CN101979800B - 电动爬升模板系统 - Google Patents

电动爬升模板系统 Download PDF

Info

Publication number
CN101979800B
CN101979800B CN201010524255XA CN201010524255A CN101979800B CN 101979800 B CN101979800 B CN 101979800B CN 201010524255X A CN201010524255X A CN 201010524255XA CN 201010524255 A CN201010524255 A CN 201010524255A CN 101979800 B CN101979800 B CN 101979800B
Authority
CN
China
Prior art keywords
load
bearing bracket
formwork
electric
guide rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201010524255XA
Other languages
English (en)
Other versions
CN101979800A (zh
Inventor
余志钢
郝海涛
鲁成胜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Mengsheng Construction Technology Co ltd
Original Assignee
BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd filed Critical BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN201010524255XA priority Critical patent/CN101979800B/zh
Publication of CN101979800A publication Critical patent/CN101979800A/zh
Application granted granted Critical
Publication of CN101979800B publication Critical patent/CN101979800B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明涉及电动爬升模板系统,用于现浇混凝土墙体施工,其结构包括模板体系、支模架体、承力支架和工作平台、爬升设备、附墙支座、导轨、防坠落装置和控制系统等部件。导轨分别与附墙支座和承力支架纵向滑动连接,支模架体和承力支架横向滑动连接,通过导轨和承力支架的交替上升就位承重实现模板体系和工作平台的爬升,通过支模架体和承力支架的滑动实现模板体系的开模和合模。所述爬升设备由链条和电动葫芦组成。链条通过滑轮组环绕导轨上端和下端及承力支架,通过电动葫芦的正转和反转驱动承力支架和导轨的交替上升就位承重,实现模板体系和工作平台的爬升。本发明具有使用方便、安拆简单、安全性能好的优点。

Description

电动爬升模板系统
技术领域
本发明属于建筑施工装备,尤其涉及一种电动爬升模板系统。 
背景技术
在中国,随着城市建设规模的高速发展和国家城镇化建设步伐的加大加快,高层和超高层建筑大量涌现,城市中的高楼越来越密集,施工场地越来越狭窄,传统的常规的人工吊装的模板由于“粗,笨,重”和严重依赖塔吊及大量的临边安装等恶劣的工作条件,已越来越难以适应高速的城市大规模的高层和超高层建筑的需要。目前,一些国家生产的液压外爬模板体系,也被中国引进使用。这些外爬模板体系由于存在多个液压系统的同步控制难以解决、液压油的泄露给结构墙体带来污染、产品的防坠落性能差等缺陷,不但存在操作困难,还存在安全隐患。因此设计一种使用方便,安拆简单,安全性能好的电动爬升模板系统是市场的需要。 
发明内容
本发明目的在于克服现有技术的缺陷,提供一种使用方便,安拆简单,安全性能好的电动爬升模板系统。 
本发明电动爬升模板系统是一种用于现浇混凝土墙体施工的装备,其结构包括模板体系、支撑模板的支模架体、支撑支模架体的承力支架、配装在承力支架上的平台;用于固装在混凝土墙体的附墙支座竖向滑配导轨、导轨竖向滑配承力支架,支模架体水平滑配在承力支架上,导轨与承力支架之间装配有防坠落装置和提升设备,其特别之处是,所述提升设备由柔性链条和驱动柔性链条的电动葫芦构成,所述柔性链条一端连接装配有滑轮组的上钩,链条另一端穿过承力支架上的电动葫芦,绕过承力支架上的牵拉结构和固定滑轮组,连接装配有滑轮组的下钩,所述上钩与导轨上端连接,所述下钩与导轨下端连接,链条绷紧后通过电动葫芦的正传和反转来实现承力支架和导轨的交替承重互爬提升。 
作为优化,在导轨上设置栅格式横杆,在承力支架上设置防坠落装置,所述防 坠落装置是一个与导轨的栅格式横杆大致啮合传动的星形轮和一个单向摆块的组合体,用以实现承力支架在爬升和工作过程中的短距离防坠落。 
作为优化,驱动支模架体在承力支架上水平开模合模的机构是一台通用的环链电动葫芦,电动葫芦的主钩钩挂在承力支架下部,链条一端通过滑轮组绕过承力支架前端与支模架体固接,链条另一端通过滑轮组绕过承力支架后端与支模架体固接。链条绷紧后通过葫芦的正转和反转实现模板体系的开模和合模。 
综上所述,本发明是一种现浇混凝土墙体的施工装备,包括模板体系、支模架体、承力支架和平台、提升设备、附墙支座、导轨、防坠落装置等部件。所述提升设备由柔性链条和电动机构成,所述柔性链条环绕导轨两端和承力支架,实现承力支架和导轨的交替承重互爬;所述支模架体的开模合模装置由柔性链条和电动机构成,所述柔性链条通过环绕所述的承力支架前端后端和所述的模板体系连接,通过电动控制使得模板体系在承力支架上滑动实现其开模合模;所述的防坠落装置设置在承力支架上,导轨上设置栅格式横杆与防坠落装置有机配合实现架体的防坠落功能。 
本发明电动爬升模板系统,操作简单实用,使用方便快捷,运行安全有序,配装电动脱模装置实现了机械化自动防坠,适应于高层和超高层建筑核心筒内外模板系统的整体或分组分片爬升。 
附图说明
图1是本发明电动爬升模板系统的侧向剖视结构示意图; 
图2是本发明电动爬升模板系统的主视结构示意图; 
图3是本发明电动爬升模板系统中防坠落装置实施方式的结构示意图; 
图4是本发明电动爬升模板系统中提升设备结构示意图; 
图5是本发明电动爬升模板系统中提升设备与导轨及承力支架连接方式示意图; 
图6是本发明电动爬升模板系统中开模合模电驱动装置配置状态结构示意图; 
图7是本发明电动爬升模板系统六个步骤的工作过程联合示意图。图中:第一步为首层浇筑,第二步为安装支模架体(承重架)和支撑模板(模板),第三步为浇筑第二层混凝土,第四步为开模、安装提升设备(提升系统),第五步为提升一层楼,第六步为安装架体下部进入正常循环。 
图中标号所表示的部件或部位为, 
1-支模架体        2-承力支架  3-附墙支座     4-导轨           5-柔性链条 
6-防坠落装置      7-平台      10-结构墙体    11-模板体系 
41-栅格式横杆     51-电动葫芦 52-牵拉结构    53-固定滑轮组    54-上钩 
55-下钩           60-星形轮   61-单向摆块。 
具体实施方式
如图所示,本发明电动爬升模板系统是一种现浇混凝土墙体的施工装备,其结构包括模板体系11、支撑模板的支模架体1、支撑支模架体1的承力支架2、配装在承力支架上的平台7;用于固装在混凝土墙体10的附墙支座3竖向滑配导轨4、导轨4竖向滑配的承力支架2,配装在承力支架2上的平台7;支模架体1水平滑配在承力支架2上,导轨4与承力支架2之间配有防坠落装置6,导轨4与承力支架2之间配装有提升设备;所述提升设备由柔性链条5和驱动柔性链条的电动葫芦51构成。所述柔性链条5一端连接装配了滑轮组的上钩54,链条5另一端穿过承力支架2上的电动葫芦51,绕过承力支架2上的牵拉结构52和固定滑轮组53,连接装配了滑轮组的下钩55,所述上钩54与导轨4上端连接,所述下钩55与导轨4下端连接,链条绷紧后通过电动葫芦的正传和反转来实现承力支架和导轨的交替承重互爬提升。 
防坠落装置6是正向可转动反向则卡阻的单向运动机构:导轨4上设置栅格式横杆41,承力支架2上设置与横杆41配合的星形轮60,再进一步设置与星形轮60配合的单向摆块61。 
爬升模板系统爬升和工作过程是这样实现防坠落的:导轨4爬升时,将单向摆块61在图3示位置翻转180度放置,星轮60如图3示顺时钟转动无卡阻,导轨4顺利爬升到位;承力支架2爬升时,将单向摆块61如图3示放置,星轮60如图3示位置反时钟转动,承力支架2顺利爬升到位;单向摆块61如图3示放置,承力支架2如在爬升过程中或工作过程中向下坠落,则星轮60会如图3示顺时钟转动,星轮60转动一个很小的角度时会被单向摆块61卡住,防止了承力支架2的继续坠落。 
支模架体1水平滑配在承力支架2上,驱动支模架体1沿承力支架2水平移动的开模合模的机构是一台通用的环链电动葫芦,电动葫芦51的主钩钩挂在承力支架2下部,柔性链条5的一端通过滑轮组绕过承力支架2前端与支模架体1固接,链条5的另一端通过滑轮组绕过承力支架2后端与支模架体1固接。链条5绷紧后通过葫芦的正转和反转实现模板体系的开模和合模。 

Claims (3)

1.一种电动爬升模板系统,用于现浇混凝土墙体施工,其结构包括模板体系、支撑模板的支模架体、支撑支模架体的承力支架、配装在承力支架上的平台;用于固装在混凝土墙体的附墙支座竖向滑配导轨、导轨竖向滑配承力支架,支模架体水平滑配在承力支架上,导轨与承力支架之间装配有防坠落装置和提升设备,其特征在于,所述提升设备由柔性链条和驱动柔性链条的电动葫芦构成,所述柔性链条一端连接装配有滑轮组的上钩,柔性链条另一端穿过承力支架上的电动葫芦,绕过承力支架上的牵拉结构和固定滑轮组,连接装配有滑轮组的下钩,所述上钩与导轨上端连接,所述下钩与导轨下端连接。
2.根据权利要求1所述的电动爬升模板系统,其特征在于,所述防坠落装置是在导轨上设置栅格式横杆,在承力支架上设置与横杆配合的星形轮,再进一步设置与星形轮配合的单向摆块。
3.根据权利要求1或2所述的电动爬升模板系统,其特征在于,驱动支模架体在承力支架上水平开模合模的机构是一台通用的环链电动葫芦,环链电动葫芦的主钩钩挂在承力支架下部,环链电动葫芦链条的一端通过滑轮组绕过承力支架前端与支模架体固接,环链电动葫芦链条另一端通过滑轮组绕过承力支架后端与支模架体固接。
CN201010524255XA 2010-10-29 2010-10-29 电动爬升模板系统 Expired - Fee Related CN101979800B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010524255XA CN101979800B (zh) 2010-10-29 2010-10-29 电动爬升模板系统

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010524255XA CN101979800B (zh) 2010-10-29 2010-10-29 电动爬升模板系统

Publications (2)

Publication Number Publication Date
CN101979800A CN101979800A (zh) 2011-02-23
CN101979800B true CN101979800B (zh) 2012-05-09

Family

ID=43600334

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010524255XA Expired - Fee Related CN101979800B (zh) 2010-10-29 2010-10-29 电动爬升模板系统

Country Status (1)

Country Link
CN (1) CN101979800B (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102155091B (zh) * 2011-03-17 2012-11-21 北城致远集团有限公司 爬模平台
CN103883120B (zh) * 2014-03-25 2016-04-20 中国三冶集团有限公司 一种带自锁功能的爬模结构
CN105908967A (zh) * 2016-06-29 2016-08-31 江苏省苏中建设集团股份有限公司 自升式电梯井剪力墙爬模操作平台及其施工方法
CN109424503B (zh) * 2017-09-01 2020-07-14 赵晓军 中心塔架的安装方法及塔筒的施工方法
CN110388048A (zh) * 2019-07-16 2019-10-29 中交一公局第二工程有限公司 一种液压爬模装置

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4403460A (en) * 1981-10-01 1983-09-13 Pittsburgh-Des Moines Corporation Method of erecting an elevated tank using formwork
CN2197410Y (zh) * 1993-06-05 1995-05-17 唐玉霞 专用于建筑物施工的爬模系统装置
US5630482A (en) * 1993-01-27 1997-05-20 Peri Gmbh Climbing device, in particular for a climbing scaffold
CN2670497Y (zh) * 2003-11-13 2005-01-12 上海市第一建筑有限公司 液压爬模防坠系统
CN101319560A (zh) * 2008-07-08 2008-12-10 上海建工股份有限公司 双作用整体式液压自动顶升平台系统及使用其的施工方法

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE102006029653B4 (de) * 2006-06-28 2009-02-12 Doka Industrie Gmbh Hubplattform und Verfahren zum Aufbauen einer Hubplattform

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4403460A (en) * 1981-10-01 1983-09-13 Pittsburgh-Des Moines Corporation Method of erecting an elevated tank using formwork
US5630482A (en) * 1993-01-27 1997-05-20 Peri Gmbh Climbing device, in particular for a climbing scaffold
CN2197410Y (zh) * 1993-06-05 1995-05-17 唐玉霞 专用于建筑物施工的爬模系统装置
CN2670497Y (zh) * 2003-11-13 2005-01-12 上海市第一建筑有限公司 液压爬模防坠系统
CN101319560A (zh) * 2008-07-08 2008-12-10 上海建工股份有限公司 双作用整体式液压自动顶升平台系统及使用其的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
浦键.爬升模板工艺在超高层建筑筒体施工中的应用.《应用能源技术》.2007,(第2期),第5-9页. *

Also Published As

Publication number Publication date
CN101979800A (zh) 2011-02-23

Similar Documents

Publication Publication Date Title
CN101979800B (zh) 电动爬升模板系统
CN110371823B (zh) 适用于装配式外加电梯施工的自提升吊装设备及施工方法
CN105971271A (zh) 单侧自爬升悬臂模板及其施工方法
CN104563491B (zh) 便捷液压自爬模板的使用方法
CN112900825B (zh) 一种井道自爬升操作平台
CN212176541U (zh) 轻型可周转高效施工造楼设备
CN106698208A (zh) 一种用于超高层建筑外部运输的吊装设备及吊装方法
CN204899238U (zh) 一种单元式幕墙板块吊装装置
CN206408952U (zh) 一种建筑施工附着式升降卸料平台
CN106121255A (zh) 一种超高层玻璃幕墙安装设备装置
CN205296803U (zh) 电梯自动提升操作台
CN103806654A (zh) 用于电梯井筒模的液压支撑系统及其运行方法
CN104531931B (zh) 高炉出铁场下部除尘管道安装方法
CN203173644U (zh) 一种多功能可升降的井道作业平台系统
CN206562264U (zh) 一种用于超高层建筑外部运输的吊装设备
CN212251443U (zh) 旧厂房除尘管道改造安装专用管道移动吊装装置
CN103074871A (zh) 一种弧形坡面混凝土滑升模板
CN205840436U (zh) 无电力双层车库
CN104150393B (zh) 一种微动力电力设备旋转起吊装置
CN206172883U (zh) 一种大型管道支架提升就位装置
CN103206076B (zh) 一种可移动式建筑装卸平台及移动方法
CN201737553U (zh) 一种用于塔式起重机的载人电梯
CN104291222A (zh) 一种超高层建筑核心筒内部硬质防护与行吊集成系统
CN211647239U (zh) 一种钢平台下挂装置
CN201507113U (zh) 一种建筑施工用电动爬模设备

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 101113 8 Guang Li street, Tongzhou District Industrial Development Zone, Beijing

Patentee after: Sunrise safety technology (Beijing) Co.,Ltd.

Address before: 101104 No. 8, Zhang Feng Road, Niu Bao Tun, Tongzhou District, Beijing.

Patentee before: BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co.,Ltd.

CP03 Change of name, title or address
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210120

Address after: 101149 3-027, building 2, 7 Yunbin Road, Tongzhou District, Beijing

Patentee after: BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co.,Ltd.

Address before: 101113 8 Guang Li street, Tongzhou District Industrial Development Zone, Beijing

Patentee before: Sunrise safety technology (Beijing) Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20241018

Address after: Intersection of Zhuangzi Avenue and Weisan Road, Economic Development Zone, Chengguan Town, Mengcheng County, Bozhou City, Anhui Province 233500

Patentee after: Anhui Mengsheng Construction Technology Co.,Ltd.

Country or region after: China

Address before: 101149 3-027, building 2, 7 Yunbin Road, Tongzhou District, Beijing

Patentee before: BEIJING TOSUN TECHNOLOGY DEVELOPMENT Co.,Ltd.

Country or region before: China

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120509