CN102277826A - Partial earth anchor intersecting cable-stayed bridge - Google Patents
Partial earth anchor intersecting cable-stayed bridge Download PDFInfo
- Publication number
- CN102277826A CN102277826A CN2011101264412A CN201110126441A CN102277826A CN 102277826 A CN102277826 A CN 102277826A CN 2011101264412 A CN2011101264412 A CN 2011101264412A CN 201110126441 A CN201110126441 A CN 201110126441A CN 102277826 A CN102277826 A CN 102277826A
- Authority
- CN
- China
- Prior art keywords
- bridge
- cable
- tower
- span
- mid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种部分地锚交叉索斜拉桥,包括相邻的第一桥塔(1)和第二桥塔(10),普通区段主梁(7)、中跨跨中区段主梁(6),所述的中跨跨中区段主梁(6)通过交叉外侧索(2)和交叉内侧索(3)分别与所述的第一桥塔(1)和第二桥塔(10)连接,所述的交叉外侧索(2)与交叉内侧索(3)在纵桥向立面投影交叉,在横桥向立面投影不相交,所述的第一桥塔(1)和第二桥塔(10)分别通过端锚索(5)与锚锭(8)相连,所述的普通区段主梁(7)通过普通索(4)与所述的第一桥塔(1)或第二桥塔(10)对称连接。本发明具有跨中区段主梁刚度大、普通区段主梁水平力小、跨越能力大等优点。
The invention discloses a partially ground-anchored cross-cable cable-stayed bridge, which comprises adjacent first bridge towers (1) and second bridge towers (10), a main girder (7) in a common section, a mid-span mid-span section The main girder (6), the main girder (6) of the mid-span mid-span section is connected with the first bridge tower (1) and the second bridge respectively through the crossing outer cable (2) and the crossing inner cable (3) The towers (10) are connected, the crossing outer cables (2) and the crossing inner cables (3) intersect in the projection of the vertical bridge to the facade, and do not intersect in the projection of the horizontal bridge to the facade, and the first bridge tower (1 ) and the second bridge tower (10) are respectively connected to each other by the end anchor cable (5) and the anchor spindle (8), and the described common section girder (7) is connected to the first bridge tower by the common cable (4) (1) or the second bridge tower (10) are symmetrically connected. The invention has the advantages of high rigidity of the main girder in the mid-span section, small horizontal force of the main girder in the ordinary section, and large spanning capacity.
Description
技术领域 technical field
本发明涉及一种桥梁,尤其涉及一种部分地锚交叉索斜拉桥。The invention relates to a bridge, in particular to a partially ground-anchored cross-cable cable-stayed bridge.
背景技术 Background technique
斜拉桥由于能以较小的梁高实现大跨度的优点,被大量修建。随着跨度的增加,桥塔附近主梁横截面压应力增加迅速,这是制约斜拉桥跨越能力的主要因素。当前国内外斜拉桥拉索的布置形式,均为单一类型的索面。对辐射形和竖琴形索面,拉索在桥塔上锚固点分散,需要较高的桥塔布置拉索锚固点;对辐射形索面,受高跨比和塔顶空间限制,可布置的拉索数量较少,不适于大跨度斜拉桥。另一方面,现有形式的斜拉索和桥塔布置对跨中主梁约束较弱,跨中梁段的刚度低,不适于对刚度要求严格的线路,否则,需要以增加索面、提高主梁高度的方式来解决跨中主梁刚度问题,而这些方式将导致工程量大增,使斜拉桥失去竞争优势。Cable-stayed bridges have been built in large numbers due to the advantages of being able to achieve large spans with relatively small girder heights. With the increase of the span, the compressive stress of the cross-section of the main girder near the bridge tower increases rapidly, which is the main factor restricting the spanning capacity of the cable-stayed bridge. At present, the arrangement form of cables of cable-stayed bridges at home and abroad is a single type of cable plane. For radial and harp-shaped cable surfaces, the anchorage points of the cables on the pylons are scattered, and higher pylons are required to arrange the anchorage points of the cables; The number of cables is small, so it is not suitable for long-span cable-stayed bridges. On the other hand, the existing cable-stayed cables and pylon layout have weak constraints on the mid-span girder, and the mid-span girder section has low stiffness, which is not suitable for lines with strict rigidity requirements. Otherwise, it is necessary to increase the cable surface and improve the The height of the main girder is used to solve the problem of the stiffness of the main girder in the span, and these methods will lead to a large increase in the amount of engineering and make the cable-stayed bridge lose its competitive advantage.
发明内容 Contents of the invention
本发明所要解决的技术问题是提供一种主梁压应力较小、跨中刚度大、经济性好的部分地锚交叉索斜拉桥。The technical problem to be solved by the present invention is to provide a partially ground-anchored cross-cable cable-stayed bridge with small main girder compressive stress, high mid-span rigidity and good economy.
为解决上述技术问题,本发明提供的部分地锚交叉索斜拉桥,包括相邻的第一桥塔和第二桥塔,普通区段主梁、中跨跨中区段主梁,所述的中跨跨中区段主梁通过交叉外侧索和交叉内侧索分别与所述的第一桥塔和第二桥塔连接,所述的交叉外侧索与交叉内侧索在纵桥向立面投影交叉,在横桥向立面投影不相交,所述的第一桥塔和第二桥塔分别通过端锚索与锚锭相连,所述的普通区段主梁通过普通索与所述的第一桥塔或第二桥塔对称连接。In order to solve the above-mentioned technical problems, the partially ground-anchored cross-cable cable-stayed bridge provided by the present invention includes adjacent first bridge towers and second bridge towers, a common section main girder, a mid-span mid-span section main girder, and The main girder of the mid-span section of the mid-span is connected to the first bridge tower and the second bridge tower respectively through crossing outer cables and crossing inner cables, and the crossing outer cables and crossing inner cables are projected on the vertical bridge to the facade Intersecting, the projection of the transverse bridge to the elevation does not intersect, the first bridge tower and the second bridge tower are connected to the anchor spindle through the end anchor cable respectively, and the main beam of the common section is connected to the first bridge bridge through the common cable A bridge tower or a second bridge tower is connected symmetrically.
所述的交叉外侧索和交叉内侧索采用辐射形索面分别锚固在所述的第一桥塔和第二桥塔的塔顶,所述的第一桥塔和第二桥塔的塔顶分别通过端锚索与锚锭相连,所述的普通索采用扇形索面或竖琴形索面对称锚固于所述的第一桥塔或第二桥塔的塔身。The crossing outer cables and crossing inner cables are respectively anchored to the tops of the first bridge tower and the second bridge tower with radial cable surfaces, and the tower tops of the first bridge tower and the second bridge tower are respectively The end anchor cable is connected to the anchor spindle, and the common cable adopts a fan-shaped cable surface or a harp-shaped cable surface and is symmetrically anchored to the body of the first bridge tower or the second bridge tower.
布置有所述的交叉外侧索和交叉内侧索的梁段长占主跨长的1/4~1/3。为使交叉外侧索与交叉内侧索在横断面上不相交,加宽中跨跨中区段主梁布置一对斜拉索所需宽度。锚锭同时兼作边跨桥墩。The length of the beam segment arranged with the said crossing outer cables and crossing inner cables accounts for 1/4-1/3 of the length of the main span. In order to make the cross-outside cables and cross-inside cables not intersect on the cross section, a pair of stay cables is arranged on the main girder of the mid-span section of the widened mid-span to the required width. The anchor spindle also serves as a side-span pier.
采用上述技术方案的部分地锚交叉索斜拉桥,与现有技术相比,本发明的优点在于:第一,能增加斜拉桥跨越能力1/4~1/3,使斜拉桥更适于在1000米以上特大跨径桥梁上应用。现有技术中,斜拉桥跨度越大,桥塔处梁段的压应力越大,斜拉桥的跨越能力受主梁材料抗压强度限制。而丹麦科技大学吉姆森教授提出的部分地锚斜拉桥方案,虽能解决主梁压应力过大的问题,但施工过程十分复杂。本发明提供的部分地锚交叉索斜拉桥,跨中梁段水平力自平衡,不增加普通梁段的压应力,从而不受主梁材料抗压强度限制;第二,大幅度增加跨中梁段的刚度。与现有技术相比,布置交叉索的斜拉桥,跨中梁段拉索增加一倍,梁段刚度得到明显提高,这将使斜拉桥能在对刚度要求严格的线路上以经济的方式应用。Compared with the prior art, the partial ground-anchor cross-cable cable-stayed bridge adopting the above-mentioned technical scheme has the advantages of: first, it can increase the spanning capacity of the cable-stayed bridge by 1/4 to 1/3, making the cable-stayed bridge more It is suitable for application on super long-span bridges over 1000 meters. In the prior art, the larger the span of the cable-stayed bridge, the greater the compressive stress of the girder section at the pylon, and the spanning capacity of the cable-stayed bridge is limited by the compressive strength of the main girder material. The partially ground-anchored cable-stayed bridge scheme proposed by Professor Jimson of the Technical University of Denmark can solve the problem of excessive compressive stress of the main girder, but the construction process is very complicated. In the partly anchored cross-cable cable-stayed bridge provided by the present invention, the horizontal force of the mid-span girder section is self-balanced, and the compressive stress of the common girder section is not increased, so that it is not limited by the compressive strength of the main girder material; secondly, the mid-span The stiffness of the beam segment. Compared with the existing technology, the cable-stayed bridge with intersecting cables doubles the number of cables in the mid-span beam section, and the stiffness of the beam section is significantly improved. way to apply.
附图说明 Description of drawings
图1为本发明的主视图;Fig. 1 is the front view of the present invention;
图2为本发明的俯视图;Fig. 2 is the top view of the present invention;
图3为图2中a处局部放大图;Fig. 3 is a partial enlarged view of place a in Fig. 2;
图4为图1中A-A处的剖面图;Fig. 4 is the sectional view of A-A place in Fig. 1;
图5为图1中B-B处的剖面图;Fig. 5 is the sectional view of B-B place in Fig. 1;
图例说明:illustration:
1、第一桥塔 2、交叉外侧索1. The
3、交叉内侧索 4、普通索3. Cross
5、端锚索 6、跨中区段主梁5.
7、普通区段主梁 8、锚锭7. Main beam of ordinary section 8. Anchor ingot
9、辅助墩 10、第二桥塔9.
具体实施方式 Detailed ways
下面结合附图和具体实施方式对本发明作进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
如图1、图2、图3和图4所示,中跨跨中区段主梁6通过交叉外侧索2和交叉内侧索3采用辐射形索面分别锚固在第一桥塔1和第二桥塔10的塔顶,交叉外侧索2与交叉内侧索3在纵桥向立面投影交叉,在横桥向立面投影不相交,普通区段主梁7通过普通索4采用扇形索面或竖琴形索面对称锚固于第一桥塔1或第二桥塔10的塔身,第一桥塔1和第二桥塔10的塔顶分别通过端锚索5与锚锭8相连,普通区段主梁7设有辅助墩9。布置有交叉外侧索2和交叉内侧索3的梁段长占主跨长的1/4~1/3;为使交叉外侧索2与交叉内侧索3在横断面上不相交,加宽中跨跨中区段主梁6布置一对斜拉索所需宽度,如图3所示。锚锭8同时兼作边跨桥墩。As shown in Figure 1, Figure 2, Figure 3 and Figure 4, the
本具体实施方式中的部分地锚交叉索斜拉桥施工步骤为:The construction steps of the part ground anchor cross-cable cable-stayed bridge in this specific embodiment are:
步骤1:首先进行桩基和第一桥塔1、第二桥塔10、辅助墩9、锚锭8的施工;Step 1: first carry out the construction of the pile foundation and the first bridge tower 1, the
步骤2:对称施工普通区段主梁7,架设普通索4;Step 2: Symmetrically construct the
步骤3:架设端锚索5;Step 3: erecting the
步骤4:对称架设跨中区段主梁6,架设交叉外侧索2和交叉内侧索3,逐次调整端锚索5索力;Step 4: Erect the
步骤5:完成附属工程及桥面铺装,达到成桥状态。Step 5: Complete the ancillary works and bridge deck pavement, and reach the completed bridge state.
上述交叉索斜拉桥的施工建造,比常规斜拉桥施工方法多了锚锭施工的步骤,这在悬索桥施工时已形成成熟技术,并不增加施工难度。The construction of the above-mentioned cross-cable cable-stayed bridge has more steps of anchor construction than the conventional cable-stayed bridge construction method, which has formed a mature technology in the construction of the suspension bridge and does not increase the difficulty of construction.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011101264412A CN102277826A (en) | 2011-05-16 | 2011-05-16 | Partial earth anchor intersecting cable-stayed bridge |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN2011101264412A CN102277826A (en) | 2011-05-16 | 2011-05-16 | Partial earth anchor intersecting cable-stayed bridge |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN102277826A true CN102277826A (en) | 2011-12-14 |
Family
ID=45103530
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN2011101264412A Pending CN102277826A (en) | 2011-05-16 | 2011-05-16 | Partial earth anchor intersecting cable-stayed bridge |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN102277826A (en) |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105133484A (en) * | 2015-10-19 | 2015-12-09 | 中铁第四勘察设计院集团有限公司 | Cable-stayed bridge structure with high and low towers for partial ground anchors |
| CN105256720A (en) * | 2015-09-17 | 2016-01-20 | 中铁大桥科学研究院有限公司 | Partial ground anchor balancing cable cable-stayed bridge |
| CN106498837A (en) * | 2016-11-02 | 2017-03-15 | 西南交通大学 | A kind of novel bridge and its construction method |
| CN112832114A (en) * | 2020-12-10 | 2021-05-25 | 中铁第四勘察设计院集团有限公司 | Stay cable bridge and anchoring optimization method thereof |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR439096A (en) * | 1912-01-18 | 1912-06-05 | Hugues Henri Georges Etcheverr | Non-deformable suspension bridge system with multiple suspensions |
| GB839413A (en) * | 1957-05-09 | 1960-06-29 | Ake Hedstroem | Improvements in or relating to bridges and other load-carrying structures |
| DE3810071C1 (en) * | 1988-03-25 | 1989-03-16 | Willy Huenibach Ch Habegger | Suspension bridge |
| US5896609A (en) * | 1997-11-21 | 1999-04-27 | Lin; Wei-Hwang | Safety method of construction a prestressed cable-stay bridge |
| CN2900614Y (en) * | 2006-06-26 | 2007-05-16 | 董兰田 | Two-way stayed-cable suspension bridge |
| CN202081371U (en) * | 2011-05-16 | 2011-12-21 | 湖南大学 | Partially ground-anchor cross cable stayed bridge |
-
2011
- 2011-05-16 CN CN2011101264412A patent/CN102277826A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| FR439096A (en) * | 1912-01-18 | 1912-06-05 | Hugues Henri Georges Etcheverr | Non-deformable suspension bridge system with multiple suspensions |
| GB839413A (en) * | 1957-05-09 | 1960-06-29 | Ake Hedstroem | Improvements in or relating to bridges and other load-carrying structures |
| DE3810071C1 (en) * | 1988-03-25 | 1989-03-16 | Willy Huenibach Ch Habegger | Suspension bridge |
| US5896609A (en) * | 1997-11-21 | 1999-04-27 | Lin; Wei-Hwang | Safety method of construction a prestressed cable-stay bridge |
| CN2900614Y (en) * | 2006-06-26 | 2007-05-16 | 董兰田 | Two-way stayed-cable suspension bridge |
| CN202081371U (en) * | 2011-05-16 | 2011-12-21 | 湖南大学 | Partially ground-anchor cross cable stayed bridge |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105256720A (en) * | 2015-09-17 | 2016-01-20 | 中铁大桥科学研究院有限公司 | Partial ground anchor balancing cable cable-stayed bridge |
| CN105133484A (en) * | 2015-10-19 | 2015-12-09 | 中铁第四勘察设计院集团有限公司 | Cable-stayed bridge structure with high and low towers for partial ground anchors |
| CN106498837A (en) * | 2016-11-02 | 2017-03-15 | 西南交通大学 | A kind of novel bridge and its construction method |
| CN106498837B (en) * | 2016-11-02 | 2017-12-05 | 西南交通大学 | A kind of bridge and its construction method |
| CN112832114A (en) * | 2020-12-10 | 2021-05-25 | 中铁第四勘察设计院集团有限公司 | Stay cable bridge and anchoring optimization method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN102296525B (en) | Support system mixed combined beam cable-stayed bridge and construction method thereof | |
| CN102286938B (en) | Diagonal tension system reinforcement structure suitable for large-span box girder bridge and continuous rigid frame bridge | |
| CN205501791U (en) | Two recessed arch integrated configurations of steel binder - entity jib - | |
| CN109778667B (en) | Arch structure for ultra-large span steel-UHPC combined truss type arch bridge and construction method thereof | |
| CN100519943C (en) | Non-cable single-tower stayed bridge | |
| CN108755385A (en) | A kind of only Cable-stayed Bridge with Slanted Pylon structure and construction method of active balance main span horizontal force | |
| CN101736686A (en) | Self-anchored hybrid beam cable-stayed suspension cooperative system bridge | |
| CN102535348B (en) | Method for tensioning stayed cables of hinged tower cable stayed bridge | |
| CN103410082B (en) | Double-layer bridge floor cable-stayed bridge | |
| CN201826249U (en) | Self-anchored hybrid beam cable-stayed suspension cooperative system bridge | |
| CN203498760U (en) | Guiding device for large-span box girder pushing | |
| CN105133484B (en) | A kind of part earth anchor higher-lower tower cable-stayed bridge structure | |
| CN102277826A (en) | Partial earth anchor intersecting cable-stayed bridge | |
| CN107119583A (en) | A kind of T-shaped rigid frame bridge back of the body tower oblique pull ruggedized construction of double width and its construction method | |
| CN202081371U (en) | Partially ground-anchor cross cable stayed bridge | |
| CN204325893U (en) | The only tower of railway mixes girder stayed-cable bridge structure | |
| CN105821753B (en) | A kind of novel railway curve Cable-stayed Bridge with Slanted Pylon | |
| CN109763417B (en) | Cable-stayed steel truss cooperative system bridge | |
| CN108824164B (en) | Space three-dimensional cable system ground anchor type suspension bridge bearing wind load of larger transverse bridge | |
| CN219490643U (en) | Multi-tower asymmetric low-tower cable-stayed bridge structure | |
| CN102644237B (en) | Dual-span spatial arch cable-stayed bridge | |
| CN116043660B (en) | A multi-tower asymmetric low-tower cable-stayed bridge | |
| CN205115988U (en) | Part earth anchor height tower cable -stay bridge structure | |
| CN105256720A (en) | Partial ground anchor balancing cable cable-stayed bridge | |
| CN111321660A (en) | A W-shaped pier |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C12 | Rejection of a patent application after its publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20111214 |