CN118814819A - A construction method for reducing excavation settlement - Google Patents
A construction method for reducing excavation settlement Download PDFInfo
- Publication number
- CN118814819A CN118814819A CN202411212013.5A CN202411212013A CN118814819A CN 118814819 A CN118814819 A CN 118814819A CN 202411212013 A CN202411212013 A CN 202411212013A CN 118814819 A CN118814819 A CN 118814819A
- Authority
- CN
- China
- Prior art keywords
- grouting
- hole
- anchor
- pressure
- horizontal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009412 basement excavation Methods 0.000 title claims abstract description 19
- 238000010276 construction Methods 0.000 title claims abstract description 19
- 239000002002 slurry Substances 0.000 claims abstract description 42
- 239000002689 soil Substances 0.000 claims abstract description 36
- 238000005553 drilling Methods 0.000 claims abstract description 6
- 238000007789 sealing Methods 0.000 claims abstract 2
- 238000010992 reflux Methods 0.000 claims description 21
- 239000011440 grout Substances 0.000 claims description 5
- 238000000926 separation method Methods 0.000 claims 3
- 238000005192 partition Methods 0.000 description 11
- 230000000694 effects Effects 0.000 description 10
- 238000004873 anchoring Methods 0.000 description 8
- 238000005728 strengthening Methods 0.000 description 5
- 101100012902 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) FIG2 gene Proteins 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 238000009792 diffusion process Methods 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000011435 rock Substances 0.000 description 3
- 101001121408 Homo sapiens L-amino-acid oxidase Proteins 0.000 description 2
- 101000827703 Homo sapiens Polyphosphoinositide phosphatase Proteins 0.000 description 2
- 102100026388 L-amino-acid oxidase Human genes 0.000 description 2
- 102100023591 Polyphosphoinositide phosphatase Human genes 0.000 description 2
- 101100233916 Saccharomyces cerevisiae (strain ATCC 204508 / S288c) KAR5 gene Proteins 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000002893 slag Substances 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/80—Ground anchors
- E02D5/808—Ground anchors anchored by using exclusively a bonding material
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及土体改良领域,公开了一种减少开挖沉降量的施工方法,包括以下步骤:步骤一、在基坑周围靠近已建构筑物一侧施工围护桩;步骤二、开挖基坑,在围护桩上部钻第i个水平锚孔,水平锚孔由上至下依次设置,在第i个水平锚孔内插入中空锚杆,中空锚杆端部设有压浆件,压浆件上开有注浆孔;步骤三、封住锚孔,预留注浆管,通过注浆管从中空锚杆和水平锚孔侧壁之间进行首次注浆;步骤四、待首次注浆的浆液凝固后,从中空锚杆内进行压力注浆,直至浆液压力达到设计压力;步骤五、重复步骤二‑步骤四,直至完成i个中空锚杆的施工,以减小已建构筑物的沉降。
The invention relates to the field of soil improvement, and discloses a construction method for reducing excavation settlement, comprising the following steps: step 1, constructing retaining piles around a foundation pit and close to one side of an existing structure; step 2, excavating a foundation pit, drilling an i-th horizontal anchor hole on the upper part of the retaining pile, the horizontal anchor holes are arranged in sequence from top to bottom, and a hollow anchor rod is inserted into the i-th horizontal anchor hole, a grouting piece is provided at the end of the hollow anchor rod, and a grouting hole is opened on the grouting piece; step 3, sealing the anchor hole, reserving a grouting pipe, and performing the first grouting between the hollow anchor rod and the side wall of the horizontal anchor hole through the grouting pipe; step 4, after the slurry of the first grouting is solidified, pressure grouting is performed from the hollow anchor rod until the slurry pressure reaches the design pressure; step 5, repeating step 2-step 4 until the construction of i hollow anchor rods is completed, so as to reduce the settlement of the existing structure.
Description
技术领域Technical Field
本发明涉及开挖领域,具体涉及一种减少开挖沉降量的施工方法。The invention relates to the field of excavation, and in particular to a construction method for reducing excavation settlement.
背景技术Background Art
深基坑具有开挖范围广、深度大等特点,在开挖过程中往往会导致周边的建筑物发生沉降过大从而导致建筑物倾斜、破坏和坍塌等安全事故。目前传统的做法就是在基坑围护结构与建筑物之间设置围护桩,起到变形隔断作用,对于坑外地层条件为土层时具有较好的效果。Deep foundation pits have the characteristics of wide excavation range and great depth. During the excavation process, they often cause excessive settlement of surrounding buildings, resulting in safety accidents such as building tilting, damage and collapse. At present, the traditional practice is to set retaining piles between the foundation pit retaining structure and the building to play a deformation partition role, which has a better effect when the ground conditions outside the pit are soil layers.
然而,基坑开挖本身就会引起岩土受力结构的变化,对于一些含水量较高的土体,在围护桩施工过程中,对既有构造物侧面的土体进行扰动,从而导致已建构筑物单侧倾斜,进而导致已建构筑物单侧沉降,进一步导致安全事故。However, foundation pit excavation itself will cause changes in the rock and soil stress structure. For some soils with high water content, the soil on the side of the existing structure will be disturbed during the construction of retaining piles, causing the existing structure to tilt on one side, and then causing the existing structure to sink on one side, further leading to safety accidents.
发明内容Summary of the invention
本发明意在提供一种减少开挖沉降量的施工方法,减小已建构筑物的沉降。The present invention aims to provide a construction method for reducing excavation settlement and reducing the settlement of built structures.
为达到上述目的,本发明采用如下技术方案:一种减少开挖沉降量的施工方法,包括以下步骤:To achieve the above object, the present invention adopts the following technical solution: a construction method for reducing excavation settlement, comprising the following steps:
步骤一、在基坑周围靠近已建构筑物一侧施工围护桩;Step 1: construct retaining piles around the foundation pit near the existing structure;
步骤二、开挖基坑,在围护桩上部钻第i个水平锚孔,水平锚孔由上至下依次设置,在第i个水平锚孔内插入中空锚杆,中空锚杆端部设有压浆件,压浆件上开有注浆孔;Step 2: excavate the foundation pit, drill the i-th horizontal anchor hole on the upper part of the retaining pile, the horizontal anchor holes are arranged in sequence from top to bottom, insert a hollow anchor rod into the i-th horizontal anchor hole, a grouting piece is provided at the end of the hollow anchor rod, and a grouting hole is opened on the grouting piece;
步骤三、封住锚孔,预留注浆管,通过注浆管从中空锚杆和水平锚孔侧壁之间进行首次注浆;Step 3: seal the anchor hole, reserve a grouting pipe, and perform the first grouting between the hollow anchor rod and the side wall of the horizontal anchor hole through the grouting pipe;
步骤四、待首次注浆的浆液凝固后,从中空锚杆内进行压力注浆,直至浆液压力达到设计压力;Step 4: After the slurry of the first grouting solidifies, pressure grouting is performed from the hollow anchor until the slurry pressure reaches the design pressure;
步骤五、重复步骤二-步骤四,直至完成i个中空锚杆的施工。Step 5: Repeat steps 2 to 4 until the construction of i hollow anchor rods is completed.
本方案的有益效果为:The beneficial effects of this program are:
1.现有技术中,围护桩上的锚杆的作用通常为向围护桩提供拉力,防止围护桩倾覆,因此锚杆的设置方向通常为倾斜向下,锚杆深入基岩中寻找着力点;1. In the prior art, the function of the anchor rod on the retaining pile is usually to provide tension to the retaining pile to prevent the retaining pile from overturning. Therefore, the setting direction of the anchor rod is usually inclined downward, and the anchor rod penetrates into the bedrock to find the fulcrum;
而本方案中的中控锚杆,其主要作用为通过注浆的方式加强已建构筑物周围土体的强度,减少基坑开挖对已建构筑物周围土体的扰动,从而减小已建构筑物的沉降;i为围护桩上设置的水平锚孔的总数,第一个水平锚孔设置在最上方。The main function of the central control anchor in this scheme is to strengthen the strength of the soil around the existing structure by grouting, reduce the disturbance of the soil around the existing structure caused by foundation pit excavation, and thus reduce the settlement of the existing structure; i is the total number of horizontal anchor holes set on the retaining piles, and the first horizontal anchor hole is set at the top.
2.通过水平设置中空锚杆,使注浆的浆液能够快速靠近已建构筑物,从而使中空锚杆端部的土体和浆液结合,从而加强土体强度,防止已建构筑物沉降。2. By setting the hollow anchor rod horizontally, the grouting slurry can quickly approach the existing structure, so that the soil at the end of the hollow anchor rod and the slurry can combine, thereby strengthening the soil strength and preventing the existing structure from settling.
3.现有的中空锚杆上不同位置上通常开有多个注浆孔,以便于浆液从中空锚杆的各个位置进入土体中进行结合加强,从而加强中空锚杆和土体的连接强度;3. The existing hollow anchor rods are usually provided with multiple grouting holes at different positions, so that the grout can enter the soil from various positions of the hollow anchor rod for bonding and strengthening, thereby strengthening the connection strength between the hollow anchor rod and the soil;
而本方案的主要目的在于,通过中空锚杆将浆液输送到靠近已建构筑物的区域,并加强该区域的土体强度,防止已建构筑物沉降;一般来说,由于注浆位置在锚孔的洞口处,越靠近锚孔,浆液压力越大,浆液在土体里扩散的范围越大,越远离锚孔,浆液压力得到释放,浆液在土体里扩散的范围越小;因此,本方案中的中空锚杆不同位置上并未开有多个注浆孔,仅在中控锚杆端部设置注浆孔,使浆液注入锚孔的位置改变为中空锚杆端部,即最靠近已建构筑物的位置,浆液优先在该区域扩散并和土体结合强化,然后浆液再通过中控锚杆和锚孔侧壁之间的空间回流,最终填满所有空间。The main purpose of this scheme is to transport the slurry to the area close to the existing structure through the hollow anchor rod, and to strengthen the soil strength in this area to prevent the settlement of the existing structure. Generally speaking, since the grouting position is at the hole mouth of the anchor hole, the closer to the anchor hole, the greater the slurry pressure, and the larger the range of the slurry diffusion in the soil, and the farther away from the anchor hole, the slurry pressure is released, and the smaller the range of the slurry diffusion in the soil. Therefore, the hollow anchor rod in this scheme does not have multiple grouting holes at different positions, and only a grouting hole is set at the end of the central control anchor rod, so that the position where the slurry is injected into the anchor hole is changed to the end of the hollow anchor rod, that is, the position closest to the existing structure. The slurry diffuses in this area first and combines with the soil to strengthen, and then the slurry flows back through the space between the central control anchor rod and the side wall of the anchor hole, and finally fills all the space.
4.首次注浆后,浆液凝固并达到一定强度形成凝固浆液,由于浆液的收缩,会在中空锚杆周围形成一些微小的缝隙。这些缝隙如果不进行处理,可能会影响中空锚杆的固定效果和承载能力。此时再进行第二次的压力注浆,可以有效地填充这些缝隙,提高锚杆与周围介质的粘结力,同时,压力注浆的压力浆液本身最开始几乎不具有强度,但是在压力浆液的压力下,带动凝固浆液在土体内扩散,凝固浆液能够挤压扰动土体,配合压力浆液扩散更远的范围,加大了强化的土体范围,提升了强化效果,进而减小已建构筑物沉降。4. After the first grouting, the slurry solidifies and reaches a certain strength to form solidified slurry. Due to the shrinkage of the slurry, some tiny gaps will be formed around the hollow anchor rod. If these gaps are not treated, they may affect the fixing effect and bearing capacity of the hollow anchor rod. At this time, a second pressure grouting can effectively fill these gaps and improve the adhesion between the anchor rod and the surrounding medium. At the same time, the pressure grouting slurry itself has almost no strength at the beginning, but under the pressure of the pressure grouting, it drives the solidified slurry to diffuse in the soil. The solidified slurry can squeeze and disturb the soil, and cooperate with the pressure grouting to spread to a farther range, which increases the range of the strengthened soil, improves the strengthening effect, and thus reduces the settlement of the built structure.
进一步的,压浆件和水平锚孔侧壁间隙配合。Furthermore, the grouting member and the side wall of the horizontal anchor hole are clearance-matched.
进一步的,压浆件为椭圆形空心球体,压浆件包括依次连接的回流部、分隔部和前端部,回流部和中空锚杆连接,回流部外表面朝向围护桩,分隔部的截面半径大于中空锚杆,分隔部和水平锚孔侧壁间隙配合,前端部外表面朝向土层深处,注浆孔包括回流注浆孔和端部注浆孔,回流注浆孔设置在回流部上,端部注浆孔设置在前端部上。Furthermore, the grouting part is an elliptical hollow sphere, which includes a reflux part, a partition part and a front end part which are connected in sequence. The reflux part is connected to the hollow anchor rod, the outer surface of the reflux part faces the retaining pile, the cross-sectional radius of the partition part is larger than the hollow anchor rod, the partition part and the side wall of the horizontal anchor hole are gap-matched, the outer surface of the front end part faces the deep soil layer, and the grouting holes include a reflux grouting hole and an end grouting hole. The reflux grouting hole is arranged on the reflux part, and the end grouting hole is arranged on the front end part.
进一步的,回流注浆孔的孔径小于5mm。Furthermore, the diameter of the reflux grouting hole is less than 5 mm.
进一步的,压浆件和水平锚孔之间的周向间隙小于6mm。Furthermore, the circumferential gap between the grouting member and the horizontal anchor hole is less than 6 mm.
进一步的,步骤二中,水平锚孔钻进到基岩位置或已建构筑物边缘时,停止钻进,水平锚孔的长度的计算公式为:Furthermore, in step 2, when the horizontal anchor hole is drilled to the bedrock position or the edge of the built structure, the drilling is stopped, and the calculation formula for the length of the horizontal anchor hole is:
Li≤Di;Li≤Di;
Li≥L(i+1);Li ≥ L(i+1);
当D(i+1)>Li-△hi/tanθ时,L(i+1)=Li-△hi/tanθ;When D(i+1)>Li-△hi/tanθ, L(i+1)=Li-△hi/tanθ;
Li-由上至下,第i个水平锚孔的长度;Li - the length of the i-th horizontal anchor hole from top to bottom;
Di-第i个水平锚孔进口端至基岩的水平距离;Di - horizontal distance from the inlet end of the i-th horizontal anchor hole to the bedrock;
△hi-第i个水平锚孔和第i+1个水平锚孔的高度差;△hi-the height difference between the i-th horizontal anchor hole and the i+1-th horizontal anchor hole;
θ-滑动面和水平面的夹角。θ - Angle between the sliding surface and the horizontal plane.
进一步的,步骤二中,中控锚杆的端部和锚孔底部之间留有余量;Furthermore, in step 2, a margin is left between the end of the center control anchor rod and the bottom of the anchor hole;
步骤三中,以0.3-0.5mpa的压力进行首次注浆,浆液在首次注浆的压力下无法通过回流注浆孔或回流注浆孔的流量小于设计流量;In step 3, the first grouting is performed at a pressure of 0.3-0.5 MPa, and the slurry cannot pass through the reflux grouting hole under the pressure of the first grouting, or the flow rate of the reflux grouting hole is less than the designed flow rate;
步骤四中,当首次注浆的浆液强度达到5mpa以上后,将中空锚杆端部推到锚孔底部,然后进行压力注浆,设计压力为4-5mpa,浆液在压力注浆的压力下通过回流注浆孔和端部注浆孔,达到设计压力后稳压2min以上。In step 4, when the slurry strength of the first grouting reaches more than 5 MPa, push the end of the hollow anchor rod to the bottom of the anchor hole, and then carry out pressure grouting. The design pressure is 4-5 MPa. The slurry passes through the reflux grouting hole and the end grouting hole under the pressure of pressure grouting, and stabilizes the pressure for more than 2 minutes after reaching the design pressure.
进一步的,围护桩下部设有从上至下若干预应力锚索,预应力锚索的倾角从上到下依次递增。Furthermore, a plurality of prestressed anchor cables are provided at the lower part of the retaining pile from top to bottom, and the inclination angles of the prestressed anchor cables increase successively from top to bottom.
本方案还有以下效果:This solution also has the following effects:
1.本方案中,通过控制回流注浆孔的孔径,保证浆液在首次注浆的压力下无法通过回流注浆孔或回流注浆孔的流量小于设计流量;1. In this scheme, by controlling the aperture of the return grouting hole, it is ensured that the slurry cannot pass through the return grouting hole under the pressure of the first grouting or the flow rate of the return grouting hole is less than the designed flow rate;
在设计流量下,首次注浆结束时,浆液无法填充压浆件的内部,即压力注浆时,浆液能够依次通过中控锚杆、压浆件和端部注浆孔;At the design flow rate, at the end of the first grouting, the slurry cannot fill the interior of the grouting part, that is, during pressure grouting, the slurry can pass through the center control anchor, the grouting part and the end grouting hole in sequence;
然后,通过压力注浆,将浆液直接注入锚孔底部,浆液在锚孔底部扩散并和土体结合。Then, the slurry is directly injected into the bottom of the anchor hole through pressure grouting, where it spreads and combines with the soil.
具体的,由于压浆件的分隔部和锚孔侧壁间隙配合,且在压浆件进入锚孔的过程中,锚孔内的孔渣将间隙填充,因此浆液难以从分隔部和锚孔侧壁之间的间隙回流;由于首次注浆时,浆液已经将中空锚杆和锚孔侧壁的空间填充,进一步加大了浆液从中空锚杆和锚孔侧壁之间的空间回流的难度。Specifically, since the partition of the grouting piece and the gap between the side wall of the anchor hole are matched, and when the grouting piece enters the anchor hole, the slag in the anchor hole fills the gap, it is difficult for the slurry to flow back from the gap between the partition and the side wall of the anchor hole; since the slurry has filled the space between the hollow anchor rod and the side wall of the anchor hole during the first grouting, the difficulty of the slurry to flow back from the space between the hollow anchor rod and the side wall of the anchor hole is further increased.
因此,锚孔底部的浆液只能在压力的作用下,朝向已建构筑物一侧的土中扩散,从而加强已建构筑物周围土体的强度,防止已建构筑物沉降。Therefore, the slurry at the bottom of the anchor hole can only diffuse into the soil on one side of the built structure under the action of pressure, thereby strengthening the strength of the soil around the built structure and preventing the built structure from settling.
2.本方案的核心目的在于对已建构筑物附近的土体进行注浆加强,因此注浆位置位于土体中的扩散效果远高于在岩石中的扩散效果,因此,水平锚孔钻进到基岩位置,需要停止钻进,从而保证注浆效果。2. The core purpose of this scheme is to strengthen the soil near the built structure by grouting. Therefore, the diffusion effect of the grouting position in the soil is much higher than that in the rock. Therefore, when the horizontal anchor hole is drilled to the bedrock position, drilling needs to be stopped to ensure the grouting effect.
3.将不同高度中空锚杆的端部连接成一条注浆中心线,用于表示注浆的范围和区域;而土体通常沿滑动面变形,注浆中心线的倾角大于滑动面的倾角,即可通过注浆同时加固滑动面上下的土体,增加土体的整体性和强度,从而有效减小土体变形。3. Connect the ends of hollow anchor rods at different heights into a grouting center line to indicate the scope and area of grouting. The soil usually deforms along the sliding surface. The inclination angle of the grouting center line is greater than the inclination angle of the sliding surface. Grouting can be used to simultaneously reinforce the soil above and below the sliding surface, thereby increasing the integrity and strength of the soil and effectively reducing soil deformation.
4.为防止首次注浆中的浆液将回流注浆孔完全堵死,致使压力注浆时,浆液无法通过回流注浆孔,无法配合凝固浆液达到二次注浆扩大注浆范围的效果;4. To prevent the slurry in the first grouting from completely blocking the return grouting hole, so that during pressure grouting, the slurry cannot pass through the return grouting hole and cannot cooperate with the solidified slurry to achieve the effect of expanding the grouting range by secondary grouting;
本方案在首次注浆前,中控锚杆的端部和锚孔底部之间留有余量,并在压力注浆前,将中空锚杆端部推到锚孔底部,使回流注浆孔和凝固浆液分离,从而疏通回流注浆孔,保证二次注浆(压力注浆)扩大注浆范围的效果得以实现。In this scheme, before the first grouting, a margin is left between the end of the center control anchor rod and the bottom of the anchor hole, and before pressure grouting, the end of the hollow anchor rod is pushed to the bottom of the anchor hole to separate the reflux grouting hole and the solidified slurry, thereby unblocking the reflux grouting hole and ensuring that the effect of expanding the grouting range of the secondary grouting (pressure grouting) is achieved.
5.预应力锚索包括自由段和锚固段,锚固段锚入岩土内的坚硬岩层中,自由段远离锚固段一端为预应力张拉端。由于同一锚固单元的两根预应力设置在同一高度,既预应力张拉端位于同一高度,两根预应力锚索的倾角差距越大,锚固段的距离越远,两根预应力锚索的锚固范围的重叠部分越小,两根预应力锚索的锚固总范围越大,锚固效果越好。5. The prestressed anchor cable includes a free section and an anchoring section. The anchoring section is anchored into the hard rock layer in the soil, and the end of the free section away from the anchoring section is the prestressed tensioning end. Since the two prestressed cables of the same anchoring unit are set at the same height, that is, the prestressed tensioning ends are at the same height, the greater the difference in the inclination angles of the two prestressed anchor cables, the farther the distance between the anchoring sections, the smaller the overlap of the anchoring ranges of the two prestressed anchor cables, the larger the total anchoring range of the two prestressed anchor cables, and the better the anchoring effect.
附图说明BRIEF DESCRIPTION OF THE DRAWINGS
图1为实施例的流程图;Fig. 1 is a flow chart of an embodiment;
图2为实施例的围护桩结构示意图;FIG2 is a schematic diagram of the retaining pile structure of an embodiment;
图3为实施例的步骤二中的中空锚杆端部示意图;FIG3 is a schematic diagram of the end of the hollow anchor rod in step 2 of the embodiment;
图4为实施例的步骤三中的中空锚杆端部示意图;FIG4 is a schematic diagram of the end of the hollow anchor rod in step three of the embodiment;
图5为实施例的步骤四中的中空锚杆端部示意图。FIG. 5 is a schematic diagram of the end of the hollow anchor rod in step 4 of the embodiment.
具体实施方式DETAILED DESCRIPTION
下面通过具体实施方式进一步详细说明:The following is further described in detail through specific implementation methods:
说明书附图中的附图标记包括:已建构筑物1、围护桩2、中空锚杆3、压浆件4、回流部41、分隔部42、前端部43、回流注浆孔44、端部注浆孔45、预应力锚索5、凝固浆液6、岩土分界线71、滑动面72。The figure marks in the drawings of the specification include: built structure 1, retaining piles 2, hollow anchor rods 3, grouting parts 4, return flow part 41, partition part 42, front end part 43, return flow grouting hole 44, end grouting hole 45, prestressed anchor cable 5, solidified slurry 6, rock-soil boundary line 71, and sliding surface 72.
实施例Example
实施例基本如图1所示:一种减少开挖沉降量的施工方法,适用于山城地形、基坑附近存在已建构筑物1的工况,如图2所示,地形中包括基岩和土体,流程图如图1所示,包括以下步骤:The embodiment is basically as shown in FIG1: a construction method for reducing excavation settlement, which is suitable for mountain terrain and the working conditions where there is an existing structure 1 near the foundation pit, as shown in FIG2, the terrain includes bedrock and soil, and the flow chart is shown in FIG1, including the following steps:
步骤一、在基坑周围靠近已建构筑物1一侧施工围护桩2;Step 1: construct retaining piles 2 around the foundation pit near the side of the built structure 1;
步骤二、开挖基坑,在围护桩2上部钻第i个水平锚孔(i=1,2,3,4,5),水平锚孔由上至下依次设置,i为围护桩2上设置的水平锚孔的总数,第一个水平锚孔设置在最上方,水平锚孔之间的高度差均为△h,水平锚孔钻进到基岩位置或已建构筑物1边缘时,停止钻进,本实施例中,已建构筑物1边缘的定义为:距离已建构筑物1基础边缘5米的地方,通常根据已建构筑物1和围护桩2的平面图纸计算得出。Step 2: excavate the foundation pit and drill the i-th horizontal anchor hole (i=1, 2, 3, 4, 5) on the upper part of the retaining pile 2. The horizontal anchor holes are arranged in sequence from top to bottom, i is the total number of horizontal anchor holes arranged on the retaining pile 2, the first horizontal anchor hole is arranged at the top, and the height difference between the horizontal anchor holes is △h. When the horizontal anchor hole is drilled to the bedrock position or the edge of the built structure 1, the drilling is stopped. In this embodiment, the edge of the built structure 1 is defined as: 5 meters away from the edge of the foundation of the built structure 1, which is usually calculated based on the plan drawings of the built structure 1 and the retaining pile 2.
水平锚孔的长度的计算公式为:The calculation formula for the length of the horizontal anchor hole is:
Li≤Di;Li≤Di;
Li≥L(i+1);Li ≥ L(i+1);
当D(i+1)>Li-△hi/tanθ时,L(i+1)=Li-△hi/tanθ;When D(i+1)>Li-△hi/tanθ, L(i+1)=Li-△hi/tanθ;
Li-由上至下,第i个水平锚孔的长度;Li - the length of the i-th horizontal anchor hole from top to bottom;
Di-第i个水平锚孔进口端至基岩的水平距离;Di - horizontal distance from the inlet end of the i-th horizontal anchor hole to the bedrock;
△hi-第i个水平锚孔和第i+1个水平锚孔的高度差,本实施例中△hi恒等于△h;△hi-the height difference between the ith horizontal anchor hole and the i+1th horizontal anchor hole. In this embodiment, △hi is always equal to △h;
θ-水平面和如图2所示的滑动面72的夹角(滑坡体移动时,它与母体之间形成一个界面并沿其下滑,称为滑动面72);θ - the angle between the horizontal plane and the sliding surface 72 shown in FIG2 (when the landslide moves, an interface is formed between it and the parent body and slides down along it, which is called the sliding surface 72);
在水平锚孔内插入中空锚杆3,如图3所示,中空锚杆3端部设有压浆件4,压浆件4和水平锚孔侧壁间隙配合,压浆件4为椭圆形空心球体,椭圆形空心球体的长径水平设置,压浆件4包括依次连接的回流部41、分隔部42和前端部43,其中,分隔部42为椭圆形空心球体竖向高度最大的一部分,分隔部42的截面半径大于中空锚杆3,分隔部42和水平锚孔侧壁间隙配合,压浆件4和水平锚孔之间的周向间隙小于6mm,本实施例中,具体为5mm,回流部41和中空锚杆3连接且连通,回流部41外表面朝向围护桩2,前端部43外表面朝向土层深处,注浆孔包括回流注浆孔44和端部注浆孔45,回流注浆孔44周向开在回流部41上,回流注浆孔44的孔径为4mm,端部注浆孔45周向开在前端部43上,前端部43和锚孔底部之间留有余量,本实施例中,余量为100mm,图中的余量仅为示意,以实际数值为准;A hollow anchor rod 3 is inserted into the horizontal anchor hole. As shown in FIG3 , a grouting piece 4 is provided at the end of the hollow anchor rod 3. The grouting piece 4 and the side wall of the horizontal anchor hole are gap-matched. The grouting piece 4 is an elliptical hollow sphere. The long diameter of the elliptical hollow sphere is horizontally arranged. The grouting piece 4 includes a reflux portion 41, a partition 42 and a front end portion 43 connected in sequence. Among them, the partition 42 is a part of the elliptical hollow sphere with the largest vertical height. The cross-sectional radius of the partition 42 is larger than the hollow anchor rod 3. The partition 42 and the side wall of the horizontal anchor hole are gap-matched. The circumferential gap between the grouting piece 4 and the horizontal anchor hole is small. The diameter of the reflux portion 41 is 6 mm, and in this embodiment, it is specifically 5 mm. The reflux portion 41 is connected and communicated with the hollow anchor rod 3. The outer surface of the reflux portion 41 faces the retaining pile 2, and the outer surface of the front end portion 43 faces the deep soil layer. The grouting holes include a reflux grouting hole 44 and an end grouting hole 45. The reflux grouting hole 44 is circumferentially opened on the reflux portion 41. The diameter of the reflux grouting hole 44 is 4 mm. The end grouting hole 45 is circumferentially opened on the front end portion 43. A margin is left between the front end portion 43 and the bottom of the anchor hole. In this embodiment, the margin is 100 mm. The margin in the figure is only for reference, and the actual value shall prevail.
步骤三、封住锚孔,预留中空锚杆左端进口和一个注浆管,如图4所示,以0.3-0.5mpa的压力,通过注浆管从中空锚杆3和水平锚孔侧壁之间进行首次注浆,浆液在首次注浆的压力下无法通过回流注浆孔44或回流注浆孔44的流量小于设计流量;Step 3: seal the anchor hole, reserve the inlet at the left end of the hollow anchor rod and a grouting pipe, as shown in FIG4 , perform the first grouting between the hollow anchor rod 3 and the side wall of the horizontal anchor hole through the grouting pipe at a pressure of 0.3-0.5 MPa, and the slurry cannot pass through the return grouting hole 44 under the pressure of the first grouting or the flow rate of the return grouting hole 44 is less than the design flow rate;
步骤四、当首次注浆的浆液强度达到5mpa以上后,如图5所示,将中空锚杆3端部推到锚孔底部,即将步骤二中留有的余量变为零,压浆件4的回流部41和首次注浆形成的凝固浆液6分离;Step 4: When the slurry strength of the first grouting reaches more than 5 MPa, as shown in FIG5 , the end of the hollow anchor rod 3 is pushed to the bottom of the anchor hole, that is, the remaining amount in step 2 becomes zero, and the return portion 41 of the grouting member 4 is separated from the solidified slurry 6 formed by the first grouting;
然后进行压力注浆,设计压力为4-5mpa,浆液在压力注浆的压力下通过回流注浆孔44和端部注浆孔45,达到设计压力后稳压2min以上,从中空锚杆3内进行压力注浆,直至浆液压力达到设计压力;Then, pressure grouting is performed, and the design pressure is 4-5 MPa. The grout passes through the return grouting hole 44 and the end grouting hole 45 under the pressure of pressure grouting. After reaching the design pressure, the pressure is stabilized for more than 2 minutes, and pressure grouting is performed from the hollow anchor rod 3 until the grout pressure reaches the design pressure.
步骤五、重复步骤二-步骤四,直至完成五个中空锚杆3的施工;Step 5: Repeat step 2 to step 4 until the construction of five hollow anchor rods 3 is completed;
步骤六,在围护桩2下部施工预应力锚索5;Step 6: construct a prestressed anchor cable 5 at the bottom of the retaining pile 2;
如图2所示,围护桩2下部设有从上至下若干预应力锚索5,预应力锚索5的端部穿过岩土分界线71进入基岩内,岩土分界线71左侧为基岩,右侧为土体,预应力锚索5的倾角α从上到下依次递增。As shown in FIG2 , a plurality of prestressed anchor cables 5 are provided at the lower part of the retaining pile 2 from top to bottom. The ends of the prestressed anchor cables 5 pass through the rock-soil boundary 71 and enter the bedrock. The left side of the rock-soil boundary 71 is the bedrock, and the right side is the soil. The inclination angle α of the prestressed anchor cables 5 increases from top to bottom.
以上所述的仅是本发明的实施例,方案中公知的具体技术方案和/或特性等常识在此未作过多描述。应当指出,对于本领域的技术人员来说,在不脱离本发明技术方案的前提下,还可以作出若干变形和改进,这些也应该视为本发明的保护范围,这些都不会影响本发明实施的效果和专利的实用性。本申请要求的保护范围应当以其权利要求的内容为准,说明书中的具体实施方式等记载可以用于解释权利要求的内容。The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and/or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202411212013.5A CN118814819B (en) | 2024-08-30 | 2024-08-30 | A construction method for reducing excavation settlement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202411212013.5A CN118814819B (en) | 2024-08-30 | 2024-08-30 | A construction method for reducing excavation settlement |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN118814819A true CN118814819A (en) | 2024-10-22 |
| CN118814819B CN118814819B (en) | 2025-01-21 |
Family
ID=93078368
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202411212013.5A Active CN118814819B (en) | 2024-08-30 | 2024-08-30 | A construction method for reducing excavation settlement |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN118814819B (en) |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1996023959A1 (en) * | 1995-02-01 | 1996-08-08 | Reburg-Patentverwertungsgesellschaft Mbh | Injection anchor |
| CN106759376A (en) * | 2016-12-21 | 2017-05-31 | 大连交通大学 | Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure |
| CN112900459A (en) * | 2021-01-27 | 2021-06-04 | 洛阳理工学院 | Composite reinforcement method for soft clay side slope |
| CN114837713A (en) * | 2022-06-13 | 2022-08-02 | 辽宁石油化工大学 | Expansion grout stop plug for grouting anchor rod and application method thereof |
| CN114934518A (en) * | 2022-05-23 | 2022-08-23 | 甘肃建投建设有限公司 | Deep foundation pit reinforcing method combining reverse pile, pressure reduction and grouting |
| CN118166783A (en) * | 2024-02-02 | 2024-06-11 | 北京建工四建工程建设有限公司 | Construction method for active foundation reinforcement comprehensive support between new and old buildings |
| CN221346994U (en) * | 2023-11-27 | 2024-07-16 | 华能庆阳煤电有限责任公司核桃峪煤矿 | Special grout stop plug for mining grouting anchor rod |
-
2024
- 2024-08-30 CN CN202411212013.5A patent/CN118814819B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO1996023959A1 (en) * | 1995-02-01 | 1996-08-08 | Reburg-Patentverwertungsgesellschaft Mbh | Injection anchor |
| CN106759376A (en) * | 2016-12-21 | 2017-05-31 | 大连交通大学 | Anchored Sheet Pile Wall for Excavation system and its construction method for closing on existing underground structure |
| CN112900459A (en) * | 2021-01-27 | 2021-06-04 | 洛阳理工学院 | Composite reinforcement method for soft clay side slope |
| CN114934518A (en) * | 2022-05-23 | 2022-08-23 | 甘肃建投建设有限公司 | Deep foundation pit reinforcing method combining reverse pile, pressure reduction and grouting |
| CN114837713A (en) * | 2022-06-13 | 2022-08-02 | 辽宁石油化工大学 | Expansion grout stop plug for grouting anchor rod and application method thereof |
| CN221346994U (en) * | 2023-11-27 | 2024-07-16 | 华能庆阳煤电有限责任公司核桃峪煤矿 | Special grout stop plug for mining grouting anchor rod |
| CN118166783A (en) * | 2024-02-02 | 2024-06-11 | 北京建工四建工程建设有限公司 | Construction method for active foundation reinforcement comprehensive support between new and old buildings |
Also Published As
| Publication number | Publication date |
|---|---|
| CN118814819B (en) | 2025-01-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN115787693B (en) | Water stopping method for water gushing in deep foundation pit under river-like gentle dip mutually-inclined layer | |
| CN109339029B (en) | Construction method for resisting uplift deformation in excavation of foundation pit above existing tunnel | |
| CN112663694B (en) | Construction method for lifting and rectifying building on silt geology | |
| JP2007239420A (en) | Structure of foundation for preventing floating of structure, its execution method and structure of pile used for its foundation or execution method | |
| CN111663538A (en) | Construction method for deep foundation pit miniature steel pipe pile support in complex geology of clearance limited area | |
| CN113089482B (en) | Double-hole single-anchor system and construction method thereof | |
| CN109024721B (en) | Reinforced foundation and method for improving bending and shearing resistance of existing building rigid foundation | |
| CN112081158A (en) | A construction technology for forming a reinforced composite pile foundation by forward grouting for high-rise buildings | |
| CN101793027B (en) | Core-grouted static pressure anchor rod pile | |
| CN118814819A (en) | A construction method for reducing excavation settlement | |
| CN214169107U (en) | Cast-in-situ bored pile structure in area with intense karst | |
| CN110821498B (en) | Safe and rapid water plugging and reinforcing method in strong water-rich soft surrounding rock of operation tunnel | |
| CN101311421B (en) | Root anchorage and its construction method | |
| CN112726627A (en) | Cast-in-situ bored pile structure in area with intense karst and construction method | |
| CN114233301A (en) | Tunnel entering construction method for stabilizing mountain body under large bias terrain | |
| CN118854934A (en) | A deformation-resistant deep foundation pit pile foundation structure and construction method | |
| CN118911155A (en) | Deep foundation pit supporting device and construction method | |
| CN108952765B (en) | Construction method of advanced support of super large tube shed in water-rich sand layer | |
| CN217078737U (en) | An assembled static pressure concrete bolt | |
| CN202755385U (en) | Anti-floating structure of shallow-buried shield tunnel | |
| CN116607548A (en) | Side slope supporting structure and side slope supporting method | |
| CN117328496A (en) | A support and jacking device and construction method for tunnels to closely pass under existing structures | |
| CN115977165A (en) | A reinforced structure of a shield tunnel passing a building at close range | |
| LU600083B1 (en) | Double-hole single-anchor system and construction method thereof | |
| CN115506380A (en) | Diagonal bracing anti-slip support system and construction method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |