CN101200898A - Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden - Google Patents
Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden Download PDFInfo
- Publication number
- CN101200898A CN101200898A CNA2007101686009A CN200710168600A CN101200898A CN 101200898 A CN101200898 A CN 101200898A CN A2007101686009 A CNA2007101686009 A CN A2007101686009A CN 200710168600 A CN200710168600 A CN 200710168600A CN 101200898 A CN101200898 A CN 101200898A
- Authority
- CN
- China
- Prior art keywords
- jacket
- casing
- cofferdam
- construction
- group
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Revetment (AREA)
Abstract
本发明涉及一种钻孔桩基础的施工方法,具体地说是一种采用护筒群导管架和钢围堰的光板岩和浅覆盖层钻孔桩基础的施工方法。它是将围堰侧板、导管和护筒制造成高低腿结构,然后将高低腿结构整体制造成钢护筒群和导管架结构,将围堰侧板焊接成钢围堰并与护筒群导管架焊接成整体,用起重装置将护筒群导管架吊起精确定位下放至墩位处,护筒群导管架调平之后,用混凝土对围堰内进行混凝土封底,稳定护筒群导管架和封堵护筒底部的漏洞,在护筒群导管架上安装施工平台进行钻孔桩施工。本发明有效的抵抗水流、风浪和风荷载的作用,保证钢护筒和平台的稳定,避免钻孔施工漏浆、窜孔现象,确保光板岩、浅覆盖层墩位钻孔桩施工的顺利进行。
The invention relates to a construction method of a bored pile foundation, in particular to a construction method of a bare slate and shallow covering layer bored pile foundation which adopts jacket group jackets and steel cofferdams. It manufactures the cofferdam side plate, conduit and casing into a high and low leg structure, and then manufactures the high and low leg structure as a whole into a steel casing group and a jacket structure, welds the cofferdam side plate into a steel cofferdam and combines it with the casing group The jacket is welded into a whole, and the casing group jacket is hoisted and accurately positioned by a lifting device and lowered to the pier position. After the casing group jacket is leveled, concrete is used to seal the inside of the cofferdam with concrete to stabilize the casing group conduits The holes at the bottom of the casing and the plugging are installed, and the construction platform is installed on the jacket of the casing group to carry out the construction of bored piles. The invention effectively resists the effects of water flow, wind wave and wind load, ensures the stability of the steel casing and the platform, avoids the phenomena of slurry leakage and hole channeling during drilling construction, and ensures the smooth construction of bored piles at pier positions in bare slate and shallow overburden layers.
Description
技术领域technical field
本发明涉及一种钻孔桩基础的施工方法,具体地说是一种采用护筒群导管架和钢围堰的光板岩和浅覆盖层钻孔桩基础的施工方法。The invention relates to a construction method of a bored pile foundation, in particular to a construction method of a bare slate and shallow covering layer bored pile foundation which adopts jacket group jackets and steel cofferdams.
背景技术Background technique
随着社会的不断发展,各种桥梁的建设越来越多,施工的难度越来越大,施工的质量要求越来越高。以往的桥梁一般建在土层比较厚的在江河、湖泊之上。在这种地质条件下,钻孔桩基础的施工一般采用传统的定位桩平台法或导管架下放后再插打定位桩及钢护筒的施工方法。但是有很多江河、湖泊和海洋地层地质状况为光板岩或浅覆盖层,如采用这些方法施工,由于水流、风浪和风荷载的作用及影响,钢护筒的稳定及护筒底口的密封性无法得到保证,从而影响施工进度和质量。因此在江河、湖泊和海洋上的光板岩或浅覆盖层上,墩位钻孔桩施工无法采用传统的定位桩平台法或导管架下放后再插打定位桩及钢护筒的施工方法。所以寻找一种新的施工方法以解决上述技术问题一直是本领域的技术人员亟待解决的问题。With the continuous development of society, more and more bridges are being built, the difficulty of construction is increasing, and the quality requirements of construction are getting higher and higher. In the past, bridges were generally built on rivers and lakes with relatively thick soil layers. Under such geological conditions, the construction of bored pile foundation generally adopts the traditional positioning pile platform method or the construction method of inserting positioning piles and steel casing after the jacket is lowered. However, there are many rivers, lakes and marine formations with bare slate or shallow overburden. If these methods are used for construction, the stability of the steel casing and the tightness of the bottom opening of the casing cannot be guaranteed due to the effects and influences of water flow, wind waves and wind loads. Guaranteed, thus affecting the construction progress and quality. Therefore, on the bare slate or shallow overburden on rivers, lakes and oceans, the traditional positioning pile platform method or the construction method of inserting positioning piles and steel casings after the jacket is lowered cannot be used for the construction of pier position bored piles. So finding a new construction method to solve the above technical problems has always been a problem to be solved urgently by those skilled in the art.
发明内容Contents of the invention
本发明的目的就是针对传统的定位桩平台法或导管架下放后再插打定位桩及钢护筒的施工方法的缺陷,提供一种采用护筒群导管架和钢围堰的光板岩和浅覆盖层钻孔桩基础的新施工方法,它能够有效的抵抗水流、风浪和风荷载的作用,使施工安全可靠的顺利进行。The purpose of the present invention is to provide a light slate and shallow concrete casing using casing group jackets and steel cofferdams for the defects of the traditional positioning pile platform method or the construction method of inserting positioning piles and steel casings after the jacket is lowered. The new construction method of the overburden pile foundation can effectively resist the effects of water flow, wind wave and wind load, so that the construction can be carried out safely and reliably.
本发明的技术方案是这样实现的:它是将围堰侧板、导管和护筒制造成高低腿结构,然后将高低腿结构整体制造成钢护筒群和导管架结构,将围堰侧板焊接成钢围堰并与护筒群导管架焊接成整体,用起重装置将护筒群导管架吊起精确定位下放至墩位处,护筒群导管架调平之后,用混凝土对围堰内进行混凝土封底,稳定护筒群导管架和封堵护筒底部的漏洞,在护筒群导管架上安装施工平台进行钻孔桩施工。The technical solution of the present invention is achieved in the following way: it is to manufacture the cofferdam side plate, conduit and casing into a high and low leg structure, and then the high and low leg structure is integrally manufactured into a steel casing group and a jacket structure, and the cofferdam side plate The steel cofferdam is welded into a steel cofferdam and integrally welded with the casing group jacket, and the casing group jacket is hoisted and accurately positioned by a lifting device and lowered to the pier. After the casing group jacket is leveled, the cofferdam is fixed with concrete Carry out concrete back sealing inside, stabilize the casing group jacket and plug the loopholes at the bottom of the casing, and install a construction platform on the casing group jacket for bored pile construction.
本发明优选的技术方案是采用多波束测深船精确测出墩位海床岩面高程,根据实测高程将围堰侧板、隔仓板、每根导管和护筒制造成高低腿形式,与岩面吻合;所述的钢围堰内设有隔仓板;所述的导管内插有插桩,施工平台安装在插桩上。The preferred technical solution of the present invention is to use a multi-beam sounding ship to accurately measure the elevation of the pier seabed rock surface, and to manufacture the cofferdam side plate, compartment plate, each conduit and casing into a form of high and low legs according to the measured elevation, and The rock surface is consistent; the steel cofferdam is provided with a partition board; the conduit is inserted with piles, and the construction platform is installed on the piles.
本发明根据江河、湖泊、海洋上的光板岩、浅覆盖层墩位钻孔桩施工特点,采取“护筒群导管架+钢围堰”的施工方法,可有效的抵抗水流、风浪和风荷载的作用,在风、浪、水流的作用下,保证钢护筒和平台的稳定,避免钻孔施工漏浆、窜孔现象,确保光板岩、浅覆盖层墩位钻孔桩施工的顺利进行。According to the construction characteristics of bare slate and shallow overburden pier bored piles on rivers, lakes and oceans, the present invention adopts the construction method of "casing group jacket + steel cofferdam", which can effectively resist water flow, wind waves and wind loads. Under the action of wind, waves and water flow, it can ensure the stability of the steel casing and the platform, avoid the phenomenon of slurry leakage and hole channeling during drilling construction, and ensure the smooth construction of bored piles in bare slate and shallow overburden piers.
附图说明Description of drawings
图1本发明光板岩、浅覆盖层墩施工总体平面布置图Fig. 1 is the overall layout plan of light slate and shallow overburden pier construction of the present invention
图2本发明光板岩、浅覆盖层墩施工另一总体平面布置图Fig. 2 is another overall layout diagram of light slate and shallow overburden pier construction of the present invention
图3本发明光板岩、浅覆盖层墩施工总体立面布置图Fig. 3 overall elevation layout of light slate and shallow overburden pier construction of the present invention
图4本发明光板岩、浅覆盖层墩施工总体侧面布置图Fig. 4 overall side layout of the pier construction of light slate and shallow overburden layer of the present invention
图中:1-高低腿护筒,2-套管,3-钢围堰侧板,4-连接套管,5-定位钢丝绳,6-施工平台,7-水下封底混凝土,8-碎石袋和混凝土袋,9-插桩。In the figure: 1-high and low leg casing, 2-casing, 3-steel cofferdam side plate, 4-connecting casing, 5-positioning steel wire rope, 6-construction platform, 7-underwater bottom sealing concrete, 8-gravel Bags and concrete bags, 9-stakes.
具体实施方式Detailed ways
以下结合附图对本发明作进一步描述:The present invention will be further described below in conjunction with accompanying drawing:
如图1、图3所示,本发明是将围堰侧板、导管和护筒制造成高低腿结构,然后将高低腿结构整体制造成钢护筒群和导管架结构,将围堰侧板焊接成钢围堰并与护筒群导管架焊接成整体,用起重装置将护筒群导管架吊起精确定位下放至墩位处,护筒群导管架调平之后,用混凝土对围堰内进行混凝土封底,稳定护筒群导管架和封堵护筒底部的漏洞,在护筒群导管架上安装施工平台进行钻孔桩施工。所述的钢围堰内可以设有隔仓板;所述的导管内插有插桩,施工平台安装在插桩上。As shown in Figures 1 and 3, the present invention manufactures the cofferdam side plates, conduits and casings into high and low leg structures, and then manufactures the high and low leg structures as a whole into steel casing groups and jacket structures, and the cofferdam side plates The steel cofferdam is welded into a steel cofferdam and integrally welded with the casing group jacket, and the casing group jacket is hoisted and accurately positioned by a lifting device and lowered to the pier. After the casing group jacket is leveled, the cofferdam is fixed with concrete Carry out concrete back sealing inside, stabilize the casing group jacket and plug the loopholes at the bottom of the casing, and install a construction platform on the casing group jacket for bored pile construction. The steel cofferdam may be provided with partition boards; the conduit is inserted with piles, and the construction platform is installed on the piles.
具体步骤如下:Specific steps are as follows:
1、地形测量1. Topographic survey
采用多波束测深船测量施工区域河(海)床面高程,测量成果转化为河(海)床面标高地形图。The elevation of the river (sea) bed in the construction area is measured by a multi-beam sounding ship, and the measurement results are converted into a topographic map of the elevation of the river (sea) bed.
2、护筒群导管架+钢围堰制造、下放、调平2. Fabrication, lowering and leveling of casing group jacket + steel cofferdam
按照测量的河(海)床面标高地形图确定每根护筒1、套管2和钢围堰侧板3的相对高差和位置,确保护筒群导管架下放后高出施工水位一定高度。通过临时抄垫将高低腿护筒1由连接套管4焊接成整体,形成护筒群,在护筒群周边布置了数根套管2,通过连接套管4与护筒1焊接形成一个大导管架,这样在下放时可在套管内插桩9用来调平护筒群导管架,同时也增大了导管架的抗倾覆力矩。在大导管架四周安装钢围堰桁架和钢围堰侧板3,安装护筒群导管架吊点,完成护筒群导管架的制造。Determine the relative height difference and position of each casing 1,
护筒群导管架制造后,采用大型浮吊将护筒群导管架吊至施工墩位处。采用测量定位系统对浮吊进行定位、抛锚。在适当的位置设置工作定位船舶,安装卷扬机,工程船舶的导向、定位钢丝绳5固定在导管架上口。导管架的下放时间应尽量避开涨落潮、涌潮及天文大潮等流速较快的时间段,选择在低平潮时下放导管架。为克服由于水流力作用下导管架的倾斜或失稳,四角处定位桩9与护筒群导管架临时固定,一起下放,在定位船舶卷扬机辅助定位的作用下进行下放,护筒群导管架下放到位后,解开四个定位角桩9,立即进行插打、调平、纠偏,使导管架的下放偏差和垂直度满足设计要求。After the casing group jacket is fabricated, the casing group jacket is hoisted to the construction pier by a large floating crane. Use the measurement and positioning system to locate and anchor the floating crane. Set up the working positioning ship at an appropriate position, install the winch, and the guiding and positioning
3、围堰内封底3. Back cover inside the cofferdam
护筒群导管架下放到位后,在风浪小的平潮天气里,用混凝土综合搅拌船或岸上砼工厂对护筒群导管架进行砼封底,灌注水下封底混凝土7,使护筒群与基岩粘结连成整体,增强护筒群导管架的整体稳定性,同时防止灌注成桩时发生砼渗漏。封底前,可利用浮吊在围堰外侧抛填碎石袋和混凝土袋8,潜水员在围堰内侧轻潜堵漏,堵漏完成后,再进行大封底。为提高封底成功率,除在护筒群导管架周边设置围堰侧板3外,并在围堰内设置隔仓板,将一个大围堰分成几个小围堰,封底顺序为由标高较低处逐步向标高较高处推进。After the casing group jacket is lowered into place, in flat tide weather with little wind and waves, use a concrete mixing ship or an onshore concrete factory to carry out concrete back sealing on the casing group jacket, and pour underwater bottom sealing concrete 7 to make the casing group and the foundation The rock is bonded into a whole to enhance the overall stability of the casing group jacket and prevent concrete leakage when pouring into piles. Before the back sealing, the floating crane can be used to throw and fill gravel bags and concrete bags 8 outside the cofferdam, and divers lightly dive inside the cofferdam to plug the leakage. In order to improve the success rate of back sealing, in addition to setting
4、安装钻孔桩平台钻孔4. Install bored pile platform for drilling
封底成功后,在护筒群导管架上搭设施工平台6,在平台6上安装钻机进行钻孔桩施工。After the back cover is successful, build a construction platform 6 on the casing group jacket, and install a drilling rig on the platform 6 to carry out bored pile construction.
Claims (4)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2007101686009A CN101200898A (en) | 2007-12-04 | 2007-12-04 | Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CNA2007101686009A CN101200898A (en) | 2007-12-04 | 2007-12-04 | Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN101200898A true CN101200898A (en) | 2008-06-18 |
Family
ID=39516237
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CNA2007101686009A Pending CN101200898A (en) | 2007-12-04 | 2007-12-04 | Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN101200898A (en) |
Cited By (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101748744B (en) * | 2008-12-19 | 2011-06-01 | 四川公路桥梁建设集团有限公司 | Asynchronous sinking construction method for large bridge foundation separation type steel cofferdam |
| CN102747954A (en) * | 2012-07-25 | 2012-10-24 | 中铁大桥局股份有限公司 | Hole-drilling guiding positioning system suitable for inclined rock surface and construction method |
| CN102953362A (en) * | 2012-12-13 | 2013-03-06 | 中铁上海工程局有限公司 | Bored pile platform built on non-covering steep bare rocks in deep rapids |
| CN103352472A (en) * | 2013-07-06 | 2013-10-16 | 中交路桥建设有限公司 | Construction method of deep water pile foundation without steel pile casings |
| CN104594352A (en) * | 2015-01-14 | 2015-05-06 | 中铁大桥局集团有限公司 | Stable structure and drilling platform construction method based on stable structure |
| CN107700504A (en) * | 2017-09-27 | 2018-02-16 | 中铁二十局集团第工程有限公司 | Based on the slope rock river bed steel cofferdam for vacantly hanging pin processing structure |
| CN111021328A (en) * | 2019-12-12 | 2020-04-17 | 天津大学 | Submerged large-diameter multi-chamber and pile foundation combined artificial island |
| CN111576247A (en) * | 2020-06-24 | 2020-08-25 | 中铁四局集团第三建设有限公司 | Double-wall steel cofferdam and short pile casing group integral positioning and mounting structure and construction method |
| CN112319716A (en) * | 2020-11-09 | 2021-02-05 | 河海大学 | Floating construction platform constructed in water curtain and installation and use method thereof |
| CN112982390A (en) * | 2019-12-17 | 2021-06-18 | 上海三航奔腾海洋工程有限公司 | Steel casing of rock-socketed cast-in-place pile capable of not sinking along with punching |
-
2007
- 2007-12-04 CN CNA2007101686009A patent/CN101200898A/en active Pending
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101748744B (en) * | 2008-12-19 | 2011-06-01 | 四川公路桥梁建设集团有限公司 | Asynchronous sinking construction method for large bridge foundation separation type steel cofferdam |
| CN102747954A (en) * | 2012-07-25 | 2012-10-24 | 中铁大桥局股份有限公司 | Hole-drilling guiding positioning system suitable for inclined rock surface and construction method |
| CN102953362A (en) * | 2012-12-13 | 2013-03-06 | 中铁上海工程局有限公司 | Bored pile platform built on non-covering steep bare rocks in deep rapids |
| CN103352472A (en) * | 2013-07-06 | 2013-10-16 | 中交路桥建设有限公司 | Construction method of deep water pile foundation without steel pile casings |
| CN104594352A (en) * | 2015-01-14 | 2015-05-06 | 中铁大桥局集团有限公司 | Stable structure and drilling platform construction method based on stable structure |
| CN107700504A (en) * | 2017-09-27 | 2018-02-16 | 中铁二十局集团第工程有限公司 | Based on the slope rock river bed steel cofferdam for vacantly hanging pin processing structure |
| CN111021328A (en) * | 2019-12-12 | 2020-04-17 | 天津大学 | Submerged large-diameter multi-chamber and pile foundation combined artificial island |
| CN112982390A (en) * | 2019-12-17 | 2021-06-18 | 上海三航奔腾海洋工程有限公司 | Steel casing of rock-socketed cast-in-place pile capable of not sinking along with punching |
| CN111576247A (en) * | 2020-06-24 | 2020-08-25 | 中铁四局集团第三建设有限公司 | Double-wall steel cofferdam and short pile casing group integral positioning and mounting structure and construction method |
| CN111576247B (en) * | 2020-06-24 | 2025-01-24 | 中铁四局集团第三建设有限公司 | An integral positioning and installation structure and construction method for a double-wall steel cofferdam and a short casing group |
| CN112319716A (en) * | 2020-11-09 | 2021-02-05 | 河海大学 | Floating construction platform constructed in water curtain and installation and use method thereof |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101200898A (en) | Construction Method of Bored Pile Foundation in Bare Slate and Shallow Overburden | |
| CN102312442A (en) | Construction method of trestle steel pipe pile foundation | |
| CN111945767A (en) | A construction technology of the outer jacket type jacket by the first pile method for offshore wind power booster station | |
| US3528254A (en) | Offshore platform structure and construction method | |
| CN101148890A (en) | Bridge caisson composite pile foundation and its reverse construction method | |
| CN102979069A (en) | Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream | |
| CN104912045A (en) | Hollow cylinder pier used for fixing overwater platform structure at water bottom and installation and construction method thereof | |
| CN103628507B (en) | Push pipe passes through the shallow earthing anti-floating construction method in seabed | |
| CN102953362A (en) | Bored pile platform built on non-covering steep bare rocks in deep rapids | |
| JP6105044B2 (en) | Partially floating offshore platform for offshore wind power, bridges and offshore structures, and construction method | |
| CN108532608A (en) | A method for precise positioning and implantation of double-walled steel cofferdams for rock-socketed foundations in deep water | |
| CN110607797A (en) | Underwater construction method for water taking head | |
| CN102561379A (en) | Novel bridge installation foundation and construction method thereof | |
| CN103911998B (en) | Leveling ship diagonal angle ballast lifting method | |
| CN102383436A (en) | Accurate positioning construction method of double-wall steel cofferdam | |
| CN204608815U (en) | Raft plate gravity offshore wind turbine foundation | |
| CN109356184A (en) | A kind of construction method of immersed pipe with anti-rainbow culvert across the river | |
| KR20140092217A (en) | Construction method of the pier with the working bardge | |
| US3961489A (en) | Method for placing a floating structure on the sea bed | |
| CN203049560U (en) | Bored pile platform arranged on steep bare rock of deepwater torrent unsheathed layer | |
| CN104762942B (en) | Fixed platform soft soil foundation seabed, aquatic building ocean fixed installation construction method | |
| CN107724416A (en) | One kind is used to build underwater foundation structure and its installation method | |
| CN106368217A (en) | Assembled barge water operation platform and construction method thereof | |
| CN202989949U (en) | Steel casing fixing structure on steep bare rock without covering layer in deep water and rapids | |
| CN206143774U (en) | Assembled barge water work platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C12 | Rejection of a patent application after its publication | ||
| RJ01 | Rejection of invention patent application after publication |
Open date: 20080618 |