[go: up one dir, main page]

CN101824997A - 一种矿井采区双上山回风的布置方法 - Google Patents

一种矿井采区双上山回风的布置方法 Download PDF

Info

Publication number
CN101824997A
CN101824997A CN 201010131926 CN201010131926A CN101824997A CN 101824997 A CN101824997 A CN 101824997A CN 201010131926 CN201010131926 CN 201010131926 CN 201010131926 A CN201010131926 A CN 201010131926A CN 101824997 A CN101824997 A CN 101824997A
Authority
CN
China
Prior art keywords
uphill
coal
return
air
mine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010131926
Other languages
English (en)
Inventor
莫技
张传恕
田昌栋
仉学利
巩庆刚
王涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201010131926 priority Critical patent/CN101824997A/zh
Publication of CN101824997A publication Critical patent/CN101824997A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

本发明公开了一种矿井采区双上山回风的布置方法,它首先在一个开采水平内将两组距离相近的前组煤采区和后组煤采区联合布置一条运输大巷,前组煤采区和后组煤采区各分别布置一条运煤上山巷道、一条轨道上山巷道和一条回风上山巷道,将前组煤采区和后组煤采区的回风上山巷道之间开掘一条石门,使两采区回风上山巷道相互贯通。本发明在矿井采区巷道总开拓量基本不变的情况下,解决了通风量不足的问题,使井下采区的温度得到有效的降低,改善了井下工作环境。

Description

一种矿井采区双上山回风的布置方法
技术领域
本发明涉及井下采煤布置系统,尤其涉及回风巷道的布置方法。
背景技术
目前在煤矿开采多层煤时,根据煤层的赋存情况,通常在一个开采水平内将两组距离相近的前组煤采区和后组煤采区联合布置一条运输大巷,每层煤布置采区,每个采区至少布置一条运煤上山巷道、一条轨道上山巷道和一条回风上山巷道。把位于上层的煤称为前组煤,位于下层的煤称为后组煤。亦可先采前组煤,亦可先采后组煤,亦可前、后组煤同时开采。
随着矿井深度的延深,地温增高,原有回风巷道的断面显得过小,通风阻力过大,造成通风量不足,使采区内温度升高,作业环境差,工作人员易产生疲劳,影响正常生产。如果加大回风上山巷道断面来解决通风量不足的问题,就要大大增加巷道的施工量。
发明内容
本发明的目的是为解决上述矿井采区通风量不足的问题,提供一种双上山回风的布置方法。
一种矿井采区双上山回风的布置方法:首先在一个开采水平内将两组距离相近的前组煤采区和后组煤采区联合布置一条运输大巷,前组煤采区和后组煤采区各分别布置一条运煤上山巷道、一条轨道上山巷道和一条回风上山巷道,其特征是,将前组煤采区和后组煤采区的回风上山巷道之间开掘一条石门,使两采区回风上山巷道相互贯通。
当开采前组煤时,使两采区回风巷道同时回风。当开采后组煤时,亦可借用前组煤的回风上山巷道同时回风。因此,无论开采前组煤还是后组煤都有两条回风巷道同时并列的回风。
本发明的优点是,在矿井采区巷道总开拓量基本不变(仅增加一条贯通石门的开拓量)的情况下,解决了通风量不足的问题,使井下采区的温度得到有效的降低,改善了井下工作环境。
附图说明
图1是本发明的断面布置示意图,图中未画出运煤上山巷道和轨道上山巷道。
图中:1-运输大巷,2、3-回风巷道,4-石门。
具体实施方式
如图1所示,本发明首先在一个开采水平内将两组距离相近的前组煤采区和后组煤采区联合布置一条运输大巷1,前组煤采区和后组煤采区各分别布置一条运煤上山巷道、一条轨道上山巷道和一条回风上山巷道2和3,再将回风上山巷道2和3之间开掘一条石门4,使两采区回风上山巷道相互贯通。
当开采前组煤时,使两采区回风巷道2和3同时回风。当开采后组煤时,亦可借用前组煤的回风上山巷道2同时回风。因此,无论开采前组煤还是后组煤都有两条回风巷道同时并列的回风。
本发明中所指的上山巷道,指上山开采方式的称谓,在煤矿下山开采方式时称为下山巷道,这是本领域技术人员共知的。所以本发明称谓的“双上山回风”亦可为“双下山回风”。
本发明的技术方案中,仅描述了先开采前组煤的情况,当开采后组煤时,布置方法与前述相同。

Claims (1)

1.一种矿井采区双上山回风的布置方法,它首先在一个开采水平内将两组距离相近的前组煤采区和后组煤采区联合布置一条运输大巷,前组煤采区和后组煤采区各分别布置一条运煤上山巷道、一条轨道上山巷道和一条回风上山巷道,其特征在于,将前组煤采区和后组煤采区的回风上山巷道之间开掘一条石门,使两采区回风上山巷道相互贯通。
CN 201010131926 2010-03-25 2010-03-25 一种矿井采区双上山回风的布置方法 Pending CN101824997A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010131926 CN101824997A (zh) 2010-03-25 2010-03-25 一种矿井采区双上山回风的布置方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010131926 CN101824997A (zh) 2010-03-25 2010-03-25 一种矿井采区双上山回风的布置方法

Publications (1)

Publication Number Publication Date
CN101824997A true CN101824997A (zh) 2010-09-08

Family

ID=42689135

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010131926 Pending CN101824997A (zh) 2010-03-25 2010-03-25 一种矿井采区双上山回风的布置方法

Country Status (1)

Country Link
CN (1) CN101824997A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362508A (zh) * 2013-07-31 2013-10-23 六盘水师范学院 一种矿井开拓方法
CN103953378A (zh) * 2014-04-29 2014-07-30 中国矿业大学(北京) 一种高温矿井通风方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3712677A (en) * 1971-03-10 1973-01-23 Atlantic Richfield Co Mining method
CN1165237A (zh) * 1997-04-24 1997-11-19 张中科 边界上(下)山沿空掘巷前进式开采方法
US6796616B2 (en) * 2002-06-26 2004-09-28 Jeffrey K. Harman Mining system
CN1676877A (zh) * 2005-04-26 2005-10-05 淮南矿业(集团)有限责任公司 相邻采煤工作面交错式布置采煤方法
CN201103402Y (zh) * 2007-12-04 2008-08-20 牛玉泉 一种矿山井下巷道通风装置
CN100494627C (zh) * 2005-03-03 2009-06-03 开滦(集团)有限责任公司 急倾斜厚煤层的采煤方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3712677A (en) * 1971-03-10 1973-01-23 Atlantic Richfield Co Mining method
CN1165237A (zh) * 1997-04-24 1997-11-19 张中科 边界上(下)山沿空掘巷前进式开采方法
US6796616B2 (en) * 2002-06-26 2004-09-28 Jeffrey K. Harman Mining system
CN100494627C (zh) * 2005-03-03 2009-06-03 开滦(集团)有限责任公司 急倾斜厚煤层的采煤方法
CN1676877A (zh) * 2005-04-26 2005-10-05 淮南矿业(集团)有限责任公司 相邻采煤工作面交错式布置采煤方法
CN201103402Y (zh) * 2007-12-04 2008-08-20 牛玉泉 一种矿山井下巷道通风装置

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362508A (zh) * 2013-07-31 2013-10-23 六盘水师范学院 一种矿井开拓方法
CN103362508B (zh) * 2013-07-31 2015-04-15 六盘水师范学院 一种矿井开拓方法
CN103953378A (zh) * 2014-04-29 2014-07-30 中国矿业大学(北京) 一种高温矿井通风方法
CN103953378B (zh) * 2014-04-29 2016-02-03 中国矿业大学(北京) 一种高温矿井通风方法

Similar Documents

Publication Publication Date Title
CN101975064B (zh) 一种缓倾斜薄矿体机械化连续开采方法
CN104060991B (zh) 一种用于缓倾斜薄矿脉的脉内斜坡道上向分层充填采矿法
CN105221179B (zh) 一种高瓦斯矿井y型通风方法
CN108060924A (zh) 急倾斜多层薄矿体机械化联合采矿方法
CN107762515B (zh) 一种缓倾斜中厚矿体盘区充填采矿方法
CN104481539B (zh) 自拉槽挤压爆破崩落采矿法
CN103953344B (zh) 一种下向进路分层胶结充填采矿法
CN104389606A (zh) 一种基于环境保护的新型矿山开采技术方案
CN102392678A (zh) 井上下联合压裂增透抽采瓦斯的方法
CN103628877A (zh) 一种多层缓倾斜薄-中厚矿床充填采矿方法
CN106761902B (zh) 一种适用于软岩保护层开采的立体综合卸压瓦斯抽采方法
CN101915118A (zh) 高瓦斯中硬煤层递进式瓦斯抽放方法
CN104179505B (zh) 一种磷矿的地下采矿方法
CN101725350A (zh) 下盘沿脉凿岩穿脉进路出矿式崩落采矿法
CN103104261A (zh) 一种多层矿体三维空间协同采矿法
CN109458181A (zh) 一种金属矿沿走向一次采全高的充填采矿方法
CN103147759B (zh) 一种倾斜小矿体探矿—浅孔留矿采矿方法
CN101824997A (zh) 一种矿井采区双上山回风的布置方法
CN105370285A (zh) 一种防止地浸方式铀矿开采中地下水位下降的方法
CN103670417B (zh) 利用电耙巷道侧部出矿的无底柱分段崩落采矿法
CN101469612B (zh) 间隔式金属矿的开采方法
CN205422716U (zh) 一种充填采矿法镶嵌式构造
CN113389550B (zh) 一种多采区集群开采连续工艺
CN205422717U (zh) 一种充填采矿法墙式构造
CN103161439A (zh) 水平段上倾井组

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100908