CN102901896A - 配电网络的预置式馈线自动化测试方法 - Google Patents

配电网络的预置式馈线自动化测试方法 Download PDF

Info

Publication number
CN102901896A
CN102901896A CN2012103859272A CN201210385927A CN102901896A CN 102901896 A CN102901896 A CN 102901896A CN 2012103859272 A CN2012103859272 A CN 2012103859272A CN 201210385927 A CN201210385927 A CN 201210385927A CN 102901896 A CN102901896 A CN 102901896A
Authority
CN
China
Prior art keywords
test
state
switch
testing tool
control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012103859272A
Other languages
English (en)
Other versions
CN102901896B (zh
Inventor
凌万水
刘�东
马杰
洪俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI SHENGDONG ELECTRIC POWER TECHNOLOGY CO LTD
Original Assignee
SHANGHAI SHENGDONG ELECTRIC POWER TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI SHENGDONG ELECTRIC POWER TECHNOLOGY CO LTD filed Critical SHANGHAI SHENGDONG ELECTRIC POWER TECHNOLOGY CO LTD
Priority to CN201210385927.2A priority Critical patent/CN102901896B/zh
Publication of CN102901896A publication Critical patent/CN102901896A/zh
Application granted granted Critical
Publication of CN102901896B publication Critical patent/CN102901896B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

一种配电网络的预置式馈线自动化测试方法,涉及电力系统自动化技术领域,所解决的是节省人力及时间的技术问题。该方法先将所有测试用例依序编制成一预置案例存入每台测试仪器中,再启动各测试仪器同步开始测试,并在测试过程中使各测试仪器同步切换测试状态断面,同步切换测试用例,直至测试完预置案例中所有的测试用例;测试仪器根据测试状态断面数据,自动产生对应的电气数据,并通过其模拟量输出端子,输出电流、电压以及各种状态量数据,被测试的馈线自动化系统根据断面数据做出决策并执行,通过控制输入端子,测试仪器可以自动响应被测系统的决策行为。本发明提供的方法,适用于配电网络的馈线自动化自动测试。

Description

配电网络的预置式馈线自动化测试方法
技术领域
本发明涉及电力系统自动化的技术,特别是涉及一种配电网络的预置式馈线自动化测试方法的技术。
背景技术
配电网络中设有很多控制开关,各个控制开关都配置有用于监控其工作的监控终端,在对配电网络的馈线进行自动化现场测试时,需要根据配电网络的拓扑结构,在被测线路的所有控制开关的监控终端上注入测试电流,并在故障点上游注入故障电流,在故障点下游不注入电流或者注入小电流,同时需要配合出口断路器保护动作后的电压变化过程,跳闸前需要在电流端子上加上电压,跳闸后需要及时去掉电压。由于电气数据同时性的特点,测试时往往需要很多的人员在线路的不同区域的监控终端处紧密配合,才能完成一个测试用例的测试,要对一条包含多个开关的线路进行完整的测试,需要耗费大量的人力与时间。
发明内容
针对上述现有技术中存在的缺陷,本发明所要解决的技术问题是提供一种能节省人力及测试时间的配电网络的预置式馈线自动化测试方法。
为了解决上述技术问题,本发明所提供的一种配电网络的预置式馈线自动化测试方法,其特征在于,具体步骤如下:
1)在被测线路中各个开关的监控终端上各安装一台测试仪器,并将所有测试用例依序编制成一预置案例存入每台测试仪器中;
每个测试用例均设有一个在预置案例中唯一的ID号;
每个测试用例中,均设有多个测试时间段,并在每个测试时间段中,对被测线路中的各个开关各设一个测试状态断面,且各个开关在同一测试时间段内的测试状态断面的开始时间点及持续时间均一致,每个开关的测试状态断面按测试时序依序排列;
每个测试状态断面中,均包含有一个在所属测试用例中唯一的断面序号,并包含有断面持续时间,四个测试电压数据,四个测试电流数据,八个状态量,两个控制输入量,一个通信控制量;
所述四个测试电压数据分别为A相测试电压数据、B相测试电压数据、C相测试电压数据、零线测试电压数据;
所述四个测试电流数据分别为A相测试电流数据、B相测试电流数据、C相测试电流数据、零线测试电流数据;
所述八个状态量分别为开关第一状态量、故障指示器状态、过流指示器状态、接地刀状态、合闸闭锁状态、远方就地状态、分闸闭锁状态、开关第二状态量;
所述两个控制输入量分别为控分量、控合量;
2)同步各测试仪器的时间;
3)各测试仪器按如下方法同步开始测试:
3.1)各测试仪器同时从预置案例中依序取出第一个测试用例;
3.2)各测试仪器同时从测试用例中依序取出本仪器对应开关的第一个测试状态断面;
3.3)各测试仪器各向对应开关的监控终端,输入所取测试状态断面的测试电压数据、测试电流数据、状态量,并根据控制输入量、通信控制量,来控制对应监控终端的工作状态,直至测试时间达到所取测试状态断面的断面持续时间;
3.4)各测试仪器同时从测试用例中依序取出本仪器对应开关的下一个测试状态断面;
3.5)重复步骤3.3至步骤3.4,直至测试完测试用例中所有的测试状态断面;
3.6)各测试仪器同时从预置案例中依序取出下一个测试用例;
3.7)重复步骤3.2至步骤3.6,直至测试完预置案例中所有的测试用例。
进一步的,各测试仪器通过两个控制输入量接收控制命令,所述测试状态断面中包含有控制响应时间Tk,各测试仪器根据控制响应时间Tk作出响应,具体响应规则如下:
如果控分量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸,各监控终端实时采集对应测试仪器的状态量;
如果Tk<0,不作任何响应;
如果控分量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸。
进一步的,各测试仪器根据通信控制量向对应开关的监控终端输入相应的通信信号;如果通信控制量为1,则向对应开关的监控终端输入正常通信信号,使监控终端的通信链路保持畅通状态;如果通信控制量为0,则向对应开关的监控终端输入中断通信信号,使监控终端的通信链路处于断开状态。
本发明提供的配电网络的预置式馈线自动化测试方法,基于配电网故障特性,依据待测配电网络的拓扑关系与测试方案,将测试方案中各个测试用例对应各个开关的状态序列预置到测试仪器中,再按相同的测试用例切换原则与结束原则启动各测试仪器同步进行测试,能节省大量的人力与测试时间。
具体实施方式
以下结合具体实施例对本发明的技术方案作进一步详细描述,但本实施例并不用于限制本发明,凡是采用本发明的相似结构及其相似变化,均应列入本发明的保护范围。
本发明实施例所提供的一种配电网络的预置式馈线自动化测试方法,其特征在于,具体步骤如下:
1)在被测线路中各个开关的监控终端上各安装一台测试仪器,并将所有测试用例依序编制成一预置案例存入每台测试仪器中;
每个测试用例均设有一个在预置案例中唯一的ID号;
每个测试用例中,均设有多个测试时间段,并在每个测试时间段中,对被测线路中的各个开关各设一个测试状态断面,且各个开关在同一测试时间段内的测试状态断面的开始时间点及持续时间均一致,每个开关的测试状态断面按测试时序依序排列;
每个测试状态断面中,均包含有一个在所属测试用例中唯一的断面序号,并包含有断面持续时间,四个测试电压数据,四个测试电流数据,八个状态量,两个控制输入量,一个通信控制量;
所述四个测试电压数据分别为A相测试电压数据、B相测试电压数据、C相测试电压数据、零线测试电压数据;
所述四个测试电流数据分别为A相测试电流数据、B相测试电流数据、C相测试电流数据、零线测试电流数据;
所述八个状态量分别为开关第一状态量、故障指示器状态、过流指示器状态、接地刀状态、合闸闭锁状态、远方就地状态、分闸闭锁状态、开关第二状态量;
所述两个控制输入量分别为控分量、控合量;
2)同步各测试仪器的时间;
3)各测试仪器按如下方法同步开始测试:
3.1)各测试仪器同时从预置案例中依序取出第一个测试用例;
3.2)各测试仪器同时从测试用例中依序取出本仪器对应开关的第一个测试状态断面;
3.3)各测试仪器各向对应开关的监控终端,输入所取测试状态断面的测试电压数据、测试电流数据、状态量,并根据控制输入量、通信控制量,来控制对应监控终端的工作状态,直至测试时间达到所取测试状态断面的断面持续时间;
各测试仪器各向对应开关的监控终端输入的测试电压数据、测试电流数据均为模拟量,用于再现被测线路在正常运行状态下通过PT或CT后的二次侧数据,各个开关的监控终端根据测试电压数据判断被测线路是否带电,根据测试电流数据判断被测线路是否正常运行或者遭受故障;
各测试仪器各向对应开关的监控终端输入的状态量,用于模拟实际开关及附属设备的状态,使得测试时各开关的监控终端能完全脱离各个开关进行实验,减少甚至消除对用户用电的影响,各个状态量都是通过空节点输出的,这样可以与实际开关的节点输出信息一致,根据现场的情况,灵活提供系统需要的空节点或者某电压湿节点的状态信息;
各测试仪器通过两个控制输入量接收控制命令,所述测试状态断面中包含有控制响应时间Tk,各测试仪器根据控制响应时间Tk作出响应,具体响应规则如下:
如果控分量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸,各监控终端实时采集对应测试仪器的状态量;
如果Tk<0,不作任何响应;
如果控分量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸;
各测试仪器根据通信控制量向对应开关的监控终端输入相应的通信信号;如果通信控制量为1,则向对应开关的监控终端输入正常通信信号,使监控终端的通信链路保持畅通状态;如果通信控制量为0,则向对应开关的监控终端输入中断通信信号,使监控终端的通信链路处于断开状态;
3.4)各测试仪器同时从测试用例中依序取出本仪器对应开关的下一个测试状态断面;
3.5)重复步骤3.3至步骤3.4,直至测试完测试用例中所有的测试状态断面;
3.6)各测试仪器同时从预置案例中依序取出下一个测试用例;
3.7)重复步骤3.2至步骤3.6,直至测试完预置案例中所有的测试用例。

Claims (3)

1.一种配电网络的预置式馈线自动化测试方法,其特征在于,具体步骤如下:
1)在被测线路中各个开关的监控终端上各安装一台测试仪器,并将所有测试用例依序编制成一预置案例存入每台测试仪器中;
每个测试用例均设有一个在预置案例中唯一的ID号;
每个测试用例中,均设有多个测试时间段,并在每个测试时间段中,对被测线路中的各个开关各设一个测试状态断面,且各个开关在同一测试时间段内的测试状态断面的开始时间点及持续时间均一致,每个开关的测试状态断面按测试时序依序排列;
每个测试状态断面中,均包含有一个在所属测试用例中唯一的断面序号,并包含有断面持续时间,四个测试电压数据,四个测试电流数据,八个状态量,两个控制输入量,一个通信控制量;
所述四个测试电压数据分别为A相测试电压数据、B相测试电压数据、C相测试电压数据、零线测试电压数据;
所述四个测试电流数据分别为A相测试电流数据、B相测试电流数据、C相测试电流数据、零线测试电流数据;
所述八个状态量分别为开关第一状态量、故障指示器状态、过流指示器状态、接地刀状态、合闸闭锁状态、远方就地状态、分闸闭锁状态、开关第二状态量;
所述两个控制输入量分别为控分量、控合量;
2)同步各测试仪器的时间;
3)各测试仪器按如下方法同步开始测试:
3.1)各测试仪器同时从预置案例中依序取出第一个测试用例;
3.2)各测试仪器同时从测试用例中依序取出本仪器对应开关的第一个测试状态断面;
3.3)各测试仪器各向对应开关的监控终端,输入所取测试状态断面的测试电压数据、测试电流数据、状态量,并根据控制输入量、通信控制量,来控制对应监控终端的工作状态,直至测试时间达到所取测试状态断面的断面持续时间;
3.4)各测试仪器同时从测试用例中依序取出本仪器对应开关的下一个测试状态断面;
3.5)重复步骤3.3至步骤3.4,直至测试完测试用例中所有的测试状态断面;
3.6)各测试仪器同时从预置案例中依序取出下一个测试用例;
3.7)重复步骤3.2至步骤3.6,直至测试完预置案例中所有的测试用例。
2.根据权利要求1所述的配电网络的预置式馈线自动化测试方法,其特征在于:
各测试仪器通过两个控制输入量接收控制命令,所述测试状态断面中包含有控制响应时间Tk,各测试仪器根据控制响应时间Tk作出响应,具体响应规则如下:
如果控分量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk=0,则立即控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸,各监控终端实时采集对应测试仪器的状态量;
如果Tk<0,不作任何响应;
如果控分量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为分闸,开关第二状态量为合闸;如果控合量收到控制命令且Tk>0,则延时Tk秒后控制测试仪器的开关第一状态量为合闸,开关第二状态量为分闸。
3.根据权利要求1所述的配电网络的预置式馈线自动化测试方法,其特征在于:
各测试仪器根据通信控制量向对应开关的监控终端输入相应的通信信号;如果通信控制量为1,则向对应开关的监控终端输入正常通信信号,使监控终端的通信链路保持畅通状态;如果通信控制量为0,则向对应开关的监控终端输入中断通信信号,使监控终端的通信链路处于断开状态。
CN201210385927.2A 2012-10-12 2012-10-12 配电网络的预置式馈线自动化测试方法 Active CN102901896B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210385927.2A CN102901896B (zh) 2012-10-12 2012-10-12 配电网络的预置式馈线自动化测试方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210385927.2A CN102901896B (zh) 2012-10-12 2012-10-12 配电网络的预置式馈线自动化测试方法

Publications (2)

Publication Number Publication Date
CN102901896A true CN102901896A (zh) 2013-01-30
CN102901896B CN102901896B (zh) 2016-03-02

Family

ID=47574242

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210385927.2A Active CN102901896B (zh) 2012-10-12 2012-10-12 配电网络的预置式馈线自动化测试方法

Country Status (1)

Country Link
CN (1) CN102901896B (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104007366A (zh) * 2014-06-12 2014-08-27 国网上海市电力公司 一种带自动干扰输入的馈线自动化测试系统
CN104133146A (zh) * 2014-08-11 2014-11-05 国家电网公司 一种馈线自动化故障处理逻辑现场测试方法
CN104635095A (zh) * 2015-03-11 2015-05-20 上海金智晟东电力科技有限公司 馈线自动化系统的测试系统
CN104460346B (zh) * 2014-11-18 2017-01-11 江苏省电力公司扬州供电公司 一种基于配电终端服务验证的馈线自动化动作逻辑试验方法
CN106789011A (zh) * 2016-12-19 2017-05-31 国家电网公司 一种电力量子保密通信系统偏振成码率的测试方法及系统
CN107703420A (zh) * 2017-10-17 2018-02-16 龙逸电科(天津)技术有限公司 一种多重电力系统故障的智能诊断方法
WO2018209945A1 (zh) * 2017-05-19 2018-11-22 国网江苏省电力公司常州供电公司 有源配电网馈线自动化系统测试方法
CN109167709A (zh) * 2018-10-11 2019-01-08 陕西银河天地智能配网技术有限公司 基于云平台的馈线自动化现场全自动测试方法
CN109271311A (zh) * 2017-07-18 2019-01-25 华为机器有限公司 一种需求场景化方法及需求场景化装置
CN110261724A (zh) * 2019-06-14 2019-09-20 广西电网有限责任公司电力科学研究院 一种电压时间型馈线自动化测试方法
CN111898264A (zh) * 2020-07-24 2020-11-06 贵州电网有限责任公司 一种基于案例预制的配电自动化现场测试方法及系统
CN112540262A (zh) * 2020-11-18 2021-03-23 广西电网有限责任公司电力科学研究院 电压时间型馈线自动化测试系统及其测试方法
CN113030642A (zh) * 2021-03-03 2021-06-25 北京天能继保电力科技有限公司 一种馈线自动化现场自动测试方法和系统

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3363002B2 (ja) * 1995-09-29 2003-01-07 株式会社日立エンジニアリングサービス 機器の試験方法および試験装置
JP2003014805A (ja) * 2001-07-03 2003-01-15 Pfu Ltd 電子機器の温度試験システムとその制御方法および温度調整装置ならびにプログラム
DE10221738A1 (de) * 2002-05-16 2003-11-27 Bosch Gmbh Robert Verfahren und Vorrichtung zum Testen eines Testobjektes und Schnittstelle in einer derartigen Vorrichtung
CN102306953A (zh) * 2011-06-23 2012-01-04 陕西电力科学研究院 配电自动化系统二次注入测试法
CN102522820A (zh) * 2011-11-29 2012-06-27 陕西电力科学研究院 配电自动化系统主站注入和二次注入同步协调的测试方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3363002B2 (ja) * 1995-09-29 2003-01-07 株式会社日立エンジニアリングサービス 機器の試験方法および試験装置
JP2003014805A (ja) * 2001-07-03 2003-01-15 Pfu Ltd 電子機器の温度試験システムとその制御方法および温度調整装置ならびにプログラム
DE10221738A1 (de) * 2002-05-16 2003-11-27 Bosch Gmbh Robert Verfahren und Vorrichtung zum Testen eines Testobjektes und Schnittstelle in einer derartigen Vorrichtung
CN102306953A (zh) * 2011-06-23 2012-01-04 陕西电力科学研究院 配电自动化系统二次注入测试法
CN102522820A (zh) * 2011-11-29 2012-06-27 陕西电力科学研究院 配电自动化系统主站注入和二次注入同步协调的测试方法

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104007366A (zh) * 2014-06-12 2014-08-27 国网上海市电力公司 一种带自动干扰输入的馈线自动化测试系统
CN104133146A (zh) * 2014-08-11 2014-11-05 国家电网公司 一种馈线自动化故障处理逻辑现场测试方法
CN104133146B (zh) * 2014-08-11 2017-10-24 国家电网公司 一种馈线自动化故障处理逻辑现场测试方法
CN104460346B (zh) * 2014-11-18 2017-01-11 江苏省电力公司扬州供电公司 一种基于配电终端服务验证的馈线自动化动作逻辑试验方法
CN104635095B (zh) * 2015-03-11 2018-02-13 上海金智晟东电力科技有限公司 馈线自动化系统的测试系统
CN104635095A (zh) * 2015-03-11 2015-05-20 上海金智晟东电力科技有限公司 馈线自动化系统的测试系统
CN106789011B (zh) * 2016-12-19 2020-09-18 北京中电普华信息技术有限公司 一种电力量子保密通信系统偏振成码率的测试方法及系统
CN106789011A (zh) * 2016-12-19 2017-05-31 国家电网公司 一种电力量子保密通信系统偏振成码率的测试方法及系统
WO2018209945A1 (zh) * 2017-05-19 2018-11-22 国网江苏省电力公司常州供电公司 有源配电网馈线自动化系统测试方法
CN109271311A (zh) * 2017-07-18 2019-01-25 华为机器有限公司 一种需求场景化方法及需求场景化装置
CN107703420A (zh) * 2017-10-17 2018-02-16 龙逸电科(天津)技术有限公司 一种多重电力系统故障的智能诊断方法
CN109167709A (zh) * 2018-10-11 2019-01-08 陕西银河天地智能配网技术有限公司 基于云平台的馈线自动化现场全自动测试方法
CN110261724A (zh) * 2019-06-14 2019-09-20 广西电网有限责任公司电力科学研究院 一种电压时间型馈线自动化测试方法
CN110261724B (zh) * 2019-06-14 2021-07-13 广西电网有限责任公司电力科学研究院 一种电压时间型馈线自动化测试方法
CN111898264A (zh) * 2020-07-24 2020-11-06 贵州电网有限责任公司 一种基于案例预制的配电自动化现场测试方法及系统
CN112540262A (zh) * 2020-11-18 2021-03-23 广西电网有限责任公司电力科学研究院 电压时间型馈线自动化测试系统及其测试方法
CN113030642A (zh) * 2021-03-03 2021-06-25 北京天能继保电力科技有限公司 一种馈线自动化现场自动测试方法和系统
CN113030642B (zh) * 2021-03-03 2021-11-16 北京天能继保电力科技有限公司 一种馈线自动化现场自动测试方法和系统

Also Published As

Publication number Publication date
CN102901896B (zh) 2016-03-02

Similar Documents

Publication Publication Date Title
CN102901896B (zh) 配电网络的预置式馈线自动化测试方法
US10680430B2 (en) Fault recovery systems and methods for electrical power distribution networks
US10355523B2 (en) Power distribution terminal capable of determining fault type and determination method thereof
CN108983006B (zh) 就地型馈线自动化开关终端现场不停电全自动测试方法
CN103051065A (zh) 一种配电自动化分布式fa联动测试方法及系统
CN102437654B (zh) 一种基于监控系统的站域控制实现方法
CN104283215A (zh) 一种智能分布式配电终端的检测试验方法及装置
CN107607833A (zh) 一种便携型智能分布式馈线自动化测试系统
CN105629128A (zh) 一种查找电网小电流单相接地故障的装置及其查找方法
CN103683228A (zh) 一种断路器失灵保护及自动重合闸装置的控制方法
CN1323476C (zh) 直流系统短路保护装置
CN103809052A (zh) 超高压电网输电线路保护动模实验系统、带电功能测试方法
JP2010161865A (ja) 配電系統の地絡保護システム、配電系統の地絡保護方法、プログラム
CN107591784B (zh) 一种配网串供线路自适应不完全差动保护方法
CN109617238A (zh) 一种带测试功能的馈线自动化远程终端装置
CN110994570A (zh) 一种配电网保护方法及其系统、保护设备、存储介质
Lifan et al. The experiences of decentralized self-healing grid
US11114892B2 (en) Electric power system transducer failure monitor and measurement recovery
CN105896496A (zh) 一种采用磁控快速断路器的多级差保护配电自动化设备
US11119128B2 (en) Loopback testing of electric power protection systems
CN100440671C (zh) 一种基于多种保护技术的集成保护系统
US11079436B2 (en) Multiple merging unit testing system
JP2006280024A (ja) 機器自動試験システムおよび機器自動試験方法
Kaijun et al. Distributed distribution automation system based on the identification of tie-switch
Golshani et al. Application of phasor-based functionality to HVDC control in reduced system strength

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 200233, 680 Guiping Road, Shanghai, 32, building 6, room 614, Xuhui District

Applicant after: SHANGHAI WISCOM SUNEST ELECTRIC POWER TECHNOLOGY CO., LTD.

Address before: 200233, 680 Guiping Road, Shanghai, 32, building 6, room 614, Xuhui District

Applicant before: Shanghai Shengdong Electric Power Technology Co.,Ltd.

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: SHANGHAI SHENGDONG ELECTRIC POWER TECHNOLOGY CO., LTD. TO: SHANGHAI WISCOM SUNEST ELECTRIC POWER TECHNOLOGY CO., LTD.

C14 Grant of patent or utility model
GR01 Patent grant