides of the standard mold table (1) for the longitudinal movement of the standard mold table (1). It is used for the lateral movement of the standard mold table on the assembly line to realize the mouth-shaped circulation assembly line; the mixing station (2) is located outside the pouring and tamping area (3), and the mixed concrete is transported to the standard by the concrete conveyor belt (3-1). The feeding hopper system directly above the die table (1); the fence (10) around the production line is enclosed; 步骤二:侧模安装;叠合板梁利用标准模台(1)制作底模,侧模根据叠合板梁结构尺寸定制,采用L型钢板结构,叠合板梁L型侧模(6-1)上按照预埋钢筋间距开设预埋钢筋预留孔(6-2);侧模通过强磁固定器(5-3)与底模固定成型;Step 2: side mold installation; the laminated plate beam uses a standard mold table (1) to make a bottom mold, and the side mold is customized according to the structure and size of the laminated plate beam, and adopts an L-shaped steel plate structure, and the laminated plate beam L-shaped side mold (6-1) is placed on the Pre-embedded steel reinforcement holes (6-2) are opened according to the spacing of the embedded steel bars; the side mold is fixed and formed with the bottom mold by a strong magnetic fixer (5-3); 步骤三:钢筋骨架安装;叠合板梁钢筋骨架半成品在钢筋加工厂内统一加工,运至钢筋安装区(7)流水线内侧场地使用;入模的钢筋、钢筋骨架和钢筋网经过检查验收;钢筋入模后,按梅花型布置保护层垫块;浇筑前,在预埋钢筋预留孔(6-2)上逐一安插防漏浆装置(7-2);Step 3: Reinforcement frame installation; The semi-finished product of the superimposed slab beam reinforcement frame is uniformly processed in the reinforcement processing plant, and transported to the inner side of the assembly line in the reinforcement installation area (7) for use; After moulding, arrange the protective layer pads according to the plum-shaped pattern; before pouring, install the anti-leakage slurry devices (7-2) on the reserved holes (6-2) of the pre-embedded steel bars one by one; 步骤四:混凝土浇筑;混凝土由搅拌站(2)集中拌和,经混凝土传输带(3-1)运输至待交模台正上方的送料斗系统,经自动布料机下料和模台下的振动系统(3-2)振动密实,采用人工辅助顶面整平;Step 4: concrete pouring; Concrete is concentrated and mixed by the mixing station (2), and is transported to the feeding hopper system directly above the mold table to be delivered through the concrete conveyor belt (3-1), and is discharged through the automatic placing machine and the vibration under the mold table The system (3-2) is vibrated and dense, and artificially assisted top surface leveling is adopted; 步骤五:构件立式养护窑养护;叠合板梁混凝土浇筑成型和面层处理后,标准模台(1)行走至立式养护窑(4-1),通过提升机(4-2)连同标准模台(1)送入养护窑高温养护;立式养护窑(4-1)通过仪器自动温控养护,养护分静停、升温、恒温和降温四阶段进行;蒸养前在常温下静停2-4小时;升温速度不超过20℃/h;恒温加热阶段温度不大于60℃;降温速度不超过20℃/h;构件表面与外界环境的温差不大于20℃时出模;Step 5: Maintenance of the component vertical curing kiln; after the composite slab beam concrete is poured and formed and the surface layer is treated, the standard mold table (1) travels to the vertical curing kiln (4-1), and the elevator (4-2) together with the standard The mold table (1) is sent to the curing kiln for high-temperature curing; the vertical curing kiln (4-1) is maintained through automatic temperature control by the instrument, and the curing is carried out in four stages: static stop, heating, constant temperature and cooling; before steam curing, stop at normal temperature 2-4 hours; the heating rate should not exceed 20℃/h; the temperature in the constant temperature heating stage should not exceed 60℃; the cooling rate should not exceed 20℃/h; 步骤六:脱模;构件在养护窑内养护至达到规定起吊、脱模强度时出窑;在构件脱模起吊之前,先压一组同条件养护试块;当该组试块强度达到设计强度75%以上或设计要求时,则脱模起吊;拆模时,先拆强磁固定器(5-3),然后拆叠合板梁L型侧模(6-1);构件出模后,进行检查验收,并按规定喷涂工程部位、构件型号和生产日期,再码放养护;Step 6: demoulding; the component is maintained in the curing kiln until reaching the specified lifting and demolding strength, and the kiln is released; before the component is demolded and lifted, a group of maintenance test blocks under the same conditions are pressed; when the strength of the group of test blocks reaches the design strength When it is more than 75% or design requirements, it shall be demoulded and lifted; when demoulding, first remove the strong magnetic fixer (5-3), and then remove the L-shaped side formwork (6-1) of the laminated beam; Check and accept, and spray the project parts, component models and production dates according to the regulations, and then store them for maintenance; 步骤七:模板清理;用腻子铲清理模具上的浆皮,然后清理底模,进入下一循环叠合板梁预制的流水施工。Step 7: Template cleaning; use a putty shovel to clean the pulp skin on the mold, then clean the bottom mold, and enter the next cycle of prefabrication of superimposed slab beams.
CN202010027564.XA 2020-01-10 2020-01-10 A composite slab beam factory prefabrication automatic assembly line layout structure and production method Active CN111186011B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010027564.XA CN111186011B (en) 2020-01-10 2020-01-10 A composite slab beam factory prefabrication automatic assembly line layout structure and production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010027564.XA CN111186011B (en) 2020-01-10 2020-01-10 A composite slab beam factory prefabrication automatic assembly line layout structure and production method

Publications (2)

Publication Number Publication Date
CN111186011A true CN111186011A (en) 2020-05-22
CN111186011B CN111186011B (en) 2024-10-29

Family

ID=70684554

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010027564.XA Active CN111186011B (en) 2020-01-10 2020-01-10 A composite slab beam factory prefabrication automatic assembly line layout structure and production method

Country Status (1)

Country Link
CN (1) CN111186011B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111975974A (en) * 2020-09-11 2020-11-24 山西建投晋西北建筑产业有限公司 Double-circulation production line and production process of prefabricated components of fabricated building
CN112078000A (en) * 2020-09-30 2020-12-15 中民筑友智能装备科技有限公司 A rotary flow PC component production line
CN112936557A (en) * 2021-02-03 2021-06-11 中核(江苏)绿色建筑产业发展有限公司 Precast concrete laminated slab production line and preparation method thereof
CN113664983A (en) * 2021-07-27 2021-11-19 重庆速装建材有限公司 Mobile workshop preparation method of assembled PC component
CN114131739A (en) * 2021-12-20 2022-03-04 江苏蓝海住宅工业有限公司 Precast concrete composite slab pouring mold, pouring equipment and pouring method thereof
CN115446959A (en) * 2022-09-26 2022-12-09 宁波优造建筑科技有限公司 A method for manufacturing three-dimensional flowing water of prefabricated concrete slabs
CN116968162A (en) * 2023-08-10 2023-10-31 昆明顺弘新材料有限公司 Prefabricated superimposed sheet production line
CN117697945A (en) * 2023-11-24 2024-03-15 中铁九局集团有限公司 Production line and production method for multiple products of concrete member

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009196333A (en) * 2008-02-25 2009-09-03 Takahashi Curtain Wall Kogyo Kk Manufacturing process of pc panel
CN102528927A (en) * 2012-01-30 2012-07-04 中铁四局集团第五工程有限公司 Production line precast beam construction method
CN103029213A (en) * 2012-12-26 2013-04-10 中南建设(沈阳)建筑产业有限公司 Production process of automatic assembly line in factory for pre-fabricating and assembling superimposed sheet of integral structure
CN204266637U (en) * 2014-12-04 2015-04-15 中民筑友有限公司 Three-dimensional precuring storehouse
CN104626348A (en) * 2014-11-20 2015-05-20 中民筑友有限公司 Prefabricated part production line
CN104723449A (en) * 2015-02-12 2015-06-24 沈阳卫德住宅工业化科技有限公司 Automatic production line of building industrialization concrete precast members
CN106217590A (en) * 2016-09-30 2016-12-14 中铁二十三局集团有限公司 Pre-tensioned rail plate flowing water unit method produces tooling device and method
CN211842522U (en) * 2020-01-10 2020-11-03 杭州临安中民筑友智造科技有限公司 Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2009196333A (en) * 2008-02-25 2009-09-03 Takahashi Curtain Wall Kogyo Kk Manufacturing process of pc panel
CN102528927A (en) * 2012-01-30 2012-07-04 中铁四局集团第五工程有限公司 Production line precast beam construction method
CN103029213A (en) * 2012-12-26 2013-04-10 中南建设(沈阳)建筑产业有限公司 Production process of automatic assembly line in factory for pre-fabricating and assembling superimposed sheet of integral structure
CN104626348A (en) * 2014-11-20 2015-05-20 中民筑友有限公司 Prefabricated part production line
CN204266637U (en) * 2014-12-04 2015-04-15 中民筑友有限公司 Three-dimensional precuring storehouse
CN104723449A (en) * 2015-02-12 2015-06-24 沈阳卫德住宅工业化科技有限公司 Automatic production line of building industrialization concrete precast members
CN106217590A (en) * 2016-09-30 2016-12-14 中铁二十三局集团有限公司 Pre-tensioned rail plate flowing water unit method produces tooling device and method
CN211842522U (en) * 2020-01-10 2020-11-03 杭州临安中民筑友智造科技有限公司 Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111975974A (en) * 2020-09-11 2020-11-24 山西建投晋西北建筑产业有限公司 Double-circulation production line and production process of prefabricated components of fabricated building
CN112078000A (en) * 2020-09-30 2020-12-15 中民筑友智能装备科技有限公司 A rotary flow PC component production line
CN112078000B (en) * 2020-09-30 2024-12-17 中民筑友智能装备科技有限公司 Rotary type running water PC component production line
CN112936557A (en) * 2021-02-03 2021-06-11 中核(江苏)绿色建筑产业发展有限公司 Precast concrete laminated slab production line and preparation method thereof
CN113664983A (en) * 2021-07-27 2021-11-19 重庆速装建材有限公司 Mobile workshop preparation method of assembled PC component
CN114131739A (en) * 2021-12-20 2022-03-04 江苏蓝海住宅工业有限公司 Precast concrete composite slab pouring mold, pouring equipment and pouring method thereof
CN115446959A (en) * 2022-09-26 2022-12-09 宁波优造建筑科技有限公司 A method for manufacturing three-dimensional flowing water of prefabricated concrete slabs
CN116968162A (en) * 2023-08-10 2023-10-31 昆明顺弘新材料有限公司 Prefabricated superimposed sheet production line
CN117697945A (en) * 2023-11-24 2024-03-15 中铁九局集团有限公司 Production line and production method for multiple products of concrete member

Also Published As

Publication number Publication date
CN111186011B (en) 2024-10-29

Similar Documents

Publication Publication Date Title
CN111186011A (en) Factory prefabricated automatic assembly line layout structure and production method of laminated slab beam
CN104626348B (en) Prefabricated components production line
CN105459258A (en) Pc component production line
CN109291229B (en) Modularized mobile multilayer stacking steam curing PC component production system and production method
CN111203972A (en) Automatic production line for pile plate type structural bridge deck
CN111975974A (en) Double-circulation production line and production process of prefabricated components of fabricated building
CN110355866B (en) Parallel PC component production system
CN211842522U (en) Automatic assembly line arrangement structure for factory prefabrication of laminated slab beams
CN110936487A (en) Novel prefabricated part production system
CN220661288U (en) A kind of prefabricated box beam production line
CN111844352A (en) Construction process for prefabricating mechanical high-efficiency guardrail
CN216634831U (en) Compact type small mold table full-automatic laminated slab production line
KR101324161B1 (en) 2-day-cycle concrete structure construction method
US4171194A (en) Plant for the production of concrete elements
CN208543605U (en) Precast prestressed concrete composite beam production mould and production equipment
CN113478633A (en) Production method of cavity wall and concrete prefabricated part production line
CN113290686A (en) Concrete prefabricated part production system
CN113021609B (en) Production device for concrete prefabricated part
CN220681176U (en) Prefabricated coincide bottom plate
CN215319481U (en) Concrete prefabricated part production line
CN215038701U (en) Stair automatic production cell and stair automatic production line
CN116021625A (en) Assembly type building element production line
CN114789505A (en) Compact type small mold table full-automatic laminated slab production line
CN108481543A (en) Precast stair production line
CN113787604A (en) Prefabricated staircase continuous-flow type production line

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 311300 Zhejiang Province Hangzhou City Lin'an District Yuqian Town Renmin Street 132.NO Room 202

Patentee after: Zhejiang Lanlv Zhi zao Jiancai Co., Ltd.

Country or region after: China

Address before: 311300 Zhejiang Province Hangzhou City Lin'an District Yuqian Town Renmin Street 132.NO Room 202

Patentee before: Hangzhou Lin'an Zhongmin zhuyou Intelligent Manufacturing Technology Co.,Ltd.

Country or region before: China