CN102832570A - Clamping device for large-section expanded diameter conductors - Google Patents
Clamping device for large-section expanded diameter conductors Download PDFInfo
- Publication number
- CN102832570A CN102832570A CN2012102497325A CN201210249732A CN102832570A CN 102832570 A CN102832570 A CN 102832570A CN 2012102497325 A CN2012102497325 A CN 2012102497325A CN 201210249732 A CN201210249732 A CN 201210249732A CN 102832570 A CN102832570 A CN 102832570A
- Authority
- CN
- China
- Prior art keywords
- wire
- section
- pressure plate
- point
- diameter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Electric Cable Installation (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
本发明提供了一种大截面扩径导线卡线器,涉及输电线路施工机具和施工技术领域。该卡线器特别适用于大截面支撑型高密度聚乙烯型线扩径导线及疏绕型圆线同心绞铝导线等的张力架线施工中的锚固连接,同时,也可用于更大截面四层圆线同心绞铝导线的锚固连接。本发明卡线器锚固时的承载能力大,没有滑移,且导线被夹持部位的结构无变形,表面无压痕;卡线器的重量减轻,便于高空作业;良好的夹持性能为大截面扩径导线的锚固连接提供了安全可靠保障,解决了架线施工中扩径导线夹紧工器具缺乏的一大难题。
The invention provides a wire gripping device for a large-section diameter-expanding wire, which relates to the field of power transmission line construction equipment and construction technology. The clamp is especially suitable for the anchoring connection in the tension erection construction of large cross-section support type high-density polyethylene wire expansion wire and sparsely wound round wire concentric stranded aluminum wire. At the same time, it can also be used for larger cross-section Anchor connection for concentrically stranded aluminum conductors of layered round wires. The wire clamping device of the present invention has a large load-bearing capacity when anchored, no slippage, and the structure of the clamped part of the wire has no deformation and no indentation on the surface; the weight of the wire clamping device is reduced, which is convenient for high-altitude operations; The anchoring connection of cross-section enlarged wires provides a safe and reliable guarantee, and solves a major problem of lack of clamping tools for enlarged diameter wires in the wiring construction.
Description
技术领域 technical field
本发明属于输电线路施工机具及施工技术领域,具体涉及一种大截面扩径导线卡线器。The invention belongs to the field of power transmission line construction equipment and construction technology, and in particular relates to a large cross-section diameter-expanding wire gripping device.
背景技术 Background technique
对于电压等级高、输电容量大、高海拔地区等耐电晕性能有特殊要求的输电线路,在同样满足输电容量和线路工程要求的前提下,采用大截面、直径扩大的新型结构导线,可减少导线的总重量和导线分裂数;减少铁塔荷载和结构重量,降低线路的工程造价。在架线过程中,经常采用导线在空中压接的方式,导线夹紧工作要在空中完成,这样,对卡线器的要求更高,可见卡线器的使用性能对架线质量起着非常重要的作用。For transmission lines with special requirements on corona resistance performance such as high voltage level, large transmission capacity, and high altitude areas, on the premise of meeting the requirements of transmission capacity and line engineering, the use of new structural conductors with large cross-sections and enlarged diameters can reduce The total weight of the conductor and the number of conductor splits; reduce the tower load and structural weight, and reduce the engineering cost of the line. In the process of stringing, the method of crimping the wires in the air is often used, and the clamping work of the wires must be completed in the air. In this way, the requirements for the wire clamp are higher. It can be seen that the performance of the wire clamp plays a very important role in the quality of the stringing. important role.
根据导线卡线器的特定工作条件及要求,目前国内外导线卡线器的结构分两类,一类是钳口型导线卡线器,有钳口不挂胶和挂胶两种;另一类是楔型导线卡线器,在国内一般用在光纤等施工中。我国圆线同心绞导线普遍采用这种钳口不挂胶的卡线器,目前有多项专利,如:专利号为CN200980159448.5,发明名称为“卡线器”的发明专利申请,提供一种在拉线作用中操作性良好且拉线作用时不对线状体增加多余的负荷而能将线状体钳持的卡线器。其技术方案为:卡线器包含固定端卡线部和可动端卡线部,使可动端卡线部进行进退移动的第一动作部、和通过连接杆与第一动作部连接的第二动作部的各自一端,分别以可自由转动的方式安装在本体上,第一动作部的另一端以可自由转动的方式安装在连接杆的一端,而第二动作部的另一端则以可自由转动的方式安装在连接杆的中部,通过对连接杆的另一端以与固定端和可动端卡线部大致平行的方向进行牵引,使连接杆、第二动作部以及第一动作部联动,并使可动端卡线部相对固定端卡线部向前移动。According to the specific working conditions and requirements of the wire gripper, the structure of the wire gripper at home and abroad is divided into two types. One is the jaw-type wire gripper, which has two types: the jaw is not glued and the jaw is glued; the other is The first type is a wedge-shaped wire clamp, which is generally used in the construction of optical fibers in China. my country's round wire concentric twisted conductors generally use this kind of clamp without glue on the jaws. At present, there are many patents, such as: the patent number is CN200980159448.5, and the invention patent application named "cable clamp" provides a A wire gripper which has good operability in the wire-drawing action and can clamp the wire-like body without adding unnecessary load to the wire-like body during the wire-drawing action. Its technical solution is: the wire clamping device includes a fixed end clamping part and a movable end clamping part, a first action part that makes the movable end clamping part move forward and backward, and a second action part that is connected to the first action part through a connecting rod. One end of each of the two action parts is installed on the body in a freely rotatable manner, the other end of the first action part is installed on one end of the connecting rod in a freely rotatable manner, and the other end of the second action part is rotatable. It is installed in the middle of the connecting rod in a free-rotating manner. By pulling the other end of the connecting rod in a direction roughly parallel to the clamping part of the fixed end and the movable end, the connecting rod, the second action part and the first action part are linked , and make the wire clamping part of the movable end move forward relative to the clamping part of the fixed end.
申请号为CN201120108487.7,发明名称为“卡线器”的实用新型专利,公开了一种卡线器,包括形成卡线器四连杆结构主体的主板、连板、拉臂、主板右边的横向通槽、拉环、下钳口和上钳口,主板中段有一段圆弧通槽;上钳口的背部偏左位置铰接在连扳上,右端头通过一个销轴卡接在所述主板的圆弧通槽中;圆弧通槽的方向和弧度应保证上钳口始终与下钳口的沿口平行;拉臂上设有一弹簧支架,该弹簧支架上安装有一个使卡线器能自动复位的弹簧。这种卡线器上下钳口的沿口在任何状态下都一直保持着互相平行的状态。The application number is CN201120108487.7, and the utility model patent with the invention name "clamping device" discloses a cable clamping device, which includes a main board forming the main body of the four-link structure of the wire clamping device, a connecting plate, a pull arm, and the right side of the main board. Horizontal through slot, pull ring, lower jaw and upper jaw, there is a section of circular arc through slot in the middle of the main board; the back of the upper jaw is hinged on the connecting lever at the left side, and the right end is clamped to the main board through a pin shaft In the circular arc slot; the direction and radian of the arc slot should ensure that the upper jaw is always parallel to the edge of the lower jaw; there is a spring bracket on the pull arm, and a spring bracket is installed on the spring bracket so that the wire clamp can Self-returning spring. The edges of the upper and lower jaws of the wire gripper are always kept parallel to each other in any state.
另有申请号为CN200920070588.2,发明名称为“一种卡线器”的实用新型专利,其技术方案为挂胶导线卡线器,卡线器包括卡线器本体,卡线器本体包括连板、拉环、上钳口、下钳口、主板、拉臂、保险钩,主板与下钳口由三个销轴连接,连板与下钳口由销轴连接;连板、上钳口、保险钩的一端由销轴连接;连板和主板由销轴连接;上钳口、下钳口在用于线的两个面上设有∪形的卡线凹腔,卡线凹腔的内表面设有波浪形的凹凸点。Another application number is CN200920070588.2, and the invention name is a utility model patent of "a wire clamp". Its technical solution is a wire clamp for glued wires. Plate, pull ring, upper jaw, lower jaw, main board, pull arm, safety hook, main board and lower jaw are connected by three pin shafts, connecting plate and lower jaw are connected by pin shafts; connecting plate,
上述专利均适用于直径较小的三层及以下圆线同心绞普遍导线,图5为三层圆线同心绞铝导线横截面图,这种卡线器不能用于扩径导线的夹紧连接,存在的主要问题是:1.钳口长度过短,超出扩径导线允许的检验应力;2.钳口平行度差,局部应力过于集中;3.钳口表面设计有防滑纹或与导线表面相同的螺旋线,必然会损伤导线表面;4.夹持导线的拉断力小于额定拉断力的50%(标准值为额定拉断力的90%);5.上下钳口与导线为三点接触,不适用扩径导线;6.钳口表面挂胶易脱落,造成卡线器滑落。上述问题会使扩径导线截面严重变形;表层受损或断线;握紧力降低;导线拉断力严重不达标等,甚至会出现导线从卡线器中滑脱而造成架线施工的重大人身伤亡事故,因此,对于这种特殊结构的大截面扩径导线而言,必须设计专用的卡线器。The above-mentioned patents are all applicable to concentrically twisted common conductors of three-layer round wires with a smaller diameter and below. Figure 5 is a cross-sectional view of a three-layer round wire concentrically twisted aluminum wire. , the main problems are: 1. The length of the jaws is too short, which exceeds the allowable inspection stress of the expanded wire; 2. The parallelism of the jaws is poor, and the local stress is too concentrated; The same helical wire will inevitably damage the surface of the wire; 4. The breaking force of the clamping wire is less than 50% of the rated breaking force (the standard value is 90% of the rated breaking force); 5. The upper and lower jaws and the wire are three Point contact is not suitable for expanded wires; 6. The glue on the surface of the jaws is easy to fall off, causing the wire clamp to slip. The above problems will seriously deform the section of the expanded wire; the surface layer will be damaged or broken; the gripping force will be reduced; Casualty accidents, therefore, for the large-section expanded-diameter wire of this special structure, a special wire clamp must be designed.
由于DL5009.2《电力建设安全工作规程第2部分:架空电力线路》和DL/T 875《输电线路施工机具设计、试验基本要求》电力行业标准规定,施工中导线卡线器不应有滑移、不应损伤导线。而普通圆线同心绞铝导线卡线器不能满足扩径导线的使用要求,施工中通常情况下不同的导线结构和线径配有专用的卡线器,该扩径导线卡线器通过对卡线器结构平衡力系、钳体形状、钳口长度、钳口最大开度、钳口两端坡口等结构参数的优化设计,使卡线器及导线达到了较理想的受力状态,在保证握力的同时卡线器不滑移、不损伤导线,为扩径导线提供了一种安全可靠的锚固工器具。Due to the provisions of DL5009.2 "Safety Work Regulations for Electric Power Construction Part 2: Overhead Power Lines" and DL/T 875 "Basic Requirements for Design and Test of Transmission Line Construction Equipment" in the power industry standard, there should be no slippage of the wire clamp during construction. , The wire should not be damaged. However, the ordinary round wire concentric twisted aluminum wire clamp cannot meet the requirements for the use of expanded wires. Usually, different wire structures and wire diameters are equipped with special wire clamps during construction. The optimal design of structural parameters such as the balance force system of the wire clamp structure, the shape of the clamp body, the length of the jaws, the maximum opening of the jaws, and the bevels at both ends of the jaws have made the wire clamps and wires reach an ideal stress state. While ensuring the grip strength, the wire clamp does not slip and does not damage the wire, providing a safe and reliable anchoring tool for the expanded wire.
按照相关标准规定,大截面扩径导线卡线器应满足以下性能要求:According to the relevant standards, the large cross-section expansion wire clamp should meet the following performance requirements:
1)在额定载荷作用下导线应无压痕、无变形无相对滑移;1) Under the rated load, the wire should have no indentation, no deformation and no relative slippage;
2)在1.25倍额定载荷作用下,导线应无压痕、无变形(无压扁,表面无滑痕和鸟巢状变形);2) Under the action of 1.25 times the rated load, the wire should have no indentation or deformation (no flattening, no slip marks and bird's nest deformation on the surface);
3)在2倍额定载荷作用下,卡线器无明显相对滑移,卸载后卡线器应装、拆自如;3) Under the action of 2 times the rated load, the wire clamp has no obvious relative slippage, and the wire clamp should be installed and disassembled freely after unloading;
4)安全系数应不小于3。4) The safety factor should not be less than 3.
发明内容 Contents of the invention
本发明目的在于提供一种大截面扩径导线卡线器,特别适用于大截面支撑型高密度聚乙烯扩径导线及疏绕型圆线同心绞铝导线等(以下简称扩径导线)的张力架线施工,同时,也可用于更大截面四层圆线同心绞铝导线(以下简称普通导线)的锚固连接,本发明通过一种大截面扩径导线卡线器结构的优化设计,提供了一种架线施工用大截面扩径导线与锚固受力系统连接的夹紧装置,起到了扩径导线工作状态下张紧力的传递作用。The object of the present invention is to provide a large cross-section expanding wire gripper, which is especially suitable for the tension of large cross-section supported high-density polyethylene expanding wires and sparsely wound round wire concentric twisted aluminum wires (hereinafter referred to as expanding wires). Wire construction, at the same time, can also be used for the anchoring connection of larger cross-section four-layer round wire concentric twisted aluminum conductors (hereinafter referred to as ordinary wires). The present invention provides The invention discloses a clamping device for connecting a large-section enlarged-diameter wire used for stringing construction with an anchoring force-bearing system, which plays the role of transmitting the tension force of the expanded-diameter wire in the working state.
为实现上述发明目的,本发明采取的技术方案为:For realizing above-mentioned purpose of the invention, the technical scheme that the present invention takes is:
一种大截面扩径导线卡线器,所述卡线器为四连杆结构,包括平行设置且铰接于C点的上夹板和定压板,与所述上夹板铰接于D点、与所述定压板铰接于E点的动压板,铰接于B点的拉板和拉环,所述拉板与动压板之间铰接于A点;所述定压板的右侧设有沿厚度方向贯通的滑槽,所述拉板和拉环的铰接点可于所述滑槽两端点之间滑动;其改进之处在于:A large cross-section expanded-diameter wire clamp, the clamp is a four-link structure, including an upper splint and a constant pressure plate arranged in parallel and hinged at point C, hinged with the upper splint at point D, and the The fixed pressure plate is hinged to the dynamic pressure plate at point E, hinged to the pull plate and the pull ring at point B, and the tie plate and the dynamic pressure plate are hinged at point A; the right side of the fixed pressure plate is provided with a slide through the thickness direction. Groove, the hinge point of the pull plate and the pull ring can slide between the two ends of the chute; the improvements are:
所述铰接点A与滑槽远端点之间的距离为L1,所述铰接点A和E之间的距离为L2,铰接点E与滑槽远端点之间的水平距离为L3,则:The distance between the hinge point A and the far end of the chute is L1 , the distance between the hinge points A and E is L2 , and the horizontal distance between the hinge point E and the far end of the chute is L 3 , then:
L1=(7.10~7.14)d;L 1 =(7.10~7.14)d;
L2=(7.68~7.72)d;L 2 =(7.68~7.72)d;
L3=(11.30~11.34)d;L 3 =(11.30~11.34)d;
d为导线直径;d is the wire diameter;
所述上夹板和定压板的内表面各设有光滑的钳口夹紧圆弧面,所述圆弧面的两端设有坡度段和圆弧过渡段。The inner surfaces of the upper splint and the constant pressure plate are respectively provided with smooth jaws to clamp arc surfaces, and both ends of the arc surfaces are provided with slope sections and arc transition sections.
本发明的又一优选技术方案为:所述钳口夹紧圆弧面的圆弧深度h≥16mm,圆弧面的圆弧角α≥152°。Another preferred technical solution of the present invention is: the arc depth h≥16mm of the arc surface clamped by the jaws, and the arc angle α≥152° of the arc surface.
本发明的又一优选技术方案为:所述圆弧面坡度段的坡度γ≥10°,坡度段长度≥30mm。Another preferred technical solution of the present invention is: the slope γ of the slope section of the circular arc surface ≥ 10°, and the length of the slope section ≥ 30mm.
本发明的又一优选技术方案为:所述上夹板和定压板的长度L=[(9.23-9.27)d-20]mm,所述上夹板和定压板之间的最大间距≤1.05d。Another preferred technical solution of the present invention is: the length L of the upper splint and the constant pressure plate = [(9.23-9.27)d-20] mm, and the maximum distance between the upper splint and the constant pressure plate is ≤1.05d.
本发明的又一优选技术方案为:所述上夹板和定压板的安装平行度≤0.3mm。Another preferred technical solution of the present invention is: the installation parallelism of the upper splint and the constant pressure plate is ≤0.3mm.
本发明的又一优选技术方案为:所述拉板上设置扭簧。Another preferred technical solution of the present invention is: a torsion spring is arranged on the pulling plate.
本发明的又一优选技术方案为:所述拉板和拉环的铰接点靠近滑槽远端点时,卡线器处于卸载状态;所述拉板和拉环的铰接点靠近滑槽近端点时,卡线器处于夹紧状态。Another preferred technical solution of the present invention is: when the hinge point of the pull plate and the pull ring is close to the far end of the chute, the wire clamp is in an unloaded state; the hinge point of the pull plate and the pull ring is close to the proximal end of the chute When pointing, the clamp is in a clamped state.
由于采用了上述技术方案,本发明不但解决了900mm2及以上大截面各种特殊结构扩径导线的锚固连接问题,也适用于更大截面四层以上普通导线的锚固连接,与现有卡线器相比,本发明的有益效果包括:Due to the adoption of the above-mentioned technical scheme, the present invention not only solves the anchoring connection problem of various special structure-expanded wires with a large cross-section of 900mm2 and above, but is also suitable for the anchoring connection of ordinary wires with a larger cross-section of four layers or more. Compared with the device, the beneficial effects of the present invention include:
1.锚固时的承载能力大,没有滑移,且导线被夹持部位的结构无变形,钳口表面为光滑圆弧面,故导线表面无压痕;1. When anchoring, the bearing capacity is large, there is no slippage, and the structure of the clamped part of the wire is not deformed, and the surface of the jaw is a smooth arc surface, so there is no indentation on the surface of the wire;
2.连杆机构的杠杆比L1、L2和L3设计合理,适用扩径导线结构形式的范围宽泛,夹持性能好;2. The lever ratios L 1 , L 2 and L 3 of the connecting rod mechanism are designed reasonably, and the range of structure applicable to the expansion wire structure is wide, and the clamping performance is good;
3.上下钳口的平行度好,上夹板和定压板之间的平行偏差小于0.3mm,导线表面与钳口始终保持足够的接触受力面积,且钳口两端设有坡度段和圆弧过渡段,不会产生夹紧状态下的应力集中;3. The parallelism of the upper and lower jaws is good, the parallel deviation between the upper splint and the constant pressure plate is less than 0.3mm, the surface of the wire and the jaws always maintain a sufficient contact force area, and the two ends of the jaws are equipped with slope sections and arcs The transition section will not produce stress concentration in the clamped state;
4.结合导线及钳口材料特性,钳口采取光滑表面设计,其表面热处理及粗糙度要求定位准确,设计合理;4. Combined with the material characteristics of the wire and the jaw, the jaw adopts a smooth surface design, and its surface heat treatment and roughness require accurate positioning and reasonable design;
5.在采用特殊高强钢的前提下,每一个部件进行了结构优化设计,使卡线器的重量减轻,便于高空作业;5. Under the premise of using special high-strength steel, each component has been optimized in structure, which reduces the weight of the wire clamp and facilitates high-altitude operations;
6.良好的夹持性能为大截面扩径导线的锚固连接提供了安全可靠保障,解决了架线施工中扩径导线夹紧工器具缺乏的一大难题。6. Good clamping performance provides a safe and reliable guarantee for the anchoring connection of large-section expanded-diameter wires, and solves a major problem in the lack of clamping tools for expanded-diameter wires in wiring construction.
附图说明 Description of drawings
下面结合附图对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings.
图1是卡线器适用扩径导线横截面结构示意图形式一;Figure 1 is a schematic diagram of the cross-sectional structure of the expanded diameter wire applicable to the wire clamp;
图2是卡线器适用扩径导线横截面结构示意图形式二;Fig. 2 is the second schematic diagram of the cross-sectional structure of the expanded diameter wire applicable to the wire clamp;
图3是卡线器适用扩径导线横截面结构示意图形式三;Fig. 3 is the third schematic diagram of the cross-sectional structure of the expanded diameter wire applicable to the wire gripper;
图4是卡线器适用扩径导线横截面结构示意图形式四;Figure 4 is a schematic diagram of the cross-sectional structure of the expanded diameter wire applicable to the wire gripper Form IV;
图5为三层圆线铝导线横截面结构示意图;Fig. 5 is a schematic diagram of a cross-sectional structure of a three-layer round aluminum conductor;
图6为卡线器工作状态(在输电线路张力架线施工中应用)示意图;Fig. 6 is a schematic diagram of the working state of the clamping device (applied in the tension stringing construction of the transmission line);
图7是卡线器结构(最小开口位置)示意图;Fig. 7 is a schematic diagram of the structure (minimum opening position) of the wire gripper;
图8是卡线器主要结构参数示意图;Fig. 8 is a schematic diagram of the main structural parameters of the wire gripper;
图9是上、下夹板钳口结构示意图;Fig. 9 is a schematic structural view of the jaws of the upper and lower splints;
图10是钳口夹紧大截面扩径导线结构型式示意图;Fig. 10 is a schematic diagram of the structure of a large cross-section enlarged diameter wire clamped by the jaws;
附图标记:Reference signs:
1-导线,2-卡线器,3-上夹板,4-定压板,5-拉环,6-拉板,7-弹簧夹紧部件,8-动压板,9-滑槽;1-wire, 2-clamp, 3-upper splint, 4-fixed pressure plate, 5-pull ring, 6-pull plate, 7-spring clamping parts, 8-dynamic pressure plate, 9-chute;
A、B、C、D、E连杆机构铰接点;A, B, C, D, E linkage hinge points;
L1、L2、L3铰接点之间距离;Distance between L1, L2, L3 hinge points;
H最大开口距离;H maximum opening distance;
γ上下夹板坡度;γ the slope of the upper and lower splints;
C钳口接触面玄长;The contact surface of the C jaw is long;
R圆弧半径;R arc radius;
h圆弧深度;h arc depth;
α圆弧角。α arc angle.
具体实施方式 Detailed ways
下面结合实例对本发明进行详细的说明。Below in conjunction with example the present invention is described in detail.
本专利合理的杠杆式连杆机构的承载力系及钳口与扩径导线最佳的接触面配合技术,提供了一种适合扩径导线锚固,并符合施工标准要求的卡线器。The reasonable bearing capacity system of the lever-type connecting rod mechanism and the optimal contact surface matching technology between the jaw and the expanding wire provide a wire clamp suitable for anchoring the expanding wire and meeting the requirements of construction standards.
图1至图4为本发明适用的不同形式扩径结构的导线横截面示意图。图1扩径导线内圈全部抽空,钢芯用绝缘材料包裹,再以十字形高密度聚乙烯支撑两层铝单线;图2和图3扩径导线的中层铝线按比例抽股,结构松散,受力不均。图4为另一形式扩径导线。由于导线表面的接触力不能均匀的传递,导线的抗拉力减小,受压部位容易变形,加之导线直径和额定工作载荷是前所未有的,本发明技术主要是合理解决这种卡线器正压力与摩擦力之间;滑移量与导线损伤;负载与重量的固有矛盾。通过连杆机构铰节点之间的杠杆比L1∶L2∶L3(杠杆力系)与钳口形状及参数合理匹配,使其受力系统处于最佳状态,达到在保证握力的同时不滑移、不损伤导线的结果。Fig. 1 to Fig. 4 are cross-sectional diagrams of wires with different diameter-expanding structures applicable to the present invention. Figure 1 The inner ring of the expanded diameter conductor is completely evacuated, the steel core is wrapped with insulating material, and then two layers of aluminum single wire are supported by cross-shaped high-density polyethylene; the middle layer aluminum wire of the expanded diameter conductor is drawn in proportion to the strands in Figure 2 and Figure 3, and the structure is loose , uneven force. Figure 4 is another form of expanded diameter wire. Since the contact force on the surface of the wire cannot be transmitted evenly, the tensile force of the wire is reduced, and the compressed part is easily deformed. In addition, the diameter of the wire and the rated working load are unprecedented. The technology of the present invention is mainly to reasonably solve the normal pressure of the wire clamp Between friction and slippage and wire damage; inherent contradiction between load and weight. Through the reasonable matching of the lever ratio L1:L2:L3 (lever force system) between the joints of the linkage mechanism and the shape and parameters of the jaws, the force-bearing system is in the best state, so as to ensure the grip force without slipping, Result without damaging the wire.
图5为普通三层铝导线横截面结构示意图。FIG. 5 is a schematic diagram of a cross-sectional structure of a common three-layer aluminum wire.
卡线器是放线、断线、紧线、附件安装等架线施工中,被架设导线需要锚固时必须的连接类工器具,用于被架设导线任何部位的各类临锚和紧线承拉的张紧系统中。图6为扩径导线卡线器在输电线路张力架线施工中,夹紧导线时的工作状态示意图。卡线器在锚固系统中要承担着25%以上导线拉断力的传递。施工中,将卡线器及锚线绳(牵引绳)与扩径导线相连接,使导线的张力传递给锚绳,实现收放导线,调整导线弧垂、导线对接,附件安装及更换导线等。The wire clamp is a necessary connection tool when the erected wire needs to be anchored during the wire erection construction such as setting out, breaking the wire, tightening the wire, and installing accessories. Pull in the tensioning system. Fig. 6 is a schematic diagram of the working state of the expanded-diameter conductor gripping device when clamping the conductor during the construction of the tensioned wire of the transmission line. In the anchoring system, the wire gripper should undertake the transmission of more than 25% of the wire breaking force. During construction, connect the wire clamp and the anchor rope (traction rope) with the expanded wire, so that the tension of the wire is transmitted to the anchor rope, so as to realize the retraction and release of the wire, adjust the sag of the wire, connect the wire, install accessories and replace the wire, etc. .
图7为扩径导线卡线器结构示意图,该结构为杠杆连杆式机构,其卡线器主要由上夹板3、定压板4、拉环5、拉板6、弹簧夹紧部件7和动压板8。定压板4设有滑槽9,滑槽9沿卡线器厚度方向贯通,滑槽9有2个端点,靠近定压板4边缘的端点定义为滑槽9的远端点,靠近定压板4内部的端点定义为滑槽9的近端点。该机构由拉环5施加以外力,在夹紧扩径导线1过程中,外力为受力系统的拉力,拉力通过拉板6传力至动压板8、上夹板3、导线1及定压板4。由于杠杆作用,使上下夹板产生大于拉力的夹紧力,在夹紧力的作用下,扩径导线与上下夹板产生摩擦力,克服导线的拉力,不使导线滑出,达到夹持住导线的目的,此时,拉环5与拉板6的铰接点B位于靠近滑槽9近端点的位置,卡线器处于最小开口状态。在卡线器2拆卸时,外力为工作人员给予拉环5的推力,推力通过拉板6传力至动压板8,使拉环5沿定压板4上的水平槽移动,推动拉板6与动压板8以E点为轴心转动,同时动压板8带动上夹板3上移,钳口被打开,此时,拉环5与拉板6的铰接点B位于靠近滑槽9远端点的位置,卡线器处于最大开口状态。Fig. 7 is a schematic diagram of the structure of the expanding diameter wire clamping device. This structure is a lever linkage mechanism. Platen 8. The constant pressure plate 4 is provided with a chute 9, and the chute 9 runs through the thickness direction of the wire clamp. The chute 9 has two endpoints, and the endpoint close to the edge of the constant pressure plate 4 is defined as the far end point of the chute 9, which is close to the interior of the constant pressure plate 4. The end point of is defined as the proximal end point of the chute 9. The mechanism is applied with an external force by the pull ring 5. In the process of clamping the expanded
卡线器2的拉板6上装有特制扭簧7,能保证在没有外力作用时,产生更有效的预夹紧力。使用时只须推动B点,夹板张开,将导线1放置于夹板中,松开卡线器2,在扭簧7的作用下,上下夹板即可夹住导线1,当施加以外力后,由于是杆杠连杆式机构,随着拉力的增大,摩擦力也越来越大,从而实现卡线器2的功能。A special torsion spring 7 is installed on the pull plate 6 of the
图8为卡线器主要结构参数示意图,本发明考虑导线结构及参数及对卡线器额定载荷(放紧线张力)、使用性能要求等因素,根据扩径导线与普通导线的结构差别大、额定工作载荷大的特点进行设计。为此,本专利采取具体技术方案如下:Fig. 8 is a schematic diagram of the main structural parameters of the wire clamp. The present invention considers the structure and parameters of the wire clamp, the rated load of the wire clamp (tension line tension), and the performance requirements of the wire clamp. It is designed with the characteristics of large rated working load. For this reason, this patent takes concrete technical scheme as follows:
1)合理设计调整力系的配比1) Reasonably design and adjust the ratio of the force system
上夹板3在D点通过铰链与动压板8联接,C点在定压板4的弧形滑槽内滑动。上夹板3与定压板4的圆弧面共同夹紧导线,这时导线的拉力由上下夹板与导线的两个接触面所产生的摩擦力来承受,为保证上夹板在整个机构运动中保持平动,将定压板4上圆弧槽对上夹板的约束反力与水平线的夹角为一范围定值52.90°~52.94°;连杆机构铰节点B、A、E之间的距离L1、L2、L3为一组定长。The upper splint 3 is connected with the dynamic pressure plate 8 through a hinge at point D, and the point C slides in the arc-shaped chute of the constant pressure plate 4 . The upper splint 3 and the circular arc surface of the constant pressure plate 4 clamp the wire together. At this time, the pulling force of the wire is borne by the friction force generated by the two contact surfaces of the upper and lower splints and the wire. Move, set the angle between the restraining reaction force of the upper splint on the upper splint of the constant pressure plate 4 and the horizontal line to a fixed value of 52.90°~52.94°; the distances L1, L2 between the joints B, A, and E of the linkage , L3 is a set of fixed length.
2)适度增加钳口长度2) Moderately increase the length of the jaws
按照标准规定卡线器的钳口长度L≥6.5d-20mm设计不能满足工程要求,本发明经过多次设计——试验——研究,得到扩径导线卡线器钳口长度(L)的选择应为:L≥9.25d-20mm,增加钳口长度是提高钳口的夹持力,降低导线局部接触应力最有效的措施之一,但是,卡线器是一个杠杆连杆式机构,为保证在夹紧导线时个连杆间的平衡,卡线器体积必须增大,若钳口过长卡线器重量过大,给高空作业带来很大困难,反之,则损伤导线,降低导线的额定拉断力。因此,钳口长度是导线与接触面的摩擦力产生的接触应力应大于钳口的夹持力即合理的平衡状态下对应的最小值。According to the standard, the design of the jaw length L≥6.5d-20mm of the clamping device cannot meet the engineering requirements. The present invention obtains the selection of the jaw length (L) of the expanding wire clamping device through repeated design-test-research. It should be: L≥9.25d-20mm. Increasing the jaw length is one of the most effective measures to increase the clamping force of the jaw and reduce the local contact stress of the wire. However, the wire clamp is a lever-link mechanism. When clamping the wire, the balance between the two connecting rods must increase the size of the wire clamp. If the jaw is too long and the weight of the clamp is too large, it will bring great difficulties to high-altitude operations. On the contrary, it will damage the wire and reduce the weight of the wire. Rated breaking force. Therefore, the length of the jaws is the minimum value corresponding to the contact stress generated by the friction between the wire and the contact surface should be greater than the clamping force of the jaws, that is, a reasonable equilibrium state.
3)确定合理的钳体最大开口3) Determine the reasonable maximum opening of the pliers
卡线器2上下夹板最大开口首先根据扩径导线的直径定位,为导线方便放入、取出留有最小的间隙,然后,在此基础上设计机构力系的平衡。通常最小间隙不大于2mm。The maximum opening of the upper and lower splints of the
4)钳口两端坡口设计4) Bevel design at both ends of the jaw
由结构决定,卡线器在工作状态下,上下夹板与外力作用线有一定的夹角,其垂直分力在钳口端部会对导线产生应力集中,为防止损伤或切断铝线,上下夹板两端部必须设计足够长的坡度和光滑的圆弧过渡,其坡度为1.00∶5.67,且坡口长度≥30mm。Determined by the structure, when the clamp is in working condition, there is a certain angle between the upper and lower splints and the line of external force, and its vertical force will produce stress concentration on the wires at the end of the jaws. In order to prevent damage or cut off the aluminum wire, the upper and lower splints The end must be designed with a sufficiently long slope and smooth arc transition, the slope is 1.00:5.67, and the groove length is ≥30mm.
图9为上下夹板钳口结构参数示意图,本发明增大钳口与扩径导线的包容量,即加大槽深和钳口圆弧包角。导线被夹线后钳口间必须有一定的空隙,避免受力过程中上夹板压紧定压板,导线滑移。所以槽深应小于导线半径。同时上下夹板钳体形状均采用和扩径导线外表面相贴合的圆弧面,使上下夹板夹紧导线时和导线啮合在一起,其圆形面的包容面越大越好,但应以上下钳口夹紧时不碰为原则,将钳口对导线1的挤压应力降低到最小值。Fig. 9 is a schematic diagram of the structural parameters of the jaws of the upper and lower splints. The present invention increases the containment capacity of the jaws and the expanded wire, that is, increases the groove depth and the arc wrap angle of the jaws. After the wire is clamped, there must be a certain gap between the jaws to prevent the upper splint from pressing the constant pressure plate and the wire slipping during the stress process. So the groove depth should be less than the wire radius. At the same time, the shape of the upper and lower splint clamps adopts the arc surface that fits the outer surface of the expanded diameter wire, so that the upper and lower splints engage with the wire when clamping the wire. The larger the containment surface of the circular surface, the better, but the upper and lower clamps should The principle is not to touch when the jaws are clamped, and the extrusion stress of the jaws on the
图10为钳口夹紧大截面扩径导线结构示意图,此图为卡线器夹紧导线状态下,卡线器与导线表面接触状态,此时,导线与上夹板3和定压板4的光滑圆弧表面相贴合。Figure 10 is a schematic diagram of the structure of a large cross-section enlarged diameter wire clamped by the jaws. This figure shows the state where the wire gripper is in contact with the surface of the wire when the wire gripper is clamping the wire. The arc surface fits together.
此处已经根据特定的示例性实施例对本发明进行了描述。对本领域的技术人员来说在不脱离本发明的范围下进行适当的替换或修改将是显而易见的。示例性的实施例仅仅是例证性的,而不是对本发明的范围的限制,本发明的范围由所附的权利要求定义。The invention has been described herein in terms of specific exemplary embodiments. Appropriate substitutions or modifications will be apparent to those skilled in the art without departing from the scope of the present invention. The exemplary embodiments are illustrative only, and not limiting of the scope of the invention, which is defined by the appended claims.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210249732.5A CN102832570B (en) | 2012-07-18 | 2012-07-18 | A kind of heavy in section expanded conductor fixing-line device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201210249732.5A CN102832570B (en) | 2012-07-18 | 2012-07-18 | A kind of heavy in section expanded conductor fixing-line device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN102832570A true CN102832570A (en) | 2012-12-19 |
| CN102832570B CN102832570B (en) | 2015-12-02 |
Family
ID=47335592
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201210249732.5A Active CN102832570B (en) | 2012-07-18 | 2012-07-18 | A kind of heavy in section expanded conductor fixing-line device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102832570B (en) |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103388418A (en) * | 2013-08-01 | 2013-11-13 | 国家电网公司 | Method for connecting pulling wires through transmission line non-self-supporting pole/tower pulling wire repair and backup protection type connector |
| CN103474915A (en) * | 2013-09-11 | 2013-12-25 | 江苏恒安电力工具有限公司 | Wire clamping device |
| CN103956684A (en) * | 2014-05-15 | 2014-07-30 | 固力发集团有限公司 | Hinge-type cable clamp installation tool |
| CN106238624A (en) * | 2016-08-26 | 2016-12-21 | 深圳市朝阳光科技有限公司 | The automatic wire arrangement structure of wire rod |
| TWI618607B (en) * | 2012-12-27 | 2018-03-21 | Nagaki Seiki Co Ltd | Clamp |
| WO2019002718A1 (en) * | 2017-06-30 | 2019-01-03 | Rte Reseau De Transport D'electricite | Device and method for gripping a cable by means of a strain relief cable clamp |
| CN110752547A (en) * | 2019-11-26 | 2020-02-04 | 国网四川省电力公司眉山供电公司 | Auxiliary tool for preventing drainage line from falling off in distribution network operation and method for preventing it from falling |
| CN111609090A (en) * | 2020-06-10 | 2020-09-01 | 国网四川电力送变电建设有限公司 | A polypropylene rope clamp, method of use and application |
| CN114156782A (en) * | 2020-09-07 | 2022-03-08 | 中国电力科学研究院有限公司 | Overhead temporary anchoring anti-bending wire clamping device for transmission conductor |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR3068422B1 (en) * | 2017-06-30 | 2019-07-26 | Rte Reseau De Transport D’Electricite | DEVICE AND METHOD FOR VOLTAGE LOCKING A CABLE USING A GREEN-CABLE CLAMP |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2779689Y (en) * | 2005-03-02 | 2006-05-10 | 嘉善东方电力机具制造有限公司 | Wire fixer with eccentric slot roller |
| CN101752816A (en) * | 2009-12-21 | 2010-06-23 | 中国电力科学研究院 | Dead-end clamp for supporting expanded diameter conductors |
| CN202084852U (en) * | 2011-04-10 | 2011-12-21 | 孙磊 | Line jamming device |
| CN102439808A (en) * | 2009-06-30 | 2012-05-02 | 株式会社永木精机 | Wire clamp |
-
2012
- 2012-07-18 CN CN201210249732.5A patent/CN102832570B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2779689Y (en) * | 2005-03-02 | 2006-05-10 | 嘉善东方电力机具制造有限公司 | Wire fixer with eccentric slot roller |
| CN102439808A (en) * | 2009-06-30 | 2012-05-02 | 株式会社永木精机 | Wire clamp |
| US20120132874A1 (en) * | 2009-06-30 | 2012-05-31 | Nagaki Seiki Co., Ltd | Wire grip |
| CN101752816A (en) * | 2009-12-21 | 2010-06-23 | 中国电力科学研究院 | Dead-end clamp for supporting expanded diameter conductors |
| CN202084852U (en) * | 2011-04-10 | 2011-12-21 | 孙磊 | Line jamming device |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| TWI618607B (en) * | 2012-12-27 | 2018-03-21 | Nagaki Seiki Co Ltd | Clamp |
| CN103388418A (en) * | 2013-08-01 | 2013-11-13 | 国家电网公司 | Method for connecting pulling wires through transmission line non-self-supporting pole/tower pulling wire repair and backup protection type connector |
| CN103474915A (en) * | 2013-09-11 | 2013-12-25 | 江苏恒安电力工具有限公司 | Wire clamping device |
| CN103956684A (en) * | 2014-05-15 | 2014-07-30 | 固力发集团有限公司 | Hinge-type cable clamp installation tool |
| CN106238624A (en) * | 2016-08-26 | 2016-12-21 | 深圳市朝阳光科技有限公司 | The automatic wire arrangement structure of wire rod |
| WO2019002718A1 (en) * | 2017-06-30 | 2019-01-03 | Rte Reseau De Transport D'electricite | Device and method for gripping a cable by means of a strain relief cable clamp |
| FR3068423A1 (en) * | 2017-06-30 | 2019-01-04 | Rte Reseau De Transport D’Electricite | DEVICE AND METHOD FOR VOLTAGE LOCKING A CABLE USING A GREEN-CABLE CLAMP |
| CN110752547A (en) * | 2019-11-26 | 2020-02-04 | 国网四川省电力公司眉山供电公司 | Auxiliary tool for preventing drainage line from falling off in distribution network operation and method for preventing it from falling |
| CN111609090A (en) * | 2020-06-10 | 2020-09-01 | 国网四川电力送变电建设有限公司 | A polypropylene rope clamp, method of use and application |
| CN114156782A (en) * | 2020-09-07 | 2022-03-08 | 中国电力科学研究院有限公司 | Overhead temporary anchoring anti-bending wire clamping device for transmission conductor |
| CN114156782B (en) * | 2020-09-07 | 2026-01-06 | 中国电力科学研究院有限公司 | A high-altitude temporary anchor anti-bending clamp for power transmission lines |
Also Published As
| Publication number | Publication date |
|---|---|
| CN102832570B (en) | 2015-12-02 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102832570B (en) | A kind of heavy in section expanded conductor fixing-line device | |
| CN202949173U (en) | Wire clamping device | |
| CN103227431B (en) | 220kV long span super high town suspension insulator charged for replacement method | |
| CN104882830B (en) | A kind of cable drum draws fixture | |
| CN116960657B (en) | A cable docking enhancement device | |
| CN204150945U (en) | Track clamper and arc orbit rail clamping device | |
| CN203806962U (en) | Cable terminal head lifting fixture | |
| CN202550413U (en) | Parallel bunched cable tightener | |
| CN107370074A (en) | The precompressed pressing device and method of carbon fiber composite core wire assorted golden tool | |
| CN203466505U (en) | Device for vertically pulling cable | |
| CN205377194U (en) | Auto -lock cable fixing device | |
| CN112531578A (en) | Wire insulating layer pulling device | |
| CN203434529U (en) | Double hook wire grip | |
| CN207339089U (en) | Line fixing device more than bypass cable | |
| CN102364792A (en) | Strain hardware fitting for optical fiber composite overhead phase wire | |
| CN217135119U (en) | Strain clamp for power transmission | |
| CN203839879U (en) | Multifunction lead clamping device with die | |
| CN211666384U (en) | A automatic fixed establishment for power output combined material cross arm | |
| CN207039072U (en) | Attachment means for carbon fiber composite core wire assorted golden tool | |
| CN204243620U (en) | A kind of pre-twisting type overhang installation wire lifting device | |
| CN211183119U (en) | A device for cutting and preventing explosion of steel-cored aluminum stranded wire | |
| CN109004576B (en) | High-altitude temporary anchor crimping construction method suitable for gap type heat-resistant capacity-increasing lead | |
| CN101593943B (en) | Split conductor slack trimmer for overhead power transmission line | |
| CN202474691U (en) | Pulley component for overturning type tackle device | |
| CN106711895A (en) | Wire clamping device specially for carbon-fiber composite core wire |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CP03 | Change of name, title or address |
Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Patentee after: China Electric Power Research Institute Country or region after: China Patentee after: STATE GRID CORPORATION OF CHINA Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Patentee before: China Electric Power Research Institute Country or region before: China Patentee before: State Grid Corporation of China |
|
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Patentee after: CHINA ELECTRIC POWER RESEARCH INSTITUTE Co.,Ltd. Country or region after: China Patentee after: STATE GRID CORPORATION OF CHINA Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15 Patentee before: China Electric Power Research Institute Country or region before: China Patentee before: STATE GRID CORPORATION OF CHINA |
|
| CP03 | Change of name, title or address |