CN103603236A - A crack control method for double-block ballastless track bed slab - Google Patents

A crack control method for double-block ballastless track bed slab Download PDF

Info

Publication number
CN103603236A
CN103603236A CN201310543247.3A CN201310543247A CN103603236A CN 103603236 A CN103603236 A CN 103603236A CN 201310543247 A CN201310543247 A CN 201310543247A CN 103603236 A CN103603236 A CN 103603236A
Authority
CN
China
Prior art keywords
concrete
double
track bed
time
hours
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201310543247.3A
Other languages
Chinese (zh)
Inventor
王栋
张彰
孙文俊
王礼
上官印
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201310543247.3A priority Critical patent/CN103603236A/en
Publication of CN103603236A publication Critical patent/CN103603236A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Abstract

A method for controlling cracks of a double-block ballastless track bed plate comprises the steps of pouring concrete, and pouring the concrete back and forth between double-block sleepers according to a zigzag line; vibrating concrete, adopting a secondary vibrating process according to the slump and the initial setting time of the concrete in the process of pouring the concrete of the double-block type track bed slab, finishing and smoothing the surface, finishing rough smoothing by using wood after the concrete is filled into a mold, performing secondary smoothing after the concrete is filled into the mold for 2 hours, and performing third smoothing and smoothing after the concrete is filled into the mold for 4 hours; loosening the vertical screw rod adjuster, the fishplate and the fastener, loosening the vertical adjusting screw rod 4.5 hours after finishing concrete plastering, simultaneously loosening the fishplate from two sides of the initial pouring end, loosening the fastener by using a bolt fastening machine after loosening the bolts of the fishplate, and removing connection; and spraying the curing liquid. The problem of reduce ballastless track bed board crackle in the work progress is solved, provide safe, economic, the quick guarantee for the operation of train. The method has the characteristics of simple process, convenience in operation and easiness in construction, and improves the construction quality of the ballastless track bed plate.

Description

一种双块式无砟轨道道床板裂纹控制方法A crack control method for double-block ballastless track bed slab

技术领域 technical field

本发明涉及一种双块式无砟轨道道床板裂纹控制方法,特别是一种CRTSⅠ型双块式无砟轨道道床板裂纹控制方法。  The invention relates to a crack control method for a double-block ballastless track bed slab, in particular to a crack control method for a CRTS Ⅰ double-block ballastless track bed slab. the

背景技术 Background technique

目前我国高铁快速发展的时期,各省会城市及大中城市之间快速客运,规划“四横四纵”的快速铁路通道都在进行施工高潮,但是已建成或者通车的高速铁路中普遍存在无砟轨道道床板开裂的情况,为运营安全及维修带来了不便。  At present, during the period of rapid development of my country's high-speed rail, rapid passenger transport between provincial capitals and large and medium-sized cities, and the planned "four horizontal and four vertical" express rail channels are all under construction climax. The cracking of the track bed slab has brought inconvenience to the operation safety and maintenance. the

已有的施工技术及工艺对无砟轨道道床板施工过程中,混凝土的浇筑使用泵车或者料斗进行直接浇筑,振捣一次性的振捣完成,表面收光只进行1次或者2次收光,且收光时洒水,收光时间不当以及收光抹子任意收抹。使用轨排框架法施工时对松竖向螺杆调节器、鱼尾板、扣件的顺序和时间不正确。在道床板的养护时工艺不正确,以上施工方法及工艺都将不同程度的造成道床板出现裂纹。违反了高铁的验收要求。  In the construction process of ballastless track bed slabs, the existing construction technology and process use pump trucks or hoppers for direct pouring of concrete, one-time vibration is completed, and the surface finishing is only performed once or twice. , and sprinkle water during lightening, improper lightening time and arbitrary lightening trowel. The sequence and timing of loosening the vertical screw adjuster, fish plate and fasteners are incorrect when using the rail-row frame method for construction. The maintenance process of the track bed slab is not correct, and the above construction methods and processes will cause cracks in the track bed slab to varying degrees. Violation of the acceptance requirements of the high-speed rail. the

对于高铁无砟轨道的裂纹出现将对道床板的损坏是严重的,水进入到裂纹中使得道床板配筋生锈、膨胀、造成道床板出现大面积的裂纹和损坏。无砟轨道道床板一旦开裂修复相当困难,费用高、时间长造成列车不能正常运行,同时,基于经济性和安全等多种因素,现有的道床板裂纹控制技术及工艺不能满足施工要求。  The occurrence of cracks on the ballastless track of high-speed rail will seriously damage the ballast bed slab. Water entering the cracks will cause the reinforcement of the ballast slab to rust and expand, causing large-area cracks and damage to the ballast bed slab. Once the ballastless track bed slab is cracked, it is very difficult to repair, the cost is high and the time is long, so the train cannot run normally. At the same time, based on various factors such as economy and safety, the existing ballast slab crack control technology and process cannot meet the construction requirements. the

发明内容 Contents of the invention

    本发明其目的就在于提供一种双块式无砟轨道道床板裂纹控制方法,解决在施工过程中减少无砟轨道道床板裂纹的问题,为列车的运行提供安全、经济、快速保障。具有工艺简单、操作方便、易于施工的特点,提高了无砟轨道道床板的施工质量。  The purpose of the present invention is to provide a double-block ballastless track bed slab crack control method to solve the problem of reducing ballastless track bed slab cracks in the construction process and provide safe, economical and fast guarantee for the operation of trains. It has the characteristics of simple process, convenient operation and easy construction, and improves the construction quality of the ballastless track bed slab. the

实现上述目的而采取的技术方案,包括步骤  Technical solutions adopted to achieve the above objectives, including steps

1)混凝土浇筑 1) Concrete pouring

凝土浇筑前对支承层、轨枕进行湿润,在双块式轨枕之间按“之”字形路线来回灌注; Moisten the supporting layer and sleepers before concrete pouring, pour back and forth between the double-block sleepers according to the zigzag route;

 2)混凝土振捣 2) Concrete vibration

 双块式道床板混凝土浇筑过程中,根据混凝土的塌落度和初凝时间采用二次振捣工艺,第一次采用Φ50振捣棒在轨枕之间振捣,第二次采用Φ30振捣棒在轨枕四周进行振捣,振动密实的标准以混凝土不在沉落、表面呈现浮浆为度; During the concrete pouring process of the double-block track bed slab, the secondary vibration process is adopted according to the slump and initial setting time of the concrete. The first time uses a Φ50 vibrator to vibrate between the sleepers, and the second time uses a Φ30 vibrator Vibrate around the sleeper, and the standard of vibrating compactness is that the concrete does not sink and the surface appears laitance;

3)收光抹面 3) Lighten and wipe the surface

混凝土入模后用木抹完成粗平,控制混凝土标高及表面平整度,在混凝土入模2小时后进行二次抹面,抹面时严禁洒水润面,入模4小时进行第三次抹面压光; After the concrete is put into the mold, use wooden trowel to complete the rough leveling, control the concrete elevation and surface flatness, and perform the second plastering 2 hours after the concrete is put into the mold. It is strictly forbidden to sprinkle water to moisten the surface, and perform the third plastering and calendering 4 hours after the concrete is put into the mold;

4)松竖向螺杆调节器、鱼尾板、扣件 4) Loose vertical screw adjuster, fish plate, fasteners

混凝土抹面结束4.5个小时后,开始松竖向调节螺杆,用扳手将竖向螺杆先向上的方向转动180度,使用轨排统一降低0.5mm-1mm,然后从开始浇筑端两侧同时松鱼尾板,鱼尾板螺栓松开后及时用螺栓紧固机松动扣件,解除连接; After 4.5 hours of concrete plastering, start to loosen the vertical adjustment screw, use a wrench to turn the vertical screw 180 degrees in the upward direction, use the rail row to lower it uniformly by 0.5mm-1mm, and then loosen the fish tail from both sides of the pouring end at the same time After the plate and fish plate bolts are loosened, use the bolt fastening machine to loosen the fasteners in time and release the connection;

5)养护液喷涂 5) Curing solution spraying

混凝土浇筑4.5h后,精平和收光质量达到要求,检查合格后,用手指轻按不粘手时,及时用喷雾器喷洒养护剂,对于钢轨、轨排下方用软刷涂刷,养护剂用量为3.9m /5kg,侧模于脱模后立即喷洒养护液,每拆一块模板涂刷养护液后,再拆下一块模板,且成模后及时的采用两布一膜的土工布进行覆盖。 After 4.5 hours of concrete pouring, the fine leveling and finishing quality meet the requirements. After passing the inspection, use a sprayer to spray the curing agent in time when it is not sticky to touch with your fingers. Use a soft brush to paint the bottom of the rails and rails. The amount of curing agent is 3.9m /5kg, the side formwork is sprayed with curing solution immediately after demoulding, and after each dismantled formwork is painted with curing solution, another formwork is removed, and the geotextile with two cloths and one film is used to cover it in time after the mold is formed.

    与现有技术相比本发明具有以下优点。  Compared with the prior art, the present invention has the following advantages. the

1.本发明使无砟轨道道床板的裂纹出现得到了大大的改善,极大的提高了无砟轨道道床板的施工质量;  1. The present invention greatly improves the occurrence of cracks in the ballastless track bed slab, and greatly improves the construction quality of the ballastless track bed slab;

2.本发明不受施工场地环境制约,在同样的人力、财力、物力和设备等投入下即可控制裂纹的出现,过程简便,易于施工; 2. The present invention is not restricted by the environment of the construction site, and can control the occurrence of cracks with the same input of manpower, financial resources, material resources and equipment, and the process is simple and easy to construct;

3.极大的减少了返工率,节约成本,社会效益及经济效益明显。 3. It greatly reduces the rework rate, saves costs, and has obvious social and economic benefits.

附图说明 Description of drawings

    下面结合附图对本发明作进一步详述。  Below in conjunction with accompanying drawing, the present invention is described in further detail. the

图1为本发明道床板浇筑的顺序示意图。  Fig. 1 is a schematic diagram of the sequence of pouring the road bed slabs of the present invention. the

图2为本发明道床板浇筑振捣示意图。  Fig. 2 is a schematic diagram of pouring and vibrating a road bed slab according to the present invention. the

图中,1为浇筑点,2为浇筑顺序,3为Φ50振捣棒,4为Φ30振捣棒。  In the figure, 1 is the pouring point, 2 is the pouring sequence, 3 is the Φ50 vibrating rod, and 4 is the Φ30 vibrating rod. the

具体实施方式 Detailed ways

包括步骤  include steps

1)混凝土浇筑 1) Concrete pouring

凝土浇筑前对支承层、轨枕进行湿润,在双块式轨枕之间按“之”字形路线来回灌注,如图1所示; Wet the supporting layer and sleepers before concrete pouring, and pour back and forth between the double-block sleepers according to the zigzag route, as shown in Figure 1;

 2)混凝土振捣 2) Concrete vibration

 双块式道床板混凝土浇筑过程中,根据混凝土的塌落度和初凝时间采用二次振捣工艺,第一次采用Φ50振捣棒在轨枕之间振捣,第二次采用Φ30振捣棒在轨枕四周进行振捣,振动密实的标准以混凝土不在沉落、表面呈现浮浆为度,如图2所示; During the concrete pouring process of the double-block track bed slab, the secondary vibration process is adopted according to the slump and initial setting time of the concrete. The first time uses a Φ50 vibrator to vibrate between the sleepers, and the second time uses a Φ30 vibrator Vibrate around the sleeper, and the standard of vibration compaction is that the concrete does not sink and the surface appears laitance, as shown in Figure 2;

3)收光抹面 3) Lighten and wipe the surface

混凝土入模后用木抹完成粗平,控制混凝土标高及表面平整度,在混凝土入模2小时后进行二次抹面,抹面时严禁洒水润面,入模4小时进行第三次抹面压光; After the concrete is put into the mould, finish the rough leveling with a wooden trowel, control the concrete elevation and surface smoothness, and carry out the second plastering 2 hours after the concrete is put into the mold. It is strictly forbidden to sprinkle water to moisten the surface, and perform the third plastering and calendering 4 hours after the concrete is put into the mold;

4)松竖向螺杆调节器、鱼尾板、扣件 4) Loose vertical screw adjuster, fish plate, fasteners

混凝土抹面结束4.5个小时后,开始松竖向调节螺杆,用扳手将竖向螺杆先向上的方向转动180度,使用轨排统一降低0.5mm-1mm,然后从开始浇筑端两侧同时松鱼尾板,鱼尾板螺栓松开后及时用螺栓紧固机松动扣件,解除连接; After 4.5 hours of concrete plastering, start to loosen the vertical adjustment screw, use a wrench to turn the vertical screw 180 degrees in the upward direction, use the rail row to lower it uniformly by 0.5mm-1mm, and then loosen the fish tail from both sides of the pouring end at the same time After the plate and fish plate bolts are loosened, use the bolt fastening machine to loosen the fasteners in time and release the connection;

5)养护液喷涂 5) Curing solution spraying

混凝土浇筑4.5h后,精平和收光质量达到要求,检查合格后,用手指轻按不粘手时,及时用喷雾器喷洒养护剂,对于钢轨、轨排下方用软刷涂刷,养护剂用量为3.9m /5kg,侧模于脱模后立即喷洒养护液,每拆一块模板涂刷养护液后,再拆下一块模板,且成模后及时的采用两布一膜的土工布进行覆盖。 After 4.5 hours of concrete pouring, the fine leveling and finishing quality meet the requirements. After passing the inspection, use a sprayer to spray the curing agent in time when it is not sticky to touch with your fingers. Use a soft brush to paint the bottom of the rails and rails. The amount of curing agent is 3.9m /5kg, the side formwork is sprayed with curing solution immediately after demoulding, and after each dismantled formwork is painted with curing solution, another formwork is removed, and the geotextile with two cloths and one film is used to cover it in time after the mold is formed.

本发明技术方案如下进行:  Technical scheme of the present invention proceeds as follows:

浇筑前支承层表面和轨枕应湿润,支承层表面洒水,轨枕四周和底部采用喷雾器多次喷洒。为减少过度振捣,道床板混凝土不能一点浇筑、振捣棒赶料,而应在双块式轨枕之间按“之”字形路线来回灌注。道床板混凝土应采用二次振捣工艺,第一次采用Φ50振捣棒在轨枕之间振捣,第二次采用Φ30振捣棒在轨枕四周进行振捣,加强新浇混凝土与轨枕的粘结以及轨枕底部混凝土的密实性。道床板混凝土初凝前应经过3-5次抹压,抹面过程中严禁洒水。抹面过程中清理轨枕时,应用毛刷或干抹布清理,不得用水清理。道床板混凝土喷涂养护剂后应及时松开新浇筑混凝土前后里程最外两端工具轨的鱼尾板螺栓,避免因前后工具轨温度变形对新浇筑混凝土的影响;工具轨扣件的螺栓宜在混凝土终凝时间附近松开。道床板混凝土宜采用喷涂养护剂并覆盖土工布、塑料薄膜和棉被的防风保温保湿养护措施。养护剂的喷涂在最后一次抹面后立即进行,应采用喷涂和滚涂相结合的方式,不得使用毛刷涂刷。在轨枕四周要对养护剂施工质量进行检查,漏喷漏涂处及时处理。两侧模板拆处后应立即进行养护及施工。养护剂在成膜前严禁与水接触,避免影响成膜质量。 Before pouring, the surface of the supporting layer and the sleeper should be wet, the surface of the supporting layer should be sprinkled with water, and the surrounding and bottom of the sleeper should be sprayed several times with a sprayer. In order to reduce excessive vibration, the concrete of the track bed slab should not be poured at one point, and the vibrator should be used to drive the material, but should be poured back and forth between the double-block sleepers in a zigzag route. The concrete of the track bed slab should be vibrated twice. For the first time, Φ50 vibrating rods are used to vibrate between the sleepers, and for the second time, Φ30 vibrating rods are used to vibrate around the sleepers to strengthen the bond between the newly poured concrete and the sleepers. and the compactness of the concrete at the bottom of the sleeper. The concrete of the road bed slab should be plastered 3-5 times before initial setting, and watering is strictly prohibited during the plastering process. When cleaning the sleeper during the plastering process, it should be cleaned with a brush or a dry rag, and water should not be used for cleaning. After spraying the curing agent on the concrete of the track bed slab, the fishplate bolts of the tool rails at the outermost ends of the front and rear mileages of the newly poured concrete should be loosened in time to avoid the influence of the temperature deformation of the front and rear tool rails on the newly poured concrete; the bolts of the tool rail fasteners should be The concrete loosens near the final setting time. The concrete of the road bed slab should adopt the measures of windproof, thermal insulation and moisture preservation by spraying curing agent and covering geotextile, plastic film and quilt. The spraying of curing agent should be carried out immediately after the last plastering. It should be combined with spraying and rolling, and brushing should not be used. The construction quality of the curing agent should be checked around the sleeper, and the leakage of spray and paint should be dealt with in time. Maintenance and construction should be carried out immediately after the formwork on both sides is removed. The curing agent is strictly forbidden to contact with water before film formation, so as to avoid affecting the quality of film formation.

实施例 Example

1.混凝土浇筑技术  1. Concrete pouring technology

凝土浇筑前应对支承层、轨枕进行湿润,确保支承层和轨枕完全湿润,且不得有明显积水,若不洒水湿润造成混凝土与支承层、轨枕接触位置混凝土失水,造成混凝土前期收缩不一致导致裂纹产生。为减少过度振捣,道床板混凝土不能一点浇筑、振捣棒赶料,而应在双块式轨枕之间按“之”字形路线来回灌注,否则造成浇筑完成的道床板表面混凝土离析出现浮浆,导致收缩不一致出现裂纹。 Before concrete pouring, the supporting layer and sleepers should be moistened to ensure that the supporting layer and sleepers are completely wet, and there should be no obvious water accumulation. If the concrete is not wetted with water, the concrete will lose water at the contact position between the concrete and the supporting layer and the sleeper, resulting in inconsistent shrinkage of the concrete in the early stage. Cracks occur. In order to reduce excessive vibration, the concrete of the track bed slab cannot be poured at one point, and the vibrator is used to drive the material, but should be poured back and forth between the double-block sleepers in a zigzag route, otherwise the concrete on the surface of the track bed slab after pouring will segregate and appear laitance , resulting in inconsistent shrinkage and cracks.

2.混凝土振捣技术  2. Concrete vibration technology

双块式道床板混凝土浇筑过程中,为了提高混凝土的密实度和减少裂纹,根据混凝土的塌落度和初凝时间采用二次振捣工艺,第一次采用Φ50振捣棒在轨枕之间振捣,第二次采用Φ30振捣棒在轨枕四周进行振捣,加强新浇混凝土与轨枕的粘结以及轨枕底部混凝土的密实性。振动密实的标准以混凝土不在沉落、表面呈现浮浆为度,防止过振、漏振。 否则造成振动不密实,混凝土凝固过程中出现裂纹。 During the concrete pouring process of the double-block track bed slab, in order to improve the compactness of the concrete and reduce cracks, the secondary vibration process was adopted according to the slump and initial setting time of the concrete. For the first time, a Φ50 vibrating rod was used to vibrate between sleepers. For the second time, use a Φ30 vibrating rod to vibrate around the sleeper to strengthen the bonding between the newly poured concrete and the sleeper and the compactness of the concrete at the bottom of the sleeper. The standard of vibration compactness is that the concrete does not sink and the surface appears laitance, so as to prevent over-vibration and vibration leakage. Otherwise, the vibration will not be compacted, and cracks will appear during the concrete solidification process.

3.收光抹面技术  3. Finishing and wiping technology

混凝土入模后用木抹完成粗平,粗平用模具控制混凝土标高及表面平整度。为防止混凝土表面失水产生细小裂纹,在混凝土入模2小时后进行二次抹面,抹面时严禁洒水润面,否则造成表层混凝土的裂纹。抹面过程中要注意加强对钢轨下方、轨枕四周等部位的施工。入模4小时进行第三次抹面压光。抹面过程中要注意加强对钢轨、托梁下方、轨枕四周等部位的施工,在轨枕四周处抹面时,抹子向轨枕方向用力,避免轨枕四周及八字裂纹早期出现。 After the concrete is put into the mold, the rough leveling is completed with a wooden trowel, and the rough leveling uses a mold to control the concrete elevation and surface flatness. In order to prevent small cracks on the concrete surface due to water loss, the concrete should be plastered 2 hours after the concrete has been put into the mold. It is strictly forbidden to sprinkle water to moisten the surface, otherwise it will cause cracks in the surface concrete. In the process of plastering, attention should be paid to strengthening the construction of the parts below the rails and around the sleepers. Enter the mold for 4 hours to carry out the third plastering and calendering. During the plastering process, attention should be paid to strengthening the construction of the rails, the bottom of the joist, and around the sleeper. When plastering the surface around the sleeper, the trowel should be applied in the direction of the sleeper to avoid the early appearance of cracks around the sleeper and around the sleeper.

4.松竖向螺杆调节器、鱼尾板、扣件时间方面技术  4. Loose vertical screw adjuster, fish plate, fastener time technology

混凝土抹面结束约4.5个小时左右,开始松竖向调节螺杆,用扳手将竖向螺杆先向上的方向转动180度,使用轨排统一降低0.5mm-1mm,提高轨枕下方道床板的密实性;然后从开始浇筑端两侧同时松鱼尾板,鱼尾板螺栓松开后及时用螺栓紧固机松动扣件,解除连接,释放应力,让混凝土不会因为温度升高而产生裂纹,让新浇混凝土处于自由状态且防止钢轨升降温导致新浇注混凝土受到拉应力产生裂缝。 About 4.5 hours after the completion of the concrete plastering, start to loosen the vertical adjustment screw, and use a wrench to turn the vertical screw 180 degrees in the upward direction, and use the rail row to lower it uniformly by 0.5mm-1mm to improve the compactness of the bed slab under the sleeper; then Loosen the fishplate at the same time from both sides of the pouring end. After the bolts of the fishplate are loosened, use the bolt fastening machine to loosen the fasteners in time to release the connection and release the stress, so that the concrete will not crack due to temperature rise, and the newly poured The concrete is in a free state and prevents the rails from heating and cooling to cause cracks in the newly poured concrete due to tensile stress.

5.养护液喷涂技术  5. Curing solution spraying technology

在混凝土浇筑后4.5h左右,精平和收光质量达到要求,检查合格后,用手指轻按不粘手时,及时用喷雾器喷洒养护剂,为防止喷洒不均匀需用滚筒刷配合作业,对于钢轨、轨排下方用软刷涂刷,确保养护剂喷洒均匀全面,养护剂用量为3.9m /5kg,侧模于脱模后立即喷洒养护液,每拆一块模板涂刷养护液后,再拆下一块模板,且成模后及时的采用两布一膜的土工布进行覆盖。 About 4.5 hours after the concrete is poured, the fine leveling and finishing quality meet the requirements. After passing the inspection, use a sprayer to spray the curing agent in time when the hands are not sticky when pressed lightly with your fingers. To prevent uneven spraying, use a roller brush to cooperate with the operation. For rails , Brush the bottom of the rail row with a soft brush to ensure that the curing agent is sprayed evenly and comprehensively. The amount of curing agent is 3.9m /5kg. Spray the curing liquid immediately after the side mold is demoulded. One template, and cover it with two geotextiles and one film in time after the mold is formed.

Claims (1)

1. a double-block ballastless track bed board crack controlling means, is characterized in that, comprises step
1) concreting
Solidifying soil is built and frontly supporting bed, sleeper is carried out moistening, between double-block type sleeper, by "the" shape route, pours into back and forth;
2) concrete vibrating
In double-block type railway roadbed board concrete casting process, according to concrete slump and initial setting time, adopt secondary vibration technique, adopt for the first time Φ 50 vibrating spears to vibrate between sleeper, adopt for the second time Φ 30 vibrating spears to vibrate at sleeper circumferential, the standard of vibratory compaction take concrete not sinking, surface presents laitance as degree;
3) receiving light wipes one's face
Concrete enters with wood, to have smeared after mould thick flatly, controls concrete absolute altitude and surface finish, enters mould after 2 hours, carry out quadric-plastering at concrete, forbids the profit face of sprinkling water while wiping one's face, and enters the mould press polish of wiping one's face for the third time for 4 hours;
4) the vertical screw regulator of pine, splice bar, fastener
Concrete coating finished after 4.5 hours, start loose vertical adjustment screw rod, the direction vertical screw rod first being made progress with spanner is rotated 180 degree, use the unified 0.5mm-1mm of reduction of the section of track, then from starting to build end both sides loose splice bar simultaneously, fish-bolt unclamps rear in time with the loosening fastener of Screw Tightening Machines, removes and connects;
5) curing fluid capable spraying
After concreting 4.5h, the gentle receipts light quality of essence reaches requirement, after passed examination, when tack-free with finger flicking, use in time atomizers spray curing agent, for rail, section of track below, with soft brushing, brush, curing agent consumption is 3.9m/5kg, and side form sprays immediately curing fluid capable after the demoulding, often tears open after a template brushing curing fluid capable, pull down again a template, and after Cheng Mo, adopt timely the geotextiles of two cloth one films to cover.
CN201310543247.3A 2013-11-06 2013-11-06 A crack control method for double-block ballastless track bed slab Pending CN103603236A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310543247.3A CN103603236A (en) 2013-11-06 2013-11-06 A crack control method for double-block ballastless track bed slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310543247.3A CN103603236A (en) 2013-11-06 2013-11-06 A crack control method for double-block ballastless track bed slab

Publications (1)

Publication Number Publication Date
CN103603236A true CN103603236A (en) 2014-02-26

Family

ID=50121491

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310543247.3A Pending CN103603236A (en) 2013-11-06 2013-11-06 A crack control method for double-block ballastless track bed slab

Country Status (1)

Country Link
CN (1) CN103603236A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105568933A (en) * 2015-12-22 2016-05-11 黄河养护集团有限公司 Construction method of concrete poured gate
CN106283960A (en) * 2016-10-17 2017-01-04 兰州理工大学 Sleeper and construction method thereof for non-fragment orbit Concrete Crack Control
CN106400616A (en) * 2016-12-05 2017-02-15 兰州理工大学 Large-radius chamfer sleeper used for controlling concrete cracks of ballastless track and construction method
CN110184864A (en) * 2019-06-11 2019-08-30 中铁七局集团有限公司 A method of reducing double-block ballastless track bed board cracking rate
CN110258207A (en) * 2019-07-01 2019-09-20 中铁七局集团有限公司 A kind of maintenance of equipment for double-block ballastless track bed board
CN114000379A (en) * 2021-11-16 2022-02-01 中铁十二局集团有限公司 Concrete construction method for CRTS I double-block ballastless track bed plate
CN114575203A (en) * 2022-03-18 2022-06-03 中铁十二局集团有限公司 Construction method for preventing and treating cracks of ballastless track bed of plateau railway tunnel
CN114941258A (en) * 2022-06-23 2022-08-26 中铁十八局集团有限公司 Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1549965A (en) * 1977-01-20 1979-08-08 Frenzel J Railway sleeper
CN101830036A (en) * 2010-04-29 2010-09-15 中国建筑股份有限公司 Concrete track slab prefabricating construction method of CRTS I type slab ballastless track
CN201620321U (en) * 2010-04-28 2010-11-03 中铁二十局集团有限公司 Assembly type bent for construction of double-block unballasted track
WO2011079677A1 (en) * 2009-12-30 2011-07-07 中铁八局集团有限公司 Construction method for double-block ballastless track bed on subgrade

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1549965A (en) * 1977-01-20 1979-08-08 Frenzel J Railway sleeper
WO2011079677A1 (en) * 2009-12-30 2011-07-07 中铁八局集团有限公司 Construction method for double-block ballastless track bed on subgrade
CN201620321U (en) * 2010-04-28 2010-11-03 中铁二十局集团有限公司 Assembly type bent for construction of double-block unballasted track
CN101830036A (en) * 2010-04-29 2010-09-15 中国建筑股份有限公司 Concrete track slab prefabricating construction method of CRTS I type slab ballastless track

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
严德平: ""浅谈荒漠戈壁地区双块式无砟轨道防开裂技术与措施"", 《轨道工程》 *
叶鸿涛: ""戈壁地区双块式无砟轨道道床板混凝土裂纹控制"", 《山西建筑》 *
崔国庆: ""双块式无砟轨道道床板裂缝控制研究"", 《铁道设计标准》 *
牛叔强: ""兰新铁路第二双线三十里风区无砟轨道道床板混凝土裂纹、裂缝控制技术"", 《城市建设理论研究(电子版)》 *
骆正甲: ""砟轨道道床板裂纹问题研究及防治措施"", 《城市建设理论研究(电子版)》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105568933A (en) * 2015-12-22 2016-05-11 黄河养护集团有限公司 Construction method of concrete poured gate
CN106283960A (en) * 2016-10-17 2017-01-04 兰州理工大学 Sleeper and construction method thereof for non-fragment orbit Concrete Crack Control
CN106283960B (en) * 2016-10-17 2018-01-05 兰州理工大学 Sleeper and its construction method for non-fragment orbit Concrete Crack Control
CN106400616A (en) * 2016-12-05 2017-02-15 兰州理工大学 Large-radius chamfer sleeper used for controlling concrete cracks of ballastless track and construction method
CN106400616B (en) * 2016-12-05 2018-01-02 兰州理工大学 Large radius chamfering sleeper and construction method for non-fragment orbit concrete crack control
CN110184864A (en) * 2019-06-11 2019-08-30 中铁七局集团有限公司 A method of reducing double-block ballastless track bed board cracking rate
CN110258207A (en) * 2019-07-01 2019-09-20 中铁七局集团有限公司 A kind of maintenance of equipment for double-block ballastless track bed board
CN114000379A (en) * 2021-11-16 2022-02-01 中铁十二局集团有限公司 Concrete construction method for CRTS I double-block ballastless track bed plate
CN114575203A (en) * 2022-03-18 2022-06-03 中铁十二局集团有限公司 Construction method for preventing and treating cracks of ballastless track bed of plateau railway tunnel
CN114941258A (en) * 2022-06-23 2022-08-26 中铁十八局集团有限公司 Anti-cracking construction method for concrete track bed slab of CRTS I type double-block ballastless track of high-speed railway tunnel
CN114941258B (en) * 2022-06-23 2023-05-23 中铁十八局集团有限公司 A construction method for anti-cracking of CRTS Ⅰ type double-block ballastless track concrete track bed slab in high-speed railway tunnel

Similar Documents

Publication Publication Date Title
CN103603236A (en) A crack control method for double-block ballastless track bed slab
CN207669500U (en) A kind of fixed production line of prestressing force superimposed sheet long-line pedestal
CN103899088B (en) Large span ultra-thin overlength cast-in-situ clear-water concrete Slate hanging construction method
CN101713237B (en) Construction method of large-volume original decorative large pier stud fair-faced concrete
CN110107085A (en) Superelevation fair-faced concrete column construction method
CN106836815A (en) Large area diamond dust floor structure plate and surface layer one-off construction method
CN103470067A (en) Transformation and construction method used for facing bare concrete of existing building outer wall
CN107143111A (en) A kind of construction method of abrasion-proof terrace
CN108638324A (en) A kind of construction method of prefabricated case beam
CN104278598B (en) A kind of self-compaction bituminous concrete water-protected enclosure layer and construction method thereof
CN101758557A (en) Rapid circulation producing method of track slabs
CN110607894A (en) Construction method for floor of constructional engineering
CN103774561A (en) Streamline operation construction method of precast small box girders for highway in assembling mode
CN107881902A (en) Concrete construction method and mirror surface concrete pier stud
CN106284984A (en) Folding structure board post poured band joint template construction method
CN104626354A (en) Manufacturing process of streetcar rail plate
CN107060271A (en) A kind of dust-proof hardened artiwear method for constructing terrace
CN104894976A (en) Method for paving bridge surface through four-machine linkage
CN204690560U (en) Tamping equipment is built in rigid pavement
CN115614063A (en) Tunnel secondary lining form trolley
CN109208934A (en) A kind of reinforcement means of concrete structured beam
CN106192699B (en) A kind of same phase out-phase road surface cutting method and device
CN111962348A (en) Concrete floor construction process
CN210685420U (en) Conical sprayer for slope concrete
CN105113421B (en) Grinding Construction Method of External Formwork of Prefabricated Box Girder

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20140226