[go: up one dir, main page]

CN102819620A - 一种通过bim进行机房cfd模拟的装置 - Google Patents

一种通过bim进行机房cfd模拟的装置 Download PDF

Info

Publication number
CN102819620A
CN102819620A CN2011101563202A CN201110156320A CN102819620A CN 102819620 A CN102819620 A CN 102819620A CN 2011101563202 A CN2011101563202 A CN 2011101563202A CN 201110156320 A CN201110156320 A CN 201110156320A CN 102819620 A CN102819620 A CN 102819620A
Authority
CN
China
Prior art keywords
bim
cfd
display
simulation
processor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011101563202A
Other languages
English (en)
Inventor
沈丽菁
倪振华
顾中坚
杨铭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI ELECTRIC POWER COMMUNICATION CO Ltd
Shanghai Electric Power Corp
State Grid Corp of China SGCC
Original Assignee
Shanghai Electric Power Corp
Shanghai Jiulong Electric Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Electric Power Corp, Shanghai Jiulong Electric Power Technology Co Ltd filed Critical Shanghai Electric Power Corp
Priority to CN2011101563202A priority Critical patent/CN102819620A/zh
Publication of CN102819620A publication Critical patent/CN102819620A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及一种通过BIM进行机房CFD模拟的装置,该装置包括多个传感器、处理器、BIM模型数据库存储器、显示器、电源模块,所述的传感器、BIM模型数据库存储器、电源模块分别与处理器连接,所述的处理器与显示器连接。与现有技术相比,本发明具有结构简单、制造成本低,能帮助工程建设项目提高效率、降低风险和提高项目施工及运维管理水平等优点。

Description

一种通过BIM进行机房CFD模拟的装置
技术领域
本发明涉及一种模拟装置,尤其是涉及一种通过BIM进行机房CFD模拟的装置。
背景技术
BIM(Building Information Modeling,即建筑信息模型)是继CAD(计算机辅助设计)技术后出现在工程建设行业又一重要的计算机应用技术,正在引发建筑行业一次史无前例的彻底革命。该技术利用数字建模软件,提高项目设计、建造和管理的效率,并给采用该技术的建筑企业带来极大的新增价值。
CFD软件(Computational Fluid Dynamics,即计算流体动力学,简称CFD)。CFD是近代流体力学,数值数学和计算机科学结合的产物,是一门具有强大生命力的边缘科学。它以电子计算机为工具,应用各种离散化的数学方法,对流体力学的各类问题进行数值实验、计算机模拟和分析研究,以解决各种实际问题。CFD在最近20年中得到飞速的发展,除了计算机硬件工业的发展给它提供了坚实的物质基础外,还主要因为无论分析的方法或实验的方法都有较大的限制,例如由于问题的复杂性,既无法作分析解,也因费用昂贵而无力进行实验确定,而CFD的方法正具有成本低和能模拟较复杂或较理想的过程等优点。经过一定考核的CFD软件可以拓宽实验研究的范围,减少成本昂贵的实验工作量。在给定的参数下用计算机对现象进行一次数值模拟相当于进行一次数值实验,历史上也曾有过首先由CFD数值模拟发现新现象而后由实验予以证实的例子。CFD软件一般都能推出多种优化的物理模型,如定常和非定常流动、层流、紊流、不可压缩和可压缩流动、传热、化学反应等等。对每一种物理问题的流动特点,都有适合它的数值解法,用户可对显式或隐式差分格式进行选择,以期在计算速度、稳定性和精度等方面达到最佳。CFD软件之间可以方便地进行数值交换,并采用统一的前、后处理工具,这就省却了科研工作者在计算机方法、编程、前后处理等方面投入的重复、低效的劳动,而可以将主要精力和智慧用于物理问题本身的探索上。
上海容灾中心是国家电网公司在全国范围内建设的三个集中式信息系统容灾中心之一。本项目涉及专业众多、设备系统复杂、工期紧、对材料、人工等成本控制要求高。项目在建设过程中主要存在以下问题:
(一)容灾中心设备众多,系统复杂,在有限的空间管线走向非常复杂,传统的CAD图纸由于使用二维方式做设计、出图,不可避免存在设备、管线、结构直接的碰撞冲突,过去这些工作需要在施工现场由施工企业和设计单位综合协调,对项目进度和成本控制都有负面影响。
(二)容灾中心工期非常紧,参与项目的团队组成复杂。这需要对施工现场的施工进度计划、施工系统设计、人员交叉施工有很强的管理和控制。
(三)容灾中心投资有严格控制,但由于设备众多、系统复杂,在工程造价中占重要比例的设备、材料工程量统计往往参考设计单位和施工单位提供的概预算数据,作为业主缺乏有效的管理手段。
(四)容灾中心作为一个数据中心,其相关基础设施的可靠性直接关系到IT服务系统能否正常、持续、稳定运行。任何一部分的效率降低或者故障,都将导致IT服务的可用性降低,轻则造成信息访问不畅,重则带来各种不可预估的重大损失。作为保障数据中心可用性的第一道防线——“集中监控”可以快速帮助容灾中心达成“高可用性”的目标。
针对以上存在的主要问题,亟需开展针对性的研究,以提高工程管理水平和效能化监测能力,解决建设中存在的难题。
发明内容
本发明的目的就是为了克服上述现有技术存在的缺陷而提供一种结构简单、制造成本低,能帮助工程建设项目提高效率、降低风险和提高项目施工及运维管理水平的通过BIM进行机房CFD模拟的装置。
本发明的目的可以通过以下技术方案来实现:一种通过BIM进行机房CFD模拟的装置,其特征在于,该装置包括多个传感器、处理器、BIM模型数据库存储器、显示器、电源模块,所述的传感器、BIM模型数据库存储器、电源模块分别与处理器连接,所述的处理器与显示器连接。
所述的传感器为采集热量数据的传感器。
所述的多个传感器包括1~20个。
所述的显示器为LCD显示器或CRT显示器。
与现有技术相比,本发明具有以下优点:
1、结构简单、制造成本低;
2、通过BIM的应用,帮助工程建设项目提高效率、降低风险;
3、提高项目施工及运维管理水平。
附图说明
图1为本发明的结构示意图。
具体实施方式
下面结合附图和具体实施例对本发明进行详细说明。
实施例1
如图1所示,一种通过BIM进行机房CFD模拟的装置,该装置包括四个传感器2、处理器1、BIM模型数据库存储器3、显示器4、电源模块5。传感器2、BIM模型数据库存储器3、电源模块5分别与处理器1连接。处理器1与显示器4连接。显示器为LCD显示器或CRT显示器。传感器为采集热量数据的传感器。
将各类带有传感器的监控系统与BIM模型整合,收集机房设备的发热量数据,建立与真实情况相同的CFD热工模型,并进行CFD模拟分析,从而提供节能方案。
实施例2
一种通过BIM进行机房CFD模拟的装置,该装置包括二十个传感器、处理器、BIM模型数据库存储器、显示器、电源模块。传感器、BIM模型数据库存储器、电源模块分别与处理器连接。处理器与显示器连接。显示器为LCD显示器或CRT显示器。

Claims (4)

1.一种通过BIM进行机房CFD模拟的装置,其特征在于,该装置包括多个传感器、处理器、BIM模型数据库存储器、显示器、电源模块,所述的传感器、BIM模型数据库存储器、电源模块分别与处理器连接,所述的处理器与显示器连接。
2.根据权利要求1所述的一种通过BIM进行机房CFD模拟的装置,其特征在于,所述的传感器为采集热量数据的传感器。
3.根据权利要求1所述的一种通过BIM进行机房CFD模拟的装置,其特征在于,所述的多个传感器包括1~20个。
4.根据权利要求1所述的一种通过BIM进行机房CFD模拟的装置,其特征在于,所述的显示器为LCD显示器或CRT显示器。
CN2011101563202A 2011-06-10 2011-06-10 一种通过bim进行机房cfd模拟的装置 Pending CN102819620A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011101563202A CN102819620A (zh) 2011-06-10 2011-06-10 一种通过bim进行机房cfd模拟的装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011101563202A CN102819620A (zh) 2011-06-10 2011-06-10 一种通过bim进行机房cfd模拟的装置

Publications (1)

Publication Number Publication Date
CN102819620A true CN102819620A (zh) 2012-12-12

Family

ID=47303731

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011101563202A Pending CN102819620A (zh) 2011-06-10 2011-06-10 一种通过bim进行机房cfd模拟的装置

Country Status (1)

Country Link
CN (1) CN102819620A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103487365A (zh) * 2013-09-23 2014-01-01 山东省计算中心 腐蚀性气体对数据中心设备影响的实时评估系统及方法
CN104458546A (zh) * 2013-09-22 2015-03-25 岳晓楠 一种腐蚀性气体对数据中心设备影响的实时评估系统及方法
CN109308383A (zh) * 2018-09-05 2019-02-05 深圳市赛为智能股份有限公司 基于bim的烟气模拟方法、终端及存储介质

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201203946Y (zh) * 2008-05-21 2009-03-04 上海新联纬讯科技发展有限公司 机柜内设备发热状态监测系统
CN201226174Y (zh) * 2008-04-02 2009-04-22 华南理工大学 一种地下空间火灾智能逃生指示装置
CN202167020U (zh) * 2011-06-10 2012-03-14 上海市电力公司 一种通过bim进行机房cfd模拟的装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201226174Y (zh) * 2008-04-02 2009-04-22 华南理工大学 一种地下空间火灾智能逃生指示装置
CN201203946Y (zh) * 2008-05-21 2009-03-04 上海新联纬讯科技发展有限公司 机柜内设备发热状态监测系统
CN202167020U (zh) * 2011-06-10 2012-03-14 上海市电力公司 一种通过bim进行机房cfd模拟的装置

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
邹志翀: "《大型公共建筑火灾逃生环境风险测度与导航路径优化》", 《中国博士学位论文全文数据库 工程科技II辑》, no. 5, 15 May 2011 (2011-05-15), pages 93 - 132 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104458546A (zh) * 2013-09-22 2015-03-25 岳晓楠 一种腐蚀性气体对数据中心设备影响的实时评估系统及方法
CN103487365A (zh) * 2013-09-23 2014-01-01 山东省计算中心 腐蚀性气体对数据中心设备影响的实时评估系统及方法
CN103487365B (zh) * 2013-09-23 2015-07-29 山东省计算中心 腐蚀性气体对数据中心设备影响的实时评估系统及方法
CN109308383A (zh) * 2018-09-05 2019-02-05 深圳市赛为智能股份有限公司 基于bim的烟气模拟方法、终端及存储介质
CN109308383B (zh) * 2018-09-05 2023-04-28 深圳市赛为智能股份有限公司 基于bim的烟气模拟方法、终端及存储介质

Similar Documents

Publication Publication Date Title
CN102819621B (zh) 一种通过bim进行施工模拟的装置
Jiang Intelligent building construction management based on BIM digital twin
CN204303029U (zh) 用于地铁管线碰撞检测及后期运营维护的bim数据库系统
Zhang et al. Scheduling of a single flow shop for minimal energy cost under real-time electricity pricing
CN107272442A (zh) 一种大型氦低温系统实时仿真平台
CN102967689A (zh) 基于相关系数的污染源辨识方法及其监测布点方法
Green et al. High performance computing for electric power systems: Applications and trends
CN114004000A (zh) 一种基于bim技术管线智能排布的系统
CN102819620A (zh) 一种通过bim进行机房cfd模拟的装置
CN202167020U (zh) 一种通过bim进行机房cfd模拟的装置
Heidarshenas et al. RETRACTED: Utilization of a solar system to charge lithium-ion batteries and using the heat generated in an in-line lithium-ion battery to heat a guard room
CN103489139A (zh) 城市配电网规划综合分析与管理系统
CN202167019U (zh) 一种通过bim进行施工模拟的装置
CN111027261B (zh) 一种用于研究结构风激励响应的混合模拟试验方法
CN112632735A (zh) 一种核反应堆蒸汽发生器网格划分方法
CN202159372U (zh) 适用于电力系统资产全寿命业务管控的处理装置
CN102819619A (zh) 一种通过bim进行人流模拟的装置
CN102819622A (zh) 一种建立bim模型的系统装置
WO2025256029A1 (zh) 核热流固耦合解析方法、电子设备、存储介质
CN116757027B (zh) 换热器通道等效力学性能通用数据库构建方法及系统
WO2025256030A1 (zh) 核热流固耦合解析方法、电子设备、存储介质
CN202120257U (zh) 一种通过bim进行人流模拟的装置
Jiang et al. Research on intelligent building equipment room operation and maintenance platform based on digital twins
CN205692026U (zh) 一种基于bim的有机合成自动控制系统
Chen Design and optimization of construction equipment pipelines in cigarette factories based on BIM technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: STATE GRID CORPORATION OF CHINA SHANGHAI ELECTRIC

Free format text: FORMER OWNER: SHANGHAI JIULONG ELECTRIC POWER SCIENCE + TECHNOLOGY CO., LTD.

Effective date: 20121224

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121224

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Applicant after: State Grid Corporation of China

Applicant after: Shanghai Electric Power Communication Co., Ltd.

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Applicant before: Shanghai Jiulong Electric Power Co., Ltd.

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121212