[go: up one dir, main page]

CN101817984A - Emulsified asphalt and preparation method thereof - Google Patents

Emulsified asphalt and preparation method thereof Download PDF

Info

Publication number
CN101817984A
CN101817984A CN 201010148059 CN201010148059A CN101817984A CN 101817984 A CN101817984 A CN 101817984A CN 201010148059 CN201010148059 CN 201010148059 CN 201010148059 A CN201010148059 A CN 201010148059A CN 101817984 A CN101817984 A CN 101817984A
Authority
CN
China
Prior art keywords
emulsified bitumen
pitch
emulsifying agent
emulsified
asphalt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010148059
Other languages
Chinese (zh)
Inventor
糜万俊
陈庆
徐小云
季永莉
肖强飞
熊兆松
阚大清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU HUAYU RAILWAY NEW MATERIAL CO Ltd
Original Assignee
JIANGSU HUAYU RAILWAY NEW MATERIAL CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU HUAYU RAILWAY NEW MATERIAL CO Ltd filed Critical JIANGSU HUAYU RAILWAY NEW MATERIAL CO Ltd
Priority to CN 201010148059 priority Critical patent/CN101817984A/en
Publication of CN101817984A publication Critical patent/CN101817984A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Compositions Of Macromolecular Compounds (AREA)

Abstract

The invention discloses emulsified asphalt and a preparation method thereof. The emulsified asphalt comprises the following components in percent by weight: 60 to 65 percent of asphalt, 1.0 to 4.0 percent of complex emulsifier, 0.04 to 0.4 percent of stabilizing agent, 0.05 to 0.2 percent of thixotropic agent, 0.1 to 4 percent of aid and the balance of water. The emulsified asphalt for CRTS II type slab ballastless track cement-emulsified-asphalt mortar solves the main problems of poor stability, short available time, poor temperature adaptability, easy delamination and the like of the emulsified asphalt in the prior art. By adopting technology of complexing the emulsifier, various stabilizing agents are added, so the emulsified asphalt has the advantages of good emulsifying effect, good storage stability, good temperature adaptability of prepared cement-emulsified-asphalt mortar, long available time and no delamination, and can completely meet the requirement of cement-emulsified-asphalt mortar for ballastless track cushion of high speed railways.

Description

A kind of emulsified bitumen and preparation method thereof
Technical field
The invention belongs to high-speed railway plate-type slag-free orbit brace mortar technical field, particularly a kind of CRTS II template formula ballastless track cement emulsified asphalt mortar is adjusted emulsified bitumen that uses in the layer and preparation method thereof.
Background technology
Because high-speed railway is to the requirement of circuit high ride and high stability, the plate-type slag-free orbit structure is all adopted in countries in the world.Ballastless track is the gordian technique of high-speed railway, by roadbed, guidance tape and between the cement emulsified asphalt mortar layer form, the cement emulsified asphalt mortar layer is a kind of semi-rigid body gelling material between cement based and asphalt-based material, is bringing into play important effect in the ballastless track structure.Main classification CRTS I template formula ballastless track, CRTS II template formula ballastless track.
Emulsified bitumen is one of crucial composition material of cement emulsified asphalt mortar, and its performance directly affects the serviceability and the endurance quality of cement emulsified asphalt mortar.CRTS II template formula ballastless track cement emulsified asphalt mortar with emulsified bitumen except that should having traditional performances such as good preservation stability, high low-temperature stability, also should have, stability good and by force, not influence performances such as hydrated cementitious speed with siccative system consistency, and the mortar of preparation can air content need determine within certain scope that mortar keeps degree of mobilization, divergence preferably in the long time.
At present, the producer of domestic production emulsified bitumen is a lot, but all is in the trial production stage, and the country/industry standard that does not have to determine is gone standard emulsified asphalt product quality.The mortar of existing emulsified bitumen preparation exists operable time weak point, thermal adaptation narrow range, the easy deficiencies such as layering, fillibility difference of emanating, if use in CRTS II template formula ballastless track, understands the quality that directly influence cement emulsified asphalt mortar.
Summary of the invention
Technical problem solved by the invention is to provide emulsified bitumen that a kind of stability in storage is good, thermal adaptability is good and preparation method thereof.
The technical solution that realizes the object of the invention is: a kind of emulsified bitumen, comprise pitch, emulsifying agent, stablizer, auxiliary agent and water, wherein each components contents is by weight percentage: pitch: 60~65%, emulsifying agent 1.0~4.0%, stablizer: 0.04~0.4%, thixotropic agent 0.05~0.2%, auxiliary agent: 0.1~4.0%, surplus is a water.
A kind of method of making emulsified bitumen may further comprise the steps:
Step 1, with pitch heating and melting in the geosyncline, beat to material-compound tank, afterwards the heating;
Step 2, stablizer, emulsifying agent, thixotropic agent and auxiliary agent are squeezed into the soap lye groove successively, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye, afterwards heating.
Step 3, above-mentioned pitch is pressed 3m 3/ h, soap lye are pressed 2m 3The flow velocity of/h is squeezed into the colloidal mill of preheating, shearing, pulverizing, grinding and mixing and emulsifying through colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, form the uniform and stable heterogeneous dispersion system of oil-in-water shape, this system is emulsified bitumen.
The present invention compared with prior art, its remarkable advantage is: the emulsified bitumen that uses in the CRTS II template formula ballastless track cement emulsified asphalt mortar of the present invention, bubble is few in the system, not only be fit to store at normal temperatures and use, also be adapted under the lower or higher environment of temperature storing and use, have that stability in storage is good, thermal adaptability is good, low bubble property; The cement emulsified asphalt mortar of preparation has advantages such as operable time length, good stability, not stratified segregation, and this mortar can be constructed under low temperature or hot environment.
Below in conjunction with accompanying drawing the present invention is described in further detail.
Description of drawings
Accompanying drawing is an emulsified bitumen preparation technology schema of the present invention.
Embodiment
A kind of emulsified bitumen of the present invention, comprise pitch, emulsifying agent, stablizer, thixotropic agent, auxiliary agent and water, wherein each components contents is by weight percentage: pitch: 60~65%, emulsifying agent 1.0~4.0%, stablizer: 0.04~0.4%, thixotropic agent 0.05~0.2%, auxiliary agent: 0.1~4.0%, surplus is a water.Described pitch is to satisfy above heavy traffic paving asphalt of B level or the bi tumenf orr oad that JTJ052-2000 requires, draw selection No. 70 or No. 90 pitches by pitch penetration degree index, the use climatope condition of the selection of the former material of pitch and emulsified bitumen adapts, and can strengthen the interaction of emulsified bitumen and siccative, improve the overall performance of mortar.Emulsifying agent is 2.0~3.5% anionic emulsifier or 2.0~3.5% anionic emulsifiers and the mixing of other emulsifying agents, and described other emulsifying agents are one or both the mixing in 0.2~1.0% nonionic emulsifier, 0.1~0.5% amphoteric ion type emulsifying agent; Described anionic emulsifier is one or both and the above mixing in lipid acid sulfoalkyl ester, sulfonated lignin, the alkyl ether carboxylic acid's salt.Described nonionic emulsifier is a kind of or two kinds and the above mixing in sorbitan ester, alkylphenol polyoxyethylene, the alkylamide type.Described amphoteric ion type emulsifying agent is a kind of or two kinds and the above mixing in basic trimethyl-glycine in the laurylamide, the amino acid type amphoteric ionic emulsifying agent.Described stablizer is the mixing of a kind of in polyethers, the cellulose family or two kinds.Described thixotropic agent is water-soluble silicon-dioxide.A kind of in preferred caustic soda of above-mentioned auxiliary agent or the inorganic salt or two kinds compound.These materials can increase the stability of emulsified bitumen system as stablizer and auxiliary agent, avoid producing laminated segregation with the cement emulsified asphalt mortar of emulsified bitumen preparation, improve the resolution of mortar.
A kind of method of making above-mentioned emulsified bitumen may further comprise the steps:
Step 1, with pitch heating and melting in the geosyncline, beat to material-compound tank, afterwards the heating; Asphalt temperature after the heating is 130 ± 5 ℃.
Step 2, stablizer, emulsifying agent, thixotropic agent and auxiliary agent are squeezed into the soap lye groove successively, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye, afterwards heating.Stablizer is: the mixing of a kind of in polyethers, the cellulose family or two kinds; Thixotropic agent is water-soluble silicon-dioxide; Emulsifying agent is 2.0~3.5% anionic emulsifier or 2.0~3.5% anionic emulsifiers and the mixing of other emulsifying agents, described other emulsifying agents are one or both the mixing in 0.2~1.0% nonionic emulsifier, 0.1~0.5% amphoteric ion type emulsifying agent, and wherein anionic emulsifier is one or both and the above mixing in lipid acid sulfoalkyl ester, sulfonated lignin, the alkyl ether carboxylic acid's salt; Nonionic emulsifier is a kind of or two kinds and the above mixing in sorbitan ester, alkylphenol polyoxyethylene, the alkylamide type; The amphoteric ion type emulsifying agent is a kind of or two kinds and the above mixing in dodecanamide propyl trimethyl-glycine, the amino acid type amphoteric ionic emulsifying agent; The pH value of solution is 11-12 behind the adjusting PH; Heated temperatures is 60 ± 5 ℃.
Step 3, above-mentioned pitch is pressed 3m 3/ h, soap lye are pressed 2m 3The flow velocity of/h is squeezed into the colloidal mill of preheating, shearing, pulverizing, grinding and mixing and emulsifying through colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, form the uniform and stable heterogeneous dispersion system of oil-in-water shape, this system is emulsified bitumen.
The performance of the emulsified bitumen among the present invention satisfies the requirement of " the provisional technical qualification of passenger dedicated railway line CRTS II template formula ballastless track cement emulsified asphalt mortar ", see Table 1, satisfy the requirement of table 2 with the performance of the cement emulsified asphalt mortar of above-mentioned emulsified bitumen preparation.
The performance index of table 1 emulsified bitumen
Figure GSA00000082241700041
Annotate: (1) carries out this detection when process low tempertaure storage in the actual use of emulsified bitumen and transportation.
(2) when adopting modifying asphalt to prepare emulsified bitumen, carry out this detection.
Table 2 cement emulsified asphalt mortar technical performance index
Figure GSA00000082241700042
Annotate: (1) Ds represents that mortar goes out machine and expands system; D30 represents to expand when mortar goes out machine 30min system; Required time when t280 represents that mortar expansion system reaches 280s.
Various technical requirements involved in the present invention and performance index require all can be with reference to the regulation in " the provisional technical qualification of passenger dedicated railway line CRTS II template formula ballastless track cement emulsified asphalt mortar " (No. [2008] 74, science and technology base) or corresponding national standards and the industry standard.
The present invention is raw materials used all by weight percentage, the asphalt stock that adopts draw by its penetration degree index and select No. 70 or No. 90 pitches, below in conjunction with embodiment the present invention is further described:
Embodiment 1
The emulsified bitumen that this example pin provides, the pitch that is adopted is No. 90 heavy-duty road asphalts, lipid acid sulfoalkyl ester anionic emulsifier, the alkylphenol polyoxyethylene nonionic emulsifier, dodecanamide propyl beet alkali ampholytic ionic emulsifying agent, polyethers and cellulose family compound stabilizer, water-soluble silicon-dioxide thixotropic agent, its composition is as shown in table 3.This example system the emulsified bitumen thixotropy good, and the mortar temperature adaptability that makes is good, the not stratified segregation in back is solidified in not sedimentation, mortar, is applicable to low-temperature construction.Preparation process is as follows:
1. open steam heating system, geosyncline inner coil pipe heating system is heated to 130 ℃ of-160 ℃ of thawings with No. 90 heavy-duty road asphalts, utilize pump that pitch is beaten to dosing vessel, the pitch of stating proportioning is heated to material-compound tank, material-compound tank also is provided with steam-heating apparatus, by PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, the control asphalt temperature is opened and is stirred at 130 ± 5 ℃;
2. with polyethers and cellulose family compound stabilizer, water-soluble silicon-dioxide thixotropic agent, lipid acid sulfoalkyl ester anionic emulsifier, alkylphenol polyoxyethylene nonionic emulsifier, dodecanamide propyl beet alkali ampholytic ionic emulsifying agent and Sulfates auxiliary agent are squeezed into the soap lye groove successively, its composition is as shown in table 3, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye to the 11-12 scope.By PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, 60 ± 5 ℃ of control soap lye asphalt temperature are opened and are stirred;
3. by the PLC Controlling System, set flow velocity pitch 3m 3/ h, soap lye flow velocity 2m 3/ h, its controlled variable is as shown in table 4, opens soap lye, bitumenpump successively, soap lye, pitch are squeezed into the colloidal mill of preheating, through shearing, pulverizing, grinding and the mixing and emulsifying of colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, the emulsified bitumen finished product of system.
Embodiment 2
The emulsified bitumen that this example pin provides, the pitch that is adopted are No. 90 heavy-duty road asphalts, the sulfonated lignin anionic emulsifier, and the cellulose family stablizer, water-soluble silicon-dioxide thixotropic agent, its composition is as shown in table 3.This example makes to such an extent that emulsified bitumen is fit to construction at normal temperatures.Preparation process is as follows:
1. open steam heating system, geosyncline inner coil pipe heating system is heated to 130 ℃ of-160 ℃ of thawings with No. 90 heavy-duty road asphalts, utilize pump that pitch is beaten to dosing vessel, the pitch of stating proportioning is heated to material-compound tank, material-compound tank also is provided with steam-heating apparatus, by PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, the control asphalt temperature is opened and is stirred at 130 ± 5 ℃;
2. with the cellulose family stablizer, water-soluble silicon-dioxide thixotropic agent, sulfonated lignin anionic emulsifier and Sulfates auxiliary agent are squeezed into the soap lye groove successively, its composition is as shown in table 3, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye to the 11-12 scope.By PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, 60 ± 5 ℃ of control soap lye asphalt temperature are opened and are stirred;
3. by the PLC Controlling System, set flow velocity pitch 3m 3/ h, soap lye flow velocity 2m 3/ h, its controlled variable is as shown in table 4, opens soap lye, bitumenpump successively, soap lye, pitch are squeezed into the colloidal mill of preheating, through shearing, pulverizing, grinding and the mixing and emulsifying of colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, the emulsified bitumen finished product of system.
Embodiment 3
The emulsified bitumen that this example pin provides, the pitch that is adopted are No. 90 heavy-duty road asphalts, the sulfonated lignin anionic emulsifier, and dodecanamide propyl trimethyl-glycine and amino acid type amphoteric ionic emulsifying agent, the cellulose family stablizer, its composition is as shown in table 3.This example makes to such an extent that emulsified bitumen is fit to construction at normal temperatures.Preparation process is as follows: the emulsified bitumen stability in storage is good, and, the mortar good fluidity, the not sedimentation that make.Preparation process is as follows:
1. open steam heating system, geosyncline inner coil pipe heating system is heated to 130 ℃ of-160 ℃ of thawings with No. 90 heavy-duty road asphalts, utilize pump that pitch is beaten to dosing vessel, the pitch of stating proportioning is heated to material-compound tank, material-compound tank also is provided with steam-heating apparatus, by PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, the control asphalt temperature is opened and is stirred at 130 ± 5 ℃;
2. with the cellulose family stablizer, the sulfonated lignin anionic emulsifier, dodecanamide propyl trimethyl-glycine and amino acid type amphoteric ionic emulsifying agent and Sulfates auxiliary agent are squeezed into the soap lye groove successively, its composition is as shown in table 3, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye to the 11-12 scope.By PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, 60 ± 5 ℃ of control soap lye asphalt temperature are opened and are stirred;
3. by the PLC Controlling System, set flow velocity pitch 3m 3/ h, soap lye flow velocity 2m 3/ h, its controlled variable is as shown in table 4, opens soap lye, bitumenpump successively, soap lye, pitch are squeezed into the colloidal mill of preheating, through shearing, pulverizing, grinding and the mixing and emulsifying of colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, the emulsified bitumen finished product of system.
Embodiment 4
The emulsified bitumen that this example pin provides, the pitch that is adopted are No. 70 heavy-duty road asphalts, sulfonated lignin anionic type emulsifying agent, and sorbitan ester and alkylphenol polyoxyethylene nonionic emulsifier, the cellulose family stablizer, its composition is as shown in table 3.This example makes to such an extent that emulsified bitumen is fit to construction at normal temperatures.Preparation process is as follows:
1. open steam heating system, geosyncline inner coil pipe heating system is heated to 130 ℃ of-160 ℃ of thawings with No. 70 heavy-duty road asphalts, utilize pump that pitch is beaten to dosing vessel, the pitch of stating proportioning is heated to material-compound tank, material-compound tank also is provided with steam-heating apparatus, by PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, the control asphalt temperature is opened and is stirred at 130 ± 5 ℃;
2. will tie up plain class stablizer, the sulfonated lignin anionic emulsifier, sorbitan ester and alkylphenol polyoxyethylene nonionic emulsifier and Sulfates auxiliary agent are squeezed into the soap lye groove successively, its composition is as shown in table 3, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye to the 11-12 scope.By PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, 60 ± 5 ℃ of control soap lye asphalt temperature are opened and are stirred;
3. by the PLC Controlling System, set flow velocity pitch 3m 3/ h, soap lye flow velocity 2m 3/ h, its controlled variable is as shown in table 4, opens soap lye, bitumenpump successively, soap lye, pitch are squeezed into the colloidal mill of preheating, through shearing, pulverizing, grinding and the mixing and emulsifying of colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, the emulsified bitumen finished product of system.
Embodiment 5
The emulsified bitumen that this example pin provides, the pitch that is adopted is No. 70 heavy-duty road asphalts, alkyl ether carboxy acid salt's anionoid type emulsifying agent, alkylamide type nonionic emulsifier, the amino acid type amphoteric ionic emulsifying agent, cellulose stabiliser, water-soluble silicon-dioxide thixotropic agent, its composition is as shown in table 3.This example system good, the high temperature of emulsified bitumen stability in storage under be difficult for breakdown of emulsion, and the mortar divergence that makes good, be easy to perfusion, be fit to high temperature construction down.Preparation process is as follows:
1. open steam heating system, geosyncline inner coil pipe heating system is heated to 130 ℃ of-160 ℃ of thawings with No. 70 heavy-duty road asphalts, utilize pump that pitch is beaten to dosing vessel, the pitch of stating proportioning is heated to material-compound tank, material-compound tank also is provided with steam-heating apparatus, by PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, the control asphalt temperature is opened and is stirred at 130 ± 5 ℃;
2. with cellulose stabiliser, water-soluble silicon-dioxide thixotropic agent, alkyl ether carboxy acid salt's anionoid type emulsifying agent, alkylamide type nonionic emulsifier, amino acid type amphoteric ionic emulsifying agent and Sulfates auxiliary agent are squeezed into the soap lye groove successively, and its composition is as shown in table 3, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye to the 11-12 scope.By PLC Controlling System design temperature controlled variable, by the aperture of control steam valve, 60 ± 5 ℃ of control soap lye asphalt temperature are opened and are stirred;
3. by the PLC Controlling System, set flow velocity pitch 3m 3/ h, soap lye flow velocity 2m 3/ h, its controlled variable is as shown in table 4, opens soap lye, bitumenpump successively, soap lye, pitch are squeezed into the colloidal mill of preheating, through shearing, pulverizing, grinding and the mixing and emulsifying of colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, the emulsified bitumen finished product of system.
The foregoing description 1-5 production formula is compared:
Table 3 embodiment 1-5 production formula composition (weight percent, %)
The foregoing description 1-5 emulsified bitumen production control parameter is compared:
Table 4 embodiment 1-5 emulsified bitumen production control parameter
Examples of parameters Pitch flow (m 3/h) Asphalt temperature (℃) Soap lye flow (m 3/h) The soap lye temperature (℃) Output (ton)
Example 1 ??3.05 ??135 ??1.95 ??65 ??1
Example 2 ??2.95 ??130 ??2.05 ??60 ??1
Examples of parameters Pitch flow (m 3/h) Asphalt temperature (℃) Soap lye flow (m 3/h) The soap lye temperature (℃) Output (ton)
Example 3 ??2.95 ??125 ??2.05 ??55 ??1
Example 4 ??295 ??125 ??205 ??55 ??1
Example 5 ??2.95 ??125 ??2.05 ??55 ??1
To the emulsified bitumen of the foregoing description 1-3 output, carry out check analysis:
The emulsified bitumen performance test results of table 5 embodiment 1-3 output
Figure GSA00000082241700092

Claims (11)

1. emulsified bitumen, it is characterized in that, comprise pitch, emulsifying agent, stablizer, thixotropic agent, auxiliary agent and water, wherein each components contents is by weight percentage: pitch 60~65%, emulsifying agent 1.0~4.0%, stablizer 0.04~0.4%, thixotropic agent 0.05~0.2%, auxiliary agent 0.1~4.0%, surplus are water.
2. emulsified bitumen according to claim 1 is characterized in that, described pitch is to satisfy above heavy traffic paving asphalt of B level or the bi tumenf orr oad that JTJ052-2000 requires.
3. emulsified bitumen according to claim 2 is characterized in that, described pitch is divided into No. 70 or No. 90 pitches by its penetration degree index.
4. emulsified bitumen according to claim 1, it is characterized in that, emulsifying agent is 2.0~3.5% anionic emulsifier or 2.0~3.5% anionic emulsifiers and the mixing of other emulsifying agents, and described other emulsifying agents are one or both the mixing in 0.2~1.0% nonionic emulsifier, 0.1~0.5% amphoteric ion type emulsifying agent; Described anionic emulsifier is one or both and the above mixing in lipid acid sulfoalkyl ester, sulfonated lignin, the alkyl ether carboxylic acid's salt.
5. emulsified bitumen according to claim 4 is characterized in that, described nonionic emulsifier is a kind of or two kinds and the above mixing in sorbitan ester, alkylphenol polyoxyethylene, the alkylamide type.
6. emulsified bitumen according to claim 4 is characterized in that, described amphoteric ion type emulsifying agent is a kind of or two kinds and the above mixing in dodecanamide propyl trimethyl-glycine, the amino acid type amphoteric ionic emulsifying agent.
7. emulsified bitumen according to claim 1 is characterized in that, described stablizer is the mixing of a kind of in polyethers, the cellulose family or two kinds.
8. emulsified bitumen according to claim 1 is characterized in that, described thixotropic agent is water-soluble silicon-dioxide.
9. a method of making the described emulsified bitumen of claim 1 is characterized in that, may further comprise the steps:
Step 1, with pitch heating and melting in the geosyncline, beat to material-compound tank, afterwards the heating;
Step 2, stablizer, emulsifying agent, thixotropic agent and auxiliary agent are squeezed into the soap lye groove successively, after adding water and fully dissolving, the regulator solution pH value is mixed with soap lye, afterwards heating;
Step 3, above-mentioned pitch is pressed 3m 3/ h, soap lye are pressed 2m 3The flow velocity of/h is squeezed into the colloidal mill of preheating, shearing, pulverizing, grinding and mixing and emulsifying through colloidal mill, make pitch with tiny microparticulate in the aqueous solution that contains emulsifying agent, form the uniform and stable heterogeneous dispersion system of oil-in-water shape, this system is emulsified bitumen.
10. want 8 described emulsified bitumen manufacture method according to right, it is characterized in that, the asphalt temperature in the step 1 after the heating is 130 ± 5 ℃.
11. want 8 described emulsified bitumen manufacture method according to right, it is characterized in that stablizer is in the step 2: the mixing of a kind of in polyethers, the cellulose family or two kinds; Thixotropic agent is water-soluble silicon-dioxide; Emulsifying agent is one or both and the above mixing in 2.0~3.5% anionic emulsifier, 0.2~1.0% nonionic emulsifier, 0.1~0.5% amphoteric ion type emulsifying agent, and wherein anionic emulsifier is one or both and the above mixing in lipid acid sulfoalkyl ester, sulfonated lignin, the alkyl ether carboxylic acid's salt; Nonionic emulsifier is a kind of or two kinds and the above mixing in sorbitan ester, alkylphenol polyoxyethylene, the alkylamide type; The amphoteric ion type emulsifying agent is a kind of or two kinds and the above mixing in dodecanamide propyl trimethyl-glycine, the amino acid type amphoteric ionic emulsifying agent; The pH value of solution is 11-12 behind the adjusting PH; Heated temperatures is 60 ± 5 ℃.
CN 201010148059 2010-04-16 2010-04-16 Emulsified asphalt and preparation method thereof Pending CN101817984A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010148059 CN101817984A (en) 2010-04-16 2010-04-16 Emulsified asphalt and preparation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010148059 CN101817984A (en) 2010-04-16 2010-04-16 Emulsified asphalt and preparation method thereof

Publications (1)

Publication Number Publication Date
CN101817984A true CN101817984A (en) 2010-09-01

Family

ID=42653267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010148059 Pending CN101817984A (en) 2010-04-16 2010-04-16 Emulsified asphalt and preparation method thereof

Country Status (1)

Country Link
CN (1) CN101817984A (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102093729A (en) * 2011-01-05 2011-06-15 东南大学 Nano particle modified asphalt and preparation method thereof
CN102504554A (en) * 2011-11-14 2012-06-20 镇江金阳道路材料科技发展有限公司 Anion slow-cracking asphalt emulsifying agent and preparation method thereof
CN103059580A (en) * 2011-10-18 2013-04-24 中国石油化工股份有限公司 Anionic anti-freezing emulsified asphalt and preparation method thereof
CN103602081A (en) * 2013-11-07 2014-02-26 河北伦特石油化工有限公司 Rubber powder asphalt and preparation method thereof
CN103773028A (en) * 2014-01-20 2014-05-07 南通东南公路工程有限公司 Fatty acid emulsified asphalt material
CN103803893A (en) * 2012-11-07 2014-05-21 中国石油化工股份有限公司 Cement asphalt mortar and preparation method thereof
CN103834183A (en) * 2012-11-27 2014-06-04 中国石油天然气股份有限公司 A special emulsified asphalt for high-speed railway slab ballastless track
CN103980868A (en) * 2014-05-27 2014-08-13 玉门油田科达化学有限责任公司 Anti-collapse agent of zwitterionic emulsified asphalt for drilling fluid
CN104130757A (en) * 2014-07-15 2014-11-05 中国石油集团长城钻探工程有限公司钻井液公司 Plugging type anti-collapse agent and preparation method thereof
CN104448848A (en) * 2014-11-21 2015-03-25 江苏省交通科学研究院股份有限公司 Quick-set wheel-adhesion-free sticky layer emulsified asphalt and preparation method thereof
CN108840606A (en) * 2018-07-31 2018-11-20 南京浦江工程检测有限公司 A kind of cold mixing cold laid asphaltic mixture and preparation method and wearing course
CN109694482A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Modified emulsifying asphalt and preparation method thereof and mist sealing material
CN109762467A (en) * 2018-12-25 2019-05-17 广西青龙化学建材有限公司 Modified viscoelastic marine glue of graphene and preparation method thereof
CN115651417A (en) * 2022-11-04 2023-01-31 喜跃发国际环保新材料股份有限公司 Emulsified asphalt enhanced by adopting cellulose nanocrystals as well as preparation method and application of emulsified asphalt
CN116354647A (en) * 2023-02-23 2023-06-30 江苏镇淮建设集团有限公司 Thus ultrathin wearing layer for pavement maintenance and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030181557A1 (en) * 2002-03-01 2003-09-25 Jsr Corporation Aqueous emulsion dispersion of thermoplastic elastomer and process for preparing the same
CN1746242A (en) * 2004-09-07 2006-03-15 深圳市海川实业股份有限公司 Asphalt emulsion coating
CN1966581A (en) * 2006-11-08 2007-05-23 苏州大学 Synthetic fiber modified pavement asphalt and its preparing process
CN101139465A (en) * 2007-09-17 2008-03-12 徐培华 High-dense emulsified asphalt and preparation method thereof
CN101642933A (en) * 2009-08-31 2010-02-10 中铁四局集团有限公司 Preparation method of emulsified asphalt mortar

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20030181557A1 (en) * 2002-03-01 2003-09-25 Jsr Corporation Aqueous emulsion dispersion of thermoplastic elastomer and process for preparing the same
CN1746242A (en) * 2004-09-07 2006-03-15 深圳市海川实业股份有限公司 Asphalt emulsion coating
CN1966581A (en) * 2006-11-08 2007-05-23 苏州大学 Synthetic fiber modified pavement asphalt and its preparing process
CN101139465A (en) * 2007-09-17 2008-03-12 徐培华 High-dense emulsified asphalt and preparation method thereof
CN101642933A (en) * 2009-08-31 2010-02-10 中铁四局集团有限公司 Preparation method of emulsified asphalt mortar

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102093729A (en) * 2011-01-05 2011-06-15 东南大学 Nano particle modified asphalt and preparation method thereof
CN103059580A (en) * 2011-10-18 2013-04-24 中国石油化工股份有限公司 Anionic anti-freezing emulsified asphalt and preparation method thereof
CN103059580B (en) * 2011-10-18 2015-12-16 中国石油化工股份有限公司 Anionic anti-freezing emulsified asphalt and preparation method thereof
CN102504554A (en) * 2011-11-14 2012-06-20 镇江金阳道路材料科技发展有限公司 Anion slow-cracking asphalt emulsifying agent and preparation method thereof
CN103803893A (en) * 2012-11-07 2014-05-21 中国石油化工股份有限公司 Cement asphalt mortar and preparation method thereof
CN103803893B (en) * 2012-11-07 2016-02-03 中国石油化工股份有限公司 A kind of cement asphalt mortar and preparation method thereof
CN103834183A (en) * 2012-11-27 2014-06-04 中国石油天然气股份有限公司 A special emulsified asphalt for high-speed railway slab ballastless track
CN103602081A (en) * 2013-11-07 2014-02-26 河北伦特石油化工有限公司 Rubber powder asphalt and preparation method thereof
CN103773028A (en) * 2014-01-20 2014-05-07 南通东南公路工程有限公司 Fatty acid emulsified asphalt material
CN103980868A (en) * 2014-05-27 2014-08-13 玉门油田科达化学有限责任公司 Anti-collapse agent of zwitterionic emulsified asphalt for drilling fluid
CN103980868B (en) * 2014-05-27 2017-01-04 玉门油田科达化学有限责任公司 Drilling fluid amphion emulsion asphalt anti-collapse agent
CN104130757A (en) * 2014-07-15 2014-11-05 中国石油集团长城钻探工程有限公司钻井液公司 Plugging type anti-collapse agent and preparation method thereof
CN104448848A (en) * 2014-11-21 2015-03-25 江苏省交通科学研究院股份有限公司 Quick-set wheel-adhesion-free sticky layer emulsified asphalt and preparation method thereof
CN109694482A (en) * 2017-10-23 2019-04-30 神华集团有限责任公司 Modified emulsifying asphalt and preparation method thereof and mist sealing material
CN109694482B (en) * 2017-10-23 2021-08-10 国家能源投资集团有限责任公司 Modified emulsified asphalt, preparation method thereof and fog sealing layer material
CN108840606A (en) * 2018-07-31 2018-11-20 南京浦江工程检测有限公司 A kind of cold mixing cold laid asphaltic mixture and preparation method and wearing course
CN109762467A (en) * 2018-12-25 2019-05-17 广西青龙化学建材有限公司 Modified viscoelastic marine glue of graphene and preparation method thereof
CN115651417A (en) * 2022-11-04 2023-01-31 喜跃发国际环保新材料股份有限公司 Emulsified asphalt enhanced by adopting cellulose nanocrystals as well as preparation method and application of emulsified asphalt
CN115651417B (en) * 2022-11-04 2023-10-20 喜跃发国际环保新材料股份有限公司 Emulsified asphalt reinforced by cellulose nanocrystalline as well as preparation method and application thereof
CN116354647A (en) * 2023-02-23 2023-06-30 江苏镇淮建设集团有限公司 Thus ultrathin wearing layer for pavement maintenance and construction method thereof

Similar Documents

Publication Publication Date Title
CN101817984A (en) Emulsified asphalt and preparation method thereof
CN102286205B (en) Anionic emulsified asphalt and preparation method thereof
CN101643584B (en) Modified emulsified asphalt with excellent temperature adaptability and preparation method thereof
CN109824318A (en) A kind of cold-mix cold-paved anionic emulsified asphalt and its preparation method and application
CN103113751B (en) A kind of adhesion coating cation-modified emulsified bitumen and preparation method thereof
CN103951343B (en) A kind of compound cold asphalt mixture for asphalt pavement pit repairing
CN101717585A (en) Emulsified SBS polymer modified asphalt and preparation method thereof
CN102675890B (en) Demulsifying slow breaking and quick setting modified emulsified asphalt by microwave heating and preparation method thereof
CN106147108A (en) One directly mixes formula SBS modifier and preparation method thereof
CN103979896B (en) A kind of high Rut resistance Emulsified Asphalt Mixture for asphalt pavement rut punishment and preparation method thereof
CN104250443B (en) High ferro modified emulsifying asphalt and preparation method thereof
CN101619149B (en) Method for preparing cation emulsified rubber asphalt
CN103059829A (en) Nanometer emulsion type water control fracturing fluid for tight gas reservation well and preparation method thereof
CN101475349A (en) Vertical connected plate type unballasted track cement emulsified bitumen mortar
CN103881401B (en) A kind of shoddy modified emulsifying asphalt and preparation method thereof
CN103980721B (en) The preparation method of epoxy composite emulsified bitumen
CN112694304B (en) Cold recycling and old asphalt pavement cold joint adhesive for pavement reconstruction and extension
CN102839587A (en) Marshall design method of Evotherm warm-mix asphalt mixture
CN106009739A (en) Modified emulsified asphalt for ultrathin wearing layers and preparation method thereof
CN101475747B (en) Emulsified asphalt for cement emulsified asphalt mortar of longitudinally connected slab ballastless track
CN105524478B (en) A kind of method of the wet-process modified emulsified asphalt of nanoclay/butadiene-styrene rubber
CN102757654A (en) Prime coat oil and method for preparing same
CN110408067A (en) A kind of foam bitumen and preparation method thereof
CN104804716A (en) Well-cementing and anti-channeling nonionic styrene-butadiene latex and preparation method thereof
CN1563196B (en) Dedicated asphalt emulsion and preparation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Open date: 20100901