CN101509358B - Pipe pressurizing device - Google Patents

Pipe pressurizing device Download PDF

Info

Publication number
CN101509358B
CN101509358B CN2009103012226A CN200910301222A CN101509358B CN 101509358 B CN101509358 B CN 101509358B CN 2009103012226 A CN2009103012226 A CN 2009103012226A CN 200910301222 A CN200910301222 A CN 200910301222A CN 101509358 B CN101509358 B CN 101509358B
Authority
CN
China
Prior art keywords
pipe
slips
hinged
bracket assembly
workover rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009103012226A
Other languages
Chinese (zh)
Other versions
CN101509358A (en
Inventor
冷曦
张丽萍
秦文革
李培江
徐志勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CNPC Xibu Drilling Engineering Co Ltd
Original Assignee
XINJIANG PETRO ADMINISTRATION BUREAU DOWNHOLE OPERATION CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by XINJIANG PETRO ADMINISTRATION BUREAU DOWNHOLE OPERATION CORP filed Critical XINJIANG PETRO ADMINISTRATION BUREAU DOWNHOLE OPERATION CORP
Priority to CN2009103012226A priority Critical patent/CN101509358B/en
Publication of CN101509358A publication Critical patent/CN101509358A/en
Application granted granted Critical
Publication of CN101509358B publication Critical patent/CN101509358B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention relates to a drilling construction pipe running auxiliary pressurizing device, which is a pipe pressurizing device and comprises a bracket assembly, a dragging device and a pipe clamping device; the two symmetrical support assemblies are respectively and fixedly arranged on the workover rig platform and the blowout preventer; two symmetrical dragging devices capable of synchronously acting are respectively and fixedly arranged on the corresponding bracket assemblies. The invention has reasonable and compact structure, convenient use, safety, labor saving and high efficiency; the conventional workover rig platform and a blowout preventer are used as a foundation, and a reverse-hanging hydraulic slip elevator is adopted to clamp a pipe tool and hydraulically drag, apply force and press down, so that the common pipe tool of an oil well is pressed down, the pipe tool can stay at any position when not pressed, and the hydraulic pipe tool can be used for operations such as shallow thick oil horizontal drilling and completion construction process, workover and top drilling tool safety control and the like, so that the working efficiency of the shallow thick oil short-radius horizontal well pipe tool downward entering is greatly improved, and the potential safety hazard of top drilling tool control is reduced.

Description

Tube fitting pressing device
One, technical field
The present invention relates to the wellbore construction pipe and be lowered to auxiliary water booster system, is a kind of tube fitting pressing device.
Two, background technology
In shallow layer thick oil Short Radius Horizontal Wells completion technique, successfully being lowered to technological pipe is the successful key of full well, and the shallow layer thick oil Short Radius Horizontal Wells is because vertical depth is short; Build angle rate is higher relatively; Self does not possess the ability that is lowered to pressurization to pipe the straight well rig, and because the complexity that reality is bored, frictional resistance calculated value certainty and the certain deviation of physical presence that large scale pipe safety is lowered to smoothly; Therefore pipe is difficult in the lower going-into-well, goes up the control of crown drill tool simultaneously and has potential safety hazard.
Three, summary of the invention
The invention provides a kind of tube fitting pressing device, it can effectively solve the problem that pipe is difficult to be lowered in the shallow layer thick oil Short Radius Horizontal Wells.
The present invention has also further solved the problem that there is potential safety hazard in last crown drill tool control.
Technical scheme of the present invention realizes through following measure: a kind of tube fitting pressing device comprises bracket assembly, actuator and pipe clamping device; Two bracket assemblys of symmetry are fixedly mounted on respectively on workover rig platform and the preventer; Two actuators of symmetry and ability synchronization action are fixedly mounted on respectively on the corresponding bracket assembly; Two actuators are connected with two pipe clamping devices through wire rope respectively, and the pipe clamping device is sleeved on the pipe above the well head and can drags pipe and moves down.
Be to the further optimization of foregoing invention technical scheme below or/and improve:
Above-mentioned each actuator can comprise telescopic hydraulic cylinder and wire rope bend wheel; The telescopic hydraulic cylinder of horizontal positioned is installed in the bracket assembly, and the pistons end of telescopic hydraulic cylinder or cylinder ends are hinged on the bracket assembly, and the cylinder ends of telescopic hydraulic cylinder or pistons end have the ear bearing pin that connects wire rope; Two guide rails are installed on the bracket assembly, and telescopic hydraulic cylinder is sitting on the guide rail and can on guide rail, slides; The changed course wheel shaft is installed on the bracket assembly between telescopic hydraulic cylinder and the pipe, on the changed course wheel shaft wire rope bend wheel that can rotate is installed; One end of wire rope is fixedly mounted on the ear bearing pin, and the race that the other end of wire rope is walked around the wire rope bend wheel is connected on the pipe clamping device.
Above-mentioned pipe clamping device can comprise the anti-slips that hangs that surges; The anti-slips that hangs that surges hangs on the top of workover rig platform through bascule, and the anti-slips that hangs that surges is sleeved on pipe top and can clamps and unclamp pipe, surges instead to hang that slips is linked up with through the bottom and the upper end of wire rope links together.
Above-mentioned bascule can comprise balanced lever, balance weight, strap, fixed pulley, balancing weight and balance bracket; Balance bracket is fixedly connected on the workover rig platform; High fixed pulleys such as two are installed on the balance bracket through rotating shaft; One end of strap is walked around fixed pulley and is linked together with balancing weight, and the middle part of balanced lever and the other end of strap link together; The anti-slips that hangs that surges is linked up with an end that is suspended on balanced lever through top, and the other end and the balance weight of balanced lever link together.
Can there be the hydraulic pressure pipe slips elevator the above-mentioned anti-slips below of hanging of surging, and the hydraulic pressure pipe slips elevator is sitting on the well head and is sleeved on the pipe, and the hydraulic pressure pipe slips elevator can clamp and unclamp pipe.
Between above-mentioned wire rope bend wheel and the pipe clamping device pressure adjusting roller device can be arranged, the pressure adjusting roller device comprises support, goes up lower plate, pulley and adjustment bolt; Support is fixedly mounted on the downside of workover rig platform crossbeam through bolt and last lower plate; Horizontal concrete chute is arranged on the support; Pulley spindle is installed in the horizontal concrete chute through slide block and can moves horizontally, and the adjustment bolt that can promote slide block is through being threaded on the support; Wire rope is pressed on the wheel trench bottom of pulley.
Above-mentioned bracket assembly can comprise two side plates of symmetry; The bottom of two side plates is connected on the preventer upper flange through bolt, and the top of two side plates links together through bolt.
Above-mentioned connecting rod can comprise front tension bar, middle pull bar, back stay, front strut and rear pole; The upper end of front tension bar is hinged on the downside of workover rig platform crossbeam, and the lower end of front tension bar is hinged on the anterior upside of bracket assembly; The upper end of middle pull bar is hinged on the downside of workover rig platform crossbeam, and the lower end of middle pull bar is hinged on the upside at bracket assembly middle part; The upper end of back stay is hinged on the downside of workover rig platform, and the lower end of back stay is hinged on the upside at bracket assembly rear portion; The upper end of front strut is hinged on the anterior downside of bracket assembly, and the lower end of front strut is hinged on the lower end of workover rig platform column; The upper end of rear pole is hinged on the downside at bracket assembly rear portion, and the lower end of rear pole is hinged on the lower end of workover rig platform column; Be connected with the female bearing with two otic placodes through bolt on workover rig platform crossbeam and the workover rig platform column, there is the public bearing with an otic placode at the two ends of each connecting rod, and public bearing and female bearing are hinged.
Can there be the adjusting screw(rod) that can regulate connecting rod length at the middle part of above-mentioned each connecting rod, and the two ends of adjusting screw(rod) have left hand thread and right-handed thread respectively, and the connecting rod at adjusting screw(rod) two ends links together through respective threads and adjusting screw(rod).
The gas electromagnetic shaker of can having time is linked up with in the above-mentioned anti-bottom of hanging slips of surging.
Reasonable and compact in structure of the present invention, easy to use, safe, laborsaving, efficient; It utilizes former workover rig platform and preventer to do the basis; Adopt the anti-hydraulic pressure pipe slips elevator that hangs to clamp pipe hydraulic pressure and drag reinforcing and press down; Realization is lowered to pressurization to oil well pipe commonly used, and can realize pipe stop at an arbitrary position when not pressurizeing, and can be used in shallow layer thick oil horizontal drilling completion work progress, the well workover operations such as crown drill tool security control; Therefore greatly improve the operating efficiency that the shallow layer thick oil Short Radius Horizontal Wells is lowered to pipe, also reduced the potential safety hazard of last crown drill tool control.
Four, description of drawings
Accompanying drawing 1 is the main TV structure sketch map of most preferred embodiment of the present invention.Accompanying drawing 2 is the local structure for amplifying sketch map at A place in the accompanying drawing 1.
Coding in the accompanying drawing is respectively: 1 is bracket assembly, and 2 is the workover rig platform, and 3 is preventer, and 4 is wire rope, and 5 is pipe, and 6 is female bearing; 7 is the wire rope bend wheel, and 8 is telescopic hydraulic cylinder, and 9 is public bearing, and 10 is adjusting screw(rod), and 11 is the ear bearing pin, and 12 is guide rail; 13 are the changed course wheel shaft, and 14 for surging the anti-slips that hangs, and 15 are the bottom hook, and 16 is balanced lever, and 17 is balance weight, and 18 is strap; 19 is fixed pulley, and 20 is balancing weight, and 21 is balance bracket, and 22 are the top hook, and 23 is the hydraulic pressure pipe slips elevator, and 24 is support; 25 is last lower plate, and 26 is pulley, and 27 are the adjustment bolt, and 28 is workover rig platform crossbeam, and 29 is horizontal concrete chute, and 30 is pulley spindle; 31 is slide block, and 32 is the conical surface of derrick rotating disk, and 33 is side plate, and 34 is the preventer upper flange, and 35 is front tension bar; 36 is middle pull bar, and 37 is back stay, and 38 is front strut, and 39 is rear pole, and 40 is workover rig platform column.
Five, the specific embodiment
The present invention does not receive the restriction of following embodiment, can confirm concrete embodiment according to technical scheme of the present invention and actual conditions.
Below in conjunction with most preferred embodiment and accompanying drawing the present invention is further described:
Like accompanying drawing 1, shown in 2, this tube fitting pressing device comprises bracket assembly 1, actuator and pipe clamping device; Two bracket assemblys 1 of symmetry are fixedly mounted on respectively on workover rig platform 2 and the preventer 3; Two actuators of symmetry and ability synchronization action are fixedly mounted on respectively on the corresponding bracket assembly 1; Two actuators are connected with two pipe clamping devices through wire rope 4 respectively, and the pipe clamping device is sleeved on the pipe 5 above the well head and can drags pipe 5 and moves down.Actuator is when the wire rope 4 drag down pipe clamping devices, and the pipe clamping device is held pipe 5 tightly, and pipe 5 is applied lower pulling force and moves down together with pipe 5.
Can according to actual needs above-mentioned tube fitting pressing device be done further to optimize or/and improve:
Like accompanying drawing 1, shown in 2, each actuator comprises telescopic hydraulic cylinder 8 and wire rope bend wheel 7; The telescopic hydraulic cylinder 8 of horizontal positioned is installed in the bracket assembly 1, and the pistons end of telescopic hydraulic cylinder 8 or cylinder ends are hinged on the bracket assembly 1, and the cylinder ends of telescopic hydraulic cylinder 8 or pistons end have the ear bearing pin 11 that connects wire rope 4; Two guide rails 12 are installed on the bracket assembly 1, and telescopic hydraulic cylinder 8 is sitting on the guide rail 12 and can on guide rail 12, slides; Changed course wheel shaft 13 is installed on the bracket assembly 1 between telescopic hydraulic cylinder 8 and the pipe 5, on the changed course wheel shaft 13 the wire rope bend wheel 7 that can rotate is installed; One end of wire rope 4 is fixedly mounted on the ear bearing pin 11, and the race that the other end of wire rope 4 is walked around wire rope bend wheel 7 is connected on the pipe clamping device.Bracket assembly 1 is the housing that bears telescopic hydraulic cylinder 8, also is the passage that telescopic hydraulic cylinder 8 stretches.Wire rope bend wheel 7 can be changed into the lower pulling force to the vertical direction of pipe 5 with the horizontal pull of telescopic hydraulic cylinder 8.Telescopic hydraulic cylinder 8 preferably adopts anti-slag hydraulic means, and this anti-slag hydraulic means has been applied for patent, its number of patent application: 2007202011275.
Like accompanying drawing 1, shown in 2, the pipe clamping device comprises the anti-slips 14 that hangs that surges; The anti-slips 14 that hangs that surges hangs on the top of workover rig platform 2 through bascule, and the anti-slips 14 that hangs that surges is sleeved on pipe 5 tops and can clamps and unclamp pipe 5, surge counter hang slips 14 through the bottom link up with 15 and the upper end of wire rope 4 link together.There is hydraulic jack anti-slips 14 inside of hanging of surging, and hydraulic jack can drive the anti-dead bolt that hangs on the slips 14, and dead bolt can clamp and unclamp and be sleeved on the anti-pipe 5 that hangs in the slips 14 that surges.This anti-slips that hangs that surges has been applied for patent, its number of patent application: 2007202005081.
Like accompanying drawing 1, shown in 2, bascule comprises balanced lever 16, balance weight 17, strap 18, fixed pulley 19, balancing weight 20 and balance bracket 21; Balance bracket 21 is fixedly connected on the workover rig platform 2; High fixed pulleys 19 such as two are installed on the balance bracket 21 through rotating shaft; One end of strap 18 is walked around fixed pulley 19 and is linked together with balancing weight 20, and the other end of the middle part of balanced lever 16 and strap 18 links together; The anti-slips 14 that hangs that surges is suspended on an end of balanced lever 16 through top hook 22, and the other end of balanced lever 16 and balance weight 17 link together.Can accomplish counter the fluctuating of slips 14 of hanging of surging by means of bascule by people's strength, reaching suitable height and position, bascule can handled easily, but only uses just complete operation of a small amount of manpower.
Like accompanying drawing 1, shown in 2, there is hydraulic pressure pipe slips elevator 23 anti-slips 14 belows of hanging of surging, and hydraulic pressure pipe slips elevator 23 is sitting on the well head and is sleeved on the pipe 5, and hydraulic pressure pipe slips elevator 23 can clamp and unclamp pipe 5.Float in top surge counter hang hydraulic pressure pipe slips elevator 23 that slips 14 and bottom be sitting in well head can alternation, box cupling is passed through smoothly; Instead owing to surge hang slips 14 and hydraulic pressure pipe slips elevator 23 the two has a maintenance to hold the state of pipe 5 tightly all the time, can also realize when not pressurizeing that pipe 5 stops at an arbitrary position.
Like accompanying drawing 1, shown in 2, between wire rope bend wheel 7 and the pipe clamping device pressure adjusting roller device is arranged, the pressure adjusting roller device comprises support 24, last lower plate 25, pulley 26 and adjustment bolt 27; Support 24 is fixedly mounted on the downside of workover rig platform crossbeam 28 through bolt and last lower plate 25; Horizontal concrete chute 29 is arranged on the support 24; Pulley spindle 30 is installed in the horizontal concrete chute 29 through slide block 31 and can moves horizontally, and the adjustment bolt 27 that can promote slide block 31 is through being threaded on the support 24; Wire rope 4 is pressed on the wheel trench bottom of pulley 26.The pressure adjusting roller device can be adjusted the conical surface 32 of wire rope 4, derrick rotating disk, the distance between pipe 5 threes; Wire rope 4 is pushed away the conical surface 32 and pipe 5 of derrick rotating disk; Avoid wire rope 4 to its wearing and tearing, can also adjust the compaction degree of 26 pairs of wire rope 4 of pulley through adjustment bolt 27.
Like accompanying drawing 1, shown in 2, bracket assembly 1 comprises two side plates 33 of symmetry; The bottom of two side plates 33 is connected on the preventer upper flange 34 through bolt, and the top of two side plates 33 links together through bolt.Bracket assembly 1 is connected the stability and the rigidity that can increase support with preventer upper flange 34, to overcome the reaction force that pipe presses down.
Like accompanying drawing 1, shown in 2, connecting rod comprises front tension bar 35, middle pull bar 36, back stay 37, front strut 38 and rear pole 39; The upper end of front tension bar 35 is hinged on the downside of workover rig platform crossbeam 28, and the lower end of front tension bar 35 is hinged on the upside of bracket assembly 1 front portion; The upper end of middle pull bar 36 is hinged on the downside of workover rig platform crossbeam 28, and the lower end of middle pull bar 36 is hinged on the upside at bracket assembly 1 middle part; The upper end of back stay 37 is hinged on the downside of workover rig platform 2, and the lower end of back stay 37 is hinged on the upside at bracket assembly 1 rear portion; The upper end of front strut 38 is hinged on the downside of bracket assembly 1 front portion, and the lower end of front strut 38 is hinged on the lower end of workover rig platform column 40; The upper end of rear pole 39 is hinged on the downside at bracket assembly 1 rear portion, and the lower end of rear pole 39 is hinged on the lower end of workover rig platform column 40; Be connected with the female bearing 6 with two otic placodes through bolt on workover rig platform crossbeam 28 and the workover rig platform column 40, there is the public bearing 9 with an otic placode at the two ends of each connecting rod, and public bearing 9 and female bearing 6 are hinged.
Like accompanying drawing 1, shown in 2; There is the adjusting screw(rod) 10 that can regulate connecting rod length at the middle part of each connecting rod; The two ends of adjusting screw(rod) 10 have left hand thread and right-handed thread respectively, and the connecting rod at adjusting screw(rod) 10 two ends links together through respective threads and adjusting screw(rod) 10.The length of connecting rod can be adjusted through adjusting screw(rod) 10, so that satisfy the demand of adjustment installation site.
Like accompanying drawing 1, shown in 2, free gas electromagnetic shaker on 15 is linked up with in the anti-bottom of hanging slips 14 of surging.The air electromagnetic shaker can shake supercharging, increases the speed and the power that press down pipe 5.
Above technical characterictic has constituted most preferred embodiment of the present invention, and it has stronger compliance and best implementation result, can increase and decrease non-essential technical characterictic according to actual needs, satisfies the demand of different situations.
The course of work of most preferred embodiment of the present invention is: at first drive telescopic hydraulic cylinder 8 stretch out piston or cylinder body to the place ahead extreme position, open the anti-dead bolt that hangs slips 14 that surges simultaneously; Utilize the bascule adjustment anti-slips 14 that hangs that surges to rise or drop to suitable height, pipe 5 is inserted in counter the hanging in slips 14 and the hydraulic pressure pipe slips elevator 23 of surging, tighten wire rope 4 in advance.Then drive the anti-dead bolt closure of hanging slips 14 of surging; Make it hold pipe 5 tightly and keep this state; Make the hydraulic pressure pipe slips elevator 23 that is sitting in well head unclamp pipe 5 simultaneously; The piston of telescopic hydraulic cylinder 8 or cylinder body begin to reclaim, and ear bearing pin 11 converts the pulling force of horizontal direction the lower pulling force of vertical direction into through wire rope 4, wire rope bend wheel 7, pulley 26, are passed to the anti-slips 14 that hangs that surges and drive pipes 5 and press down together; When the piston of telescopic hydraulic cylinder 8 or cylinder body were recovered to the rear extreme position, the anti-slips 14 that hangs that surges unclamped pipe 5 and under the effect of balancing weight 20, rises and resets, and hydraulic pressure pipe slips elevator 23 is held pipe 5 tightly and kept this state simultaneously; The piston or the cylinder body of telescopic hydraulic cylinder 8 stretch out once more, and hydraulic pressure pipe slips elevator 23 is kept pipe 5 states of holding tightly; Arrive the place ahead extreme position when the piston of telescopic hydraulic cylinder 8 or cylinder body stretch out once more, the anti-slips 14 that hangs that surges is held pipe 5 tightly and is kept this state, and hydraulic pressure pipe slips elevator 23 unclamps pipe 5 simultaneously; Then to reclaim once more be drop-down pipe 5 for the piston of telescopic hydraulic cylinder 8 or cylinder body.Repeat above-mentioned steps at last repeatedly, until pipe 5 G.I.Hs with Len req.On dismounting and adjunction during pipe 5, make the hydraulic pressure pipe slips elevator 23 that is sitting in well head hold pipe 5 tightly and keep this state, pipe 5 is fallen in the well.

Claims (7)

1. a tube fitting pressing device is characterized in that comprising bracket assembly, actuator and pipe clamping device; Two bracket assemblys of symmetry are fixedly mounted on respectively on workover rig platform and the preventer; Two actuators of symmetry and ability synchronization action are fixedly mounted on respectively on the corresponding bracket assembly; Two actuators are connected with two pipe clamping devices through wire rope respectively, and the pipe clamping device is sleeved on the pipe above the well head and can drags pipe and moves down; Wherein, each actuator comprises telescopic hydraulic cylinder and wire rope bend wheel; The telescopic hydraulic cylinder of horizontal positioned is installed in the bracket assembly, and the pistons end of telescopic hydraulic cylinder or cylinder ends are hinged on the bracket assembly, and the cylinder ends of telescopic hydraulic cylinder or pistons end have the ear bearing pin that connects wire rope; Two guide rails are installed on the bracket assembly, and telescopic hydraulic cylinder is sitting on the guide rail and can on guide rail, slides; The changed course wheel shaft is installed on the bracket assembly between telescopic hydraulic cylinder and the pipe, on the changed course wheel shaft wire rope bend wheel that can rotate is installed; One end of wire rope is fixedly mounted on the ear bearing pin, and the race that the other end of wire rope is walked around the wire rope bend wheel is connected on the pipe clamping device; The pipe clamping device comprises the anti-slips that hangs that surges; The anti-slips that hangs that surges hangs on the top of workover rig platform through bascule, and the anti-slips that hangs that surges is sleeved on pipe top and can clamps and unclamp pipe, surges instead to hang that slips is linked up with through the bottom and the upper end of wire rope links together; Bascule comprises balanced lever, balance weight, strap, fixed pulley, balancing weight and balance bracket; Balance bracket is fixedly connected on the workover rig platform; High fixed pulleys such as two are installed on the balance bracket through rotating shaft; One end of strap is walked around fixed pulley and is linked together with balancing weight, and the middle part of balanced lever and the other end of strap link together; The anti-slips that hangs that surges is linked up with an end that is suspended on balanced lever through top, and the other end and the balance weight of balanced lever link together.
2. tube fitting pressing device according to claim 1, the anti-slips below of hanging that it is characterized in that surging has hydraulic pressure pipe slips elevator, hydraulic pressure pipe slips elevator to be sitting on the well head and is sleeved on the pipe, and the hydraulic pressure pipe slips elevator can clamp and unclamp pipe.
3. tube fitting pressing device according to claim 2 is characterized in that between wire rope bend wheel and the pipe clamping device pressure adjusting roller device being arranged, and the pressure adjusting roller device comprises support, goes up lower plate, pulley and adjustment bolt; Support is fixedly mounted on the downside of workover rig platform crossbeam through bolt and last lower plate; Horizontal concrete chute is arranged on the support; Pulley spindle is installed in the horizontal concrete chute through slide block and can moves horizontally, and the adjustment bolt that can promote slide block is through being threaded on the support; Wire rope is pressed on the wheel trench bottom of pulley.
4. tube fitting pressing device according to claim 3 is characterized in that bracket assembly comprises two side plates of symmetry; The bottom of two side plates is connected on the preventer upper flange through bolt, and the top of two side plates links together through bolt.
5. tube fitting pressing device according to claim 4 is characterized in that connecting rod comprises front tension bar, middle pull bar, back stay, front strut and rear pole; The upper end of front tension bar is hinged on the downside of workover rig platform crossbeam, and the lower end of front tension bar is hinged on the anterior upside of bracket assembly; The upper end of middle pull bar is hinged on the downside of workover rig platform crossbeam, and the lower end of middle pull bar is hinged on the upside at bracket assembly middle part; The upper end of back stay is hinged on the downside of workover rig platform, and the lower end of back stay is hinged on the upside at bracket assembly rear portion; The upper end of front strut is hinged on the anterior downside of bracket assembly, and the lower end of front strut is hinged on the lower end of workover rig platform column; The upper end of rear pole is hinged on the downside at bracket assembly rear portion, and the lower end of rear pole is hinged on the lower end of workover rig platform column; Be connected with the female bearing with two otic placodes through bolt on workover rig platform crossbeam and the workover rig platform column, there is the public bearing with an otic placode at the two ends of each connecting rod, and public bearing and female bearing are hinged.
6. tube fitting pressing device according to claim 5; There is the adjusting screw(rod) that can regulate connecting rod length at the middle part that it is characterized in that each connecting rod; The two ends of adjusting screw(rod) have left hand thread and right-handed thread respectively, and the connecting rod at adjusting screw(rod) two ends links together through respective threads and adjusting screw(rod).
7. tube fitting pressing device according to claim 6, the anti-bottom hook that hangs slips that it is characterized in that surging is gone up free gas electromagnetic shaker.
CN2009103012226A 2009-03-30 2009-03-30 Pipe pressurizing device Expired - Fee Related CN101509358B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009103012226A CN101509358B (en) 2009-03-30 2009-03-30 Pipe pressurizing device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009103012226A CN101509358B (en) 2009-03-30 2009-03-30 Pipe pressurizing device

Publications (2)

Publication Number Publication Date
CN101509358A CN101509358A (en) 2009-08-19
CN101509358B true CN101509358B (en) 2012-05-23

Family

ID=41001877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009103012226A Expired - Fee Related CN101509358B (en) 2009-03-30 2009-03-30 Pipe pressurizing device

Country Status (1)

Country Link
CN (1) CN101509358B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102061899B (en) * 2009-11-13 2013-02-13 江苏省金峰石油机械制造有限公司 Hydraulic pressure balance work over rig
CN104229634B (en) * 2014-09-22 2016-04-27 上海外高桥造船有限公司 For load test apparatus and the method for the auxiliary tension system of jack-up platform sleeve pipe
CN114877669B (en) * 2022-05-09 2023-07-25 常州市佳发制粒干燥设备有限公司 Material conveying device of boiling granulating dryer

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3865256A (en) * 1973-11-08 1975-02-11 Sr Richard B Freeman Casing and drill pipe handling device
US5839514A (en) * 1997-05-23 1998-11-24 Fleet Cementers, Inc. Method and apparatus for injection of tubing into wells
CN2437854Y (en) * 2000-06-13 2001-07-04 临邑县机械制造总厂 Fluid producing downhole sand removing forward hydrocyclone for oil well
CA2410574A1 (en) * 2000-06-02 2001-12-13 Oil & Gas Rental Services, Inc. Pipe handling apparatus and method of landing items at a well location
RU2231618C2 (en) * 2001-07-24 2004-06-27 Открытое акционерное общество "Волгабурмаш" Wedge device for holding boring pipes in rotor of boring plant
EP1210498B1 (en) * 1999-08-16 2007-11-28 Smart Drilling and completion, Inc. Smart shuttles to complete oil and gas wells
CN201083083Y (en) * 2007-12-11 2008-07-09 王德庆 Hydraulic pressurization well borer
EP1990502A2 (en) * 2007-05-09 2008-11-12 Dietswell Engineering SA Device for driving the rotation of a driven tubular element, capable of receiving and carrying a fluid under pressure
CN201381811Y (en) * 2009-03-30 2010-01-13 新疆石油管理局井下作业公司 Tube pressurizing device

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3865256A (en) * 1973-11-08 1975-02-11 Sr Richard B Freeman Casing and drill pipe handling device
US5839514A (en) * 1997-05-23 1998-11-24 Fleet Cementers, Inc. Method and apparatus for injection of tubing into wells
EP1210498B1 (en) * 1999-08-16 2007-11-28 Smart Drilling and completion, Inc. Smart shuttles to complete oil and gas wells
CA2410574A1 (en) * 2000-06-02 2001-12-13 Oil & Gas Rental Services, Inc. Pipe handling apparatus and method of landing items at a well location
CN2437854Y (en) * 2000-06-13 2001-07-04 临邑县机械制造总厂 Fluid producing downhole sand removing forward hydrocyclone for oil well
RU2231618C2 (en) * 2001-07-24 2004-06-27 Открытое акционерное общество "Волгабурмаш" Wedge device for holding boring pipes in rotor of boring plant
EP1990502A2 (en) * 2007-05-09 2008-11-12 Dietswell Engineering SA Device for driving the rotation of a driven tubular element, capable of receiving and carrying a fluid under pressure
CN201083083Y (en) * 2007-12-11 2008-07-09 王德庆 Hydraulic pressurization well borer
CN201381811Y (en) * 2009-03-30 2010-01-13 新疆石油管理局井下作业公司 Tube pressurizing device

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
关志刚等.《超浅层稠油水平井套管外部加压装置研制》.《石油天然气学报(江汉石油学院学报)》.2006,第28卷(第4期),第414-415页. *
王新东等.《HW6001超浅水平井技术套管固井技术》.《钻采工艺》.2006,第29卷(第5期),第15-17,34页. *

Also Published As

Publication number Publication date
CN101509358A (en) 2009-08-19

Similar Documents

Publication Publication Date Title
CN104477734B (en) Tensioning device and tensioning method for steel wire rope of ultra-deep vertical shaft cage guide
CN201087717Y (en) Integral high-pressure oil water well operation device under pressure
CN107218000B (en) Multi-cylinder lifting and rotation integrated form ocean hydraulic workover unit
CN110259404B (en) Shaft under-pressure operation device
CN204342334U (en) That a kind of oil-well rig is changed the large rope of drilling well leads large rope device
CN101509358B (en) Pipe pressurizing device
CN203742443U (en) Pile casing pressing and pulling drill rig
CN204139219U (en) The hydraulic pressure guide rod grab bucket can impact, can pressurizeed
CN201381811Y (en) Tube pressurizing device
CN103291210B (en) Gate-type double-tower gear-driven drilling machine
CN114320191A (en) A device for making up and shattering wellhead pipe string for snubbing operation
CN102061899A (en) Hydraulic pressure balance work over rig
CN202300240U (en) Single-guide rail dual-hydraulic cylinder high-accuracy bit feeding system
CN204552639U (en) A kind of Novel wellhead automation equipment
CN202832296U (en) Drill rod lifting device on drilling equipment
CN105781445B (en) A kind of continuous motion oil-well rig and its trip-out, lower drill method
CN205277295U (en) Operation equipment is pressed in stand alone type area
CN201902199U (en) Power combined type oil pumping machine with ultra long stroke for a plurality of wells
CN206957620U (en) An anti-top pressure device for casing milling pipe string
CN102602801A (en) Vertical lifting clamp for heavy barrel
CN106639923A (en) Petroleum drilling machine achieving continuous motion of tripping in and tripping out and method for continuous motion of tripping in and tripping out
CN201982035U (en) Independent type high pressure oil-water-gas well snubbing service device
CN206386093U (en) Full-sleeve full-rotation drill hydraulic multi-head gripper
CN204238848U (en) A kind of oil cylinder water booster system of engineering pile machine
CN209308630U (en) A core top direct drive drilling device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CNPC XIBU DRILLING ENGINEERING COMPANY LIMITED

Free format text: FORMER OWNER: XINJIANG PETROLEUM ADMINISTRATION BUREAU DOWNHOLE OPERATION COMPANY

Effective date: 20121224

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 834000 KARAMAY, XINJIANG UYGUR AUTONOMOUS REGION TO: 830026 URUMQI, XINJIANG UYGUR AUTONOMOUS REGION

TR01 Transfer of patent right

Effective date of registration: 20121224

Address after: 830026, No. 68 South Central Road, Urumqi economic and Technological Development Zone, the Xinjiang Uygur Autonomous Region

Patentee after: CNPC Xibu Drilling Engineering Company Limited

Address before: 834000 Karamay Road, the Xinjiang Uygur Autonomous Region, No. 34

Patentee before: Xinjiang Petro Administration Bureau Downhole Operation Corp.

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120523

Termination date: 20150330

EXPY Termination of patent right or utility model