CN116905818A - Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method - Google Patents
Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method Download PDFInfo
- Publication number
- CN116905818A CN116905818A CN202310904192.8A CN202310904192A CN116905818A CN 116905818 A CN116905818 A CN 116905818A CN 202310904192 A CN202310904192 A CN 202310904192A CN 116905818 A CN116905818 A CN 116905818A
- Authority
- CN
- China
- Prior art keywords
- tongue
- hole
- groove
- pouring
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G13/00—Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/12—Mounting of reinforcing inserts; Prestressing
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)
Abstract
本发明涉及多层或高层建筑预留洞后浇筑施工方法,具体为现浇楼板预留洞企口式封堵施工方法。本发明通过特制的企口式定型铝模对现浇楼板预留洞进行封堵,采用回顶支撑进行模板加固,在后浇构件处加设植筋后,分两次进行混凝土浇筑,既保证了构件的结构安全,又大大降低了混凝土开裂的风险。企口式定型铝模主要由主框、把手、定位板和压片组成。主框的垂直方向中部设置企口台阶板,能在浇筑混凝土时形成企口,有效保证后浇构件受力牢固;同时洞口四周的企口增加了渗漏路径,降低了后期的渗漏风险。该方法法操作简单,实用性强,定型化铝模装置周转次数高,科技环保,且有效解决楼板预留洞口的渗漏问题。
The invention relates to a construction method for post-pouring reserved holes in multi-story or high-rise buildings, specifically a tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs. This invention uses a special tongue-and-groove shaped aluminum form to seal the reserved holes in the cast-in-place floor slab, and uses back-top supports to reinforce the formwork. After adding planting bars at the post-cast components, the concrete is poured in two steps, which ensures that It improves the structural safety of the components and greatly reduces the risk of concrete cracking. The tongue-and-groove shaped aluminum mold is mainly composed of a main frame, a handle, a positioning plate and a pressing piece. A tongue-and-groove step plate is set in the vertical middle of the main frame, which can form a tongue-and-groove when pouring concrete, effectively ensuring that the post-poured components are firmly stressed; at the same time, the tongue-and-groove around the hole increases the leakage path and reduces the risk of later leakage. This method is simple to operate, highly practical, has a high turnover rate of the stereotyped aluminum mold device, is technologically environmentally friendly, and can effectively solve the leakage problem of reserved holes in the floor slab.
Description
技术领域Technical field
本发明涉及多层或高层建筑预留洞后浇筑施工方法,具体为现浇楼板预留洞企口式封堵施工方法。The invention relates to a construction method for post-pouring reserved holes in multi-story or high-rise buildings, specifically a tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs.
背景技术Background technique
随着建筑业及国民经济的发展,越来越多的人选择商品房作为自己的住宅。由于一般的住宅多是多层或高层建筑,为了满足施工控制线的传递需求,需要在现浇楼板上预留放线孔。部分高层建筑由于高度过大,还需采用车载泵进行施工作业,使得需要在楼板上增设泵管孔。由于多层或高层建筑水平洞口较多,后浇筑部位多,且根据以往施工经验,后浇筑构件渗漏风险极大,所以对这些孔洞的封堵质量控制是一项重要工作。With the development of the construction industry and the national economy, more and more people choose commercial housing as their residence. Since most general residences are multi-story or high-rise buildings, in order to meet the transmission requirements of construction control lines, it is necessary to reserve wiring holes in the cast-in-place floor slabs. Due to their excessive height, some high-rise buildings need to use vehicle-mounted pumps for construction operations, which requires additional pump pipe holes in the floor slabs. Since there are many horizontal openings in multi-story or high-rise buildings, there are many post-casting parts, and based on past construction experience, the risk of leakage of post-casting components is extremely high, so the quality control of the plugging of these holes is an important task.
发明内容Contents of the invention
本发明针对多层或高层建筑预留洞后浇筑渗漏风险极大的问题,提供了现浇楼板预留洞企口式封堵施工方法。Aiming at the problem of extremely high risk of leakage during pouring after reserved holes in multi-story or high-rise buildings, the present invention provides a tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs.
本发明是采用如下的技术方案实现的:现浇楼板预留洞企口式封堵施工方法,包括以下步骤:企口式定型铝模制作→墙柱板模板安装→洞口预留→预留洞口设置加强筋→板面浇筑→拆模→洞口凿毛→植筋→模板安装→浇筑→养护;所述企口式定型铝模包括主框、把手、定位板和压片,主框包括上斜板围成的上框和下斜板围成的下框,上框和下框之间设置由企口台阶板围成的企口平台,企口式定型铝模采用一次成型的工艺,阴角位置焊接三角片;下框的下方连接有定位板,定位板的内部设置有压片,定位板上开有若干销钉孔,预留洞口四周顶板模板和预留洞口企口式定型铝模通过定位板上的销钉孔连接来固定企口式定型铝模;主框两条长边上部设置把手。The present invention is realized by adopting the following technical solution: a tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs, which includes the following steps: making tongue-and-groove shaped aluminum molds → installing wall column board templates → reserving openings → reserving openings Set up reinforcing ribs → Pour the board → Remove the form → Chise the hole → Plant the ribs → Install the template → Pour → Maintain; the tongue-and-groove shaped aluminum mold includes a main frame, a handle, a positioning plate and a pressing piece, and the main frame includes an upward slope The upper frame is surrounded by boards and the lower frame is surrounded by lower inclined plates. A tongue-and-groove platform surrounded by tongue-and-groove step boards is set between the upper frame and the lower frame. The tongue-and-groove shaped aluminum mold adopts a one-time molding process, and the inner corners The triangle piece is welded at the position; a positioning plate is connected to the bottom of the lower frame. There is a pressing plate inside the positioning plate. There are a number of pin holes on the positioning plate. The top plate template around the reserved hole and the tongue-and-groove shaped aluminum mold of the reserved hole are positioned through The pin holes on the board are connected to fix the tongue-and-groove shaped aluminum mold; handles are provided on the two long sides of the main frame.
上述的现浇楼板预留洞企口式封堵施工方法,洞口预留的具体步骤为:预留洞口的四周顶板模板上留有销钉孔,销钉孔位置与企口式定型铝模的定位板上的销钉孔一致;待顶板模板校核无误后开始安装预留洞口的企口式定型铝模,安装时将定位板销钉孔与洞口四周顶板模板的销钉孔对齐,打入销钉销片进行固定。The above-mentioned tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs. The specific steps for reserving the holes are: leave pin holes on the roof formwork around the reserved holes. The positions of the pin holes are consistent with the positioning plates of the tongue-and-groove shaped aluminum molds. The pin holes on the top plate are consistent; after the roof template is verified to be correct, start installing the tongue-and-groove shaped aluminum mold with the reserved hole. During installation, align the pin holes of the positioning plate with the pin holes of the roof template around the hole, and drive in pins for fixation. .
上述的现浇楼板预留洞企口式封堵施工方法,植筋的具体过程为:The above-mentioned construction method of tongue-and-groove sealing of reserved holes in cast-in-place floor slabs, the specific process of planting reinforcement is as follows:
(1)定位:按设计要求标示植筋钻孔的位置、规格;(1) Positioning: Mark the location and specifications of drilling holes for planting reinforcement according to design requirements;
(2)钻孔:用电锤或风钻对设计的直径及深度钻孔;(2) Drilling: Use an electric hammer or pneumatic drill to drill holes to the designed diameter and depth;
(3)清孔:钻孔完毕后将孔内粉尘用鼓风机吹出,用毛刷或棉布将壁孔刷净,反复多次进行,直至孔内无尘;(3) Hole cleaning: After drilling, blow out the dust in the hole with a blower, and use a brush or cotton cloth to clean the wall hole. Repeat this process many times until there is no dust in the hole;
(4)粘胶剂配制:植筋胶按配比要求放入洁净的容器中充分混合,直至A、B组分完全混合均匀为止;(4) Adhesive preparation: Put the adhesive in a clean container according to the proportion requirements and mix thoroughly until components A and B are completely mixed;
(5)植筋:将配好的植筋胶通过胶枪打入孔内,从底部开始将空气排出,再将钢筋以旋转方式插至孔底部;植筋锚固长度按基准15d;(5) Rebar planting: drive the prepared rebar planting glue into the hole through a glue gun, discharge the air from the bottom, and then insert the steel bar to the bottom of the hole in a rotating manner; the anchorage length of the rebar planting is 15d according to the benchmark;
(6)固化:依据环境温度等待胶体固化,完全固化后可进行负载安装。(6) Curing: Wait for the colloid to solidify according to the ambient temperature. After complete solidification, load installation can be carried out.
上述的现浇楼板预留洞企口式封堵施工方法,模板安装的具体过程为:植筋完成后,进行模板安装,模板安装前要对预留洞口四周进行清理,侧壁进行冲洗,模板清理干净,涂刷脱模剂,洞口底部采用钢管进行回顶,边长过大的洞口底部可根据需求设置多根立杆进行回顶,以免模板挠度过大,造成侧面漏浆,影响观感质量。For the above-mentioned construction method of tongue-and-groove sealing of reserved holes in cast-in-place floor slabs, the specific process of formwork installation is as follows: after the reinforcement planting is completed, the formwork is installed. Before installing the formwork, the surroundings of the reserved holes must be cleaned, the side walls must be flushed, and the formwork must be installed. Clean it, apply release agent, and use steel pipes at the bottom of the hole for backing. If the bottom of the hole is too long, multiple vertical poles can be set up as needed to prevent the template from deflecting too much, causing side slurry leakage and affecting the visual quality.
上述的现浇楼板预留洞企口式封堵施工方法,浇筑的具体过程为:在浇筑混凝土之前对模板及洞口侧壁进行浇水湿润,采用比原楼板高一标号的微膨胀细石混凝土进行浇筑;若结构无特殊防水要求,则一次性浇筑完成;若结构有特殊防水要求,浇筑混凝土时分为两次,第一次浇筑高度为板厚的1/2,待第一层混凝土表面有强度以后涂刷渗透结晶,再进行二次浇筑。The above-mentioned construction method of tongue-and-groove sealing of reserved holes in cast-in-place floor slabs. The specific pouring process is: before pouring concrete, water the formwork and side walls of the openings to moisten them, and use micro-expanded fine stone concrete that is one grade higher than the original floor slab. Carry out pouring; if the structure does not have special waterproofing requirements, the pouring will be completed in one go; if the structure has special waterproofing requirements, the concrete pouring will be divided into two times. The first pouring height will be 1/2 of the plate thickness. When the surface of the first layer of concrete is After the strength is applied, the penetration crystallization is applied, and then the second pouring is carried out.
本发明具有以下技术优点:The invention has the following technical advantages:
1.便捷高效,节约成本:预留洞口通过采用企口式定型铝模方便安装、拆卸,可以大大提高施工效率,且定型模板可周转次数高,节约了成本。1. Convenient, efficient, and cost-saving: The reserved holes are easy to install and disassemble by using tongue-and-groove shaped aluminum molds, which can greatly improve construction efficiency, and the shaped formwork can be turned over a lot, saving costs.
2.成型质量可靠:铝合金模板刚度大,表面平整光滑,可以保证洞口不变形,成型质量好,观感质量佳。2. Reliable molding quality: The aluminum alloy template has high stiffness and a flat and smooth surface, which can ensure that the hole is not deformed, has good molding quality and good visual quality.
3.封堵效果好,降低质量缺陷:预留洞口采用企口式定型铝模可以在一次浇筑时,使洞口四周形成企口,有效保证后浇构件受力可靠,结构牢固。采用模板底部回顶支撑的方法,从根本上降低了渗漏点。防水要求高的部位混凝土浇筑由一次成型改为分层浇筑,在两层混凝土中间涂刷渗透结晶,形成防水层,提高结构自防水能力。采用本方法,预留洞口封堵渗漏几率大大降低,观感质量好,减少二次修补工作。3. The sealing effect is good and the quality defects are reduced: the reserved hole adopts tongue-and-groove shaped aluminum mold, which can form a tongue and groove around the hole during one pouring, effectively ensuring that the post-poured components are stressed reliably and the structure is firm. The method of back-top support at the bottom of the formwork fundamentally reduces leakage points. Concrete pouring in areas with high waterproofing requirements is changed from one-time molding to layered pouring. Penetrating crystals are painted between the two layers of concrete to form a waterproof layer and improve the self-waterproofing ability of the structure. Using this method, the probability of sealing the reserved holes and leakage is greatly reduced, the visual quality is good, and the secondary repair work is reduced.
4.经济合理,绿色环保:本方法解决了后浇构件渗漏问题,减少后期修补的人工费用及砂浆等建筑材料的使用,体现出经济性和环保性。4. Economical and reasonable, green and environmentally friendly: This method solves the problem of leakage of post-cast components, reduces labor costs for later repairs and the use of mortar and other building materials, and reflects economy and environmental protection.
附图说明Description of the drawings
图1为企口式定型铝模的结构示意图。Figure 1 is a schematic structural diagram of a tongue-and-groove shaped aluminum mold.
图2为企口式定型铝模的使用状态图。Figure 2 is a diagram of the use status of the tongue-and-groove shaped aluminum mold.
图中:1-主框,2-把手,3-企口台阶板,4-压片,5-定位板,6-销钉孔,7-上斜板,8-下斜板,9-楼板。In the picture: 1-main frame, 2-handle, 3-tongue and groove step plate, 4-pressing piece, 5-positioning plate, 6-pin hole, 7-upper inclined plate, 8-lower inclined plate, 9-floor.
具体实施方式Detailed ways
本发明通过特制的企口式定型铝模对现浇楼板预留洞进行封堵,采用回顶支撑进行模板加固,在后浇构件处加设植筋后,分两次进行混凝土浇筑,既保证了构件的结构安全,又大大降低了混凝土开裂的风险。企口式定型铝模主要由主框1、把手2、定位板5和压片4组成。主框1的垂直方向中部设置企口台阶板3,能在浇筑混凝土时形成企口,有效保证后浇构件受力牢固;同时洞口四周的企口增加了渗漏路径,降低了后期的渗漏风险;主框1的两条长边上部各居中设置一个把手2,既方便拆卸,又可避免阻碍传料口物料的通过。该方法操作简单,实用性强,企口式定型铝模周转次数高,科技环保,且有效解决楼板预留洞口的渗漏问题。This invention uses a special tongue-and-groove shaped aluminum form to seal the reserved holes in the cast-in-place floor slab, and uses back-top supports to reinforce the formwork. After adding planting bars at the post-cast components, the concrete is poured in two steps, which ensures It improves the structural safety of the components and greatly reduces the risk of concrete cracking. The tongue-and-groove shaped aluminum mold is mainly composed of the main frame 1, the handle 2, the positioning plate 5 and the pressing plate 4. A tongue-and-groove step plate 3 is provided in the vertical middle of the main frame 1, which can form a tongue-and-groove when pouring concrete, effectively ensuring that the post-poured components are firmly stressed; at the same time, the tongue-and-groove around the hole increases the leakage path and reduces later leakage. Risk; a handle 2 is provided in the middle of each of the two long sides of the main frame 1, which not only facilitates disassembly, but also avoids blocking the passage of materials through the material transfer port. This method is simple to operate, highly practical, has a high turnover rate of tongue-and-groove shaped aluminum molds, is technologically environmentally friendly, and can effectively solve the leakage problem of reserved holes in floor slabs.
本发明现浇楼板预留洞企口式封堵施工方法,包括以下步骤:企口式定型铝模制作→墙柱板模板安装→洞口预留(企口式定型铝模安装)→预留洞口设置加强筋→板面浇筑→拆模→洞口凿毛→植筋→模板安装→一次浇筑→涂刷渗透结晶→二次浇筑→养护。The present invention's tongue-and-groove sealing construction method for reserved holes in cast-in-place floor slabs includes the following steps: making tongue-and-groove shaped aluminum molds → installation of wall column board templates → hole reservation (installation of tongue-and-groove shaped aluminum molds) → reserved holes Set up reinforcing ribs → Pour the slab → Remove the formwork → Chisel the hole → Plant the ribs → Install the formwork → Primary pouring → Apply penetrating crystals → Secondary pouring → Maintenance.
企口式定型铝模制作Tongue-and-groove shaped aluminum mold production
企口式定型铝模主要由主框1、把手2、定位板5、压片4四部分组成。主框1包括上斜板7围成的上框和下斜板8围成的下框,上框和下框之间设置由企口台阶板3围城的企口平台,企口式定型铝模采用一次成型的工艺,阴角位置焊接三角片,以增强整体性,提高定型铝模刚度。倾斜向外设置的斜板与预留洞口周边的混凝土形成拔模角度,方便定型模板的脱模,并且倾斜设置的主框1使传料孔的开口变大,方便建筑材料的传递。主框1上的企口台阶板3使预留孔洞周围的顶板第一次浇筑混凝土时形成的预留洞口带有企口,增加了渗漏路径,同时有效保证后浇构件受力牢固。定位板5和压片4的作用是通过和洞口四周顶板模板及预留洞口企口式定型铝模相互连接来固定企口式定型铝模。主框1两条长边上部设置把手2,在对企口式定型模板进行脱模时,把手2容易受力,方便模板脱模。The tongue-and-groove shaped aluminum mold is mainly composed of four parts: the main frame 1, the handle 2, the positioning plate 5, and the pressing piece 4. The main frame 1 includes an upper frame surrounded by an upper inclined plate 7 and a lower frame surrounded by a lower inclined plate 8. A tongue-and-groove platform surrounded by a tongue-and-groove step plate 3 is set between the upper frame and the lower frame. A tongue-and-groove shaped aluminum mold is provided. Using a one-time molding process, triangular pieces are welded at the inner corners to enhance the integrity and improve the stiffness of the shaped aluminum mold. The inclined plate set outwards forms a draft angle with the concrete around the reserved opening, which facilitates the demoulding of the finalized formwork, and the main frame 1 set inclined makes the opening of the material transfer hole larger to facilitate the transfer of building materials. The tongue-and-groove step plate 3 on the main frame 1 makes the reserved hole in the roof around the reserved hole formed when concrete is poured for the first time have a tongue and groove, which increases the leakage path and effectively ensures that the post-poured components are firmly stressed. The function of the positioning plate 5 and the pressing plate 4 is to fix the tongue-and-groove shaped aluminum mold by interconnecting with the roof template around the hole and the reserved hole tongue-and-groove shaped aluminum mold. Handles 2 are provided on the upper parts of the two long sides of the main frame 1. When demoulding the tongue-and-groove shaped template, the handles 2 are easily stressed, making it convenient to demould the template.
模板安装Template installation
模板安装要严格按照施工方案进行,安装前要对模板进行清理,安装过程中要注意销钉销片的数量、间距及紧固程度。支撑体系要按照方案及规范要求进行搭设,安装完成后要及时对标高、垂直度、平整度进行检验校核。The formwork installation must be carried out in strict accordance with the construction plan. The formwork must be cleaned before installation. During the installation process, pay attention to the number, spacing and tightening degree of the pins. The support system must be erected in accordance with the plan and specification requirements. After the installation is completed, the elevation, verticality, and flatness must be inspected and checked in a timely manner.
洞口预留Cave entrance reserved
在图纸深化时提前规划好传料口、放线口等位置,在现场安装模板时预留好水平洞口。预留洞口的四周顶板模板上留有销钉孔,这些销钉孔位置与企口式定型铝模的定位板5上的销钉孔一致。待顶板模板校核无误后开始安装预留洞口的企口式定型铝模,安装时将定位板销钉孔与洞口四周顶板模板的销钉孔对齐,打入销钉销片进行固定。所有企口式定型铝模安装完成后要及时检查模板是否牢固可靠。Plan the locations of the material transfer port and pay-out port in advance when drawing the drawings, and reserve horizontal holes when installing the formwork on site. Pin holes are left on the top plate template around the reserved hole, and the positions of these pin holes are consistent with the pin holes on the positioning plate 5 of the tongue-and-groove shaped aluminum mold. After the roof template is verified to be correct, start installing the tongue-and-groove shaped aluminum mold with the reserved hole. During installation, align the pin holes of the positioning plate with the pin holes of the roof template around the hole, and drive in pins for fixation. After the installation of all tongue-and-groove shaped aluminum molds, it is necessary to promptly check whether the templates are firm and reliable.
设置加强筋Set stiffeners
洞口四周按图纸要求设置加强筋。加强筋可以有效防止洞口的角部开裂,钢筋后台加工过程中注意检查加强筋下料长度,必须满足图纸要求。钢筋绑扎过程中注意将加强筋与周边楼板钢筋绑扎在一起,确保绑扎牢固,避免浇筑混凝土过程中钢筋受到扰动移位,造成露筋现象。Reinforcement ribs should be set around the hole according to the drawing requirements. Reinforcement ribs can effectively prevent cracking at the corners of the opening. During the background processing of steel bars, pay attention to checking the cutting length of the reinforcement ribs, which must meet the drawing requirements. During the process of tying the steel bars, pay attention to tying the reinforcing bars with the surrounding floor slab steel bars to ensure that they are firmly tied and to avoid the steel bars being disturbed and displaced during the concrete pouring process, resulting in exposed steel bars.
板面浇筑slab pouring
按照施工方案进行浇筑,浇筑过程中,要铺设脚手板,最大程度减少对钢筋的踩踏破坏,对受到扰动的钢筋需及时进行修复。浇筑到预留洞口位置时,需特别注意模板、钢筋是否发生位移或破坏,对受到破坏的部位及时停止浇筑,待修复完成后继续浇筑。收面过程中注意控制板厚及标高,收面平整光滑,收面完成及时覆盖薄膜,以免失水开裂。Carry out pouring according to the construction plan. During the pouring process, scaffolding boards must be laid to minimize trampling damage to the steel bars. Disturbed steel bars must be repaired in time. When pouring to the reserved opening, pay special attention to whether the formwork and steel bars are displaced or damaged. Stop pouring in the damaged parts in time, and continue pouring after the repair is completed. During the closing process, pay attention to controlling the thickness and height of the board, making the closing surface smooth and smooth, and covering the surface with film in time to avoid water loss and cracking.
拆模Remove the mold
待混凝土强度达到规定要求时方可进行模板拆除,拆除过程中需要注意施工力度,严禁暴力拆除,以免造成混凝土结构缺棱掉角。预留洞口处模板应待其他部位拆除完成后再拆除,且拆除过程中要轻敲侧壁,以免造成破坏。The formwork can be removed only when the strength of the concrete reaches the specified requirements. During the dismantling process, attention must be paid to the construction intensity, and violent dismantling is strictly prohibited to avoid missing edges and corners of the concrete structure. The formwork for the reserved opening should be removed after other parts have been dismantled, and the side walls should be tapped lightly during the dismantling process to avoid damage.
洞口凿毛Chiseling the hole
在封堵预留洞口之前要对洞口周边进行清扫冲洗,对洞口侧壁进行凿毛处理。凿毛应采用花锤,严禁使用电镐,楼板厚度较小,电镐容易破坏原有结构及板内钢筋。凿毛应达到石子外露,凿毛完成后用清水进行清洗。Before sealing the reserved hole, the surrounding area of the hole should be cleaned and flushed, and the side walls of the hole should be chiseled. A flower hammer should be used for chipping, and the use of electric picks is strictly prohibited. The thickness of the floor is small, and electric picks can easily damage the original structure and the steel bars in the slab. The chiseling should be done until the stone is exposed. After the chiseling is completed, clean it with clean water.
植筋Planting tendons
沿原楼板配筋延长线方向进行植筋,钢筋型号及钢筋间距同原楼板配筋。预留洞口可以采用植筋胶植筋锚固,具体操作流程为:Plant the steel bars along the extension line of the original floor slab reinforcement. The steel bar type and spacing are the same as the original floor slab reinforcement. The reserved holes can be anchored with glue and reinforcement. The specific operation process is as follows:
(1)定位:按设计要求标示植筋钻孔的位置、规格;(1) Positioning: Mark the location and specifications of drilling holes for planting reinforcement according to design requirements;
(2)钻孔:宜用电锤或风钻对设计的直径及深度钻孔,如遇不可切断的钢筋应避开,调整孔位后再施工;(2) Drilling: It is advisable to use an electric hammer or pneumatic drill to drill holes to the designed diameter and depth. If there are steel bars that cannot be cut off, avoid them and adjust the hole position before construction;
(3)清孔:钻孔完毕后将孔内粉尘用鼓风机吹出,用毛刷或棉布将壁孔刷净,应反复多次进行,直至孔内无尘;(3) Hole cleaning: After drilling, blow out the dust in the hole with a blower, and use a brush or cotton cloth to clean the wall hole. This should be repeated several times until there is no dust in the hole;
(4)粘胶剂配制:植筋胶严格按配比要求放入洁净的容器中充分混合,直至A,B组分完全混合均匀为止;(4) Adhesive preparation: Put the adhesive in a clean container and mix it thoroughly according to the proportion requirements until components A and B are completely mixed;
(5)植筋:将配好的植筋胶通过胶枪打入孔内,从底部开始将空气排出,再将钢筋以旋转方式插至孔底部;植筋锚固长度按基准15d;(5) Rebar planting: drive the prepared rebar planting glue into the hole through a glue gun, discharge the air from the bottom, and then insert the steel bar to the bottom of the hole in a rotating manner; the anchoring length of the rebar planting is 15d according to the benchmark;
(6)固化:依据环境温度等待胶体固化,完全固化后可进行负载安装。(6) Curing: Wait for the colloid to solidify according to the ambient temperature. After complete solidification, load installation can be carried out.
模板安装Template installation
植筋完成后,进行模板安装,模板安装前要对洞口四周进行清理,侧壁进行冲洗,模板要清理干净,涂刷脱模剂。底部采用钢管进行回顶,边长过大(超过300mm)的洞口底部可根据需求设置多根立杆进行回顶,以免模板挠度过大,造成侧面漏浆,影响观感质量。After the reinforcement is planted, the formwork should be installed. Before installing the formwork, the surroundings of the hole should be cleaned, the side walls should be rinsed, the formwork should be cleaned, and a release agent should be applied. Steel pipes are used at the bottom for backing up. If the side length of the hole is too large (over 300mm), multiple vertical poles can be set up at the bottom for backing up as needed to avoid excessive deflection of the formwork, causing slurry leakage on the sides and affecting the visual quality.
混凝土浇筑concrete pouring
在浇筑混凝土之前对模板及洞口侧壁进行浇水湿润,采用比原楼板高一标号的微膨胀细石混凝土进行浇筑。若结构无特殊防水要求,则一次性浇筑完成。若结构有特殊防水要求,浇筑混凝土时分为两次,第一次浇筑高度为板厚的1/2(覆盖住钢筋),待第一层混凝土表面有强度以后涂刷渗透结晶,再进行二次浇筑。Before pouring concrete, water the formwork and side walls of the opening to moisten, and use micro-expanded fine stone concrete that is one grade higher than the original floor slab for pouring. If the structure does not have special waterproofing requirements, the pouring will be completed in one go. If the structure has special waterproofing requirements, pour the concrete twice. The first pouring height is 1/2 of the plate thickness (to cover the steel bars). After the surface of the first layer of concrete has strength, apply penetrating crystals, and then pour it twice. pouring.
养护maintenance
浇筑完成后12小时开始进行养护,养护时间不小于7天,养护时即可做为盛水试验。若出现渗漏,则将已浇筑完成的混凝土凿掉重新浇筑,直至无渗漏。Curing begins 12 hours after the pouring is completed, and the curing time is no less than 7 days. During curing, it can be used as a water test. If leakage occurs, chisel out the poured concrete and pour it again until there is no leakage.
模板拆除Formwork removal
混凝土强度达到75%时即可拆除模板,拆模时要两个人互相配合,一人拆除立杆,另外一人取下模板,以防模板脱落伤人。要将拆下的构件轻拿轻放,堆放整齐,严禁乱扔乱放。拆除下的的模板要及时清理。The formwork can be removed when the concrete strength reaches 75%. Two people must cooperate with each other when removing the formwork. One person removes the vertical pole and the other person removes the formwork to prevent the formwork from falling off and injuring people. The dismantled components should be handled with care and stacked neatly. It is strictly forbidden to throw them around. The removed formwork must be cleaned in time.
板底打磨Polishing the bottom of the board
模板拆除后检查板底密实度、平整度,对于部分出现涨模和顶板不平现象,将超过原板底部分的砼进行剔凿、打磨处理,保证顶板接茬处成型质量。After the formwork is removed, check the density and flatness of the bottom of the board. For parts where the formwork is expanded and the roof is uneven, the concrete that exceeds the bottom of the original board will be chiseled and polished to ensure the molding quality of the joints of the roof.
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310904192.8A CN116905818A (en) | 2023-07-24 | 2023-07-24 | Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202310904192.8A CN116905818A (en) | 2023-07-24 | 2023-07-24 | Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN116905818A true CN116905818A (en) | 2023-10-20 |
Family
ID=88354606
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202310904192.8A Pending CN116905818A (en) | 2023-07-24 | 2023-07-24 | Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN116905818A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117605266A (en) * | 2024-01-09 | 2024-02-27 | 中建八局轨道交通建设有限公司 | Preserved opening structure and construction method of steel concrete return shear wall |
| CN119243991A (en) * | 2024-10-18 | 2025-01-03 | 中国一冶集团有限公司 | Pre-reserved hole combined mold with clamping and positioning function and construction method thereof |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101544482A (en) * | 2009-01-13 | 2009-09-30 | 鄢飞 | PTB inorganic environment-friendly inserted bar adhesive and method for using same |
| JP2011069151A (en) * | 2009-09-28 | 2011-04-07 | Masuo Okouchi | Concrete panel form |
| CN210032613U (en) * | 2019-05-14 | 2020-02-07 | 湖南鑫政铝业科技有限公司 | Pre-buried section structure in entrance to a cave, case and pre-buried structure, reservation entrance to a cave |
| CN110863598A (en) * | 2019-11-15 | 2020-03-06 | 中国十七冶集团有限公司 | Construction method for cast-in-situ floor slab construction hole |
| CN114718298A (en) * | 2022-03-16 | 2022-07-08 | 中国十七冶集团有限公司 | Installation structure and installation method of simple construction reserved hole plugging template |
-
2023
- 2023-07-24 CN CN202310904192.8A patent/CN116905818A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101544482A (en) * | 2009-01-13 | 2009-09-30 | 鄢飞 | PTB inorganic environment-friendly inserted bar adhesive and method for using same |
| JP2011069151A (en) * | 2009-09-28 | 2011-04-07 | Masuo Okouchi | Concrete panel form |
| CN210032613U (en) * | 2019-05-14 | 2020-02-07 | 湖南鑫政铝业科技有限公司 | Pre-buried section structure in entrance to a cave, case and pre-buried structure, reservation entrance to a cave |
| CN110863598A (en) * | 2019-11-15 | 2020-03-06 | 中国十七冶集团有限公司 | Construction method for cast-in-situ floor slab construction hole |
| CN114718298A (en) * | 2022-03-16 | 2022-07-08 | 中国十七冶集团有限公司 | Installation structure and installation method of simple construction reserved hole plugging template |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN117605266A (en) * | 2024-01-09 | 2024-02-27 | 中建八局轨道交通建设有限公司 | Preserved opening structure and construction method of steel concrete return shear wall |
| CN119243991A (en) * | 2024-10-18 | 2025-01-03 | 中国一冶集团有限公司 | Pre-reserved hole combined mold with clamping and positioning function and construction method thereof |
| CN119243991B (en) * | 2024-10-18 | 2025-10-24 | 中国一冶集团有限公司 | Pre-reserved hole combined mold with clamping and positioning function and construction method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN116905818A (en) | Cast-in-situ floor slab reserved hole tongue-and-groove type plugging construction method | |
| CN107268878B (en) | How to make and install prefabricated sandwich wall panels | |
| CN110258848A (en) | A kind of construction method of building energy conservation CL composite shear wall | |
| CN103615053B (en) | Monolithic reinforced concrete structure post empiricism engineering method | |
| CN104594387A (en) | Improved post-pouring strip advanced water-stopping construction method | |
| CN103590603B (en) | Large span multi-curvature shell structure of reinforced concrete method | |
| CN112412027A (en) | Method for manufacturing large-section special-shaped load-bearing concrete bare concrete member | |
| CN210117716U (en) | Trapezoidal foundation ditch lateral wall concrete typical forms of elevartor shaft | |
| CN113931384B (en) | Construction method for steel structure pressure relief roof | |
| CN112112360B (en) | Construction method for prefabricated and shaped building block masonry | |
| CN104481149B (en) | Using the super plane concrete structure seamless construction method of low temperature variation call method | |
| CN109797899A (en) | Blockwork and its construction with air-conditioning hole | |
| CN116856606A (en) | Waffle plate construction method for high-cleanliness requirements of factory building | |
| CN113914530B (en) | Inclined roof fish scale type concrete structure and construction method | |
| CN110965778B (en) | Cast-in-situ plate water stop type reserved hole telescopic shaping die | |
| CN113232152B (en) | Method for prefabricating concrete well chamber | |
| CN111516096A (en) | Precast column concrete pouring method in fabricated building | |
| CN114517593A (en) | Bottom-to-plate grouting reinforcement process for floor slab, matching device thereof and reinforced formed floor slab | |
| CN115717480A (en) | Concrete pouring method for narrow space of cavity wall | |
| CN113833033A (en) | Anti-seepage anti-floating dismantling-free construction process for building in area close to water area | |
| CN115822295A (en) | A kind of hole plugging process and its plugging structure | |
| CN111576681A (en) | FS composite heat-preservation construction integrated technology construction process | |
| CN120119801B (en) | A construction method for cast-in-situ counter-beating integrated molding of exterior wall stone | |
| CN111042047A (en) | Construction process for lower cross beam of platform | |
| CN112900515B (en) | Protection method and protection structure based on fan foundation ring rotten root treatment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination |