CN102561705A - 一种群索张拉工艺 - Google Patents

一种群索张拉工艺 Download PDF

Info

Publication number
CN102561705A
CN102561705A CN2010106186947A CN201010618694A CN102561705A CN 102561705 A CN102561705 A CN 102561705A CN 2010106186947 A CN2010106186947 A CN 2010106186947A CN 201010618694 A CN201010618694 A CN 201010618694A CN 102561705 A CN102561705 A CN 102561705A
Authority
CN
China
Prior art keywords
rope
stretch
draw
cables
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010106186947A
Other languages
English (en)
Inventor
宋海丰
俞晓萌
余纯
陈恒江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN2010106186947A priority Critical patent/CN102561705A/zh
Publication of CN102561705A publication Critical patent/CN102561705A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lift-Guide Devices, And Elevator Ropes And Cables (AREA)

Abstract

本发明涉及一种群索张拉工艺,其特征在于:先对索进行受力计算,得到所有索的弹性变形的变形数组,在索的张拉施工过程中按照索的弹性变形的变形数组中的值进行索的张拉,待所有索都张拉到预定变形后,整体结构形成。本发明的优点是:结构简单、设计紧凑、传力直接、且无须对建筑物核心筒进行加固处理,能大大降低施工成本,提高施工效率。

Description

一种群索张拉工艺
技术领域
本发明涉及一种适用群索的张拉工艺。
背景技术
类似于上海浦东机场的索结构顶因为其轻,适用于大面积场所的建设,目前在国内外大型建筑结构中索结构得到广泛的到应用,一些超大跨度、体量的大型体育场所等建筑孕育而生。但是施工中,索的张拉和固定是关键,对于超大跨度、体量的大型体育场所在索的张拉施工过程中,总会存在整体结构完成后,由于群索结构的复杂性,局部的拉索应力存在与设计应力不同的情况,由于索的受力结构复杂,索多,因此有的地方索的受力集中,其所受张力大于索的设计值。这样的结构必然缺乏安全可控性,严重时将危害到固定索的结构,为了给结构预留一些安全余量,则必须大范围地提高拉索的自身结构和安装索的结构的承载能力,这必然会造成材料的浪费。因此如何保证索在施工结束后所承受的张力限制在设计范围内是索的张拉施工中一个亟待解决的关键问题。
发明内容
本发明的目的在于提出一种较为可行施工工艺,以保证群索结构的拉索施工完成后,拉索应力能够尽可能地接近设计数值。为实现上述目的,本发明的技术方案如下:一种群索张拉工艺,其特征在于:先对索进行受力计算,得到所有索的弹性变形的变形数组,在索的张拉施工过程中按照索的弹性变形的变形数组中的值进行索的张拉,待所有索都张拉到预定变形后,整体结构形成,其特征在于:索的张拉从中间的刚性结构开始拉索的张拉,然后向两侧刚性结构对称进行索的张拉。本发明的优点是解决了索之间在张拉过程中相互影响,从而导致索的受力难以控制的问题,相比传统的张拉方法,针对性强、索力可控、节约工期。
附图说明:
图1为本发明的结构张拉模型示意图。图2为一个施工实例结构图,图3为张拉索张拉时的结构示意图,图3中,11为穿心千斤顶,12为绞索,13为反力架,14为连接螺栓,15为拉索,16为拉索连接件,
具体实施方式:
下面结合附图和实施实例对本实用新型作详细说明。
一种群索张拉工艺,其特征在于:先对索进行受力计算,得到所有索的弹性变形的变形数组,在索的张拉施工过程中按照索的弹性变形的变形数组中的值进行索的张拉,待所有索都张拉到预定变形后,整体结构形成,其特征在于:索的张拉从中间的刚性结构开始拉索的张拉,然后向两侧刚性结构对称进行索的张拉。
本发明主要是采用分析索构件的弹性变形来代替原来的索构件的应力分析。用计算机模拟结构整体的弹性变形,分别计算每个区域内索具的变形,形成一个数组,而多个区域的分量变形组合形成最终的变形数组,如下公式:
T 1 1 T 2 1 T 3 1 T 4 1 + T 1 2 T 2 2 T 3 2 T 4 2 + . . . + T 1 n T 2 n T 3 n T 4 n = T 1 T 2 T 3 T 4
然后只需要利用计算软件分别计算每个分量数组的数值,在施工过程中按照计算结论进行索的张拉,即可保证索内力能够接近设计值。
本发明综合解决群索施工中,索之间在张拉过程中相互影响,从而导致索的受力难以控制。相比传统的张拉方法,针对性强、索力可控、节约工期。
图1为某一群索示意图,结构区间1与结构区间2之间布置有刚性结构构件3,刚性结构之间有联系梁4,张拉区间1内拉索的时候会对区间2内拉索有影响。通过计算机模拟计算施工顺序后,可预先确定索5变形值,待所有索都张拉到预定变形后,整体结构形成,索的受力均能达到要求。
一个施工实例,室外跳水池由18榀悬挑式钢架组合而成,形成圆弧形状。整体为一个轴对称形态,对称地可以分为9对钢架,在底部都是刚性连接。最高的钢架高度为24.883m,标高下起12.000m,上至36.883m,总体重量约为70.0t;最小钢架高度为9.169m,标高下起6.175m,上至15.344m,重量约为11.5t;其它钢架的高度和重量在这些区间内分布。在钢架之间有环梁和拉杆作为平面内的拉结构件,利用拉索在立面上加强侧向稳定。张拉顺序为先张拉钢架之间的钢棒(环梁和拉杆),再张拉索,均从中间向两侧进行,最后进行支撑拆除。实际张拉施工过程:先安装整个18榀桁架及屋面撑杆;在对中间榀桁架屋面拉索进行张拉,然后向两侧桁架对称张拉;对中间榀桁架侧面拉索进行张拉,然后向两侧桁架对称张拉。施工模拟计算方法:对整体结构进行迭代计算,得到设计终态;根据实际张拉施工顺序进行施工分组,共定义了18个施工组;采用施工模拟“倒退法”,从设计终态逐次回到张拉初态,从而得到各个施工阶段拉索的张拉值。

Claims (2)

1.一种群索张拉工艺,其特征在于:先对索进行受力计算,得到所有索的弹性变形的变形数组,在索的张拉施工过程中按照索的弹性变形的变形数组中的值进行索的张拉,待所有索都张拉到预定变形后,整体结构形成。
2.按权利要求1所述的一种群索张拉工艺,其特征在于:索的张拉从中间的刚性结构开始拉索的张拉,然后向两侧刚性结构对称进行索的张拉。
CN2010106186947A 2010-12-31 2010-12-31 一种群索张拉工艺 Pending CN102561705A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010106186947A CN102561705A (zh) 2010-12-31 2010-12-31 一种群索张拉工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010106186947A CN102561705A (zh) 2010-12-31 2010-12-31 一种群索张拉工艺

Publications (1)

Publication Number Publication Date
CN102561705A true CN102561705A (zh) 2012-07-11

Family

ID=46408172

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010106186947A Pending CN102561705A (zh) 2010-12-31 2010-12-31 一种群索张拉工艺

Country Status (1)

Country Link
CN (1) CN102561705A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118461899A (zh) * 2024-03-11 2024-08-09 北京市建筑设计研究院股份有限公司 一种利用抗侧力索控制框架结构温度和地震响应的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003301411A (ja) * 2002-04-09 2003-10-24 Asahi Engineering Kk 鋼桁へのプレストレス導入方法
CN201420400Y (zh) * 2009-03-17 2010-03-10 上海市机械施工有限公司 高耸网壳结构的支撑结构
CN101775906A (zh) * 2010-01-22 2010-07-14 清华大学 一种用于轮辐式屋盖结构的施工张拉控制方法
CN101793094A (zh) * 2010-03-11 2010-08-04 潮峰钢构集团有限公司 多榀张悬桁架渐进张拉施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003301411A (ja) * 2002-04-09 2003-10-24 Asahi Engineering Kk 鋼桁へのプレストレス導入方法
CN201420400Y (zh) * 2009-03-17 2010-03-10 上海市机械施工有限公司 高耸网壳结构的支撑结构
CN101775906A (zh) * 2010-01-22 2010-07-14 清华大学 一种用于轮辐式屋盖结构的施工张拉控制方法
CN101793094A (zh) * 2010-03-11 2010-08-04 潮峰钢构集团有限公司 多榀张悬桁架渐进张拉施工方法

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN118461899A (zh) * 2024-03-11 2024-08-09 北京市建筑设计研究院股份有限公司 一种利用抗侧力索控制框架结构温度和地震响应的方法
CN118461899B (zh) * 2024-03-11 2024-10-11 北京市建筑设计研究院股份有限公司 一种利用抗侧力索控制框架结构温度和地震响应的方法

Similar Documents

Publication Publication Date Title
CN104989105B (zh) 一种“n”型索网节点间拉索安装及张拉的方法
CN104234433B (zh) 轮辐式环向悬臂索承网格结构张拉成形方法及张拉装置
CN102094489B (zh) 双层双向预应力索桁架及其施工方法
CN102733481A (zh) 一种非对称开口式整体张拉索膜结构的施工方法
CN202169644U (zh) 先张法预应力混凝土板桩整体式张拉台座
CN202090286U (zh) 一种适用于自锚式双索面悬索桥的牵引系统
CN105442704A (zh) 一种加固后的网架结构及网架结构加固的施工方法
CN102505636A (zh) 一种双薄壁墩连续刚构桥0号块施工方法
CN106758837B (zh) 一种结合拱上立柱的斜拉扣挂施工系统
CN101290268A (zh) 大型结构试验加载框架
CN111119494A (zh) 一种超大跨度张弦拱形钢结构的高空原位施工方法
CN203222919U (zh) 网架结构圆弧形储煤钢棚
CN102199931B (zh) 环向索弦支网格梁结构及对其施加预应力的方法
CN102733525B (zh) 一种基于承载全过程开口式整体张拉结构多阶段设计方法
CN102561705A (zh) 一种群索张拉工艺
CN102561706A (zh) 空间大跨度预应力钢结构钢绞线体内穿线方法
CN102622491A (zh) 钢筋混凝土结构预应力施工至使用全过程分析方法
CN103174309A (zh) 一种伞状定型化加工棚
CN108374323A (zh) 一种用于拱承斜拉桥的索塔集束锚固结构
CN102677708A (zh) 桩基静载荷试验用反力梁施加预应力的方法及钢箱梁
CN206279788U (zh) 一种在板面采用预应力拉索加固的结构
CN201420400Y (zh) 高耸网壳结构的支撑结构
CN116882002A (zh) 一种含预应力结构的空间桁架施工方法
CN204174848U (zh) 一种仿古建筑的斗拱预制钢筋骨架
CN111321666B (zh) 一种高效的拱圈扣索拆除的方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711