[go: up one dir, main page]

CN103437556B - Building water supply and drainage and heating engineering waterproofing and insulation construction method - Google Patents

Building water supply and drainage and heating engineering waterproofing and insulation construction method Download PDF

Info

Publication number
CN103437556B
CN103437556B CN201310390217.3A CN201310390217A CN103437556B CN 103437556 B CN103437556 B CN 103437556B CN 201310390217 A CN201310390217 A CN 201310390217A CN 103437556 B CN103437556 B CN 103437556B
Authority
CN
China
Prior art keywords
tube coupling
sleeve
waterproof
insulation
insulation layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310390217.3A
Other languages
Chinese (zh)
Other versions
CN103437556A (en
Inventor
王巧利
王西胜
张峰
高博
贾飞俊
马伟力
赵强
王勋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shaanxi Province In Third Construction Co In Fourth Branch
Shaanxi Construction Engineering Group Co Ltd
Original Assignee
Branch Co Of Shanxi Third Engineering Co Ltd 4th
Shaanxi Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Branch Co Of Shanxi Third Engineering Co Ltd 4th, Shaanxi Construction Engineering Group Co Ltd filed Critical Branch Co Of Shanxi Third Engineering Co Ltd 4th
Priority to CN201310390217.3A priority Critical patent/CN103437556B/en
Publication of CN103437556A publication Critical patent/CN103437556A/en
Application granted granted Critical
Publication of CN103437556B publication Critical patent/CN103437556B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sink And Installation For Waste Water (AREA)
  • Building Environments (AREA)

Abstract

本发明公开了一种建筑给排水及采暖工程用防水与保温施工方法,包括以下步骤:一、建筑给排水及采暖工程管道与卫生器具安装;卫生器具通过地脚螺栓固定安装在楼板上,楼板为现浇混凝土楼板且施工完成后,还需对地脚螺栓进行防水防腐;二、管道防水及保温处理:对需安装管道进行防水及保温处理;需安装管道中穿过楼板的管道节段为穿楼板管节且穿过墙体的管道节段为穿墙管节,需安装管道中位于墙体与楼板外侧的管道节段为外露管节。本发明方法步骤简单、设计合理、施工操作简便且施工进度快、施工效果好,能有效解决现有建筑给排水及采暖工程用防水与保温施工方法存在的施工操作不规范、施工效率较低、防水与保温效果较差等问题。

The invention discloses a waterproof and thermal insulation construction method for building water supply and drainage and heating engineering, comprising the following steps: 1. Installation of building water supply and drainage and heating engineering pipelines and sanitary appliances; the sanitary appliances are fixed and installed on the floor through anchor bolts, and the floor slab It is a cast-in-place concrete floor and after the construction is completed, the anchor bolts need to be waterproofed and anti-corrosion; 2. Pipeline waterproofing and heat preservation treatment: Waterproof and heat preservation treatment is carried out on the pipes to be installed; the pipe sections that pass through the floor in the pipes to be installed are The pipe section that passes through the floor pipe joint and passes through the wall is a wall pipe joint, and the pipe section that is located outside the wall and floor in the pipe to be installed is an exposed pipe joint. The method of the invention has simple steps, reasonable design, convenient construction operation, fast construction progress and good construction effect, and can effectively solve the problems of non-standard construction operation, low construction efficiency, and low construction efficiency in existing building water supply and drainage and heating engineering waterproof and thermal insulation construction methods. Problems such as poor waterproof and thermal insulation effects.

Description

建筑给排水及采暖工程用防水与保温施工方法Waterproof and thermal insulation construction method for building water supply and drainage and heating engineering

技术领域technical field

本发明属于建筑给排水及采暖工程施工技术领域,尤其是涉及一种建筑给排水及采暖工程用防水与保温施工方法。The invention belongs to the technical field of building water supply and drainage and heating engineering construction, and in particular relates to a waterproof and heat preservation construction method for building water supply and drainage and heating engineering.

背景技术Background technique

现代建筑中,给排水及采暖安装工程的质量,不仅关系到人民的生活、工作,还直接影响到人民群众生命、财产的安全,而且对建筑物的使用寿命也有很大影响。随着国民经济的发展,人民生活水平日益提高,建筑物规模和功能的增加,对给排水及采暖安装工程的质量要求也愈来愈高。其中,防水与保温施工建筑给排水及采暖工程中的重要施工环节之一,其施工质量直接影响建筑物给排水及采暖工程的施工质量。但现如今,建筑物给排水及采暖工程用防水与保温施工没有一个统一、规范且具体的施工方法可遵循,因而实际施工时不可避免地存在施工操作比较随意、不规范、施工效率较低、防水与保温效果较差等诸多问题。In modern buildings, the quality of water supply, drainage and heating installation projects is not only related to people's life and work, but also directly affects the safety of people's lives and property, and has a great impact on the service life of buildings. With the development of the national economy, people's living standards are improving day by day, the scale and function of buildings are increasing, and the quality requirements for water supply, drainage and heating installation projects are also getting higher and higher. Among them, waterproof and thermal insulation construction is one of the important construction links in building water supply, drainage and heating engineering, and its construction quality directly affects the construction quality of building water supply, drainage and heating engineering. But nowadays, there is no unified, standardized and specific construction method for waterproofing and thermal insulation construction of building water supply and drainage and heating engineering. There are many problems such as poor waterproof and thermal insulation effects.

发明内容Contents of the invention

本发明所要解决的技术问题在于针对上述现有技术中的不足,提供一种建筑给排水及采暖工程用防水与保温施工方法,其方法步骤简单、设计合理、施工操作简便且施工进度快、施工效果好,能有效解决现有建筑给排水及采暖工程用防水与保温施工方法存在的施工操作不规范、施工效率较低、防水与保温效果较差等问题。The technical problem to be solved by the present invention is to provide a waterproof and thermal insulation construction method for building water supply and drainage and heating engineering in view of the deficiencies in the above-mentioned prior art. The method has simple steps, reasonable design, simple construction operation and fast construction progress. The effect is good, and it can effectively solve the problems of non-standard construction operation, low construction efficiency, poor waterproof and heat preservation effect existing in the waterproof and heat preservation construction method of the existing building water supply and drainage and heating engineering.

为解决上述技术问题,本发明采用的技术方案是:一种建筑给排水及采暖工程用防水与保温施工方法,其特征在于该方法包括以下步骤:In order to solve the above-mentioned technical problems, the technical solution adopted in the present invention is: a waterproof and thermal insulation construction method for building water supply and drainage and heating engineering, which is characterized in that the method comprises the following steps:

步骤一、建筑给排水及采暖工程管道与卫生器具安装:对所施工建筑内需安装管道分别进行安装,所述需安装管道为给排水管道或采暖管道,所述给排水管道与所施工建筑内所安装的卫生器具相接;Step 1. Installation of building water supply and drainage and heating engineering pipelines and sanitary appliances: install the pipelines that need to be installed in the building under construction respectively. The pipelines to be installed are water supply and drainage pipelines or heating pipelines. The installed sanitary fixtures are connected;

对所述需安装管道进行安装的同时,还需对所述卫生器具进行安装;所述卫生器具通过地脚螺栓固定安装在楼板上,所述楼板为现浇混凝土楼板,所述地脚螺栓底部预埋在所述现浇混凝土楼板内;所述现浇混凝土楼板施工完成后,还需对地脚螺栓进行防水防腐;对地脚螺栓进行防水防腐时,先将所述卫生器具的安装底座平放于所述现浇混凝土楼板上,并使得地脚螺栓的螺栓杆由下至上自安装底座上所开的螺栓安装孔穿出,再由上至下在地脚螺栓上部同轴套装一个外套管;所述外套管的底部支撑在安装底座上;所述地脚螺栓的螺栓杆上安装有螺母,所述螺母位于安装底座上且其布设在外套管内;所述外套管的顶端比地脚螺栓的螺栓杆顶端高不小于5mm;所述外套管内填充有黄油,所填充黄油的上表面与外套管的顶端相平齐;While installing the pipes to be installed, the sanitary fixtures also need to be installed; the sanitary fixtures are fixed on the floor through anchor bolts, the floor is cast-in-situ concrete floor, and the bottom of the anchor bolts pre-buried in the cast-in-place concrete floor; after the construction of the cast-in-place concrete floor is completed, the anchor bolts need to be waterproofed and anti-corrosion; when the anchor bolts are waterproof and anti-corrosion, the installation base of the sanitary ware Put it on the cast-in-place concrete floor, and make the bolt rod of the anchor bolt pass through the bolt installation hole opened on the installation base from bottom to top, and then set an outer sleeve coaxially on the upper part of the anchor bolt from top to bottom The bottom of the outer casing is supported on the installation base; nuts are installed on the bolt rods of the anchor bolts, and the nuts are located on the installation base and arranged in the outer casing; the top of the outer casing is larger than the anchor bolts The height of the top of the bolt shaft is not less than 5mm; the outer casing is filled with butter, and the upper surface of the filled butter is flush with the top of the outer casing;

步骤二、管道防水及保温处理:对步骤一中所述需安装管道进行防水及保温处理;所述需安装管道中穿过楼板的管道节段为穿楼板管节,所述需安装管道中穿过墙体的管道节段为穿墙管节,所述需安装管道中位于墙体与楼板外侧的管道节段为外露管节;对所述需安装管道进行防水及保温处理时,处理过程如下:Step 2. Pipeline waterproofing and heat preservation treatment: Waterproof and heat preservation treatment is carried out on the pipes to be installed in step 1; the pipe section passing through the floor in the pipe to be installed is a pipe joint through the floor, and the pipe to be installed in the pipe The pipe section passing through the wall is a wall pipe joint, and the pipe section outside the wall and the floor among the pipes to be installed is an exposed pipe joint; when waterproofing and heat preservation are performed on the pipes to be installed, the processing process is as follows :

步骤201、穿楼板管节与穿墙管节防水及保温处理:对所述需安装管道中的穿楼板管节和管道节段为穿墙管节分别进行防水及保温处理;Step 201, waterproofing and heat preservation treatment of the floor pipe joint and the wall pipe joint: performing waterproof and heat preservation treatment on the floor pipe joint and the pipe section in the pipeline to be installed as the wall pipe joint;

对穿楼板管节进行防水及保温处理时,在穿楼板管节外侧同轴套装一个第一钢套管,并在第一钢套管与穿楼板管节之间设置第一保温层;所述楼板上开有供第一钢套管安装的钢管安装孔,所述第一钢套管的底端与楼板的底面相平齐且其顶端高于楼板的上表面;所述第一钢套管的内外侧壁上均涂刷有一层防锈漆,所述第一保温层密封填充于第一钢套管与穿楼板管节之间,第一保温层以第一防水层为界分为上下两部分;When carrying out waterproof and heat preservation treatment on the pipe joint through the floor, a first steel sleeve is coaxially set outside the pipe joint through the floor, and a first insulation layer is set between the first steel sleeve and the pipe joint through the floor; There is a steel pipe installation hole for the installation of the first steel casing on the floor, the bottom end of the first steel casing is flush with the bottom surface of the floor and its top is higher than the upper surface of the floor; the first steel casing A layer of anti-rust paint is painted on the inner and outer walls of the building. The first insulation layer is sealed and filled between the first steel casing and the pipe joint through the floor. The first insulation layer is divided into upper and lower sections with the first waterproof layer as the boundary. two parts;

对穿墙管节进行防水及保温处理时,在穿墙管节外侧同轴套装一个第二钢套管,并在第二钢套管与穿墙管节之间设置第二保温层;所述墙体上开有供第二钢套管安装的钢管安装孔,所述第二钢套管的左右两端分别与墙体的左右侧壁相平齐;所述第二钢套管的内外侧壁上均涂刷有一层防锈漆,所述第二保温层密封填充于第二钢套管与穿墙管节之间,第二保温层以第二防水层为界分为左右两部分;When performing waterproof and heat preservation treatment on the wall-piercing pipe joint, a second steel sleeve is coaxially installed outside the wall-piercing pipe joint, and a second insulation layer is set between the second steel sleeve and the wall-piercing pipe joint; The wall is provided with a steel pipe installation hole for the installation of the second steel sleeve, and the left and right ends of the second steel sleeve are respectively flush with the left and right side walls of the wall; the inner and outer sides of the second steel sleeve A layer of anti-rust paint is painted on the walls, the second insulation layer is sealed and filled between the second steel casing and the wall pipe joint, and the second insulation layer is divided into left and right parts with the second waterproof layer as the boundary;

步骤202、外露管节防水及保温处理:对所述需安装管道中的所述外露管节进行防水及保温处理。Step 202, waterproofing and thermal insulation treatment of exposed pipe joints: performing waterproof and thermal insulation treatment on the exposed pipe joints in the pipeline to be installed.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤201中所述第一钢套管的外侧壁上焊接有第一防水翼板,所述第二钢套管的外侧壁上焊接有第二防水翼板,所述第一防水翼板和第二防水翼板均为圆环板。The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the outer wall of the first steel casing described in step 201 is welded with a first water-proof flap, and the outer wall of the second steel casing A second waterproof flap is welded on the top, and both the first waterproof flap and the second waterproof flap are circular ring plates.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤一中所述需安装管道为PVC管或金属管;当所述需安装管道为PVC管道时,步骤202中对所述外露管节进行防水及保温处理时,仅需在所述外露管节外侧包裹一层第三保温层即可;当所述需安装管道为金属管时,步骤202中对所述外露管节进行防水及保温处理时,先在所述外露管节的外侧壁上涂刷一层防锈漆,再在所述外露管节外侧包裹一层所述第三保温层;The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the pipeline to be installed in step 1 is a PVC pipe or a metal pipe; when the pipeline to be installed is a PVC pipeline, the pipeline in step 202 When the exposed pipe joints are subjected to waterproof and heat preservation treatment, it is only necessary to wrap a third insulation layer on the outside of the exposed pipe joints; During waterproofing and heat preservation treatment, firstly paint a layer of antirust paint on the outer wall of the exposed pipe joint, and then wrap a layer of the third heat insulation layer on the outer side of the exposed pipe joint;

所述需安装管道上外侧所设置的第一保温层、第二保温层和所述第三保温层均连接为一体。The first insulation layer, the second insulation layer and the third insulation layer arranged on the outer side of the pipeline to be installed are all connected as one.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤201中所述第一保温层为由填塞于第一钢套管与穿楼板管节之间的保温材料形成的保温层,所述第一防水层为由填塞于第一钢套管与穿楼板管节之间的防水材料形成的防水层;所述第二保温层为由填塞于第二钢套管与穿墙管节之间的保温材料形成的保温层,所述第二防水层为由填塞于第二钢套管与穿墙管节之间的防水材料形成的防水层。The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the first thermal insulation layer described in step 201 is a thermal insulation layer formed by thermal insulation materials stuffed between the first steel casing and the pipe joints passing through the floor , the first waterproof layer is a waterproof layer formed by filling the waterproof material between the first steel casing and the pipe joint through the floor; the second insulation layer is made of filling the second steel casing and the wall pipe The second waterproof layer is a waterproof layer formed by the waterproof material stuffed between the second steel casing and the wall-piercing pipe joints.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤201中对穿楼板管节进行防水及保温处理时,将第一钢套管同轴套装在穿楼板管节外侧后,用木楔将所套装第一钢套管临时固定于楼板上,再将所述防水材料填塞于第一钢套管与穿楼板管节之间并形成第一防水层,之后对第一钢套管与穿楼板管节的同心度进行调整,然后在第一防水层的上下侧分别填塞所述保温材料并形成第一保温层,最后用密封胶对第一钢套管顶端与穿楼板管节之间进行封堵;The waterproof and thermal insulation construction method for building water supply, drainage and heating engineering is characterized in that: in step 201, when waterproofing and thermal insulation treatment is carried out on the pipe joints passing through the floor, after the first steel sleeve is coaxially placed on the outside of the pipe joints passing through the floor, Use wooden wedges to temporarily fix the set first steel sleeve on the floor, and then fill the waterproof material between the first steel sleeve and the pipe joint through the floor to form the first waterproof layer, and then install the first steel sleeve Adjust the concentricity of the pipe and the pipe joint through the floor, then fill the insulation material on the upper and lower sides of the first waterproof layer respectively to form the first insulation layer, and finally seal the top of the first steel casing and the pipe joint through the floor with sealant block between

对穿楼板管节进行防水及保温处理时,将第二钢套管同轴套装在穿楼板管节外侧后,用木楔将所套装第二钢套管临时固定于墙体上,再将所述防水材料填塞于第二钢套管与穿墙管节之间并形成第二防水层,之后对第二钢套管与穿墙管节的同心度进行调整,然后在第二防水层的左右侧分别填塞所述保温材料并形成第二保温层,最后用防火胶泥对第二钢套管的左右两端进行收口。When carrying out waterproof and heat preservation treatment on the pipe joint through the floor, after the second steel sleeve is coaxially set on the outside of the pipe joint through the floor, the second steel sleeve is temporarily fixed on the wall with a wooden wedge, and then the second steel sleeve is fixed on the wall The above-mentioned waterproof material is filled between the second steel casing and the wall-piercing pipe joint to form a second waterproof layer, and then the concentricity of the second steel casing and the wall-piercing pipe joint is adjusted, and then around the second waterproof layer Fill the insulation material on the sides respectively to form a second insulation layer, and finally close the left and right ends of the second steel casing with fireproof mortar.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤201中所述的第一保温层为由粘接固定在穿楼板管节外侧且由橡塑保温板弯曲形成的保温套筒,所述第二保温层为由粘接固定在穿墙管节外侧且由橡塑保温板弯曲形成的保温套筒。The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the first thermal insulation layer described in step 201 is a thermal insulation cover that is fixed on the outside of the pipe joint that passes through the floor and is formed by bending a rubber-plastic thermal insulation board The second insulation layer is an insulation sleeve fixed on the outside of the wall-piercing pipe joint and bent by a rubber-plastic insulation board.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤一中所述需安装管道通过支吊架进行支承或悬吊,步骤202中对所述外露管节进行防水及保温处理后,还需在所述支吊架布设位置处布设一个对外露管节保温套筒进行进行限位固定的限位件,所述限位件上设置有圆形通孔,所述圆形通孔的孔径与外露管节保温套筒的外径一致,外露管节保温套筒通过粘接胶粘贴固定在所述限位件上;所述限位件通过卡箍紧固固定在对所述需安装管道进行支承的管道支架或对所述需安装管道进行悬吊的管道吊架上;所述限位件为木托或高密度聚氨酯管托;所述木托和所述高密度聚氨酯管托的厚度均不小于外露管节保温套筒的壁厚;所述外露管节保温套筒夹装于所述需安装管道和所述限位件之间。The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the pipelines to be installed in step 1 are supported or suspended by support hangers; Finally, it is also necessary to arrange a limiter at the position where the support and hanger is arranged to limit and fix the heat preservation sleeve of the exposed pipe joint. The limiter is provided with a circular through hole, and the circular through hole The aperture of the hole is consistent with the outer diameter of the exposed pipe joint insulation sleeve, and the exposed pipe joint insulation sleeve is pasted and fixed on the limit piece by adhesive; The pipe bracket that needs to be installed to support the pipe or the pipe hanger that suspends the pipe that needs to be installed; the spacer is a wooden support or a high-density polyurethane pipe support; the wooden support and the high-density polyurethane The thickness of the pipe support is not less than the wall thickness of the exposed pipe joint insulation sleeve; the exposed pipe joint insulation sleeve is sandwiched between the pipe to be installed and the limiting member.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤一中所述需安装管道由多个平直管道由前至后拼装而成,相邻两个平直管道之间通过管道连接弯头进行连接;步骤202中所述第三保温层为由粘接固定在所述外露管节外侧且由橡塑保温板弯曲形成的外露管节保温套筒;步骤202中对所述外露管节进行防水及保温处理时,需对所述平直管道和管道连接弯头均进行防水及保温处理;所述管道连接弯头为PVC弯头或金属弯头;The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the pipeline to be installed in step 1 is assembled from a plurality of straight pipelines from front to back, and the two adjacent straight pipelines pass through The pipe is connected with an elbow; the third insulation layer in step 202 is an exposed pipe section insulation sleeve formed by bonding and fixing on the outside of the exposed pipe section and bent by a rubber-plastic insulation board; in step 202, the When the exposed pipe joints are treated for waterproofing and heat preservation, it is necessary to carry out waterproof and heat preservation treatment for the straight pipe and the pipe connecting elbow; the pipe connecting elbow is a PVC elbow or a metal elbow;

当所述管道连接弯头为PVC弯头时,步骤202中对管道连接弯头进行防水及保温处理时,仅需在管道连接弯头外侧包裹一层第一保温套筒即可;当管道连接弯头为金属弯头时,步骤202中对管道连接弯头进行防水及保温处理时,先在管道连接弯头的外侧壁上涂刷一层防锈漆,再在管道连接弯头外侧包裹一层所述第一保温套筒;When the pipeline connection elbow is a PVC elbow, when the pipeline connection elbow is waterproofed and heat-insulated in step 202, it is only necessary to wrap a layer of first insulation sleeve on the outside of the pipeline connection elbow; When the elbow is a metal elbow, in step 202, when waterproofing and insulating the pipe connecting elbow, first paint a layer of anti-rust paint on the outer wall of the pipe connecting elbow, and then wrap a layer of antirust paint on the outside of the pipe connecting elbow. Layer the first insulation sleeve;

所述第一保温套筒通过粘接胶粘贴固定在管道连接弯头的外侧壁上,所述第一保温套筒由一块第一橡塑保温板粘接而成;所述第一橡塑保温板的形状为长方形,所述第一橡塑保温板的宽度D=π×d2,且所述第一橡塑保温板的长度L=L1+2×d1,其中L1为管道连接弯头的外弧长度,d1不小于10mm,d2为管道连接弯头的外径;所述第一橡塑保温板由外至内包装在管道连接弯头外侧,所述第一橡塑保温板的接缝位于管道连接弯头的内侧;所述第一橡塑保温板的板厚为20mm~30mm。The first thermal insulation sleeve is pasted and fixed on the outer wall of the pipe connection elbow by adhesive glue, and the first thermal insulation sleeve is formed by bonding a first rubber-plastic thermal insulation board; the first rubber-plastic thermal insulation The shape of the insulation board is rectangular, the width of the first rubber and plastic insulation board is D=π×d2, and the length of the first rubber and plastic insulation board is L=L1+2×d1, where L1 is the length of the pipe connecting elbow The length of the outer arc, d1 is not less than 10mm, and d2 is the outer diameter of the pipe connecting elbow; the first rubber and plastic insulation board is packaged on the outside of the pipe connecting elbow from outside to inside, and the seam of the first rubber and plastic insulation board It is located on the inner side of the pipe connecting elbow; the thickness of the first rubber-plastic insulation board is 20mm-30mm.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:所述第一保温套筒外侧还设置有连接弯头保温层保护壳,所述连接弯头保温层保护壳包括套装在第一保温套筒外侧的虾米弯头;The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: the outer side of the first thermal insulation sleeve is also provided with a connecting elbow insulation layer protective shell, and the connecting elbow insulation layer protective shell includes A shrimp elbow on the outside of the insulation sleeve;

所述第一保温套筒的前端伸出管道连接弯头前端的宽度为d1,第一保温套筒的后端伸出管道连接弯头后端的宽度为d1,其中d1不小于10mm;所述虾米弯头的前端与第一保温套筒的前端相平齐,且所述虾米弯头的后端与第一保温套筒的后端相平齐;所述管道连接弯头连接于第一平直管道和第二平直管道之间,第一平直管道和第二平直管道呈垂直布设;所述虾米弯头由多个虾米节从前至后拼装而成,多个所述虾米节的节数不小于4个,且当管道连接弯头的口径越大,多个所述虾米节的节数越多。The width of the front end of the first insulation sleeve protruding from the front end of the pipe connection elbow is d1, and the width of the rear end of the first heat insulation sleeve protruding from the rear end of the pipe connection elbow is d1, wherein d1 is not less than 10mm; The front end of the elbow is flush with the front end of the first insulation sleeve, and the rear end of the shrimp elbow is flush with the rear end of the first insulation sleeve; the pipe connecting elbow is connected to the first straight Between the pipeline and the second straight pipeline, the first straight pipeline and the second straight pipeline are arranged vertically; the shrimp elbow is assembled from a plurality of shrimp joints from front to back, and the joints of the multiple shrimp joints The number is not less than 4, and when the caliber of the pipe connecting elbow is larger, the number of multiple shrimp joints is more.

上述建筑给排水及采暖工程用防水与保温施工方法,其特征是:步骤202中对所述外露管节上所安装的阀门进行保温处理时,采用粘接固定在阀门外侧且由第四橡塑保温板弯曲形成的第四保温套筒对阀门进行保温处理,所述第四保温套筒与阀门之间的间隙通过橡胶填料进行密封填充;所述第四保温套筒外侧套装阀门保温层保护壳对第四保温套筒进行保护;所述外露管节中的平直管道上所设置的第三保温层外侧套装有圆筒状保温层保护壳;所述外露管节上所安装的所述连接弯头保温层保护壳、所述圆筒状保温层保护壳和阀门保温层保护壳均连接为一体。The waterproof and thermal insulation construction method for building water supply and drainage and heating engineering is characterized in that: when performing thermal insulation treatment on the valve installed on the exposed pipe joint in step 202, it is fixed on the outside of the valve by bonding and is made of a fourth rubber and plastic The fourth insulation sleeve formed by bending the insulation board insulates the valve, and the gap between the fourth insulation sleeve and the valve is sealed and filled with rubber packing; the outer side of the fourth insulation sleeve is fitted with a valve insulation layer protection shell Protect the fourth insulation sleeve; the outer side of the third insulation layer set on the straight pipe in the exposed pipe joint is covered with a cylindrical insulation layer protective shell; the connection installed on the exposed pipe joint The elbow insulation layer protection shell, the cylindrical insulation layer protection shell and the valve insulation layer protection shell are all connected as one.

本发明与现有技术相比具有以下优点:Compared with the prior art, the present invention has the following advantages:

1、施工方法步骤简单、设计合理且操作简便、实现方便,投入施工成本较低。1. The steps of the construction method are simple, the design is reasonable, the operation is simple, the realization is convenient, and the construction cost is relatively low.

2、施工方法简单、操作简易且实现方便,施工工效高且劳动强度低,省时省力。2. The construction method is simple, the operation is simple and the realization is convenient, the construction efficiency is high and the labor intensity is low, saving time and effort.

3、采用采用卫生器具地脚螺栓的防水防腐方法简单、实现方便且施工质量易于保证、施工效果好,能简便、快速且高质量完成地脚螺栓防水防腐施工,并且地脚螺栓防水防腐效果好,能有效保证所安装卫生器具的稳固性,地脚螺栓防水防腐效果好。3. The waterproof and anti-corrosion method using the anchor bolts of sanitary appliances is simple, convenient to implement, easy to guarantee the construction quality, and has good construction effects. The waterproof and anti-corrosion construction of the anchor bolts can be completed simply, quickly and with high quality, and the waterproof and anti-corrosion effect of the anchor bolts is good , can effectively ensure the stability of the installed sanitary appliances, and the anchor bolts have good waterproof and anti-corrosion effects.

4、穿楼板管节与穿墙管节的防水与保温方法简单、实现方便且施工质量易于保证、施工效果好,保温效果高且耐久性强,同时拆装及更换简便。4. The waterproof and heat preservation method of the floor pipe joint and the wall pipe joint is simple, convenient to realize, easy to guarantee the construction quality, good construction effect, high heat preservation effect and strong durability, and easy to disassemble and replace.

5、管道连接弯头的保温处理方法简单、设计合理、操作简易且实现方便、投入成本较低,能简便、快速且高质量完成,并且外形美观、粘贴固定牢固、不易开裂,保温效果好。5. The heat preservation treatment method of the pipe connection elbow is simple, reasonable in design, easy to operate and easy to implement, low in investment cost, simple, fast and high-quality to complete, and has a beautiful appearance, firm paste and fixation, not easy to crack, and good heat preservation effect.

6、管道连接弯头保温层保护壳的结构简单、设计合理且加工制作简便、投入成本较低,并且拆装简便,实际组装方便,使用效果好,能对管道连接弯头保温层进行有效保护,使得管道连接弯头不易开裂,从而大幅度提高了管道连接弯头的保温效果。6. The protective shell of the pipe connection elbow insulation layer has simple structure, reasonable design, easy processing and production, low investment cost, easy disassembly and assembly, convenient actual assembly, good use effect, and can effectively protect the pipe connection elbow insulation layer , so that the pipe connecting elbow is not easy to crack, thus greatly improving the insulation effect of the pipe connecting elbow.

7、所采用阀门阀门保温层和阀门保温层保护壳的结构简单、设计合理且加工制作简便、投入成本较低,并且拆装简便,实际组装方便,使用效果好,通过阀门保温层保护壳对管道阀门保温层进行有效保护,大幅度提高了管道阀门的保温效果。7. The valve insulation layer and valve insulation layer protective shell adopted have simple structure, reasonable design, easy processing and production, low input cost, easy disassembly and assembly, convenient actual assembly, and good use effect. The insulation layer of pipeline valves is effectively protected, which greatly improves the insulation effect of pipeline valves.

8、需安装管道中穿楼板管节、穿墙管节与外露管节的保温层均连接为一体,因而大幅度提高了管道保温效果,并且穿楼板管节、穿墙管节与外露管节外侧所设置保温层外侧均设置有保温层保护层,能进一步大幅度提高管道的整体保温效果。8. It is necessary to install the insulation layer of the floor pipe joint, wall pipe joint and exposed pipe joint in the pipeline, which greatly improves the insulation effect of the pipeline, and the floor pipe joint, wall pipe joint and exposed pipe joint The outside of the insulation layer provided on the outside is provided with an insulation layer protection layer, which can further greatly improve the overall insulation effect of the pipeline.

9、需安装管道支吊架布设位置处的保温结构简单、设计合理、投入成本较低且保温施工方法简单、操作简易、实现方便,能简便、快速且高质量完成管道支吊架布设位置处的保温施工过程,由于保温筒的外侧壁与限位件紧密连接,能有效避免冷桥,因而施工完成后管道支吊架位置处的保温结构外形美观、不易出现冷桥现象且保温效果好。9. The insulation structure at the position where the pipeline support and hanger is to be installed is simple, reasonable in design, low in investment cost, and the insulation construction method is simple, easy to operate, and convenient to implement. During the thermal insulation construction process, since the outer wall of the thermal insulation cylinder is closely connected with the limit parts, cold bridges can be effectively avoided. Therefore, after the construction is completed, the thermal insulation structure at the position of the pipe support and hanger has a beautiful appearance, is not prone to cold bridges, and has a good thermal insulation effect.

综上所述,本发明方法步骤简单、设计合理、施工操作简便且施工进度快、施工效果好,能有效解决现有建筑给排水及采暖工程用防水与保温施工方法存在的施工操作不规范、施工效率较低、防水与保温效果较差等问题。To sum up, the method of the present invention has simple steps, reasonable design, convenient construction operation, fast construction progress and good construction effect, and can effectively solve the problems of non-standard construction operation and non-standard construction in the waterproof and thermal insulation construction methods of existing building water supply and drainage and heating engineering Low construction efficiency, poor waterproof and thermal insulation effects and other issues.

下面通过附图和实施例,对本发明的技术方案做进一步的详细描述。The technical solutions of the present invention will be described in further detail below with reference to the accompanying drawings and embodiments.

附图说明Description of drawings

图1为本发明的方法流程框图。Fig. 1 is a flow chart of the method of the present invention.

图2为本发明卫生器具地脚螺栓的防水防腐结构示意图。Fig. 2 is a schematic diagram of the waterproof and anti-corrosion structure of the anchor bolts of the sanitary ware according to the present invention.

图3为本发明穿楼板管节的防水及保温处理结构示意图。Fig. 3 is a schematic diagram of the waterproof and thermal insulation treatment structure of the pipe joint through the floor according to the present invention.

图4对本发明穿墙管节的防水及保温处理结构示意图。Fig. 4 is a schematic diagram of the waterproof and thermal insulation treatment structure of the wall-piercing pipe joint of the present invention.

图5为本发明支吊架布设位置处管道保温结构的结构示意图。Fig. 5 is a structural schematic diagram of the heat preservation structure of the pipeline at the location where the support and hanger are arranged according to the present invention.

图6为本发明管道连接弯头外侧包裹第一保温套筒的结构示意图。Fig. 6 is a schematic structural view of the outer side of the pipe connecting elbow wrapped with the first thermal insulation sleeve according to the present invention.

图7为本发明连接弯头保温层保护壳的结构示意图。Fig. 7 is a structural schematic diagram of the protection shell of the connecting elbow insulation layer of the present invention.

图8为本发明阀门保温层保护壳的结构示意图。Fig. 8 is a schematic structural view of the protective shell of the valve insulation layer of the present invention.

图9对本发明穿墙管节采用保温套筒进行保温处理时的结构示意图。Fig. 9 is a schematic structural view of the wall-piercing pipe joint of the present invention when heat-insulating sleeves are used for heat-insulation treatment.

附图标记说明:Explanation of reference signs:

1-1—穿楼板管节;   1-2—穿墙管节;        1-3—外露管节;1-1—pipe joint through floor; 1-2—pipe joint through wall; 1-3—exposed pipe joint;

2—墙体;           3—楼板;              4-1—第一钢套管;2—Wall; 3—Floor; 4-1—The first steel casing;

4-2—第二钢套管;   5-1—第一保温层;      5-2—第二保温层;4-2—the second steel casing; 5-1—the first insulation layer; 5-2—the second insulation layer;

6-1—第一防水层;   6-2—第二防水层;      7-1—地脚螺栓;6-1—the first waterproof layer; 6-2—the second waterproof layer; 7-1—anchor bolts;

7-2—外套管;       7-4—安装底座;        7-5—螺母;7-2—Outer casing; 7-4—Installation base; 7-5—Nut;

7-6—黄油;         8-1—第一保温套筒;    8-2—管道连接弯头;7-6—butter; 8-1—the first insulation sleeve; 8-2—pipeline connection elbow;

8-3—第一平直管道; 8-4—第二平直管道;    8-5—第二保温套筒;8-3—the first straight pipe; 8-4—the second straight pipe; 8-5—the second insulation sleeve;

8-6—第三保温套筒; 9-2—外露管节保温套筒;9-3—木托;8-6—the third insulation sleeve; 9-2—exposed pipe joint insulation sleeve; 9-3—wooden support;

9-4—U形卡箍;      9-5-1—下托板一;      9-5-2—吊杆;9-4—U-shaped clamp; 9-5-1—lower support plate 1; 9-5-2—suspension rod;

9-6—连接螺栓;     10—虾米节;9-6—Connecting bolts; 10—Shrimp section;

11-1—第一防水翼板;11-2—第二防水翼板;   12—阀门;11-1—the first waterproof flap; 11-2—the second waterproof flap; 12—valve;

13—第四保温套筒;  14—阀门保温层保护壳; 15—橡胶填料。13—the fourth insulation sleeve; 14—protective shell of valve insulation layer; 15—rubber packing.

具体实施方式detailed description

实施例1Example 1

如图1所示的一种建筑给排水及采暖工程用防水与保温施工方法,包括以下步骤:A kind of building water supply and drainage and heating engineering as shown in Figure 1 are used waterproof and thermal insulation construction method, comprises the following steps:

步骤一、建筑给排水及采暖工程管道与卫生器具安装:对所施工建筑内需安装管道分别进行安装,所述需安装管道为给排水管道或采暖管道,所述给排水管道与所施工建筑内所安装的卫生器具相接。Step 1. Installation of building water supply and drainage and heating engineering pipelines and sanitary appliances: install the pipelines that need to be installed in the building under construction respectively. The pipelines to be installed are water supply and drainage pipelines or heating pipelines. The installed sanitary fixtures are connected.

对所述需安装管道进行安装的同时,还需对所述卫生器具进行安装。所述卫生器具通过地脚螺栓7-1固定安装在楼板3上,所述楼板3为现浇混凝土楼板,所述地脚螺栓7-1底部预埋在所述现浇混凝土楼板内。所述现浇混凝土楼板施工完成后,还需对地脚螺栓7-1进行防水防腐。如图2所示,对地脚螺栓7-1进行防水防腐时,先将所述卫生器具的安装底座7-4平放于所述现浇混凝土楼板上,并使得地脚螺栓7-1的螺栓杆由下至上自安装底座7-4上所开的螺栓安装孔穿出,再由上至下在地脚螺栓7-1上部同轴套装一个外套管7-2;所述外套管7-2的底部支撑在安装底座7-4上。所述地脚螺栓7-1的螺栓杆上安装有螺母7-5,所述螺母7-5位于安装底座7-4上且其布设在外套管7-2内。所述外套管7-2的顶端比地脚螺栓7-1的螺栓杆顶端高不小于5mm。所述外套管7-2内填充有黄油7-6,所填充黄油7-6的上表面与外套管7-2的顶端相平齐。While installing the pipes to be installed, the sanitary appliances also need to be installed. The sanitary appliance is fixedly installed on the floor 3 through anchor bolts 7-1, and the floor 3 is a cast-in-place concrete floor, and the bottom of the anchor bolts 7-1 is pre-buried in the cast-in-place concrete floor. After the construction of the cast-in-place concrete floor slab is completed, the anchor bolts 7-1 need to be waterproofed and anti-corrosion. As shown in Figure 2, when the anchor bolt 7-1 is waterproof and anticorrosion, the installation base 7-4 of the sanitary appliance is first placed flat on the cast-in-situ concrete floor, and the anchor bolt 7-1 is The bolt rod passes through the bolt installation hole opened on the installation base 7-4 from bottom to top, and then sets an outer casing 7-2 coaxially on the top of the anchor bolt 7-1 from top to bottom; the outer casing 7- The bottom of 2 is supported on the mounting base 7-4. A nut 7-5 is installed on the bolt shaft of the anchor bolt 7-1, and the nut 7-5 is located on the installation base 7-4 and arranged in the outer casing 7-2. The top of the outer sleeve 7-2 is not less than 5mm higher than the top of the bolt shank of the anchor bolt 7-1. The outer casing 7-2 is filled with butter 7-6, and the upper surface of the filled butter 7-6 is flush with the top of the outer casing 7-2.

本实施例中,所述外套管7-2为PVC套管。In this embodiment, the outer sleeve 7-2 is a PVC sleeve.

本实施例中,所述外套管7-2为圆管。In this embodiment, the outer sleeve 7-2 is a round tube.

实际使用时,所述外套管7-2也可以采用正多边形管。In actual use, the outer sleeve 7-2 may also be a regular polygonal tube.

本实施例中,所述外套管7-2的顶端比所述螺栓杆的顶端高5mm~10mm。实际使用时,也可以根据具体需要,对所述外套管7-2的高度进行相应调整。In this embodiment, the top end of the outer sleeve 7-2 is 5mm-10mm higher than the top end of the bolt rod. In actual use, the height of the outer sleeve 7-2 can also be adjusted accordingly according to specific needs.

本实施例中,所述螺母7-5为圆柱形螺母或正多边形螺母。In this embodiment, the nut 7-5 is a cylindrical nut or a regular polygonal nut.

本实施例中,所述圆管的内径比所述圆柱形螺母的外径或正多边形螺母的外接圆直径大2mm~3mm。In this embodiment, the inner diameter of the circular tube is 2 mm to 3 mm larger than the outer diameter of the cylindrical nut or the diameter of the circumscribed circle of the regular polygonal nut.

本实施例中,所述安装底座7-4上所安装地脚螺栓7-1的数量为多个,多个所述地脚螺栓7-1的顶端高度均相同,且多个所述地脚螺栓7-1上部所套装的外套管7-2的顶端均相平齐。In this embodiment, the number of anchor bolts 7-1 installed on the installation base 7-4 is multiple, and the top heights of the multiple anchor bolts 7-1 are the same, and the multiple anchor bolts 7-1 The tops of the outer casing 7-2 set on the top of the bolt 7-1 are all flush.

本实施例中,所述外套管7-2的壁厚为1mm~1.5mm。In this embodiment, the wall thickness of the outer sleeve 7-2 is 1mm˜1.5mm.

步骤二、管道防水及保温处理:对步骤一中所述需安装管道进行防水及保温处理;所述需安装管道中穿过楼板3的管道节段为穿楼板管节1-1,所述需安装管道中穿过墙体2的管道节段为穿墙管节1-2,所述需安装管道中位于墙体2与楼板3外侧的管道节段为外露管节1-3。对所述需安装管道进行防水及保温处理时,处理过程如下:Step 2. Pipeline waterproofing and heat preservation treatment: Waterproof and heat preservation treatment is carried out on the pipes to be installed as described in step 1; the pipe section passing through the floor 3 in the pipes to be installed is the pipe joint 1-1 through the floor, and the pipes to be installed are pipe joints 1-1. The pipe section passing through the wall 2 in the installation pipe is the wall-penetrating pipe section 1-2, and the pipe section outside the wall 2 and the floor 3 among the pipes to be installed is the exposed pipe section 1-3. When carrying out waterproof and heat preservation treatment on the pipelines to be installed, the treatment process is as follows:

步骤201、穿楼板管节与穿墙管节防水及保温处理:对所述需安装管道中的穿楼板管节1-1和管道节段为穿墙管节1-2分别进行防水及保温处理。Step 201. Waterproof and thermal insulation treatment of floor-through pipe joints and wall-penetration pipe joints: Waterproof and heat-insulation treatment is performed on the floor-through pipe joints 1-1 and the wall-penetration pipe joints 1-2 of the pipelines to be installed, respectively .

如图3所示,对穿楼板管节1-1进行防水及保温处理时,在穿楼板管节1-1外侧同轴套装一个第一钢套管4-1,并在第一钢套管4-1与穿楼板管节1-1之间设置第一保温层5-1。所述楼板3上开有供第一钢套管4-1安装的钢管安装孔,所述第一钢套管4-1的底端与楼板3的底面相平齐且其顶端高于楼板3的上表面。所述第一钢套管4-1的内外侧壁上均涂刷有一层防锈漆,所述第一保温层5-1密封填充于第一钢套管4-1与穿楼板管节1-1之间,第一保温层5-1以第一防水层6-1为界分为上下两部分。As shown in Figure 3, when waterproofing and heat-insulating treatment is carried out on the pipe joint 1-1 through the floor, a first steel sleeve 4-1 is coaxially installed on the outside of the pipe joint 1-1 through the floor, and the first steel sleeve The first insulation layer 5-1 is set between 4-1 and the pipe joint 1-1 through the floor. The floor 3 has a steel pipe installation hole for the installation of the first steel casing 4-1, the bottom of the first steel casing 4-1 is flush with the bottom of the floor 3 and its top is higher than the floor 3 of the upper surface. The inner and outer walls of the first steel casing 4-1 are coated with a layer of anti-rust paint, and the first thermal insulation layer 5-1 is sealed and filled in the first steel casing 4-1 and the floor-through pipe joint 1 Between -1, the first thermal insulation layer 5-1 is divided into upper and lower parts with the first waterproof layer 6-1 as the boundary.

如图4所示,对穿墙管节1-2进行防水及保温处理时,在穿墙管节1-2外侧同轴套装一个第二钢套管4-2,并在第二钢套管4-2与穿墙管节1-2之间设置第二保温层5-2。所述墙体2上开有供第二钢套管4-2安装的钢管安装孔,所述第二钢套管4-2的左右两端分别与墙体2的左右侧壁相平齐。所述第二钢套管4-2的内外侧壁上均涂刷有一层防锈漆,所述第二保温层5-2密封填充于第二钢套管4-2与穿墙管节1-2之间,第二保温层5-2以第二防水层6-2为界分为左右两部分。As shown in Figure 4, when performing waterproof and heat preservation treatment on the wall-piercing pipe joint 1-2, a second steel sleeve 4-2 is coaxially installed on the outside of the wall-piercing pipe joint 1-2, and the second steel sleeve A second insulation layer 5-2 is set between 4-2 and the wall-piercing pipe joint 1-2. The wall 2 is provided with a steel pipe installation hole for the second steel casing 4-2 to be installed, and the left and right ends of the second steel casing 4-2 are flush with the left and right side walls of the wall 2 respectively. The inner and outer walls of the second steel casing 4-2 are coated with a layer of anti-rust paint, and the second thermal insulation layer 5-2 is sealed and filled in the second steel casing 4-2 and the wall-piercing pipe joint 1 Between -2, the second thermal insulation layer 5-2 is divided into left and right parts with the second waterproof layer 6-2 as the boundary.

步骤202、外露管节防水及保温处理:对所述需安装管道中的外露管节1-3进行防水及保温处理。Step 202, waterproofing and thermal insulation treatment of exposed pipe joints: performing waterproof and thermal insulation treatment on the exposed pipe joints 1-3 in the pipeline to be installed.

本实施例中,步骤201中所述第一钢套管4-1的外侧壁上焊接有第一防水翼板11-1,所述第二钢套管4-2的外侧壁上焊接有第二防水翼板11-2,所述第一防水翼板11-1和第二防水翼板11-2均为圆环板。In this embodiment, the first waterproof flap 11-1 is welded on the outer wall of the first steel casing 4-1 in step 201, and the first waterproof flap 11-1 is welded on the outer wall of the second steel casing 4-2. Two waterproof wing plates 11-2, the first waterproof wing plate 11-1 and the second waterproof wing plate 11-2 are ring plates.

实际施工时,对于多水房间而言,所述第一钢套管4-1的外侧壁上必须焊接第一防水翼板11-1,并且第一防水翼板11-1处于楼板3的中部。相应地,对于多水房间而言,所述第二钢套管4-2的外侧壁上必须焊接第二防水翼板11-2,并且第二防水翼板11-2位于墙体2的中部。另外,对于所施工建筑内除多水房间之外的其它房间,所述第一钢套管4-1的外侧壁上也可以不焊接第一防水翼板11-1,相应地第二钢套管4-2的外侧壁上也可以不焊接第二防水翼板11-2。During actual construction, for a multi-water room, the first waterproof flap 11-1 must be welded on the outer wall of the first steel casing 4-1, and the first waterproof flap 11-1 is in the middle of the floor 3 . Correspondingly, for a multi-water room, the second waterproof flap 11-2 must be welded on the outer wall of the second steel casing 4-2, and the second waterproof flap 11-2 is located in the middle of the wall 2 . In addition, for other rooms in the building under construction except the multi-water room, the first waterproof wing plate 11-1 may not be welded on the outer wall of the first steel sleeve 4-1, and the second steel sleeve accordingly The second waterproof flap 11-2 may not be welded on the outer wall of the pipe 4-2.

本实施例中,所述第二防水翼板11-2的宽度为50mm。实际加工时,可以根据具体需要,对第一防水翼板11-1和第二防水翼板11-2的宽度进行相应调整。In this embodiment, the width of the second waterproof flap 11-2 is 50mm. During actual processing, the widths of the first waterproof flap 11-1 and the second waterproof flap 11-2 can be adjusted accordingly according to specific needs.

实际施工时,所述第一钢套管4-1的顶端高于楼板3的上表面20mm~50mm。本实施例中,对于多水房间而言,所述第一钢套管4-1的顶端高于楼板3的上表面50mm;对于所施工建筑内除多水房间之外的其它房间,所述第一钢套管4-1的顶端高于楼板3的上表面20mm~30mm。During actual construction, the top end of the first steel casing 4-1 is 20 mm to 50 mm higher than the upper surface of the floor 3 . In this embodiment, for the multi-water room, the top of the first steel casing 4-1 is 50mm higher than the upper surface of the floor 3; for other rooms in the constructed building except the multi-water room, the The top of the first steel casing 4-1 is 20mm-30mm higher than the upper surface of the floor 3.

本实施例中,步骤201中所述穿楼板管节1-1与其所穿楼板3呈垂直布设,所述穿墙管节1-2与其所穿墙体2呈垂直布设。In this embodiment, the floor-piercing pipe joint 1-1 in step 201 is arranged vertically to the floor 3 it passes through, and the wall-piercing pipe joint 1-2 is arranged vertically to the wall 2 it passes through.

实际施工时,步骤201中所述第一钢套管4-1与穿楼板管节1-1之间的间隙宽度为10mm~20mm,所述第一钢套管4-1的长度与楼板3的厚度大20mm~50mm;所述第二钢套管4-2与穿墙管节1-2之间的间隙宽度为10mm~20mm。本实施例中,所述第一钢套管4-1与穿楼板管节1-1之间的间隙宽度以及所述第二钢套管4-2与穿墙管节1-2之间的间隙宽度均为20mm。During actual construction, the width of the gap between the first steel casing 4-1 and the floor piercing pipe joint 1-1 in step 201 is 10 mm to 20 mm, and the length of the first steel casing 4-1 is the same as that of the floor 3 The thickness is 20mm-50mm larger; the gap width between the second steel casing 4-2 and the wall-piercing pipe joint 1-2 is 10mm-20mm. In this embodiment, the width of the gap between the first steel casing 4-1 and the floor-piercing pipe joint 1-1 and the gap width between the second steel casing 4-2 and the wall-piercing pipe joint 1-2 The gap width is 20mm.

实际施工时,步骤一中所述需安装管道为PVC管或金属管;当所述需安装管道为PVC管道时,步骤202中对所述外露管节1-3进行防水及保温处理时,仅需在所述外露管节1-3外侧包裹一层第三保温层即可;当所述需安装管道为金属管时,步骤202中对所述外露管节1-3进行防水及保温处理时,先在所述外露管节1-3的外侧壁上涂刷一层防锈漆,再在所述外露管节1-3外侧包裹一层所述第三保温层。During actual construction, the pipes to be installed in step 1 are PVC pipes or metal pipes; when the pipes to be installed are PVC pipes, in step 202, the exposed pipe joints 1-3 are treated with waterproofing and heat preservation, only It is necessary to wrap a layer of third insulation layer on the outside of the exposed pipe joint 1-3; when the pipe to be installed is a metal pipe, in step 202, the exposed pipe joint 1-3 is subjected to waterproof and heat preservation treatment First, paint a layer of anti-rust paint on the outer wall of the exposed pipe joint 1-3, and then wrap a layer of the third heat insulation layer on the outer side of the exposed pipe joint 1-3.

并且,所述需安装管道上外侧所设置的第一保温层5-1、第二保温层5-2和所述第三保温层均连接为一体。因而,所述需安装管道所设置的保温层连续布设,不仅施工简便、外形美观,而且保温效果好。Moreover, the first insulation layer 5-1, the second insulation layer 5-2 and the third insulation layer arranged on the upper and outer sides of the pipeline to be installed are all connected as one. Therefore, the continuous laying of the thermal insulation layers for the pipelines to be installed not only facilitates the construction, but also has a beautiful appearance and good thermal insulation effect.

本实施例中,步骤201中所述的第一保温层5-1为由填塞于第一钢套管4-1与穿楼板管节1-1之间的保温材料形成的保温层,所述第一防水层6-1为由填塞于第一钢套管4-1与穿楼板管节1-1之间的防水材料形成的防水层。所述第二保温层5-2为由填塞于第二钢套管4-2与穿墙管节1-2之间的保温材料形成的保温层,所述第二防水层6-2为由填塞于第二钢套管4-2与穿墙管节1-2之间的防水材料形成的防水层。In this embodiment, the first insulation layer 5-1 described in step 201 is an insulation layer formed by the insulation material stuffed between the first steel casing 4-1 and the pipe joint 1-1 through the floor. The first waterproof layer 6-1 is a waterproof layer formed by waterproof material stuffed between the first steel casing 4-1 and the floor-piercing pipe joint 1-1. The second thermal insulation layer 5-2 is a thermal insulation layer filled between the second steel casing 4-2 and the thermal insulation material between the wall pipe joint 1-2, and the second waterproof layer 6-2 is made of The waterproof layer formed by the waterproof material filled between the second steel casing 4-2 and the wall-piercing pipe joint 1-2.

本实施例中,所述保温材料为石棉绳,所述防水材料为油麻。In this embodiment, the thermal insulation material is asbestos rope, and the waterproof material is linseed.

实际施工时,也可以采用其它保温材料和防水材料。In actual construction, other thermal insulation materials and waterproof materials can also be used.

步骤201中对穿楼板管节1-1进行防水及保温处理时,将第一钢套管4-1同轴套装在穿楼板管节1-1外侧后,用木楔将所套装第一钢套管4-1临时固定于楼板3上,再将所述防水材料填塞于第一钢套管4-1与穿楼板管节1-1之间并形成第一防水层6-1,之后对第一钢套管4-1与穿楼板管节1-1的同心度进行调整,然后在第一防水层6-1的上下侧分别填塞所述保温材料并形成第一保温层5-1,最后用密封胶对第一钢套管4-1顶端与穿楼板管节1-1之间进行封堵。In step 201, when the waterproof and heat preservation treatment is performed on the floor-through pipe joint 1-1, the first steel sleeve 4-1 is coaxially fitted on the outside of the floor-through pipe joint 1-1, and the first steel sleeve 4-1 is fitted with a wooden wedge. The sleeve 4-1 is temporarily fixed on the floor 3, and then the waterproof material is filled between the first steel sleeve 4-1 and the pipe joint 1-1 through the floor to form the first waterproof layer 6-1, and then the Adjust the concentricity between the first steel casing 4-1 and the pipe joint 1-1 through the floor, and then fill the upper and lower sides of the first waterproof layer 6-1 with the thermal insulation material to form the first thermal insulation layer 5-1, Finally, sealant is used to seal the space between the top of the first steel casing 4-1 and the pipe joint 1-1 through the floor.

本实施例中,用捻凿将油麻填塞于第一钢套管4-1与穿楼板管节1-1之间,并且所述第一防水层6-1位于所述第一钢套管4-1的中下部,所述第一防水层6-1与第一钢套管4-1顶端的距离为第一钢套管4-1高度的2/3。In this embodiment, twisting chisel is used to fill the oil hemp between the first steel casing 4-1 and the floor-through pipe joint 1-1, and the first waterproof layer 6-1 is located in the first steel casing 4-1, the distance between the first waterproof layer 6-1 and the top of the first steel casing 4-1 is 2/3 of the height of the first steel casing 4-1.

实际施工时,所述第一钢套管4-1与楼板3之间的间隙通过混凝土进行封堵。待第一防水层6-1与第一保温层5-1均施工完成后,所述第一钢套管4-1顶部打密封胶密封,密封胶要求与第一钢套管4-1顶端平齐,胶缝要求均匀,第一钢套管4-1的底部安装饰圈。当设计有阻火圈时,还需在第一钢套管4-1底部加阻火圈。During actual construction, the gap between the first steel casing 4-1 and the floor 3 is blocked with concrete. After the construction of the first waterproof layer 6-1 and the first insulation layer 5-1 is completed, the top of the first steel casing 4-1 is sealed with sealant, and the sealant is required to be the same as the top of the first steel casing 4-1. Flush, the glue seam is required to be uniform, and the bottom of the first steel casing 4-1 is installed with a decorative ring. When a fire arresting ring is designed, it is also necessary to add a fire arresting ring at the bottom of the first steel casing 4-1.

对穿楼板管节1-1进行防水及保温处理时,将第二钢套管4-2同轴套装在穿楼板管节1-1外侧后,用木楔将所套装第二钢套管4-2临时固定于墙体2上,再将所述防水材料填塞于第二钢套管4-2与穿墙管节1-2之间并形成第二防水层6-2,之后对第二钢套管4-2与穿墙管节1-2的同心度进行调整,然后在第二防水层6-2的左右侧分别填塞所述保温材料并形成第二保温层5-2,最后用防火胶泥对第二钢套管4-2的左右两端进行收口。When carrying out waterproof and heat preservation treatment on the pipe joint 1-1 through the floor, the second steel sleeve 4-2 is coaxially set on the outside of the pipe joint 1-1 through the floor, and the second steel sleeve 4-2 is fitted with a wooden wedge. -2 is temporarily fixed on the wall 2, and then the waterproof material is filled between the second steel casing 4-2 and the wall pipe joint 1-2 to form the second waterproof layer 6-2, and then the second Adjust the concentricity between the steel casing 4-2 and the wall-piercing pipe joint 1-2, then fill the left and right sides of the second waterproof layer 6-2 with the thermal insulation material to form the second thermal insulation layer 5-2, and finally use The fireproof mortar closes the left and right ends of the second steel casing 4-2.

本实施例中,步骤202中所述第三保温层为由粘接固定在所述外露管节1-3外侧且由橡塑保温板弯曲形成的外露管节保温套筒9-2。In this embodiment, the third insulation layer in step 202 is the exposed pipe section insulation sleeve 9-2 which is fixed on the outer side of the exposed pipe section 1-3 and formed by bending a rubber-plastic insulation board.

如图5所示,步骤一中所述需安装管道通过支吊架进行支承或悬吊,步骤202中对所述外露管节1-3进行防水及保温处理后,还需在所述支吊架布设位置处布设一个对外露管节保温套筒9-2进行进行限位固定的限位件,所述限位件上设置有圆形通孔,所述圆形通孔的孔径与外露管节保温套筒9-2的外径一致,外露管节保温套筒9-2通过粘接胶粘贴固定在所述限位件上。所述限位件通过卡箍紧固固定在对所述需安装管道进行支承的管道支架或对所述需安装管道进行悬吊的管道吊架上。所述限位件为木托9-3或高密度聚氨酯管托。所述木托9-3和所述高密度聚氨酯管托的厚度均不小于外露管节保温套筒9-2的壁厚;所述外露管节保温套筒9-2夹装于所述需安装管道和所述限位件之间。As shown in Figure 5, in step 1, the pipeline needs to be installed to be supported or suspended by the support and hanger. A spacer for limiting and fixing the exposed pipe joint insulation sleeve 9-2 is arranged at the position where the frame is arranged. The outer diameters of the joint heat preservation sleeves 9-2 are consistent, and the exposed pipe joint heat preservation sleeves 9-2 are pasted and fixed on the position-limiting parts by bonding glue. The limiting member is fastened and fixed on the pipe support for supporting the pipe to be installed or the pipe hanger for suspending the pipe to be installed by clamps. The limiter is a wooden bracket 9-3 or a high-density polyurethane tube bracket. The thickness of the wooden support 9-3 and the high-density polyurethane pipe support are not less than the wall thickness of the exposed pipe joint insulation sleeve 9-2; the exposed pipe joint insulation sleeve 9-2 is clamped on the required Install between the pipe and the stopper.

本实施例中,所述圆形通孔布设在所述限位件的纵向中心线上。In this embodiment, the circular through hole is arranged on the longitudinal centerline of the limiting member.

本实施例中,所述卡箍为U形卡箍9-4,所述U形卡箍9-4包括半圆形节段和两个分别连接在所述半圆形节段一左右两端下方的直线形节段组成,两个所述直线形节段呈平行布设且二者之间的间距与所述半圆形节段的直径相同。所述管道吊架包括下托板一9-5-1和安装在下托板一9-5-1上的吊杆9-5-2,所述管道支架包括下托板二和安装在所述下托板二上的支撑件,所述支撑件位于所述下托板二下方。两个所述直线形节段均通过可拆卸连接件固定在下托板一9-5-1或所述下托板二上。所述限位件固定于U形卡箍9-4与下托板一9-5-1或所述下托板二之间。In this embodiment, the clamp is a U-shaped clamp 9-4, and the U-shaped clamp 9-4 includes a semicircular segment and two segments respectively connected to the left and right ends of the semicircular segment. The lower linear segment is composed of two linear segments arranged in parallel and the distance between them is the same as the diameter of the semicircular segment. The pipeline hanger includes a lower supporting plate 9-5-1 and a suspension rod 9-5-2 installed on the lower supporting plate 9-5-1, and the pipeline support includes a lower supporting plate 2 and a suspension rod installed on the lower supporting plate 9-5-1. The supporting member on the second lower supporting board, the supporting member is located below the second lower supporting board. The two linear segments are fixed on the first lower support plate 9-5-1 or the second lower support plate through detachable connectors. The limiting member is fixed between the U-shaped clamp 9-4 and the first lower supporting plate 9-5-1 or the second lower supporting plate.

本实施例中,所述限位件也可以通过卡箍紧固固定在对所述需安装管道进行支承的管道吊架上。两个所述直线形节段均通过可拆卸连接件固定在下托板一9-5-1上。所述限位件固定于U形卡箍9-4与下托板一9-5-1之间。In this embodiment, the limiting member may also be fastened and fixed on the pipe hanger supporting the pipe to be installed through a clamp. The two linear segments are all fixed on the lower supporting plate 9-5-1 through detachable connectors. The limiter is fixed between the U-shaped clamp 9-4 and the lower supporting plate 9-5-1.

实际使用时,所述限位件也可以通过卡箍紧固固定在对所述需安装管道进行支承的管道支架上。两个所述直线形节段均通过可拆卸连接件固定在所述下托板二上。所述限位件固定于U形卡箍4与所述下托板二之间。In actual use, the limiting member may also be fastened and fixed on the pipe support supporting the pipe to be installed by a clamp. The two straight segments are fixed on the second lower support plate through detachable connectors. The limiting member is fixed between the U-shaped clamp 4 and the second lower supporting plate.

实际布设安装时,所述限位件与U形卡箍9-4布设在同一平面上。During actual layout and installation, the limiting member and the U-shaped clamp 9-4 are arranged on the same plane.

实际加工时,所述半圆形节段和两个所述直线形节段均为钢管或钢杆,两个所述直线形节段与所述半圆形节段加工制作为一体或分别焊接固定在所述半圆形节段的左右两端下方。During actual processing, the semicircular segment and the two linear segments are both steel pipes or steel rods, and the two linear segments and the semicircular segment are processed as one or welded separately fixed below the left and right ends of the semicircular segment.

本实施例中,所述可拆卸连接件为连接螺栓9-6,所述连接螺栓9-6的螺栓杆上部固定在所述直线形节段的下部外侧壁上,且下托板一9-5-1或所述下托板二上对应开有供所述螺栓杆穿过的螺栓安装孔,所述连接螺栓9-6的螺母三位于下托板一9-5-1或所述下托板二下方。In this embodiment, the detachable connector is a connecting bolt 9-6, the upper part of the bolt rod of the connecting bolt 9-6 is fixed on the lower outer side wall of the linear segment, and the lower supporting plate-9- 5-1 or the second lower supporting plate is correspondingly provided with a bolt installation hole for the bolt rod to pass through, and the nut three of the connecting bolt 9-6 is located on the lower supporting plate 9-5-1 or the lower supporting plate 9-5-1. Below the second pallet.

实际加工时,所述半圆形节段和两个所述直线形节段均为钢管或钢杆,两个所述直线形节段与所述半圆形节段加工制作为一体或分别焊接固定在所述半圆形节段的左右两端下方。During actual processing, the semicircular segment and the two linear segments are both steel pipes or steel rods, and the two linear segments and the semicircular segment are processed as one or welded separately fixed below the left and right ends of the semicircular segment.

本实施例中,所述半圆形节段和两个所述直线形节段均为扁钢,两个所述直线形节段与所述半圆形节段加工制作为一体。In this embodiment, the semicircular segment and the two linear segments are flat steel, and the two linear segments are processed as one with the semicircular segment.

本实施例中,步骤一中所述需安装管道由多个平直管道由前至后拼装而成,相邻两个平直管道之间通过管道连接弯头8-2进行连接,步骤202中对所述外露管节1-3进行防水及保温处理时,需对所述平直管道和管道连接弯头8-2均进行防水及保温处理;所述管道连接弯头8-2为PVC弯头或金属弯头。In this embodiment, the pipeline to be installed in step 1 is assembled from a plurality of straight pipelines from front to back, and two adjacent straight pipelines are connected by pipeline connecting elbow 8-2. In step 202 When performing waterproof and heat preservation treatment on the exposed pipe joint 1-3, it is necessary to perform waterproof and heat preservation treatment on the straight pipe and the pipe connection elbow 8-2; the pipe connection elbow 8-2 is a PVC bend head or metal elbow.

如图6所示,当所述管道连接弯头8-2为PVC弯头时,步骤202中对管道连接弯头8-2进行防水及保温处理时,仅需在管道连接弯头8-2外侧包裹一层第一保温套筒8-1即可;当管道连接弯头8-2为金属弯头时,步骤202中对管道连接弯头8-2进行防水及保温处理时,先在管道连接弯头8-2的外侧壁上涂刷一层防锈漆,再在管道连接弯头8-2外侧包裹一层所述第一保温套筒8-1。As shown in Figure 6, when the pipeline connection elbow 8-2 is a PVC elbow, when the pipeline connection elbow 8-2 is waterproofed and heat-insulated in step 202, only the pipeline connection elbow 8-2 needs to be sealed. It is sufficient to wrap a layer of the first thermal insulation sleeve 8-1 on the outside; when the pipeline connection elbow 8-2 is a metal elbow, in step 202, when the pipeline connection elbow 8-2 is waterproofed and heat-insulated, the Brush a layer of antirust paint on the outer wall of the connecting elbow 8-2, and then wrap a layer of the first insulation sleeve 8-1 on the outer side of the pipe connecting elbow 8-2.

所述第一保温套筒8-1通过粘接胶粘贴固定在管道连接弯头8-2的外侧壁上,所述第一保温套筒8-1由一块第一橡塑保温板粘接而成;所述第一橡塑保温板的形状为长方形,所述第一橡塑保温板的宽度D=π×d2,且所述第一橡塑保温板的长度L=L1+2×d1,其中L1为管道连接弯头8-2的外弧长度,d1不小于10mm,d2为管道连接弯头8-2的外径。所述第一橡塑保温板由外至内包装在管道连接弯头8-2外侧,所述第一橡塑保温板的接缝位于管道连接弯头8-2的内侧。所述第一橡塑保温板的板厚为20mm~30mm。所述管道连接弯头8-2的外径d2为管道连接弯头8-2的横截面外径。The first thermal insulation sleeve 8-1 is pasted and fixed on the outer wall of the pipeline connection elbow 8-2 by adhesive glue, and the first thermal insulation sleeve 8-1 is bonded by a first rubber-plastic thermal insulation board formed; the shape of the first rubber and plastic insulation board is rectangular, the width of the first rubber and plastic insulation board is D=π×d2, and the length of the first rubber and plastic insulation board is L=L1+2×d1 , where L1 is the length of the outer arc of the pipeline connection elbow 8-2, d1 is not less than 10 mm, and d2 is the outer diameter of the pipeline connection elbow 8-2. The first rubber and plastic insulation board is packaged on the outside of the pipeline connection elbow 8-2 from the outside to the inside, and the seam of the first rubber and plastic insulation board is located on the inside of the pipeline connection elbow 8-2. The thickness of the first rubber-plastic insulation board is 20mm-30mm. The outer diameter d2 of the pipe connecting elbow 8-2 is the cross-sectional outer diameter of the pipe connecting elbow 8-2.

本实施例中,所述第一橡塑保温板的板厚为20mm。In this embodiment, the thickness of the first rubber and plastic insulation board is 20mm.

本实施例中,所述管道连接弯头8-2连接于第一平直管道8-3和第二平直管道8-4之间,所述第一平直管道8-3和第二平直管道8-4的管径相同,所述第一平直管道8-3的后端与管道连接弯头8-2的一个连接端口相接,第二平直管道8-4的前端与管道连接弯头8-2的另一个端口相接;所述第一平直管道8-3上通过粘接胶粘贴固定有第二保温套筒8-5,所述第二保温套筒8-5由一块长方形的第二橡塑保温板粘接而成;所述第二保温套筒8-5上通过粘接胶粘贴固定有第三保温套筒8-6,所述第三保温套筒8-6由一块长方形的第三橡塑保温板粘接而成;所述第二保温套筒8-5的后端与第一保温套筒8-1的前端粘贴固定为一体,所述第三保温套筒8-6的前端与第一保温套筒8-1的后端粘贴固定为一体。所述第一橡塑保温板、所述第二橡塑保温板和所述第三橡塑保温板的板厚相同。In this embodiment, the pipe connecting elbow 8-2 is connected between the first straight pipe 8-3 and the second straight pipe 8-4, and the first straight pipe 8-3 and the second straight pipe The pipe diameters of the straight pipes 8-4 are the same, the rear end of the first straight pipe 8-3 is connected to a connection port of the pipe connecting elbow 8-2, and the front end of the second straight pipe 8-4 is connected to the pipe The other port of the connecting elbow 8-2 is connected; the first straight pipe 8-3 is pasted and fixed with a second thermal insulation sleeve 8-5 by adhesive glue, and the second thermal insulation sleeve 8- 5 is formed by bonding a rectangular second rubber-plastic insulation board; the second insulation sleeve 8-5 is pasted and fixed with a third insulation sleeve 8-6 by adhesive glue, and the third insulation sleeve The cylinder 8-6 is formed by bonding a rectangular third rubber-plastic insulation board; the rear end of the second insulation sleeve 8-5 is pasted and fixed together with the front end of the first insulation sleeve 8-1, and the The front end of the third insulation sleeve 8-6 is pasted and fixed as a whole with the rear end of the first insulation sleeve 8-1. The first rubber and plastic insulation board, the second rubber and plastic insulation board and the third rubber and plastic insulation board have the same thickness.

本实施例中,所述第一平直管道8-3和第二平直管道8-4的管径均与管道连接弯头8-2的外径d2相同,此处第一平直管道8-3和第二平直管道8-4的管径均为管道外径。In this embodiment, the pipe diameters of the first straight pipe 8-3 and the second straight pipe 8-4 are the same as the outer diameter d2 of the pipe connecting elbow 8-2, where the first straight pipe 8 The pipe diameters of -3 and the second straight pipe 8-4 are pipe outer diameters.

本实施例中,d1=10mm~15mm。In this embodiment, d1=10mm˜15mm.

实际加工时,可以根据具体需要,对d1的取值大小进行相应调整。During actual processing, the value of d1 can be adjusted accordingly according to specific needs.

本实施例中,所述第一橡塑保温板的接缝位于管道连接弯头8-2的内侧中部,且所述接缝与管道连接弯头8-2的轴向中心线呈平行布设。In this embodiment, the seam of the first rubber-plastic insulation board is located in the middle of the inner side of the pipe connecting elbow 8-2, and the seam is arranged parallel to the axial centerline of the pipe connecting elbow 8-2.

实际加工时,所述第一保温套筒8-1与第二保温套筒8-5和第三保温套筒8-6之间的接缝处均用粘接胶进行粘贴固定。也就是说,所述外露管节保温套筒9-2中的第一保温套筒8-1、第二保温套筒8-5和第三保温套筒8-6均连接为一体。During actual processing, the seams between the first thermal insulation sleeve 8-1, the second thermal insulation sleeve 8-5 and the third thermal insulation sleeve 8-6 are pasted and fixed with adhesive glue. That is to say, the first thermal insulation sleeve 8-1, the second thermal insulation sleeve 8-5 and the third thermal insulation sleeve 8-6 in the exposed pipe joint thermal insulation sleeve 9-2 are all connected as one.

如图7所示,所述第一保温套筒8-1外侧还设置有连接弯头保温层保护壳,所述连接弯头保温层保护壳包括套装在第一保温套筒8-1外侧的虾米弯头。As shown in Figure 7, the outer side of the first insulation sleeve 8-1 is also provided with a connecting elbow insulation layer protection shell, and the connection elbow insulation layer protection shell includes a sleeve on the outside of the first insulation sleeve 8-1 Shrimp elbow.

所述第一保温套筒8-1的前端伸出管道连接弯头8-2前端的宽度为d1,第一保温套筒8-1的后端伸出管道连接弯头8-2后端的宽度为d1,其中d1不小于10mm。所述虾米弯头的前端与第一保温套筒8-1的前端相平齐,且所述虾米弯头的后端与第一保温套筒8-1的后端相平齐。所述管道连接弯头8-2连接于第一平直管道8-3和第二平直管道8-4之间,第一平直管道8-3和第二平直管道8-4呈垂直布设。所述虾米弯头由多个虾米节10从前至后拼装而成,多个所述虾米节10的节数不小于4个,且当管道连接弯头8-2的口径越大,多个所述虾米节10的节数越多。The front end of the first thermal insulation sleeve 8-1 protrudes from the front end of the pipeline connection elbow 8-2, and the width of the front end is d1, and the rear end of the first thermal insulation sleeve 8-1 protrudes from the width of the rear end of the pipeline connection elbow 8-2. is d1, where d1 is not less than 10mm. The front end of the shrimp elbow is flush with the front end of the first insulation sleeve 8-1, and the rear end of the shrimp elbow is flush with the rear end of the first insulation sleeve 8-1. The pipe connecting elbow 8-2 is connected between the first straight pipe 8-3 and the second straight pipe 8-4, and the first straight pipe 8-3 and the second straight pipe 8-4 are vertical layout. The shrimp elbow is assembled from a plurality of shrimp joints 10 from front to back, the number of the multiple shrimp joints 10 is not less than 4, and when the diameter of the pipe connecting elbow 8-2 is larger, the plurality of shrimp joints 10 are not less than 4. The number of knots described in shrimp section 10 is more.

本实施例中,前后相邻两个所述虾米节10之间相互扣接。In this embodiment, two adjacent dried shrimp sections 10 are fastened to each other.

实际安装时,前后相邻两个所述虾米节10之间的接缝处通过沿圆周方向布设的多个紧固件进行紧固连接。During actual installation, the seams between two adjacent dried shrimp sections 10 are fastened and connected by a plurality of fasteners arranged along the circumferential direction.

本实施例中,多个所述紧固件呈均匀布设,所述紧固件为自攻螺丝或铆钉。具体安装时,可以根据具体需要对所述紧固件的数量和相邻两个所述紧固件之间的间距进行相应调整。In this embodiment, the plurality of fasteners are evenly arranged, and the fasteners are self-tapping screws or rivets. During specific installation, the number of the fasteners and the distance between two adjacent fasteners can be adjusted accordingly according to specific needs.

所述管道连接弯头8-2的口径为D1、D2、D3或D4,其中D1<150mm,150mm≤D2<250mm,250mm≤D2<300mm,且D4≥300mm;当管道连接弯头8-2的口径为D1时,多个所述虾米节10的节数为4个;当管道连接弯头8-2的口径为D2时,多个所述虾米节10的节数为8个或9个;当管道连接弯头8-2的口径为D3时,多个所述虾米节10的节数为11个;当管道连接弯头8-2的口径为D4时,多个所述虾米节10的节数为13个。The caliber of the pipe connecting elbow 8-2 is D1, D2, D3 or D4, wherein D1<150mm, 150mm≤D2<250mm, 250mm≤D2<300mm, and D4≥300mm; when the pipe connecting elbow 8-2 When the caliber is D1, the number of multiple shrimp joints 10 is 4; when the diameter of the pipe connecting elbow 8-2 is D2, the number of multiple shrimp joints 10 is 8 or 9 ; When the caliber of the pipe connecting elbow 8-2 is D3, the number of joints 10 of the multiple shrimp joints 10 is 11; when the caliber of the pipeline connecting elbow 8-2 is D4, the multiple shrimp joints 10 The number of sections is 13.

本实施例中,所述需保护管道连接弯头的口径为280mm,多个所述虾米节10的节数为8个。实际加工时,可以根据具体需要,对多个所述虾米节10的节数进行相应调整。In this embodiment, the caliber of the connecting elbow of the pipeline to be protected is 280 mm, and the number of the plurality of dried shrimp joints 10 is 8. During actual processing, the number of multiple dried shrimp joints 10 can be adjusted accordingly according to specific needs.

本实施例中,多个所述虾米节10均由平板弯曲而成,所述平板为镀锌钢板、彩钢板或铝板。In this embodiment, the plurality of dried shrimp joints 10 are bent from a flat plate, and the flat plate is galvanized steel plate, color steel plate or aluminum plate.

实际加工时,根据需保护管道连接弯头8-2的口径和所述第一橡塑保温板的板厚,确定所采用虾米节的节数和各虾米节的尺寸。实际组装时,所述虾米弯头中多个虾米节10要过渡自然、圆滑平顺,相邻两个所述虾米节10之间的接缝无折皱。During actual processing, according to the caliber of the connecting elbow 8-2 of the pipeline to be protected and the thickness of the first rubber-plastic insulation board, the number of joints of shrimp joints and the size of each shrimp joint are determined. During actual assembly, the plurality of shrimp joints 10 in the shrimp elbow should transition naturally, smoothly and smoothly, and the seams between two adjacent shrimp joints 10 should have no wrinkles.

实际施工时,如图8所示,对所述需安装管道的外露管节1-3上所安装的阀门12进行保温处理时,采用粘接固定在阀门12外侧且由第四橡塑保温板弯曲形成的第四保温套筒13对阀门12进行保温处理,所述第四保温套筒13与阀门12之间的间隙通过橡胶填料15进行密封填充。同时,在所述第四保温套筒13外侧套装阀门保温层保护壳14对第四保温套筒13进行保护,所述阀门保温层保护壳14由锌钢板、彩钢板或铝板加工而成。实际施工时,所述阀门保温层保护壳14与第四保温套筒13之间通过多个所述紧固件进行紧固连接。During actual construction, as shown in Figure 8, when the valve 12 installed on the exposed pipe joint 1-3 of the pipeline to be installed is heat-insulated, it is fixed on the outside of the valve 12 by bonding and the fourth rubber-plastic insulation board The bent fourth insulation sleeve 13 performs insulation treatment on the valve 12 , and the gap between the fourth insulation sleeve 13 and the valve 12 is sealed and filled with rubber packing 15 . At the same time, a valve insulation layer protection shell 14 is installed outside the fourth insulation sleeve 13 to protect the fourth insulation sleeve 13. The valve insulation layer protection shell 14 is made of zinc steel plate, color steel plate or aluminum plate. During actual construction, the valve insulation layer protection shell 14 and the fourth insulation sleeve 13 are fastened and connected by a plurality of fasteners.

本实施例中,所述外露管节1-3中的平直管道上所设置的第三保温层外侧套装有圆筒状保温层保护壳。所述外露管节1-3上所安装的所述连接弯头保温层保护壳、所述圆筒状保温层保护壳和阀门保温层保护壳14均连接为一体。In this embodiment, the outer side of the third insulation layer provided on the straight pipe in the exposed pipe section 1-3 is covered with a cylindrical insulation layer protection shell. The connecting elbow insulation layer protection shell, the cylindrical insulation layer protection shell and the valve insulation layer protection shell 14 installed on the exposed pipe joints 1-3 are all connected as one.

实施例2Example 2

本实施例中,与实施例1不同的是:步骤201中所述的第一保温层5-1为由粘接固定在穿楼板管节1-1外侧且由橡塑保温板弯曲形成的保温套筒,所述第二保温层5-2为由粘接固定在穿墙管节1-2外侧且由橡塑保温板弯曲形成的保温套筒,详见图9。In this embodiment, the difference from Embodiment 1 is that the first thermal insulation layer 5-1 described in step 201 is an thermal insulation layer formed by bonding and fixing on the outer side of the pipe joint 1-1 through the floor and formed by bending a rubber-plastic thermal insulation board. The sleeve, the second insulation layer 5-2 is an insulation sleeve fixed on the outside of the wall pipe joint 1-2 by bonding and bent by a rubber-plastic insulation board, see Figure 9 for details.

本实施例中,其余部分结构、连接关系和施工方法步骤均与实施例1相同。In this embodiment, the rest of the structure, connection relationship and construction method steps are the same as those in Embodiment 1.

以上所述,仅是本发明的较佳实施例,并非对本发明作任何限制,凡是根据本发明技术实质对以上实施例所作的任何简单修改、变更以及等效结构变化,均仍属于本发明技术方案的保护范围内。The above are only preferred embodiments of the present invention, and do not limit the present invention in any way. All simple modifications, changes and equivalent structural changes made to the above embodiments according to the technical essence of the present invention still belong to the technical aspects of the present invention. within the scope of protection of the scheme.

Claims (10)

1. a building water supply and drainage and heating engineering waterproofing and insulation construction method, is characterized in that the method comprises the following steps:
Step one, building water supply and drainage and heating engineering pipeline and sanitary apparatus are installed: install respectively institute's construction building domestic demand pipe laying, the described pipe laying that needs is water supply and sewerage pipeline or heating pipe, and described water supply and sewerage pipeline connects with the sanitary apparatus installed in institute construction building;
To described need pipe laying to install while, also need to install described sanitary apparatus; Described sanitary apparatus is fixedly mounted on floor (3) by stone bolt (7-1), described floor (3) is cast-in-place concrete floor, and described stone bolt (7-1) bottom is embedded in described cast-in-place concrete floor; After described cast-in-place concrete floor has been constructed, also need to carry out water-tight corrosion-proof to stone bolt (7-1); When water-tight corrosion-proof is carried out to stone bolt (7-1), first the mounting seat (7-4) of described sanitary apparatus is lain against on described cast-in-place concrete floor, and the bolt mounting holes making the shank of bolt of stone bolt (7-1) open in mounting seat (7-4) from the bottom to top passes, more from top to bottom stone bolt (7-1) top coaxial package outer tube (7-2); The bottom support of described outer tube (7-2) is in mounting seat (7-4); The shank of bolt of described stone bolt (7-1) is provided with nut (7-5), described nut (7-5) is positioned at that mounting seat (7-4) is upper and it is laid in outer tube (7-2); The top of described outer tube (7-2) is higher than the shank of bolt top of stone bolt (7-1) is not less than 5mm; Be filled with butter (7-6) in described outer tube (7-2), to fill the upper surface of butter (7-6) mutually concordant with the top of outer tube (7-2);
Step 2, pipeline waterproof and isothermal holding: carry out waterproof and isothermal holding to needing pipe laying described in step one; Described need in pipe laying through the duct segments of floor (3) is through-flooring tube coupling (1-1), described need in pipe laying through the duct segments of body of wall (2) is tube coupling through walls (1-2), and the described duct segments needing to be positioned in pipe laying body of wall (2) and floor (3) outside is for exposing tube coupling (1-3); To described need pipe laying to carry out waterproof and isothermal holding time, processing procedure is as follows:
Step 201, through-flooring tube coupling and tube coupling waterproof through walls and isothermal holding: be that tube coupling through walls (1-2) carries out waterproof and isothermal holding respectively to the described through-flooring tube coupling (1-1) in pipe laying and the duct segments of needing;
When waterproof and isothermal holding are carried out to through-flooring tube coupling (1-1), through-flooring tube coupling (1-1) outside coaxial package first steel sleeve (4-1), and the first insulation layer (5-1) is set between the first steel sleeve (4-1) and through-flooring tube coupling (1-1); Described floor (3) has for the first steel sleeve (4-1) the penstock installation hole of installing, and its top mutually concordant with the bottom surface of floor (3), the bottom of described first steel sleeve (4-1) is higher than the upper surface of floor (3); The outboard sidewalls of described first steel sleeve (4-1) is all coated with and is brushed with one deck rustproof paint, the sealing of described first insulation layer (5-1) is filled between the first steel sleeve (4-1) and through-flooring tube coupling (1-1), the first insulation layer (5-1) with the first waterproofing course (6-1) for boundary is divided into upper and lower two parts;
When waterproof and isothermal holding are carried out to tube coupling through walls (1-2), tube coupling through walls (1-2) outside coaxial package second steel sleeve (4-2), and the second insulation layer (5-2) is set between the second steel sleeve (4-2) and tube coupling through walls (1-2); Described body of wall (2) has the penstock installation hole of installing for the second steel sleeve (4-2), the two ends, left and right of described second steel sleeve (4-2) are equal together with the left and right sidewall of body of wall (2) respectively; The outboard sidewalls of described second steel sleeve (4-2) is all coated with and is brushed with one deck rustproof paint, the sealing of described second insulation layer (5-2) is filled between the second steel sleeve (4-2) and tube coupling through walls (1-2), the second insulation layer (5-2) with the second waterproofing course (6-2) for boundary is divided into left and right two parts;
Step 202, expose tube coupling waterproof and isothermal holding: need the tube coupling (1-3) that exposes in pipe laying to carry out waterproof and isothermal holding to described.
2. according to building water supply and drainage according to claim 1 and heating engineering waterproofing and insulation construction method, it is characterized in that: the lateral wall of the first steel sleeve described in step 201 (4-1) is welded with the first waterproof wing plate (11-1), the lateral wall of described second steel sleeve (4-2) is welded with the second waterproof wing plate (11-2), described first waterproof wing plate (11-1) and the second waterproof wing plate (11-2) are Circular Plate.
3. according to the building water supply and drainage described in claim 1 or 2 and heating engineering waterproofing and insulation construction method, it is characterized in that: described in step one, need pipe laying to be pvc pipe or metal tube; When described need pipe laying to be PVC pipeline time, in step 202 to described expose tube coupling (1-3) carry out waterproof and isothermal holding time, only need expose tube coupling (1-3) outside parcel one deck the 3rd insulation layer described; When described need pipe laying to be metal tube time, in step 202 to described expose tube coupling (1-3) carry out waterproof and isothermal holding time, first brushing one deck rustproof paint on the described lateral wall exposing tube coupling (1-3), then expose the 3rd insulation layer described in the parcel one deck of tube coupling (1-3) outside described;
Describedly the first insulation layer (5-1), the second insulation layer (5-2) and described 3rd insulation layer set by outside is needed on pipe laying all to connect as one.
4. according to the building water supply and drainage described in claim 1 or 2 and heating engineering waterproofing and insulation construction method, it is characterized in that: the first insulation layer described in step 201 (5-1) is the insulation layer formed by the heat insulating material clogged between the first steel sleeve (4-1) and through-flooring tube coupling (1-1), described first waterproofing course (6-1) is the waterproofing course formed by the waterproofing materials clogged between the first steel sleeve (4-1) and through-flooring tube coupling (1-1); Described second insulation layer (5-2) is the insulation layer formed by the heat insulating material clogged between the second steel sleeve (4-2) and tube coupling through walls (1-2), and described second waterproofing course (6-2) is the waterproofing course formed by the waterproofing materials clogged between the second steel sleeve (4-2) and tube coupling through walls (1-2).
5. according to building water supply and drainage according to claim 4 and heating engineering waterproofing and insulation construction method, it is characterized in that: when waterproof and isothermal holding being carried out to through-flooring tube coupling (1-1) in step 201, by the first steel sleeve (4-1) coaxial package in through-flooring tube coupling (1-1) outer rear flank, with timber wedge by be set with the first steel sleeve (4-1) and be temporarily fixed on floor (3), again described waterproofing materials to be clogged between the first steel sleeve (4-1) and through-flooring tube coupling (1-1) and to form the first waterproofing course (6-1), afterwards the concentricity of the first steel sleeve (4-1) with through-flooring tube coupling (1-1) is adjusted, then clog described heat insulating material respectively at the upper and lower sides of the first waterproofing course (6-1) and form the first insulation layer (5-1), finally carry out shutoff with fluid sealant between the first steel sleeve (4-1) top and through-flooring tube coupling (1-1),
When waterproof and isothermal holding are carried out to through-flooring tube coupling (1-1), by the second steel sleeve (4-2) coaxial package in through-flooring tube coupling (1-1) outer rear flank, with timber wedge by be set with the second steel sleeve (4-2) and be temporarily fixed on body of wall (2), again described waterproofing materials to be clogged between the second steel sleeve (4-2) and tube coupling through walls (1-2) and to form the second waterproofing course (6-2), afterwards the concentricity of the second steel sleeve (4-2) with tube coupling through walls (1-2) is adjusted, then clog described heat insulating material respectively at the left and right sides of the second waterproofing course (6-2) and form the second insulation layer (5-2), finally close up with the fire prevention two ends, left and right of clay to the second steel sleeve (4-2).
6. according to the building water supply and drainage described in claim 1 or 2 and heating engineering waterproofing and insulation construction method, it is characterized in that: the first insulation layer (5-1) described in step 201 is by being adhesively fixed on through-flooring tube coupling (1-1) outside and the insulation sleeve be bent to form by rubber and plastic warming plate, described second insulation layer (5-2) is by being adhesively fixed on tube coupling through walls (1-2) outside and the insulation sleeve be bent to form by rubber and plastic warming plate.
7. according to the building water supply and drainage described in claim 1 or 2 and heating engineering waterproofing and insulation construction method, it is characterized in that: in step 202, the 3rd insulation layer is incubated sleeve (9-2) for exposing the tube coupling that exposes be bent to form outside tube coupling (1-3) and by rubber and plastic warming plate described in being adhesively fixed on; Pipe laying is needed to be undertaken supporting or suspending in midair by suspension and support described in step one, expose after tube coupling (1-3) carries out waterproof and isothermal holding to described in step 202, also need lay one at described suspension and support installation position place to exposing tube coupling insulation sleeve (9-2) locating part that fixes, described locating part is provided with manhole, to be incubated the external diameter of sleeve (9-2) consistent with exposing tube coupling for the aperture of described manhole, exposes tube coupling insulation sleeve (9-2) and be pasted and fixed on described locating part by bonded adhesives; Described locating part is fastened and fixed at the support of pipelines needing pipe laying to support to described or on the described pipeline elevator needing pipe laying to suspend in midair by clip; Described locating part is wooden block (9-3) or high density polyurethane conduit saddle; The thickness of described wooden block (9-3) and described high density polyurethane conduit saddle is all not less than the wall thickness exposing tube coupling insulation sleeve (9-2); Described tube coupling insulation sleeve (9-2) that exposes is clipped on described need between pipe laying and described locating part.
8. according to the building water supply and drainage described in claim 1 or 2 and heating engineering waterproofing and insulation construction method, it is characterized in that: described in step one, need pipe laying assembled from front to back by multiple flat tube, connected by pipeline connecting bend (8-2) between adjacent two flat tube; In step 202, the 3rd insulation layer is incubated sleeve (9-2) for exposing the tube coupling that exposes be bent to form outside tube coupling (1-3) and by rubber and plastic warming plate described in being adhesively fixed on; In step 202 to described expose tube coupling (1-3) carry out waterproof and isothermal holding time, all need carry out waterproof and isothermal holding to described flat tube and pipeline connecting bend (8-2); Described pipeline connecting bend (8-2) is PVC elbow or metal bends;
When described pipeline connecting bend (8-2) is for PVC elbow, when waterproof and isothermal holding being carried out to pipeline connecting bend (8-2) in step 202, only need be incubated sleeve (8-1) at pipeline connecting bend (8-2) outside parcel one deck first; When pipeline connecting bend (8-2) is for metal bends, when waterproof and isothermal holding being carried out to pipeline connecting bend (8-2) in step 202, first brushing one deck rustproof paint on the lateral wall of pipeline connecting bend (8-2), then the first insulation sleeve (8-1) described in the parcel one deck of pipeline connecting bend (8-2) outside;
Described first insulation sleeve (8-1) is pasted and fixed on by bonded adhesives on the lateral wall of pipeline connecting bend (8-2), and described first insulation sleeve (8-1) forms by one piece of first rubber and plastic warming plate is bonding; The shape of described first rubber and plastic warming plate is rectangle, width D=π × the d2 of described first rubber and plastic warming plate, and the length L=L1+2 × d1 of described first rubber and plastic warming plate, wherein L1 is the outer arc length of pipeline connecting bend (8-2), d1 is not less than 10mm, and d2 is the external diameter of pipeline connecting bend (8-2); Described first rubber and plastic warming plate is packaged in pipeline connecting bend (8-2) outside from outside to inside, and the seam of described first rubber and plastic warming plate is positioned at the inner side of pipeline connecting bend (8-2); The thickness of slab of described first rubber and plastic warming plate is 20mm ~ 30mm.
9. according to building water supply and drainage according to claim 8 and heating engineering waterproofing and insulation construction method, it is characterized in that: described first insulation sleeve (8-1) outside is also provided with connecting bend insulation layer containment vessel, and described connecting bend insulation layer containment vessel comprises the dried shrimp elbow being sleeved on the first insulation sleeve (8-1) outside;
The width that pipeline connecting bend (8-2) front end is stretched out in described first front end being incubated sleeve (8-1) is d1, the width that pipeline connecting bend (8-2) rear end is stretched out in first rear end being incubated sleeve (8-1) is d1, and wherein d1 is not less than 10mm; The front end that the front end and first of described dried shrimp elbow is incubated sleeve (8-1) is mutually concordant, and the rear end that the rear end of described dried shrimp elbow and first is incubated sleeve (8-1) is mutually concordant; Described pipeline connecting bend (8-2) is connected between the first flat tube (8-3) and the second flat tube (8-4), and the first flat tube (8-3) and the second flat tube (8-4) are in vertical runs; It is assembled from front to back that described dried shrimp elbow saves (10) by multiple dried shrimp, the joint number of multiple described dried shrimp joint (10) is not less than 4, and when the bore of pipeline connecting bend (8-2) is larger, the joint number of multiple described dried shrimp joint (10) is more.
10. according to building water supply and drainage according to claim 9 and heating engineering waterproofing and insulation construction method, it is characterized in that: in step 202 to described expose the valve (12) that tube coupling (1-3) is installed carry out isothermal holding time, employing is adhesively fixed on valve (12) outside and the 4th insulation sleeve (13) be bent to form by the 4th rubber and plastic warming plate carries out isothermal holding to valve (12), and the gap between described 4th insulation sleeve (13) and valve (12) is carried out sealing by gum filler (15) and filled; Described 4th insulation sleeve (13) outside suit valve heat insulation layer containment vessel (14) is protected the 4th insulation sleeve (13); Be set with cylindric insulation layer containment vessel outside the 3rd insulation layer set in the described flat tube exposed in tube coupling (1-3), described in expose the described connecting bend insulation layer containment vessel that tube coupling (1-3) is installed, described cylindric insulation layer containment vessel and valve heat insulation layer containment vessel (14) and all connect as one.
CN201310390217.3A 2013-08-30 2013-08-30 Building water supply and drainage and heating engineering waterproofing and insulation construction method Expired - Fee Related CN103437556B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310390217.3A CN103437556B (en) 2013-08-30 2013-08-30 Building water supply and drainage and heating engineering waterproofing and insulation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310390217.3A CN103437556B (en) 2013-08-30 2013-08-30 Building water supply and drainage and heating engineering waterproofing and insulation construction method

Publications (2)

Publication Number Publication Date
CN103437556A CN103437556A (en) 2013-12-11
CN103437556B true CN103437556B (en) 2015-09-02

Family

ID=49691263

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310390217.3A Expired - Fee Related CN103437556B (en) 2013-08-30 2013-08-30 Building water supply and drainage and heating engineering waterproofing and insulation construction method

Country Status (1)

Country Link
CN (1) CN103437556B (en)

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103836268A (en) * 2014-02-28 2014-06-04 中天建设集团有限公司 Construction method for mounting waterproof sleeve of external concrete wall of basement
CN106704769A (en) * 2015-11-17 2017-05-24 中建四局安装工程有限公司 Insulating method and structure for air conditioner water tube in eccentric state in sleeve
CA3111442A1 (en) * 2018-09-04 2020-03-12 Cortex Composites, Inc. Cementitious composite structure
CN111022757A (en) * 2019-05-20 2020-04-17 安徽省中功立业建设工程有限责任公司 Waterproof and heat-insulating construction method for building water supply and drainage and heating engineering
CN110425623B (en) * 2019-07-16 2021-06-15 上海一建安装工程有限公司 Installation method of hot water pipeline for indoor heating
CN111608281B (en) * 2020-05-28 2021-11-30 河北三楷深发科技股份有限公司 Construction method of wall-penetrating pipeline
CN112282364A (en) * 2020-11-24 2021-01-29 河南超诚建材科技有限公司 Construction process of indoor ski center insulation board punching and bridge-cut insulation system
CN114857366B (en) * 2022-03-22 2023-09-08 深圳市隆金达实业有限公司 A sealing structure for pipes passing through floor slabs and its construction method

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100370088C (en) * 2003-11-05 2008-02-20 湖北省孝感市建设工程质量监督站 Constructing method for preventing toilet and kitchen from leakage
JP2005214247A (en) * 2004-01-28 2005-08-11 Sekisui House Ltd Waterproof structure in penetrations such as downspout
US20130000073A1 (en) * 2011-07-01 2013-01-03 Rusmir Canic Pipe sleeve
CN202834424U (en) * 2012-09-27 2013-03-27 唐山市热力总公司 Waterproof, thermal insulation and anticorrosion structure of building heating pipes through walls

Also Published As

Publication number Publication date
CN103437556A (en) 2013-12-11

Similar Documents

Publication Publication Date Title
CN103437556B (en) Building water supply and drainage and heating engineering waterproofing and insulation construction method
CN202884378U (en) Steel composite anti-corrosion pipe
CN114370529B (en) Mounting technology of air conditioner water pipe
CN205908935U (en) Thermal -insulated stagnant water does not have thrust sleeve compensator
CN216405651U (en) A prefabricated concrete drainage inspection well structure
CN107763372A (en) Heavy in section circular pipe insulation and the construction method of installation of outer casing
CN204113295U (en) A kind of municipal shield tunnel
CN202834424U (en) Waterproof, thermal insulation and anticorrosion structure of building heating pipes through walls
CN220486994U (en) Side wall structure of lining type exhaust passage and lining type exhaust passage
CN203113788U (en) Adjustable reserved sleeve capable of penetrating floorslab
CN216408186U (en) Prefabricated polyurethane heat-preservation fixed heat-insulation pipe bracket
CN207049454U (en) A kind of structure through walls using the thermal insulation casing component with outer protection tube
CN206708563U (en) A kind of water proof structure of Pipeline Crossing Program floor
CN104649121A (en) Adjustable clamp for hoisting in air hoses
CN220037679U (en) Invisible bracket for pipeline installation
CN210107439U (en) A gallows for exhaust pipe convenient to adjust
CN203052096U (en) Multifunctional special-shaped tee huff section
CN208535348U (en) A kind of new indoor hot water pipe and its mounting structure
CN102705584B (en) Pipeline supporting device and mounting method thereof
CN207796342U (en) It is easily installed the feed pipe of docking
CN201884833U (en) Lined flange composite glass wool board air duct
CN206368459U (en) Steel building Side fascia crack stopper
CN202442010U (en) Pre-buried casing pipe for buildings
CN206093278U (en) Novel feedwater socket joint formula welding steel pipe structure
CN220301437U (en) A temporary fire-fighting water device installed on the working surface

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: SHAANXI PROVINCE IN THE THIRD CONSTRUCTION COMPANY

Effective date: 20150609

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Wang Qiaoli

Inventor after: Wang Xisheng

Inventor after: Zhang Feng

Inventor after: Gao Bo

Inventor after: Jia Feijun

Inventor after: Ma Weili

Inventor after: Zhao Qiang

Inventor after: Wang Xun

Inventor before: Wang Qiaoli

Inventor before: Wang Xisheng

Inventor before: Zhang Feng

Inventor before: Gao Bo

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: WANG QIAOLI WANG XISHENG ZHANG FENG GAO BO TO: WANG QIAOLI WANG XISHENG ZHANG FENG GAO BO JIA FEIJUN MA WEILI ZHAO QIANG WANG XUN

TA01 Transfer of patent application right

Effective date of registration: 20150609

Address after: 710003 No. 199, North Main Street, Shaanxi, Xi'an

Applicant after: Shaanxi Construction Engineering Group Corp.

Applicant after: Shaanxi Province in the Third Construction Company in the Fourth Branch

Address before: 710003 No. 199, North Main Street, Shaanxi, Xi'an

Applicant before: Shaanxi Construction Engineering Group Corp.

C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 710003 Xi'an, Lianhu District, Shaanxi, North Street, No. 199

Co-patentee after: SHAANXI PROVINCE IN THE THIRD CONSTRUCTION COMPANY IN THE FOURTH BRANCH

Patentee after: Shaanxi Construction Engineering Group Co.,Ltd.

Address before: 710003 Xi'an, Lianhu District, Shaanxi, North Street, No. 199

Co-patentee before: SHAANXI PROVINCE IN THE THIRD CONSTRUCTION COMPANY IN THE FOURTH BRANCH

Patentee before: SHAANXI CONSTRUCTION ENGINEERING GROUP Corp.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 710003 Xi'an, Lianhu District, Shaanxi, North Street, No. 199

Co-patentee after: SHAANXI PROVINCE IN THE THIRD CONSTRUCTION COMPANY IN THE FOURTH BRANCH

Patentee after: SHAANXI CONSTRUCTION ENGINEERING GROUP Corp.,Ltd.

Address before: 710003 No. 199, North Main Street, Shaanxi, Xi'an

Co-patentee before: SHAANXI PROVINCE IN THE THIRD CONSTRUCTION COMPANY IN THE FOURTH BRANCH

Patentee before: SHAANXI CONSTRUCTION ENGINEERING Group Corp.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150902