CN116128301A - Distribution network infrastructure project material management whole-flow risk early warning method and system - Google Patents

Distribution network infrastructure project material management whole-flow risk early warning method and system Download PDF

Info

Publication number
CN116128301A
CN116128301A CN202310081088.3A CN202310081088A CN116128301A CN 116128301 A CN116128301 A CN 116128301A CN 202310081088 A CN202310081088 A CN 202310081088A CN 116128301 A CN116128301 A CN 116128301A
Authority
CN
China
Prior art keywords
distribution network
network infrastructure
stage
management
early warning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202310081088.3A
Other languages
Chinese (zh)
Inventor
高斯琴
白杨
王鑫陶
付喆
逯春
白日升
冀雅静
胡凤英
孟兴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yuanguang Software Co Ltd
State Grid East Inner Mongolia Electric Power Co Ltd
Original Assignee
Yuanguang Software Co Ltd
State Grid East Inner Mongolia Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yuanguang Software Co Ltd, State Grid East Inner Mongolia Electric Power Co Ltd filed Critical Yuanguang Software Co Ltd
Priority to CN202310081088.3A priority Critical patent/CN116128301A/en
Publication of CN116128301A publication Critical patent/CN116128301A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/08Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
    • G06Q10/087Inventory or stock management, e.g. order filling, procurement or balancing against orders
    • GPHYSICS
    • G06COMPUTING OR CALCULATING; COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Development Economics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • Accounting & Taxation (AREA)
  • Finance (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a total-flow risk early warning method and a total-flow risk early warning system for material management of a power distribution network infrastructure project, which are characterized by comprising the following steps: taking the whole material management process of the distribution network infrastructure projects as a main line, and carrying out material management stage division on the distribution network infrastructure projects; acquiring required data of each stage of material management of a power distribution network infrastructure project; the method and the system can objectively reflect the abnormality in the whole flow of the power distribution network infrastructure item material management, and can be widely applied to the field of power distribution networks.

Description

一种配电网基建项目物资管理全流程风险预警方法及系统A risk early warning method and system for the whole process of distribution network infrastructure project material management

技术领域technical field

本发明涉及配电网领域,特别是关于一种配电网基建项目物资管理全流程风险预警方法及系统。The invention relates to the field of distribution networks, in particular to a method and system for early warning of risks in the whole process of material management for distribution network infrastructure projects.

背景技术Background technique

随着城乡用电需求的日趋扩大,配电网基建项目数量随之增多、规模不断加大,一直以来,对配电网基建项目投资过程监控不仅是重点,更是难点所在。由于配电网基建项目数量过多,单个项目投资规模小,当前统计监控手段相对滞后,使得配电网基建项目建设过程中存在的管控风险较高。With the increasing demand for electricity in urban and rural areas, the number and scale of distribution network infrastructure projects are increasing. For a long time, monitoring the investment process of distribution network infrastructure projects is not only the focus, but also the difficulty. Due to the large number of distribution network infrastructure projects, the small investment scale of individual projects, and the relatively lagging current statistical monitoring methods, the management and control risks in the construction of distribution network infrastructure projects are relatively high.

工程建设物资是组成工程建设实体的物质条件,确保物资按期供应是保证配电网基建项目建设顺利实施的基础条件,工程物资和设备的到货进度直接影响着配电网基建项目的建设质量、建设进度和建设项目总投资。配电网基建项目具有工程周期短、易集中和物资在工程投资中占比较大等特点,易造成配电网基建项目物资需求量大而集中,对投资管理与效率效益提升带来了潜在的影响与风险。Engineering construction materials are the material conditions for the composition of engineering construction entities. Ensuring the timely supply of materials is the basic condition for ensuring the smooth implementation of distribution network infrastructure projects. The arrival progress of engineering materials and equipment directly affects the construction quality of distribution network infrastructure projects. Construction progress and total investment of construction projects. Distribution network infrastructure projects have the characteristics of short project period, easy concentration, and large proportion of materials in project investment, which can easily lead to large and concentrated demand for materials in distribution network infrastructure projects, which has brought potential benefits to investment management and efficiency benefits. Impact and Risk.

然而,首先,现有技术中对配电网基建项目物资风险管理的研究主要集中在电网安全风险、工程项目风险以及财务风险方面。其次,在电力物资风险管理方面的研究一般侧重于整个电力物资管理流程中的某一个或几个环节的研究,目前没有对整个环节进行系统研究的成果。再次,目前对电力物资管理方面的研究,不管是从电力物资的管理流程上还是从电力物资的实物方面,都比较多而且系统,但是很少是从风险管理的角度来提除解决方案的。However, first of all, the research on material risk management of distribution network infrastructure projects in the prior art mainly focuses on power grid security risks, engineering project risks and financial risks. Secondly, the research on the risk management of power materials generally focuses on one or several links in the entire power material management process, and there is no systematic research on the whole link. Thirdly, the current research on power material management, whether it is from the management process of power materials or from the physical aspects of power materials, is more and more systematic, but few solutions are proposed from the perspective of risk management.

发明内容Contents of the invention

针对上述问题,本发明的目的是提供一种基于风险管理角度的配电网基建项目物资管理全流程风险预警方法及系统。In view of the above problems, the object of the present invention is to provide a risk early warning method and system for the whole process of material management of distribution network infrastructure projects based on the perspective of risk management.

为实现上述目的,本发明采取以下技术方案:第一方面,提供一种配电网基建项目物资管理全流程风险预警方法,包括:In order to achieve the above purpose, the present invention adopts the following technical solutions: In the first aspect, it provides a risk early warning method for the whole process of distribution network infrastructure project material management, including:

以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分;Taking the whole process of material management of distribution network infrastructure projects as the main line, divide the material management stages of distribution network infrastructure projects;

获取配电网基建项目物资管理各阶段的所需数据;Obtain the data required for each stage of material management of distribution network infrastructure projects;

将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警。Input the required data of each stage of distribution network infrastructure project material management into the pre-built early warning model of each stage of distribution network infrastructure project material management, and provide early warning for each stage of distribution network infrastructure project material management.

进一步地,所述配电网基建项目的物资管理阶段包括需求提报阶段、物资采购阶段、物资领料阶段和物资退库阶段。Further, the material management phase of the distribution network infrastructure project includes a demand report phase, a material procurement phase, a material requisition phase, and a material withdrawal phase.

进一步地,所述配电网基建项目物资管理各阶段的预警模型包括配电网基建项目物资管理各阶段的风险管控指标及其表达式和预警阈值。Further, the early warning model for each stage of distribution network infrastructure project material management includes risk control indicators and their expressions and early warning thresholds for each stage of distribution network infrastructure project material management.

进一步地,所述配电网基建项目物资管理各阶段的预警模型的构建过程为:Further, the construction process of the early warning model at each stage of the material management of the distribution network infrastructure project is as follows:

基于配电网基建项目的需求提报结果、需求提报金额和可研批复总金额,确定配电网基建项目物资管理需求提报阶段的预警模型;Based on the demand report results, demand report amount and feasibility study approval total amount of the distribution network infrastructure project, determine the early warning model for the material management demand report stage of the distribution network infrastructure project;

基于配电网基建项目的物资采购订单总金额,确定配电网基建项目物资管理物资采购阶段的预警模型;Based on the total amount of the material purchase order of the distribution network infrastructure project, determine the early warning model of the material management material procurement stage of the distribution network infrastructure project;

基于配电网基建项目的物资领料程序、物资领用时间与设备安装、组塔和架线的进度、累计物资领用金额、主要物资规模和可研批复建设规模,确定配电网基建项目物资管理物资领料阶段的预警模型;Determine the distribution network infrastructure project based on the material requisition procedure, material requisition time and equipment installation, tower and wiring progress, accumulated material requisition amount, main material scale and feasibility study approval construction scale of the distribution network infrastructure project The early warning model of material management material picking stage;

基于配电网基建项目的物资退库比例,确定配电网基建项目物资管理物资退库阶段的预警模型。Based on the proportion of materials withdrawn from the distribution network infrastructure project, the early warning model for the material management material withdrawal stage of the distribution network infrastructure project is determined.

进一步地,所述将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警,包括:Further, the data required for each stage of material management of the distribution network infrastructure project is input into the pre-built early warning model of each stage of material management of the distribution network infrastructure project, and early warning is carried out for each stage of material management of the distribution network infrastructure project ,include:

将配电网基建项目物资管理各阶段的所需数据输入至确定的预警模型的对应表达式中得到对应指标值;Input the required data at each stage of material management of the distribution network infrastructure project into the corresponding expression of the determined early warning model to obtain the corresponding index value;

根据确定的预警模型中的预警阈值和得到的对应指标值进行预警。Early warning is carried out according to the early warning threshold in the determined early warning model and the obtained corresponding index value.

进一步地,所述需求提报阶段的风险管控指标包括物资需求提报及时性指标和物资需求提报金额准确性指标,物资采购阶段的风险管控指标包括物资采购订单签订率过低指标,物资领料阶段的风险管控指标包括物资领料金额是否超需求提报指标、物资领用时间与建设进度是否匹配指标、物资领料金额占可研总投资比例是否过高指标、最后一笔物资领用时间合理性指标和投产项目主要物资领用规模异常指标,物资退库阶段的风险管控指标包括物资退库比例过高指标。Further, the risk management and control indicators in the demand report stage include the timeliness index of material demand report and the accuracy index of the material demand report amount, the risk management and control indicators in the material procurement stage include the low signing rate of material purchase orders, the material lead The risk management and control indicators in the material stage include whether the material requisition amount exceeds the demand report indicator, whether the material requisition time matches the construction progress, whether the material requisition amount accounts for an excessively high proportion of the total investment in the feasibility study, and the last material requisition Time rationality indicators and abnormal indicators of the scale of main materials used in production projects, and risk management and control indicators in the stage of material withdrawals include indicators of excessively high proportions of materials withdrawn from storage.

进一步地,所述需求提报阶段的风险管控指标中物资需求提报及时性指标的所需数据包括ERP系统的第一笔物资采购申请创建日期和规划计划系统的项目开工时间,物资需求提报金额准确性指标的所需数据包括ERP系统的物资类采购申请总金额和规划计划系统的可研批复总投资;Further, the data required for the timeliness index of material demand reporting in the risk management and control indicators of the demand reporting stage include the creation date of the first material purchase application in the ERP system and the project start time of the planning and planning system. Material demand reporting The required data for the amount accuracy index includes the total amount of material procurement application in the ERP system and the total investment in the feasibility study approval of the planning and planning system;

所述物资采购阶段的风险管控指标中物资采购订单签订率过低指标的所需数据包括ERP系统的物资类采购订单总金额以及规划计划系统的项目实际开工时间和可研批复总投资;The data required for the low signing rate of material purchase orders in the risk management and control indicators of the material procurement stage include the total amount of material purchase orders in the ERP system, the actual start time of the project in the planning and planning system, and the total investment in feasibility study approval;

所述物资领料阶段的风险管控指标中物资领料金额是否超需求提报指标的所需数据包括ERP系统的物资类采购申请总金额和领料总金额;物资领用时间与建设进度是否匹配指标的所需数据包括ERP系统的物资类本月入账成本和物资类自开始建设累计入账成本以及规划计划系统的项目实际开工时间;物资领料金额占可研总投资比例是否过高指标的所需数据包括ERP系统的领料总金额;最后一笔物资领用时间合理性指标的所需数据包括ERP系统的最后一笔领料日期和规划计划系统的项目实际开工时间;投产项目主要物资领用规模异常指标的所需数据包括规划计划系统的项目投产时间和建设规模以及PMS系统的设备规模。In the risk management and control indicators of the material requisition stage, whether the material requisition amount exceeds the required data for reporting indicators include the total amount of material procurement applications and the total amount of material requisition in the ERP system; whether the material requisition time matches the construction progress The data required for the indicators include the cost of materials recorded in the ERP system this month and the accumulated cost of materials recorded in the account since the beginning of construction, as well as the actual start time of the project in the planning and planning system; The required data includes the total amount of materials received by the ERP system; the required data for the rationality index of the last material received includes the date of the last material received by the ERP system and the actual start time of the project in the planning and planning system; The required data for scale anomaly indicators include the project commissioning time and construction scale of the planning planning system and the equipment scale of the PMS system.

所述物资退库阶段的风险管控指标中物资退库比例过高指标的所需数据包括ERP系统的领料总金额和退料总金额。The required data of the risk management and control indicators in the material withdrawal stage include the total amount of materials picked and the total amount of materials returned by the ERP system.

第二方面,提供一种配电网基建项目物资管理全流程风险预警系统,包括:In the second aspect, a risk warning system for the whole process of distribution network infrastructure project material management is provided, including:

物资管理阶段划分模块,用于以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分;The material management stage division module is used to divide the material management stage of the distribution network infrastructure project based on the whole process of material management of the distribution network infrastructure project;

数据获取模块,用于获取配电网基建项目物资管理各阶段的所需数据;The data acquisition module is used to acquire the required data at each stage of material management of distribution network infrastructure projects;

预警模块,用于将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警。The early warning module is used to input the required data of each stage of distribution network infrastructure project material management into the pre-built early warning model of each stage of distribution network infrastructure project material management, and provide early warning for each stage of distribution network infrastructure project material management .

第三方面,提供一种处理设备,包括计算机程序指令,其中,所述计算机程序指令被处理设备执行时用于实现上述配电网基建项目物资管理全流程风险预警方法对应的步骤。In a third aspect, a processing device is provided, including computer program instructions, wherein, when the computer program instructions are executed by the processing device, it is used to implement the steps corresponding to the above-mentioned risk warning method for the whole process of distribution network infrastructure project material management.

第四方面,提供一种计算机可读存储介质,所述计算机可读存储介质上存储有计算机程序指令,其中,所述计算机程序指令被处理器执行时用于实现上述配电网基建项目物资管理全流程风险预警方法对应的步骤。In a fourth aspect, a computer-readable storage medium is provided, where computer program instructions are stored on the computer-readable storage medium, wherein, when the computer program instructions are executed by a processor, they are used to implement the above-mentioned distribution network infrastructure project material management The steps corresponding to the whole process risk early warning method.

本发明由于采取以上技术方案,其具有以下优点:The present invention has the following advantages due to the adoption of the above technical scheme:

1、本发明预设设定配电网基建项目各阶段的物资管理风险指标表达式,能够量化风险,客观反应配电网基建项目物资管理全流程中的异常。1. The present invention presets the material management risk index expressions of each stage of the distribution network infrastructure project, which can quantify the risk and objectively reflect the abnormalities in the whole process of distribution network infrastructure project material management.

2、本发明规范统一了配电网基建项目各阶段物资管理风险预警阈值,避免主观因素造成的干扰,实现物资管理风险管理“有依据”,实现配网物资管理全过程风险的自动识别、预警与管控。2. The present invention standardizes and unifies the early warning thresholds of material management risks at each stage of distribution network infrastructure projects, avoids interference caused by subjective factors, realizes "based" material management risk management, and realizes automatic identification and early warning of risks in the whole process of distribution network material management and control.

附图说明Description of drawings

通过阅读下文优选实施方式的详细描述,各种其他的优点和益处对于本领域普通技术人员将变得清楚明了。附图仅用于示出优选实施方式的目的,而并不认为是对本发明的限制。在整个附图中,用相同的附图标记表示相同的部件。在附图中:Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiment. The drawings are only for the purpose of illustrating a preferred embodiment and are not to be considered as limiting the invention. Throughout the drawings, the same reference numerals are used to refer to the same parts. In the attached picture:

图1是本发明一实施例提供的方法流程示意图;Fig. 1 is a schematic flow chart of a method provided by an embodiment of the present invention;

图2是本发明一实施例提供的蒙东某10kV线路改造工程物资管理各阶段的风险预警示意图。Fig. 2 is a schematic diagram of risk early warning at various stages of material management for a 10kV line renovation project in eastern Mongolia provided by an embodiment of the present invention.

具体实施方式Detailed ways

下面将参照附图更详细地描述本发明的示例性实施方式。虽然附图中显示了本发明的示例性实施方式,然而应当理解,可以以各种形式实现本发明而不应被这里阐述的实施方式所限制。相反,提供这些实施方式是为了能够更透彻地理解本发明,并且能够将本发明的范围完整地传达给本领域的技术人员。Exemplary embodiments of the present invention will be described in more detail below with reference to the accompanying drawings. Although exemplary embodiments of the present invention are shown in the drawings, it should be understood that the invention may be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided for more thorough understanding of the present invention, and to fully convey the scope of the present invention to those skilled in the art.

应理解的是,文中使用的术语仅出于描述特定示例实施方式的目的,而无意于进行限制。除非上下文另外明确地指出,否则如文中使用的单数形式“一”、“一个”以及“所述”也可以表示包括复数形式。术语“包括”、“包含”、“含有”以及“具有”是包含性的,并且因此指明所陈述的特征、步骤、操作、元件和/或部件的存在,但并不排除存在或者添加一个或多个其它特征、步骤、操作、元件、部件、和/或它们的组合。文中描述的方法步骤、过程、以及操作不解释为必须要求它们以所描述或说明的特定顺序执行,除非明确指出执行顺序。还应当理解,可以使用另外或者替代的步骤。It should be understood that the terminology used herein is for the purpose of describing particular example embodiments only and is not intended to be limiting. As used herein, the singular forms "a", "an" and "the" may also be meant to include the plural forms unless the context clearly dictates otherwise. The terms "comprising", "comprising", "containing" and "having" are inclusive and thus indicate the presence of stated features, steps, operations, elements and/or parts but do not exclude the presence or addition of one or Various other features, steps, operations, elements, components, and/or combinations thereof. The method steps, processes, and operations described herein are not to be construed as necessarily requiring their performance in the particular order described or illustrated, unless an order of performance is specifically indicated. It should also be understood that additional or alternative steps may be used.

尽管可以在文中使用术语第一、第二、第三等来描述多个元件、部件、区域、层和/或部段,但是,这些元件、部件、区域、层和/或部段不应被这些术语所限制。这些术语可以仅用来将一个元件、部件、区域、层或部段与另一区域、层或部段区分开。除非上下文明确地指出,否则诸如“第一”、“第二”之类的术语以及其它数字术语在文中使用时并不暗示顺序或者次序。因此,以下讨论的第一元件、部件、区域、层或部段在不脱离示例实施方式的教导的情况下可以被称作第二元件、部件、区域、层或部段。Although the terms first, second, third, etc. may be used herein to describe various elements, components, regions, layers and/or sections, these elements, components, regions, layers and/or sections should not be referred to as These terms are limited. These terms may be only used to distinguish one element, component, region, layer or section from another region, layer or section. Terms such as "first," "second," and other numerical terms when used herein do not imply a sequence or order unless clearly indicated by the context. Thus, a first element, component, region, layer or section discussed below could be termed a second element, component, region, layer or section without departing from the teachings of the example embodiments.

本发明实施例提供的配电网基建项目物资管理全流程风险预警方法及系统,能够规范统一配电网基建项目各阶段物资管理的风险预警,避免主观因素造成的干扰,实现物资管理风险管理“有依据”。The risk early warning method and system for the whole process of material management of distribution network infrastructure projects provided by the embodiments of the present invention can standardize and unify the risk early warning of material management at each stage of distribution network infrastructure projects, avoid interference caused by subjective factors, and realize material management risk management " There is a basis."

实施例1Example 1

本实施例提供一种配电网基建项目物资管理全流程风险预警方法,包括以下步骤:This embodiment provides a risk early warning method for the whole process of distribution network infrastructure project material management, including the following steps:

1)以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分。1) Taking the whole process of material management of distribution network infrastructure projects as the main line, the material management stages of distribution network infrastructure projects are divided.

具体地,配电网基建项目的物资管理阶段包括需求提报阶段、物资采购阶段、物资领料阶段和物资退库阶段。Specifically, the material management phase of the distribution network infrastructure project includes the demand reporting phase, the material procurement phase, the material requisition phase, and the material withdrawal phase.

2)预先构建配电网基建项目物资管理各阶段的预警模型,其中,配电网基建项目物资管理各阶段的预警模型包括配电网基建项目物资管理各阶段的风险管控指标及其表达式和预警阈值,具体为:2) Pre-construct the early warning model of each stage of distribution network infrastructure project material management, in which the early warning model of each stage of distribution network infrastructure project material management includes the risk control indicators and their expressions and Early warning thresholds, specifically:

2.1)基于配电网基建项目的需求提报结果、需求提报金额和可研批复总金额,确定配电网基建项目物资管理需求提报阶段的预警模型,即配电网基建项目物资管理需求提报阶段的风险管控指标及其表达式和预警阈值。2.1) Based on the demand reporting results of distribution network infrastructure projects, the amount of demand reporting and the total amount of feasibility study approval, determine the early warning model for the material management demand reporting stage of distribution network infrastructure projects, that is, the material management requirements of distribution network infrastructure projects Risk control indicators and their expressions and early warning thresholds in the reporting stage.

具体地,需求提报阶段的风险管控指标包括物资需求提报及时性指标和物资需求提报金额准确性指标,其中:Specifically, the risk management and control indicators in the demand report stage include the timeliness index of material demand report and the accuracy index of the amount of material demand report, among which:

物资需求提报及时性指标的分析内容为:检查配电网基建项目的需求提报是否及时、合规。物资需求提报及时性指标的表达式为:物资需求提报及时性=实际开工时间-实际物资需求提报时间。物资需求提报及时性指标的数据来源为:ER(Enterprise ResourcePlanning,企业资源计划)系统的“第一笔物资采购申请创建日期”;规划计划系统的“项目开工时间”。物资需求提报及时性指标的适用范围为:不适用“利库”、“寄售”等方式领用物资而无需提报物资需求的配电网基建项目。The analysis content of the timeliness index of material demand report is as follows: check whether the demand report of the distribution network infrastructure project is timely and compliant. The expression of the timeliness index of material demand report is: timeliness of material demand report = actual start time - actual material demand report time. The data source of the timeliness indicator of material demand report is: the "creation date of the first material procurement application" in the ER (Enterprise Resource Planning) system; the "project start time" in the planning and planning system. The scope of application of the timeliness index of material demand reporting is: distribution network infrastructure projects that do not apply to "library", "consignment" and other methods of receiving materials and do not need to report material demand.

物资需求提报金额准确性指标的分析内容为:通过ERP系统获取配电网基建项目的需求提报金额,与可研批复总金额对比,监测物资需求提报金额的准确性。物资需求提报金额准确性指标的表达式为:物资需求提报金额占比=物资需求提报金额/可研批复总投资。物资需求提报金额准确性指标的数据来源为:ERP系统的“物资类采购申请总金额”;规划计划系统的“可研批复总投资”。物资需求提报金额准确性指标的适用范围为:适用于全部配电网基建项目。The analysis content of the accuracy index of material demand report amount is as follows: obtain the demand report amount of distribution network infrastructure projects through the ERP system, compare with the total amount of feasibility study approval, and monitor the accuracy of material demand report amount. The expression of the accuracy indicator of the reported amount of material demand is: the proportion of the reported amount of material demand = the amount of material demand reported / the total investment of the feasibility study approval. The data sources for the accuracy index of the reported amount of material demand are: the "total amount of material procurement application" in the ERP system; the "total investment in feasibility study approval" in the planning and planning system. The scope of application of the accuracy index for the reported amount of material demand is: applicable to all distribution network infrastructure projects.

2.2)基于配电网基建项目的物资采购订单总金额,确定配电网基建项目物资管理物资采购阶段的预警模型,即配电网基建项目物资管理物资采购阶段的风险管控指标及其表达式和预警阈值。2.2) Based on the total amount of the material purchase order of the distribution network infrastructure project, determine the early warning model of the material management material procurement stage of the distribution network infrastructure project, that is, the risk control index and its expression and Early warning threshold.

具体地,物资采购阶段的风险管控指标包括物资采购订单签订率过低指标,其中,物资采购订单签订率过低指标的分析内容为:通过ERP系统获取物资采购订单总金额,监测物资采购订单是否比例过低,影响工程进度。物资采购订单签订率过低指标的表达式为:物资采购订单比例=累计物资类采购订单含税总金额/可研批复总投资。物资采购订单签订率过低指标的数据来源为:ERP系统的“物资类采购订单总金额”;规划计划系统的“项目实际开工时间”、“可研批复总投资”。物资采购订单签订率过低指标的适用范围为:“利库”、“寄售”等方式领用物资无需签订采购订单的配电网基建项目,指标不适用。Specifically, the risk management and control indicators in the material procurement stage include the indicator of low signing rate of material purchase orders. If the ratio is too low, it will affect the progress of the project. The expression of the indicator for the low signing rate of material purchase orders is: the proportion of material purchase orders = the total tax-included amount of accumulated material purchase orders / the total investment approved by the feasibility study. The data sources for the low signing rate of material purchase orders are: the "total amount of material purchase orders" in the ERP system; the "actual start time of the project" and "total investment approved by feasibility study" in the planning and planning system. The scope of application of the indicator for the low signing rate of material purchase orders is: distribution network infrastructure projects that do not need to sign a purchase order for receiving materials through "library", "consignment" and other methods, the indicator is not applicable.

2.3)基于配电网基建项目的物资领料程序、物资领用时间与设备安装、组塔和架线的进度、累计物资领用金额、主要物资规模和可研批复建设规模,确定配电网基建项目物资管理物资领料阶段的预警模型,即配电网基建项目物资管理物资领料阶段的风险管控指标及其表达式和预警阈值。2.3) Determine the distribution network based on the material requisition procedure, material requisition time and equipment installation, tower and wiring progress, accumulative material requisition amount, main material scale and feasibility study approval construction scale of the distribution network infrastructure project The early warning model of the material management material picking stage of infrastructure projects, that is, the risk control indicators and their expressions and early warning thresholds of the distribution network infrastructure project material management material picking stage.

具体地,物资领料阶段的风险管控指标包括物资领料金额是否超需求提报指标、物资领用时间与建设进度是否匹配指标、物资领料金额占可研总投资比例是否过高指标、最后一笔物资领用时间合理性指标和投产项目主要物资领用规模异常指标,其中:Specifically, the risk management and control indicators in the material requisition stage include whether the material requisition amount exceeds the demand report indicator, whether the material requisition time matches the construction progress, whether the material requisition amount accounts for an excessively high proportion of the total investment in the feasibility study, and finally An indicator of the rationality of the time for material requisition and an abnormal indicator of the scale of main material requisition for the project put into operation, of which:

物资领料金额是否超需求提报指标的分析内容为:检查物资领料程序的合理性,物资领料的前序环节是否完成。物资领料金额是否超需求提报指标的表达式为:需求未提报,判断物资领料金额=0;需求已提报,判断物资领用金额<需求提报金额。物资领料金额是否超需求提报指标的数据来源为:ERP系统的“物资类采购申请总金额“、“领料总金额”。物资领料金额是否超需求提报指标的适用范围为:“利库”、“寄售”等方式领取的物资的配网基建项目,指标不适用。The analysis content of whether the material requisition amount exceeds the demand report indicator is: check the rationality of the material requisition procedure, and whether the pre-order link of the material requisition is completed. The expression of whether the material requisition amount exceeds the demand report indicator is: if the demand is not reported, it is judged that the material requisition amount = 0; if the demand has been reported, it is judged that the material requisition amount < the demand report amount. The data sources for reporting whether the amount of material requisition exceeds demand are: "Total Amount of Material Purchase Application" and "Total Requisition Amount" of the ERP system. The scope of application of the reporting indicators for whether the amount of materials received exceeds the demand is: the distribution network infrastructure projects of materials received through "library", "consignment" and other methods, and the indicators are not applicable.

物资领用时间与建设进度是否匹配指标的分析内容为:检查物资领用时间与设备安装、组塔和架线的进度是否匹配。物资领用时间与建设进度是否匹配指标的表达式为:第一笔物资领用时间-项目实际开工日期。物资领用时间与建设进度是否匹配指标的数据来源为:ERP系统的“物资类本月入账成本”、物资类自开始建设累计入账成本;规划计划系统的“项目实际开工时间”。物资领用时间与建设进度是否匹配指标的适用范围为:适用于全部配电网基建项目。The analysis content of whether the material requisition time matches the construction progress is as follows: check whether the material requisition time matches the progress of equipment installation, tower assembly and wiring. The expression of the matching index between the material receiving time and the construction progress is: the first material receiving time - the actual start date of the project. The data sources for the matching indicators between the time of material requisition and the construction progress are: the "cost of materials recorded in this month" of the ERP system, the accumulated cost of materials recorded since the beginning of construction; the "actual start time of the project" of the planning and planning system. The scope of application of the matching index between the time of material requisition and the construction progress is: applicable to all distribution network infrastructure projects.

物资领料金额占可研总投资比例是否过高指标的分析内容为:通过统计分析项目累计物资领用金额是否超过对应的项目物资概算。物资领料金额占可研总投资比例是否过高指标的表达式为:物资领料占比=累计物资领用总金额/可研总投资(概算)。物资领料金额占可研总投资比例是否过高指标的数据来源为:ERP系统的“领料总金额”;规划计划系统的“可研批复总投资”。物资领料金额占可研总投资比例是否过高指标的适用范围为:适用于全部配电网基建项目。The content of the analysis of the indicator of whether the proportion of material requisition to the total investment in the feasibility study is too high is: through statistical analysis, whether the accumulated material requisition amount of the project exceeds the corresponding project material estimate. The expression of whether the ratio of material requisition amount to the total investment in feasibility study is too high is as follows: ratio of material requisition=accumulated total amount of material requisition/total investment in feasibility study (estimate). The data source of the indicator of whether the proportion of material picking amount to the total investment in the feasibility study is too high is: the "total amount of material picking" in the ERP system; the "total investment in feasibility study approval" in the planning and planning system. The scope of application of the indicator of whether the proportion of material requisition to the total investment in the feasibility study is too high is: applicable to all distribution network infrastructure projects.

最后一笔物资领用时间合理性指标的分析内容为:检查物资领用时间的合理性;检查项目投产后是否仍有大额物资领用发生。最后一笔物资领用时间合理性指标的表达式为:最后一笔物资领用时间的合理性=投产日期-最后一笔领料日期。最后一笔物资领用时间合理性指标的数据来源为:ERP系统的“最后一笔领料日期”;规划计划系统的“项目实际开工时间”。最后一笔物资领用时间合理性指标的适用范围为:适用于全部配电网基建项目。The analysis content of the rationality index of the last material requisition time is: check the rationality of the material requisition time; check whether there is still a large amount of material requisition after the project is put into production. The expression of the rationality index of the last material requisition time is: the rationality of the last material requisition time = production date - the last material requisition date. The data sources for the rationality index of the last material requisition time are: the "last material requisition date" of the ERP system; the "actual project start time" of the planning and planning system. The scope of application of the last material receiving time rationality index is: applicable to all distribution network infrastructure projects.

投产项目主要物资领用规模异常指标的分析内容为:检查投产项目变压器、电缆等主要物资规模是否超过可研批复建设规模;检查是否存在领用与该工程无关的物资类型。投产项目主要物资领用规模异常指标的表达式为:可研批复的变电容量-领用变压器容量;可研批复的电缆线路长度-领用电缆线路长度。投产项目主要物资领用规模异常指标的数据来源为:规划计划系统的“项目投产时间”、“建设规模”;PMS(power productionmanagement system,设备管理系统)系统的设备“规模”。投产项目主要物资领用规模异常指标的适用范围为:适用于全部配电网基建项目。The analysis content of the abnormal index of the main materials used in the project is: check whether the scale of main materials such as transformers and cables of the project in the project exceeds the construction scale approved by the feasibility study; check whether there are types of materials that are not related to the project. The expression of the abnormal index of the scale of main materials used in the production project is: transformer capacity approved by feasibility study - capacity of transformer used; length of cable line approved by feasibility study - length of cable line used. The data sources for the abnormal indicators of the scale of main materials used in the production project are: the "project commissioning time" and "construction scale" of the planning and planning system; the equipment "scale" of the PMS (power production management system, equipment management system) system. The scope of application of the abnormal index of the main material consumption scale of the project put into operation is: applicable to all distribution network infrastructure projects.

2.4)基于配电网基建项目的物资退库比例,确定配电网基建项目物资管理物资退库阶段的预警模型,即配电网基建项目物资管理物资退库阶段的风险管控指标及其表达式和预警阈值。2.4) Based on the proportion of materials withdrawn from the distribution network infrastructure project, determine the early warning model for the material management material withdrawal stage of the distribution network infrastructure project, that is, the risk control index and its expression in the material management material withdrawal stage of the distribution network infrastructure project and warning thresholds.

具体地,物资退库阶段的风险管控指标包括物资退库比例过高指标,其中,物资退库比例过高指标的分析内容为:统计项目层面物资退库比例,监测退库比例过高的项目。物资退库比例过高指标的表达式为:物资退库率=退料总金额/领料总金额。物资退库比例过高指标的数据来源为:ERP系统的“领料总金额”、“退料总金额”。物资退库比例过高指标的适用范围为:适用于全部配电网基建项目。Specifically, the risk management and control indicators in the stage of material withdrawal include the indicator of excessive material withdrawal ratio. Among them, the analysis content of the excessive material withdrawal ratio indicator is: statistics of the material withdrawal ratio at the project level, and monitoring of projects with an excessively high withdrawal ratio . The expression of the indicator of excessive material return ratio is: material return rate = total amount of returned materials/total amount of received materials. The data source for the indicator of excessive material return ratio is: "total amount of material picked" and "total amount of material returned" in the ERP system. The scope of application of the excessively high ratio of material withdrawals is: applicable to all distribution network infrastructure projects.

具体地,配电网基建项目物资管理各阶段的风险管控指标的预警阈值均可以基于若干样本数据的统计分析,结合项目物资管理规定,通过分析预警项目验证指标制定的合理性和可用性,确定配电网基建项目物资管理各阶段的风险管控指标的预警阈值。Specifically, the early warning thresholds of risk management and control indicators at each stage of distribution network infrastructure project material management can be based on the statistical analysis of several sample data, combined with project material management regulations, by analyzing the rationality and usability of early warning project verification indicators to determine the distribution network. Early warning thresholds for risk control indicators at each stage of material management for power grid infrastructure projects.

3)从ERP系统中获取配电网基建项目物资管理各阶段的所需数据。3) Obtain the required data at each stage of material management for distribution network infrastructure projects from the ERP system.

具体地,需求提报阶段的风险管控指标中物资需求提报及时性指标的所需数据包括ERP系统的“第一笔物资采购申请创建日期”;规划计划系统的“项目开工时间”,物资需求提报金额准确性指标的所需数据包括ERP系统的“物资类采购申请总金额”;规划计划系统的“可研批复总投资”。Specifically, the data required for the timeliness of material demand reporting in the risk control indicators of the demand reporting stage include the "creation date of the first material purchase application" in the ERP system; the "project start time" in the planning and planning system, and the material demand The required data for reporting the accuracy indicators of the amount includes the "total amount of material procurement application" in the ERP system; the "total investment in feasibility study approval" in the planning and planning system.

具体地,物资采购阶段的风险管控指标中物资采购订单签订率过低指标的所需数据包括ERP系统的“物资类采购订单总金额”;规划计划系统的“项目实际开工时间”、“可研批复总投资”。Specifically, in the risk management and control indicators of the material procurement stage, the data required for the low rate of signing of material purchase orders include the "total amount of material purchase orders" in the ERP system; the "actual project start time" and "feasibility study Approval of the total investment".

具体地,物资领料阶段的风险管控指标中物资领料金额是否超需求提报指标的所需数据包括ERP系统的“物资类采购申请总金额“、“领料总金额”;物资领用时间与建设进度是否匹配指标的所需数据包括ERP系统的“物资类本月入账成本”和物资类自开始建设累计入账成本、规划计划系统的“项目实际开工时间”;物资领料金额占可研总投资比例是否过高指标的所需数据包括ERP系统的“领料总金额”;最后一笔物资领用时间合理性指标的所需数据包括ERP系统的“最后一笔领料日期”,规划计划系统的“项目实际开工时间”;投产项目主要物资领用规模异常指标的所需数据包括规划计划系统的“项目投产时间”、“建设规模”;PMS系统的设备“规模”。Specifically, in the risk management and control indicators of the material requisition stage, the data required for whether the material requisition amount exceeds the demand reporting index includes the "total amount of material procurement applications" and "total requisition amount" of the ERP system; the time of material requisition The required data for indicators matching with the construction progress include the "cost of materials recorded this month" in the ERP system, the accumulated cost of materials recorded in the account since the beginning of construction, and the "actual start time of the project" in the planning and planning system; The required data for the indicator of whether the total investment ratio is too high includes the "total amount of material picking" of the ERP system; the required data for the indicator of the rationality of the last material receiving time include the "last material picking date" of the ERP system, planning The "actual start time of the project" of the planning system; the data required for the abnormal indicators of the scale of main materials used in the production project include the "project production time" and "construction scale" of the planning and planning system; the equipment "scale" of the PMS system.

具体地,物资退库阶段的风险管控指标中物资退库比例过高指标所需数据包括ERP系统的“领料总金额”、“退料总金额”。Specifically, the data required for the risk management and control indicators in the material withdrawal stage include the "total amount of materials received" and "total amount of materials returned" in the ERP system.

4)将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警,具体为:4) Input the required data at each stage of material management of distribution network infrastructure project into the pre-built early warning model of each stage of material management of distribution network infrastructure project, and carry out early warning for each stage of material management of distribution network infrastructure project, specifically: :

4.1)将配电网基建项目物资管理各阶段的所需数据输入至确定的预警模型的对应表达式中得到对应指标值。4.1) Input the required data of each stage of distribution network infrastructure project material management into the corresponding expression of the determined early warning model to obtain the corresponding index value.

4.2)根据确定的预警模型中的预警阈值和得到的对应指标值进行预警。4.2) Carry out early warning according to the early warning threshold in the determined early warning model and the obtained corresponding index value.

具体地,需求提报阶段的风险管控指标中物资需求提报及时性指标的预警规则为:若物资需求提报及时性指标晚于配电网基建项目开工后一个月,则物资需求提报不及时,进行预警。物资需求提报金额准确性指标的预警规则为:若物资需求提报金额占比>70%,则物资需求提报金额不准确,进行预警。Specifically, the early warning rules for the timeliness of material demand reporting in the risk management and control indicators of the demand reporting stage are as follows: if the material demand reporting timeliness indicator is later than one month after the start of the distribution network infrastructure project, the material demand reporting is not valid. In time, give an early warning. The early warning rule for the accuracy indicator of the material demand report amount is as follows: if the material demand report amount accounts for more than 70%, the material demand report amount is inaccurate and an early warning is issued.

具体地,物资采购阶段的风险管控指标中物资采购订单签订率过低指标的预警规则为:当配电网基建项目实际开工时间超过3个月,物资采购订单比例<10%,则视为物资采购订单签订率过低,进行预警。Specifically, the early warning rules for the low signing rate of material purchase orders in the risk management and control indicators of the material procurement stage are as follows: when the actual start time of the distribution network infrastructure project exceeds 3 months, and the proportion of material purchase orders is less than 10%, it will be regarded as a material purchase order. The purchase order signing rate is too low, and an early warning is issued.

具体地,物资领料阶段的风险管控指标中物资领料金额是否超需求提报指标的预警规则为:若需求未提报,已发生物资领用,则领用程序不合规,进行预警;若需求已提报,物资领用金额大于需求提报金额,则不合规,进行预警。物资领用时间与建设进度是否匹配指标的预警规则为:第一笔物资领用时间在项目开工3个月后,则物资领用时间与建设进度不匹配,进行预警。物资领料金额占可研总投资比例是否过高指标的预警规则为:物资领料占比>70%,则物资领用比例过高,进行预警。最后一笔物资领用时间合理性指标的预警规则为:若最后一笔物资领料日期在配电网基建项目投产日期之前为正常,否则为物资领用异常,进行预警。投产项目主要物资领用规模异常指标的预警规则为:项目投产后,建设规模在可研批复规模范围内,则为正常;否则为异常,进行预警。Specifically, the early warning rules for whether the material requisition amount in the risk management and control indicators of the material requisition stage exceeds the demand reporting indicator are: if the demand has not been reported and the material requisition has occurred, the requisition procedure is not in compliance and an early warning will be issued; If the demand has been reported and the amount of materials received is greater than the amount reported for the demand, it is not in compliance and an early warning will be issued. The early warning rules for whether the material requisition time matches the construction progress are as follows: the first material requisition time is 3 months after the start of the project, and if the material requisition time does not match the construction progress, an early warning will be issued. The early warning rules for whether the proportion of material requisition to the total investment in the feasibility study is too high are: if the proportion of material requisition is >70%, the proportion of material requisition is too high, and an early warning will be issued. The early warning rule for the rationality index of the last material requisition time is as follows: if the last material requisition date is before the distribution network infrastructure project commissioning date, it is normal; otherwise, the material requisition is abnormal, and an early warning is given. The early warning rules for the abnormal indicators of the main material consumption scale of the project put into operation are as follows: after the project is put into production, if the construction scale is within the scale approved by the feasibility study, it is considered normal; otherwise, it is abnormal and an early warning is issued.

具体地,物资退库阶段的风险管控指标中物资退库比例过高指标的预警规则为:物资退库率≤5%时,则退库正常,否则异常,进行预警。Specifically, the early warning rules for the high ratio of material withdrawals in the risk management and control indicators of the material withdrawal stage are as follows: when the rate of material withdrawals is ≤ 5%, the withdrawals are normal; otherwise, an early warning is issued.

下面以中国蒙东某10kV线路改造工程具体实施例详细说明本发明的配电网基建项目物资管理全流程风险预警方法:The following is a specific example of a 10kV line renovation project in eastern Mongolia, China, in detail for the risk warning method for the entire process of material management of distribution network infrastructure projects according to the present invention:

配电网基建项目基本情况为:配电网基建项目的开工日期为2020年3月30日,可研总投资132.14万元,可研批复线路长度7.31千米,需求提报金额22.26万元,物资领料总金额183.68万元,退料总金额80.92万元,领料净额102.76万元。The basic situation of the distribution network infrastructure project is as follows: the start date of the distribution network infrastructure project is March 30, 2020, the total investment in the feasibility study is 1.3214 million yuan, the length of the feasibility study approved line is 7.31 kilometers, and the amount of demand submitted is 222,600 yuan. The total amount of materials received was 1.8368 million yuan, the total amount of materials returned was 809,200 yuan, and the net amount of materials received was 1.0276 million yuan.

按照本发明的方法对该配电网基建项目物资管理各阶段进行处理,该配电网基建项目的物资管理各阶段预警情况如图1所示。According to the method of the present invention, each stage of material management of the distribution network infrastructure project is processed, and the early warning situation of each stage of material management of the distribution network infrastructure project is shown in FIG. 1 .

物资领料金额是否超需求提报指标预警:Whether the amount of material picking exceeds the demand report indicator warning:

截止6月底,物资领料净额超需求提报金额80.50万元,因此物资领料金额是否超需求指标预警。原因分析:按照“先利库、后采购”原则,结合库存物资利库工作,在该工程刚开工阶段,将现有个别库存物资进行出库,导致物料领用金额超需求提报。As of the end of June, the net amount of material requisition exceeded the demand and reported an amount of 805,000 yuan, so whether the material requisition amount exceeds the demand indicator is an early warning. Reason analysis: In accordance with the principle of "beneficiary first, then purchase", combined with the work of inventory materials, when the project was just started, some existing inventory materials were out of the warehouse, resulting in the amount of materials used exceeding the demand and reported.

物资领料金额占可研总投资比例是否过高指标预警:Whether the proportion of material picking amount to the total investment in the feasibility study is too high indicator warning:

物资领料净额占可研总投资78%,超过70%的预警标准,因此物资领用时间与建设进度匹配情况指标预警。原因分析:该配电网基建项目物资提取时未能充分考虑配电网基建项目实际,匹配操作失误,将其它工程利库物资匹配到该配电网基建项目。截止6月底,物资退库80.92万元,在7月份再次退库68.84万元,最终剩余用在该项目的物资33.92万元。The net amount of material requisition accounts for 78% of the total investment in the feasibility study, which exceeds the early warning standard of 70%. Therefore, the matching indicator between the material requisition time and the construction progress is an early warning. Reason analysis: The distribution network infrastructure project failed to fully consider the actual situation of the distribution network infrastructure project when the materials were extracted, and the matching operation was wrong, and the materials from other projects were matched to the distribution network infrastructure project. As of the end of June, 809,200 yuan of materials had been withdrawn from the warehouse, and another 688,400 yuan had been withdrawn from the warehouse in July, leaving 339,200 yuan of materials used in the project.

物资退库比例过高指标预警:Early warning of high ratio of materials returned from storage:

项目物资退料比例为44%,退库比例过高,因此物资退库比例过高指标预警。原因分析:该配电网基建项目物资提取时未能充分考虑配电网基建项目实际,匹配操作失误,将其它工程利库物资匹配到该配电网基建项目,因此退库比例过高。The proportion of project materials returned is 44%, and the proportion of returned materials is too high, so the indicator for the high proportion of materials returned to warehouse is an early warning. Reason analysis: The distribution network infrastructure project failed to fully consider the actual situation of the distribution network infrastructure project when the materials were extracted, and the matching operation was wrong, and the materials from other projects were matched to the distribution network infrastructure project, so the proportion of withdrawals was too high.

实施例2Example 2

本实施例提供一种配电网基建项目物资管理全流程风险预警系统,包括物资管理阶段划分模块、数据获取模块和预警模块。This embodiment provides a risk early warning system for the whole process of material management of distribution network infrastructure projects, including a material management stage division module, a data acquisition module and an early warning module.

物资管理阶段划分模块用于以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分。The material management stage division module is used to divide the material management stage of the distribution network infrastructure project based on the whole process of material management of the distribution network infrastructure project.

数据获取模块用于从ERP系统中获取配电网基建项目物资管理各阶段的所需数据。The data acquisition module is used to acquire the required data at each stage of material management of the distribution network infrastructure project from the ERP system.

预警模块用于将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警。The early warning module is used to input the required data of each stage of distribution network infrastructure project material management into the pre-built early warning model of each stage of distribution network infrastructure project material management, and provide early warning for each stage of distribution network infrastructure project material management.

在一个优选的实施例中,配电网基建项目的物资管理阶段包括需求提报阶段、物资采购阶段、物资领料阶段和物资退库阶段。In a preferred embodiment, the material management phase of the distribution network infrastructure project includes a demand report phase, a material procurement phase, a material requisition phase, and a material withdrawal phase.

在一个优选的实施例中,该系统还包括模型构建模块,用于预先构建配电网基建项目物资管理各阶段的预警模型,包括配电网基建项目物资管理各阶段的风险管控指标及其表达式和预警阈值。In a preferred embodiment, the system also includes a model building module, which is used to pre-build early warning models for each stage of distribution network infrastructure project material management, including risk control indicators and their expressions for each stage of distribution network infrastructure project material management formula and warning threshold.

在一个优选的实施例中,需求提报阶段的风险管控指标包括物资需求提报及时性指标和物资需求提报金额准确性指标,物资采购阶段的风险管控指标包括物资采购订单签订率过低指标,物资领料阶段的风险管控指标包括物资领料金额是否超需求提报指标、物资领用时间与建设进度是否匹配指标、物资领料金额占可研总投资比例是否过高指标、最后一笔物资领用时间合理性指标和投产项目主要物资领用规模异常指标,物资退库阶段的风险管控指标包括物资退库比例过高指标。In a preferred embodiment, the risk management and control indicators in the demand report stage include the timeliness index of material demand report and the accuracy index of the material demand report amount, and the risk management and control indicators in the material procurement stage include the low signing rate of material purchase orders. , the risk management and control indicators in the material requisition stage include whether the material requisition amount exceeds the demand reporting index, whether the material requisition time matches the construction progress, whether the material requisition amount accounts for an excessively high proportion of the total investment in the feasibility study, and the last payment The indicators of the rationality of material requisition time and the abnormal scale of the main material requisition of the project put into production, and the risk control indicators of the material withdrawal stage include the indicator of the high proportion of material withdrawal from the warehouse.

本实施例提供的系统是用于执行上述各方法实施例,具体流程和详细内容请参照上述实施例,此处不再赘述。The system provided in this embodiment is used to execute the above-mentioned method embodiments. Please refer to the above-mentioned embodiments for specific procedures and details, and details will not be repeated here.

实施例3Example 3

本实施例提供一种与本实施例1所提供的配电网基建项目物资管理全流程风险预警方法对应的处理设备,处理设备可以适用于客户端的处理设备,例如手机、笔记本电脑、平板电脑、台式机电脑等,以执行实施例1的方法。This embodiment provides a processing device corresponding to the risk warning method for the whole process of distribution network infrastructure project material management provided in Embodiment 1. The processing device can be applied to the processing device of the client, such as a mobile phone, a notebook computer, a tablet computer, Desktop computer etc., to carry out the method of embodiment 1.

所述处理设备包括处理器、存储器、通信接口和总线,处理器、存储器和通信接口通过总线连接,以完成相互间的通信。存储器中存储有可在处理设备上运行的计算机程序,处理设备运行计算机程序时执行本实施例1所提供的配电网基建项目物资管理全流程风险预警方法。The processing device includes a processor, a memory, a communication interface and a bus, and the processor, the memory and the communication interface are connected through the bus to complete mutual communication. A computer program that can run on the processing device is stored in the memory, and when the processing device runs the computer program, it executes the risk warning method for the whole process of distribution network infrastructure project material management provided in Embodiment 1.

在一些实现中,存储器可以是高速随机存取存储器(RAM:Random AccessMemory),也可能还包括非不稳定的存储器(non-volatile memory),例如至少一个磁盘存储器。In some implementations, the memory may be a high-speed random access memory (RAM: Random Access Memory), and may also include a non-volatile memory (non-volatile memory), such as at least one disk memory.

在另一些实现中,处理器可以为中央处理器(CPU)、数字信号处理器(DSP)等各种类型通用处理器,在此不做限定。In other implementations, the processor may be various types of general-purpose processors such as a central processing unit (CPU) and a digital signal processor (DSP), which are not limited herein.

此外,上述的存储器中的逻辑指令可以通过软件功能单元的形式实现并作为独立的产品销售或使用时,可以存储在一个计算机可读取存储介质中。基于这样的理解,本发明的技术方案本质上或者说对现有技术做出贡献的部分或者该技术方案的部分可以以软件产品的形式体现出来,该计算机软件产品存储在一个存储介质中,包括若干指令用以使得一台计算机设备(可以是个人计算机,服务器,或者网络设备等)执行本发明各个实施例所述方法的全部或部分步骤。而前述的存储介质包括:U盘、移动硬盘、只读存储器(ROM,Read-Only Memory)、随机存取存储器(RAM,Random Access Memory)、磁碟或者光盘等各种可以存储程序代码的介质。In addition, the above logic instructions in the memory can be implemented in the form of software functional units and can be stored in a computer-readable storage medium when sold or used as an independent product. Based on this understanding, the essence of the technical solution of the present invention or the part that contributes to the prior art or the part of the technical solution can be embodied in the form of a software product, and the computer software product is stored in a storage medium, including Several instructions are used to make a computer device (which may be a personal computer, a server, or a network device, etc.) execute all or part of the steps of the methods described in various embodiments of the present invention. The aforementioned storage media include: U disk, mobile hard disk, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), magnetic disk or optical disc, etc., which can store program codes. .

本领域技术人员可以理解,上述计算设备的结构,仅仅是与本申请方案相关的部分结构,并不构成对本申请方案所应用于其上的计算设备的限定,具体的计算设备可以包括更多或更少的部件,或者组合某些部件,或者具有不同的部件布置。Those skilled in the art can understand that the structure of the above-mentioned computing device is only a part of the structure related to the solution of this application, and does not constitute a limitation on the computing device to which the solution of this application is applied. A specific computing device may include more or more Fewer parts, or combining certain parts, or having a different arrangement of parts.

实施例4Example 4

本实施例提供一种与本实施例1所提供的配电网基建项目物资管理全流程风险预警方法对应的计算机程序产品,计算机程序产品可以包括计算机可读存储介质,其上载有用于执行本实施例1所述的配电网基建项目物资管理全流程风险预警方法的计算机可读程序指令。This embodiment provides a computer program product corresponding to the risk warning method for the whole process of distribution network infrastructure project material management provided in Embodiment 1. The computer program product may include a computer-readable storage medium, which is uploaded with a The computer-readable program instructions of the risk early warning method for the whole process of distribution network infrastructure project material management described in Example 1.

计算机可读存储介质可以是保持和存储由指令执行设备使用的指令的有形设备。计算机可读存储介质例如可以是但不限于电存储设备、磁存储设备、光存储设备、电磁存储设备、半导体存储设备或者上述的任意组合。A computer readable storage medium may be a tangible device that holds and stores instructions for use by an instruction execution device. A computer readable storage medium may be, for example, but is not limited to, an electrical storage device, a magnetic storage device, an optical storage device, an electromagnetic storage device, a semiconductor storage device, or any combination of the above.

上述实施例提供的一种计算机可读存储介质,其实现原理和技术效果与上述方法实施例类似,在此不再赘述。The implementation principle and technical effect of the computer-readable storage medium provided by the foregoing embodiments are similar to those of the foregoing method embodiments, and details are not repeated here.

本申请是参照根据本申请实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present application is described with reference to flowcharts and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the present application. It should be understood that each procedure and/or block in the flowchart and/or block diagram, and a combination of procedures and/or blocks in the flowchart and/or block diagram can be realized by computer program instructions. These computer program instructions may be provided to a general purpose computer, special purpose computer, embedded processor, or processor of other programmable data processing equipment to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing equipment produce a An apparatus for realizing the functions specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions The device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded onto a computer or other programmable data processing device, causing a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process, thereby The instructions provide steps for implementing the functions specified in the flow chart or blocks of the flowchart and/or the block or blocks of the block diagrams.

上述各实施例仅用于说明本发明,其中各部件的结构、连接方式和制作工艺等都是可以有所变化的,凡是在本发明技术方案的基础上进行的等同变换和改进,均不应排除在本发明的保护范围之外。The above-mentioned embodiments are only used to illustrate the present invention, wherein the structure, connection mode and manufacturing process of each component can be changed to some extent, and any equivalent transformation and improvement carried out on the basis of the technical solution of the present invention should not be used. excluded from the protection scope of the present invention.

Claims (10)

1.一种配电网基建项目物资管理全流程风险预警方法,其特征在于,包括:1. A risk early warning method for the whole process of distribution network infrastructure project material management, characterized in that it includes: 以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分;Taking the whole process of material management of distribution network infrastructure projects as the main line, divide the material management stages of distribution network infrastructure projects; 获取配电网基建项目物资管理各阶段的所需数据;Obtain the data required for each stage of material management of distribution network infrastructure projects; 将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警。Input the required data of each stage of distribution network infrastructure project material management into the pre-built early warning model of each stage of distribution network infrastructure project material management, and provide early warning for each stage of distribution network infrastructure project material management. 2.如权利要求1所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述配电网基建项目的物资管理阶段包括需求提报阶段、物资采购阶段、物资领料阶段和物资退库阶段。2. The whole-process risk warning method for distribution network infrastructure project material management as claimed in claim 1, characterized in that, the material management stage of the distribution network infrastructure project includes a demand report stage, a material procurement stage, a material The picking stage and the material return stage. 3.如权利要求2所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述配电网基建项目物资管理各阶段的预警模型包括配电网基建项目物资管理各阶段的风险管控指标及其表达式和预警阈值。3. A kind of distribution network infrastructure project material management full-process risk early warning method as claimed in claim 2, it is characterized in that, the early warning model of each stage of distribution network infrastructure project material management includes distribution network infrastructure project material management Risk control indicators and their expressions and early warning thresholds at each stage. 4.如权利要求3所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述配电网基建项目物资管理各阶段的预警模型的构建过程为:4. A kind of distribution network infrastructure project material management whole-process risk early warning method as claimed in claim 3, is characterized in that, the construction process of the early warning model of each stage of described distribution network infrastructure project material management is: 基于配电网基建项目的需求提报结果、需求提报金额和可研批复总金额,确定配电网基建项目物资管理需求提报阶段的预警模型;Based on the demand report results, demand report amount and feasibility study approval total amount of the distribution network infrastructure project, determine the early warning model for the material management demand report stage of the distribution network infrastructure project; 基于配电网基建项目的物资采购订单总金额,确定配电网基建项目物资管理物资采购阶段的预警模型;Based on the total amount of the material purchase order of the distribution network infrastructure project, determine the early warning model of the material management material procurement stage of the distribution network infrastructure project; 基于配电网基建项目的物资领料程序、物资领用时间与设备安装、组塔和架线的进度、累计物资领用金额、主要物资规模和可研批复建设规模,确定配电网基建项目物资管理物资领料阶段的预警模型;Determine the distribution network infrastructure project based on the material requisition procedure, material requisition time and equipment installation, tower and wiring progress, accumulated material requisition amount, main material scale and feasibility study approval construction scale of the distribution network infrastructure project The early warning model of material management material picking stage; 基于配电网基建项目的物资退库比例,确定配电网基建项目物资管理物资退库阶段的预警模型。Based on the proportion of materials withdrawn from the distribution network infrastructure project, the early warning model for the material management material withdrawal stage of the distribution network infrastructure project is determined. 5.如权利要求3所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警,包括:5. A method for early warning of risk in the whole process of distribution network infrastructure project material management as claimed in claim 3, wherein the required data of each stage of distribution network infrastructure project material management is input into the pre-built distribution network. In the early warning model of each stage of material management of power grid infrastructure projects, early warnings are carried out for each stage of material management of distribution network infrastructure projects, including: 将配电网基建项目物资管理各阶段的所需数据输入至确定的预警模型的对应表达式中得到对应指标值;Input the required data at each stage of material management of the distribution network infrastructure project into the corresponding expression of the determined early warning model to obtain the corresponding index value; 根据确定的预警模型中的预警阈值和得到的对应指标值进行预警。Early warning is carried out according to the early warning threshold in the determined early warning model and the obtained corresponding index value. 6.如权利要求3所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述需求提报阶段的风险管控指标包括物资需求提报及时性指标和物资需求提报金额准确性指标,物资采购阶段的风险管控指标包括物资采购订单签订率过低指标,物资领料阶段的风险管控指标包括物资领料金额是否超需求提报指标、物资领用时间与建设进度是否匹配指标、物资领料金额占可研总投资比例是否过高指标、最后一笔物资领用时间合理性指标和投产项目主要物资领用规模异常指标,物资退库阶段的风险管控指标包括物资退库比例过高指标。6. The whole-process risk early warning method for distribution network infrastructure project material management as claimed in claim 3, characterized in that, the risk management and control indicators in the demand report stage include material demand report timeliness indicators and material demand report The accuracy index of reported amount, the risk management and control indicators in the material procurement stage include the low signing rate of material purchase orders, and the risk management and control indicators in the material requisition stage include whether the material requisition amount exceeds the demand report indicator, the time of material requisition and construction progress Whether it matches the index, whether the proportion of the amount of material requisition in the total investment of the feasibility study is too high, the index of the rationality of the last material requisition time, and the abnormal index of the main material requisition scale of the project put into operation, the risk management and control indicators of the material withdrawal stage include material The indicator of the high proportion of withdrawals. 7.如权利要求1所述的一种配电网基建项目物资管理全流程风险预警方法,其特征在于,所述需求提报阶段的风险管控指标中物资需求提报及时性指标的所需数据包括ERP系统的第一笔物资采购申请创建日期和规划计划系统的项目开工时间,物资需求提报金额准确性指标的所需数据包括ERP系统的物资类采购申请总金额和规划计划系统的可研批复总投资;7. A risk early warning method for the whole process of distribution network infrastructure project material management as claimed in claim 1, characterized in that, in the risk management and control indicators of the demand reporting stage, the required data of material demand reporting timeliness indicators Including the creation date of the first material purchase requisition in the ERP system and the project start time of the planning and planning system, the required data for the accuracy index of the reported amount of material demand includes the total amount of material procurement requisitions in the ERP system and the feasibility study of the planning and planning system Approve the total investment; 所述物资采购阶段的风险管控指标中物资采购订单签订率过低指标的所需数据包括ERP系统的物资类采购订单总金额以及规划计划系统的项目实际开工时间和可研批复总投资;The data required for the low signing rate of material purchase orders in the risk management and control indicators of the material procurement stage include the total amount of material purchase orders in the ERP system, the actual start time of the project in the planning and planning system, and the total investment in feasibility study approval; 所述物资领料阶段的风险管控指标中物资领料金额是否超需求提报指标的所需数据包括ERP系统的物资类采购申请总金额和领料总金额;物资领用时间与建设进度是否匹配指标的所需数据包括ERP系统的物资类本月入账成本和物资类自开始建设累计入账成本以及规划计划系统的项目实际开工时间;物资领料金额占可研总投资比例是否过高指标的所需数据包括ERP系统的领料总金额;最后一笔物资领用时间合理性指标的所需数据包括ERP系统的最后一笔领料日期和规划计划系统的项目实际开工时间;投产项目主要物资领用规模异常指标的所需数据包括规划计划系统的项目投产时间和建设规模以及PMS系统的设备规模。In the risk management and control indicators of the material requisition stage, whether the material requisition amount exceeds the required data for reporting indicators include the total amount of material procurement applications and the total amount of material requisition in the ERP system; whether the material requisition time matches the construction progress The data required for the indicators include the cost of materials recorded in the ERP system this month and the accumulated cost of materials recorded in the account since the beginning of construction, as well as the actual start time of the project in the planning and planning system; The required data includes the total amount of materials received by the ERP system; the required data for the rationality index of the last material received includes the date of the last material received by the ERP system and the actual start time of the project in the planning and planning system; The required data for scale anomaly indicators include the project commissioning time and construction scale of the planning planning system and the equipment scale of the PMS system. 所述物资退库阶段的风险管控指标中物资退库比例过高指标的所需数据包括ERP系统的领料总金额和退料总金额。The required data of the risk management and control indicators in the material withdrawal stage include the total amount of materials picked and the total amount of materials returned by the ERP system. 8.一种配电网基建项目物资管理全流程风险预警系统,其特征在于,包括:8. A whole-process risk warning system for distribution network infrastructure project material management, characterized in that it includes: 物资管理阶段划分模块,用于以配网基建项目物资管理全过程为主线,对配电网基建项目进行物资管理阶段划分;The material management stage division module is used to divide the material management stage of the distribution network infrastructure project based on the whole process of material management of the distribution network infrastructure project; 数据获取模块,用于获取配电网基建项目物资管理各阶段的所需数据;The data acquisition module is used to acquire the required data at each stage of material management of distribution network infrastructure projects; 预警模块,用于将配电网基建项目物资管理各阶段的所需数据输入至预先构建的配电网基建项目物资管理各阶段的预警模型中,对配电网基建项目物资管理各阶段进行预警。The early warning module is used to input the required data of each stage of distribution network infrastructure project material management into the pre-built early warning model of each stage of distribution network infrastructure project material management, and provide early warning for each stage of distribution network infrastructure project material management . 9.一种处理设备,其特征在于,包括计算机程序指令,其中,所述计算机程序指令被处理设备执行时用于实现权利要求1-7中任一项所述的配电网基建项目物资管理全流程风险预警方法对应的步骤。9. A processing device, characterized in that it includes computer program instructions, wherein, when the computer program instructions are executed by the processing device, it is used to realize the material management of the distribution network infrastructure project described in any one of claims 1-7 The steps corresponding to the whole process risk early warning method. 10.一种计算机可读存储介质,其特征在于,所述计算机可读存储介质上存储有计算机程序指令,其中,所述计算机程序指令被处理器执行时用于实现权利要求1-7中任一项所述的配电网基建项目物资管理全流程风险预警方法对应的步骤。10. A computer-readable storage medium, wherein computer program instructions are stored on the computer-readable storage medium, wherein the computer program instructions are used to implement any of claims 1-7 when executed by a processor The steps corresponding to the risk early warning method for the whole process of distribution network infrastructure project material management described in one item.
CN202310081088.3A 2023-01-18 2023-01-18 Distribution network infrastructure project material management whole-flow risk early warning method and system Pending CN116128301A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202310081088.3A CN116128301A (en) 2023-01-18 2023-01-18 Distribution network infrastructure project material management whole-flow risk early warning method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202310081088.3A CN116128301A (en) 2023-01-18 2023-01-18 Distribution network infrastructure project material management whole-flow risk early warning method and system

Publications (1)

Publication Number Publication Date
CN116128301A true CN116128301A (en) 2023-05-16

Family

ID=86309802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202310081088.3A Pending CN116128301A (en) 2023-01-18 2023-01-18 Distribution network infrastructure project material management whole-flow risk early warning method and system

Country Status (1)

Country Link
CN (1) CN116128301A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120218623A (en) * 2025-03-26 2025-06-27 国网湖北省电力有限公司物资公司 Power grid engineering material protection scheme evaluation method and device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN120218623A (en) * 2025-03-26 2025-06-27 国网湖北省电力有限公司物资公司 Power grid engineering material protection scheme evaluation method and device

Similar Documents

Publication Publication Date Title
CN104794206B (en) A kind of substation data QA system and method
CN118732633B (en) A method for optimizing production task scheduling in a digital workshop of intelligent manufacturing
CN114443437B (en) Alarm root cause output methods, devices, equipment, media and program products
CN103413188A (en) Method for predicting monthly industrial power consumption based on industrial business expansion
CN113065234A (en) Batch reliability risk level assessment method and system for intelligent electric meters
CN114298591A (en) Enterprise project application method and system
CN105574039A (en) Wafer test data processing method and system
CN114462298A (en) Electric power measurement asset management method, device, equipment and storage medium
CN115409381A (en) Line loss cause determination method and device, electronic equipment and storage medium
CN115034927A (en) Data processing method and device, electronic equipment and storage medium
CN116128301A (en) Distribution network infrastructure project material management whole-flow risk early warning method and system
CN104915785B (en) Power grid enterprises&#39; regenerated resources price evaluation method based on social fair value
CN115511297A (en) A virtual power plant application benefit evaluation method, equipment and storage medium
CN115187117A (en) Order distribution system and method based on component structure tree
CN114581263A (en) Power grid load analysis method and device, electronic equipment and storage medium
CN111967918A (en) System model for predicting electricity price based on support vector regression algorithm
CN114139612B (en) A power grid equipment asset data fusion method and its application based on LCC theory
CN116011698B (en) Method, device, computer equipment and storage medium for determining unit combination
CN107239880B (en) Power grid technical improvement fund demand measurement and calculation model based on equipment life statistical analysis
CN114706732B (en) Monitoring method and device for photovoltaic power station operation data
CN117236785A (en) A method, device and equipment for determining abnormal line loss
CN115395658A (en) Power distribution network fault disposal benefit evaluation method, device, equipment and medium
Kimura Does Foreign Direct Investment Affect the Growth of Local Firms? The Case of China's Electrical and Electronics Industry
CN112241587B (en) Distribution line risk assessment model construction method, risk assessment method and system
CN117455710A (en) Method and device for determining full life cycle cost of equipment and computer equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination