CN102296568A - 一种在拱坝上采用波纹板成缝的方法及结构 - Google Patents

一种在拱坝上采用波纹板成缝的方法及结构 Download PDF

Info

Publication number
CN102296568A
CN102296568A CN2010102097817A CN201010209781A CN102296568A CN 102296568 A CN102296568 A CN 102296568A CN 2010102097817 A CN2010102097817 A CN 2010102097817A CN 201010209781 A CN201010209781 A CN 201010209781A CN 102296568 A CN102296568 A CN 102296568A
Authority
CN
China
Prior art keywords
corrugated sheet
arch
seam
dam
sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010102097817A
Other languages
English (en)
Inventor
罗洪波
杨家修
陈宏�
崔进
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hydrochina Guiyang Engineering Corp
Original Assignee
Hydrochina Guiyang Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hydrochina Guiyang Engineering Corp filed Critical Hydrochina Guiyang Engineering Corp
Priority to CN2010102097817A priority Critical patent/CN102296568A/zh
Publication of CN102296568A publication Critical patent/CN102296568A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

本发明公开了一种在拱坝上采用波纹板成缝的方法及结构,本发明是在用混凝土碾压拱坝时,在拱坝拱端的坝体迎着上游方向摆放一道平行于拱端面的波纹板,以增强拱端的径向抗剪切能力。本发明采用波纹型成缝结构可一次浇筑成缝,不需进行接缝灌浆,既可传递拱向压应力,又可增强径向抗剪切能力,还省去了设置键槽施工工序复杂、工期长的弊端。本发明特别对碾压混凝土拱坝所具有的快速施工特点其优越性更为突出。

Description

一种在拱坝上采用波纹板成缝的方法及结构
技术领域
本发明涉及一种在拱坝上采用波纹板成缝的方法及结构,属于水坝建筑结构技术领域。
背景技术
拱坝是一种建筑在峡谷中的拦水坝,做成水平拱形,凸边面向上游,两端紧贴着峡谷壁。借助拱的作用将水压力的全部或部分传给河谷两岸的基岩。拱坝两端与峡谷壁的连接处称为拱端,一般来说拱端上游面为受拉区,为了释放拱端的拉应力,常在拱端附近设置周边短缝。而拱端是拱坝挡水后将作用力传递给坝肩岩体的关键部位,拱端除了传递拱向压应力外,还需抵抗径向剪切力。而周边短缝的设置却削弱了拱端的径向抵抗力。为了克服周边短缝造成的径向抵抗力下降的问题,目前通常需要在周边短缝中灌浆后方可蓄水;或者采取增厚拱端的措施来提高拱端的径向抗剪切能力;或者采用预留键槽分开浇筑的方法来提高拱端的径向抗剪切能力。采用上述方法施工工序复杂、工期长。
发明内容
本发明的目的在于,提供一种可一次浇筑成缝、不需进行接缝灌浆、并且既可传递拱向压应力、又可增强径向抗剪切能力的在拱坝上采用波纹板成缝的方法及结构,从而克服现有技术的不足。
本发明的技术方案:在拱坝上采用波纹板成缝的方法,该方法是在用混凝土碾压拱坝时,在拱坝拱端的坝体迎着上游方向摆放一道平行于拱端面的一层水平设置的波纹板,以提高拱端的径向抗剪切能力。波纹板的迎水边设有止水片,波纹板的背水边设有止缝板。
前述在拱坝上采用波纹板成缝的方法中,所述波纹板上设有一组孔径为5~20 cm的通孔。
前述在拱坝上采用波纹板成缝的方法中,所述波纹板采用既能传力,又能防腐的材料制成。
前述在拱坝上采用波纹板成缝的方法中,所述的既能传力,又能防腐的材料为不锈钢板或镀锌铁板。
前述在拱坝上采用波纹板成缝的方法中,所述波纹板板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。
前述在拱坝上采用波纹板成缝的方法中,在所述波纹板的迎水边设置止水片,防止上游的水顺着波纹板浸入;止水片用紫铜片或不锈钢板制成。
前述在拱坝上采用波纹板成缝的方法中,在所述波纹板的背水边设有止缝板,防止混凝土沿径向在波纹板的背水边处开裂;止缝板用型钢制成。
前述在拱坝上采用波纹板成缝的方法中,在所述止缝板后的混凝土坝体内的非缝断面设有一组垂直设置的插筋。
按照前述的在拱坝上采用波纹板成缝的方法所用的结构,包括设在拱端坝体内的波纹板,在波纹板的迎水边设有止水片,在波纹板的背水边设有止缝板,止缝板后的混凝土坝体内沿径向的非缝断面设有一组垂直设置的插筋。
前述的结构中,所述波纹板的板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。
由于采用了上述技术方案,本发明与现有技术相比,本发明采用“波纹型成缝设施”可一次浇筑成缝,不需进行接缝灌浆,既可传递拱向压应力,又可增强径向抗剪切能力,而且还省去了现有技术中必须设置键槽施工工序复杂、工期长的弊端。本发明特别对碾压混凝土拱坝所具有的快速施工特点,其优越性更为突出。
附图说明
图1是本发明的结构示意图。
附图中的标记为:1-波纹板,2-止水片,3-止缝板,4-插筋。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明,但不作为对本发明进行任何限制的依据。
本发明的实施例:如图1所示,采用本发明的在拱坝上采用波纹板成缝的方法进行施工时,在用混凝土碾压拱坝的时候,在拱坝拱端的坝体迎着上游方向摆放一道平行于拱端面的波纹板,以提高拱端的径向抗剪切能力;波纹板的迎水边设有止水片,波纹板的背水边设有止缝板;波纹板上设有一组孔径为5~20 cm的通孔;波纹板采用既能传力,又能防腐的材料制成;所述的既能传力,又能防腐的材料为不锈钢板或镀锌铁板;所述波纹板板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。在所述波纹板的迎水边设置止水片,防止上游的水顺着波纹板浸入;止水片用紫铜片或不锈钢板制成。在所述波纹板的背水边设有止缝板,防止沿径向混凝土在波纹板的背水边处开裂;止缝板用型钢制成;在所述止缝板后的混凝土坝体内的非缝断面设有一组垂直设置的插筋。
用于本发明方法的一种在拱坝上采用波纹板成缝的结构包括设在拱端坝体内的波纹板1,制作时,在波纹板1的迎水边制作出止水片2,在波纹板1的背水边制作出止缝板3,在止缝板3后的混凝土坝体内的非缝断面设置一组垂直设置的插筋4,插筋4的数量可根据坝体的大小按常规方式确定,波纹板1的板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。
本发明在具体实施时,是与筑坝工程同步进行的,在筑坝时,在坝的拱面与拱端的山体岩石交接处附近本应设置周边短缝的地方,铺设波纹板,用一道波纹板替代原来的周边短缝。铺设好波纹板后,连同波纹板迎水边的止水片和波纹板背水边的止缝板也一起做好,止水片的作用是防止水顺着波纹板与混凝土的结合处渗入。止缝板的作用是防止压力从波纹板端部沿径向形成的混凝土缝处撕裂。 在波纹板背水一边的非缝断面设有多根垂直设置的插筋,以提高挡水能力。在浇筑混凝土时,连同波纹板、止水片、止缝板和插筋一次浇筑在坝体内。

Claims (10)

1. 一种在拱坝上采用波纹板成缝的方法,其特征在于:该方法是在用混凝土碾压拱坝时,在拱坝拱端的坝体迎着上游方向摆放一道平行于拱端面的波纹板,以增强拱端的径向抗剪切能力。
2.根据权利要求1所述在拱坝上采用波纹板成缝的方法,其特征在于:所述波纹板上设有一组孔径为5~20 cm的通孔。
3.根据权利要求2所述在拱坝上采用波纹板成缝的方法,其特征在于:所述波纹板采用既能传力,又能防腐的材料制成。
4.根据权利要求3所述在拱坝上采用波纹板成缝的方法,其特征在于:所述的既能传力,又能防腐的材料为不锈钢板或镀锌铁板。
5.根据权利要求1所述在拱坝上采用波纹板成缝的方法,其特征在于:所述波纹板板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。
6.根据权利要求1所述在拱坝上采用波纹板成缝的方法,其特征在于:在所述波纹板的迎水边设置止水片,防止上游的水顺着波纹板浸入;止水片用紫铜片或不锈钢板制成。
7.根据权利要求1所述在拱坝上采用波纹板成缝的方法,其特征在于:在所述波纹板的背水边设有止缝板,防止混凝土沿缝在波纹板的背水边处开裂;止缝板用型钢制成。
8.根据权利要求1所述在拱坝上采用波纹板成缝的方法,其特征在于:在所述止缝板后沿径向的混凝土坝体内的非缝断面设有一组垂直设置的插筋。
9.一种在拱坝上采用波纹板成缝的结构,其特征在于:包括设置在拱端坝体内的波纹板(1),在波纹板(1)的迎水边设有止水片(2),在波纹板(1)的背水边设有止缝板(3),在止缝板(3)后的混凝土坝体内的非缝断面设有一组垂直设置的插筋(4)。
10.根据权利要求9所述的在拱坝上采用波纹板成缝的结构,其特征在于:所述波纹板(1)的板厚为1~5mm;波纹板的波长为50~100cm;波纹板的波幅为10~20cm。
CN2010102097817A 2010-06-25 2010-06-25 一种在拱坝上采用波纹板成缝的方法及结构 Pending CN102296568A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010102097817A CN102296568A (zh) 2010-06-25 2010-06-25 一种在拱坝上采用波纹板成缝的方法及结构

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010102097817A CN102296568A (zh) 2010-06-25 2010-06-25 一种在拱坝上采用波纹板成缝的方法及结构

Publications (1)

Publication Number Publication Date
CN102296568A true CN102296568A (zh) 2011-12-28

Family

ID=45357232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010102097817A Pending CN102296568A (zh) 2010-06-25 2010-06-25 一种在拱坝上采用波纹板成缝的方法及结构

Country Status (1)

Country Link
CN (1) CN102296568A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464047A (zh) * 2015-12-17 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 一种碾压混凝土拱坝周边短缝快速成缝方法及装置
CN117552430A (zh) * 2024-01-11 2024-02-13 中国电建集团西北勘测设计研究院有限公司 一种拱坝坝肩非径向开挖方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2387142Y (zh) * 1999-09-30 2000-07-12 南京晨光东螺波纹管有限公司 砼面板堆石坝用不锈钢波纹止水片
US6413014B1 (en) * 1997-05-12 2002-07-02 Sigurd Melin Damming device for erecting a liquid-damming protective bank
CN201411661Y (zh) * 2009-05-21 2010-02-24 王大卫 一种新型周边缝表面止水结构
CN201695382U (zh) * 2010-06-25 2011-01-05 中国水电顾问集团贵阳勘测设计研究院 一种在拱坝上采用波纹板成缝的结构

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6413014B1 (en) * 1997-05-12 2002-07-02 Sigurd Melin Damming device for erecting a liquid-damming protective bank
CN2387142Y (zh) * 1999-09-30 2000-07-12 南京晨光东螺波纹管有限公司 砼面板堆石坝用不锈钢波纹止水片
CN201411661Y (zh) * 2009-05-21 2010-02-24 王大卫 一种新型周边缝表面止水结构
CN201695382U (zh) * 2010-06-25 2011-01-05 中国水电顾问集团贵阳勘测设计研究院 一种在拱坝上采用波纹板成缝的结构

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈宏: "大花水水电站碾压混凝土坝设计", 《水力发电》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105464047A (zh) * 2015-12-17 2016-04-06 中国电建集团贵阳勘测设计研究院有限公司 一种碾压混凝土拱坝周边短缝快速成缝方法及装置
CN117552430A (zh) * 2024-01-11 2024-02-13 中国电建集团西北勘测设计研究院有限公司 一种拱坝坝肩非径向开挖方法
CN117552430B (zh) * 2024-01-11 2024-04-12 中国电建集团西北勘测设计研究院有限公司 一种拱坝坝肩非径向开挖方法

Similar Documents

Publication Publication Date Title
CN202000380U (zh) 地下室外墙后浇带回填保护板
CN104120686B (zh) 一种高弹模垫座式复合坝
CN202099816U (zh) 一种地下室外墙后浇带预制防水挡土板
CN107806349B (zh) 一种钢-frp复合波纹板隧洞二次衬砌结构及其施作方法
CN106760054B (zh) 预制钢筋混凝土剪力墙
CN204199330U (zh) 一种后浇带整体止水钢板
CN112392043A (zh) 一种psb精轧螺纹钢抗浮锚杆结构及其施工方法
CN202559326U (zh) 高边墩高填土船闸闸室u型预应力索坞式结构体系
CN1594833A (zh) 钢板—混凝土组合衬砌
CN201891133U (zh) 人工装配式自防水地下室外墙后浇带预制板
CN201165661Y (zh) 一种抗拔高压旋喷桩
CN201473974U (zh) 一种新型钢板止水带
CN201857603U (zh) 加高的重力坝
CN104790435A (zh) 沉降后浇带超前止水抗渗混凝土结构及其施工工艺
CN207063226U (zh) 预制钢筋混凝土剪力墙
CN108643585A (zh) 预制混凝土夹心保温外墙板及其制备施工方法
CN102296568A (zh) 一种在拱坝上采用波纹板成缝的方法及结构
CN104594389A (zh) 一种带弹性止水条的后浇带外墙封堵结构
CN115262531A (zh) 一种地下连续墙兼做隔振屏障的成型及设计方法
CN105464047A (zh) 一种碾压混凝土拱坝周边短缝快速成缝方法及装置
CN102677679A (zh) 建筑基坑用现浇异型钢筋混凝土桩芯水泥土地下连续墙
CN201695382U (zh) 一种在拱坝上采用波纹板成缝的结构
CN204455987U (zh) 一种塑钢板桩与混凝土组合的护岸结构
CN204589917U (zh) 土心墙堆石坝岸坡混凝土盖板
CN209942844U (zh) 适于护盾式tbm的边钢内嵌式钢组合管片

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20111228