[go: up one dir, main page]

CN109162456A - A kind of Split bolt sleeve structure, molding plate fixed structure and application method - Google Patents

A kind of Split bolt sleeve structure, molding plate fixed structure and application method Download PDF

Info

Publication number
CN109162456A
CN109162456A CN201810889322.4A CN201810889322A CN109162456A CN 109162456 A CN109162456 A CN 109162456A CN 201810889322 A CN201810889322 A CN 201810889322A CN 109162456 A CN109162456 A CN 109162456A
Authority
CN
China
Prior art keywords
split bolt
heating wire
screw rod
lapping layer
sleeve structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810889322.4A
Other languages
Chinese (zh)
Inventor
袁凌飞
缪建杨
叶文浩
朱陈磊
杨宏辉
殷超越
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai No 7 Construction Co Ltd
Original Assignee
Shanghai No 7 Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai No 7 Construction Co Ltd filed Critical Shanghai No 7 Construction Co Ltd
Priority to CN201810889322.4A priority Critical patent/CN109162456A/en
Publication of CN109162456A publication Critical patent/CN109162456A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0651One-piece elements
    • E04G17/0652One-piece elements fully recoverable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Aiming at the problem that recycling split bolt in the prior art needs to realize production and stores a large amount of different size casings, the present invention provides a kind of Split bolt sleeve structures, molding plate fixed structure and application method, the Split bolt sleeve structure, including split bolt, heating wire, heating device and lapping layer, heating wire winding is on the screw rod of split bolt, heating wire is connect with heating device, lapping layer is wrapped in the outside of split bolt, and heating wire is between lapping layer and the screw rod of split bolt, using after the split bolt fixed form and after building body pours, utilize the heating devices heat heating wire, melt so that lapping layer is heated, gap is generated so that being wound between the screw rod and building body of the split bolt of heating wire, realize the recycling of split bolt.The present invention can be to avoid the production and storage of a large amount of different size of casings, not only save the cost and space occupied, while casing rolling also being avoided to cause injury to personnel and casing impaired.

Description

A kind of Split bolt sleeve structure, molding plate fixed structure and application method
Technical field
The present invention relates to connection fixture field more particularly to a kind of Split bolt sleeve structure, molding plate fixed structure and Application method.
Background technique
Currently, the continuous renewal of construction techniques, new material largely makes with the rapid development of modern architecture industry With more and more buildings are rised sheer from level ground.But in construction nowadays with rapid changepl. never-ending changes and improvements, some problems are still unresolved, such as now After condensing completely in construction to concrete, split bolt can not be successfully recycling, even if can solve now with metal sleeve to drawing Bolt recycles problem, but metal sleeve cannot recycle, and cause waste.
And there are a large amount of problems using metal sleeve, on the one hand, uses split bolt type due to required in a project Number specification is more, it is therefore desirable to buy in a large amount of corresponding bolt sleeves, rear different size casing is used for multiple times and easily obscures, and cover Pipe is excessively huge, extremely occupies site operation place;On the other hand, since Split bolt sleeve shape is mostly hollow cylinder It easily rolls and falls, if construction personnel does not pay attention to stepping down on casing, first is that be easy to causeing casing to damage, second is that being easy to cause to construct Personnel slip to cause injury to personnel.
Therefore how to provide one kind does not need entity casing, so that it may realize the Split bolt sleeve knot of split bolt recycling Structure, molding plate fixed structure and application method are this field technical problems urgently to be resolved.
Summary of the invention
Just needing to make and store a large amount of different to solve casing must be used to be able to achieve split bolt recycling in existing The entity casing of size specification causes construction cost high, and required the problem of taking up a large area, the present invention provides a kind of split bolt Cannula structure, molding plate fixed structure and application method, structure is simple, easy to use, can under the premise of not needing entity casing To recycle split bolt from the building body poured, the production and storage of the casing of different size specification are avoided, material has been saved Expect cost, occupied area needed for reducing casing.
In order to solve the above technical problems, the invention provides the following technical scheme:
A kind of Split bolt sleeve structure, including the split bolt, heating wire, heating device for fixing two side templates with And lapping layer, on the screw rod of the split bolt, the heating wire and the heating device connect the heating wire winding It connects, the lapping layer is wrapped in the outside of split bolt, and heating wire is located at the screw rod of lapping layer and split bolt Between, lapping melting layer is enabled to after the heating devices heat heating wire.
Preferably, in above-mentioned Split bolt sleeve structure, the lapping layer is low melting point lapping layer.
Preferably, in above-mentioned Split bolt sleeve structure, the lapping layer is resin or paraffin.
Preferably, in above-mentioned Split bolt sleeve structure, the heating wire is heating alloy.
Preferably, in above-mentioned Split bolt sleeve structure, after the lapping layer is melted by lapping is heated It is formed on being wrapped on the outside of the screw rod for being wound with the split bolt of heating wire.
Preferably, in above-mentioned Split bolt sleeve structure, the heating wire is ferrum-chromium-aluminum or nichrome wire.
Preferably, in above-mentioned Split bolt sleeve structure, the heating device is 2~3 at a distance from split bolt Rice.
The invention also discloses a kind of molding plate fixed structure, for fixing the template of two sides, including as described above to drawing Bolt sleeve structure, the lumps of wood and formwork keel open up the spiral shell of the split bolt for being enclosed with lapping layer in the template The through-hole that bar passes through, the screw rod of the split bolt wear translateral template, and the template is orderly arranged outside each the lumps of wood And formwork keel, the nut of the split bolt are located at the outside of the formwork keel.
The invention also discloses a kind of application methods of Split bolt sleeve structure as described above, include the following steps:
Step 1, by heating wire winding on the screw rod of split bolt;
One layer of lapping layer is arranged in the outside of the screw rod for the split bolt for being wound with heating wire in step 2;
Step 3 binds the reinforcing bar of building body to be poured, solid using the split bolt with heating wire and lapping layer Solid plate, casting concrete;
Step 4 heats heating wire using heating device after the intensity of concrete is met the requirements, so that package Material layer is heated to melt;
Step 5 takes out the screw rod for being wound with the split bolt of heating wire from concrete;
Step 6, form removal.
Preferably, in the application method of above-mentioned Split bolt sleeve structure, in the step 2, heating device is utilized Heating wire is heated, so that lapping is wrapped in the outside for being wound with the screw rod of split bolt of heating wire, wraps up material The outside of screw rod after material is cooling in the split bolt for being wound with heating wire forms lapping layer.
Preferably, in the application method of above-mentioned Split bolt sleeve structure, the side of being successively arranged on the outside of the template Wood and formwork keel, the nut of the split bolt are located at the outside of formwork keel, are opened up in the template for being enclosed with Wrap up in the through-hole that the screw rod of the split bolt of material layer passes through.
By techniques disclosed above scheme it is found that compared with prior art, beneficial effects of the present invention are as follows:
Split bolt sleeve structure provided in this embodiment, using for fixing two side templates split bolt, heating wire, Heating device and lapping layer, the heating wire winding on the screw rod of the split bolt, the heating wire with it is described Heating device connection, the lapping layer is wrapped in the outside of split bolt, and heating wire is located at lapping layer and to drawing Between the screw rod of bolt, lapping melting layer is enabled to after the heating devices heat heating wire, using the split bolt After fixed form and after building body pours, the heating devices heat heating wire can use, so that lapping layer is heated Melt, generates gap so that being wound between the screw rod of the split bolt of heating wire and the concrete of building body, Jin Erke To realize the recycling of split bolt.Casing in the prior art is replaced using the heated lapping layer that can melt, can be kept away The production and storage for exempting from a large amount of casings of different specifications and sizes have not only been saved cost of manufacture and material cost, and have been saved Space occupied required for casing, while also avoiding casing from being easy rolling causes injury to personnel and casing impaired.
Formwork reinforcement structure provided in this embodiment, using Split bolt sleeve structure, the lumps of wood and mould as described above Board keel opens up the through-hole that the screw rod of the split bolt for being enclosed with lapping layer passes through, described pair of drawing spiral shell in the template The screw rod of bolt wears translateral template, and the template is orderly arranged outside each the lumps of wood and formwork keel, described pair of drawing spiral shell The nut of bolt is located at the outside of the formwork keel, after building body pours, using the heating devices heat heating wire, makes The heated thawing of lapping layer is obtained, generates seam so that being wound between the screw rod and building body of the split bolt of heating wire Gap, so as to realize the recycling of split bolt.Set in the prior art is replaced using the heated lapping layer that can melt Pipe can save a large amount of casings of different specifications and sizes, not only save material cost, and saved required for a large amount of casings Space occupied, while casing also being avoided to be easy to roll and cause injury to personnel and casing impaired.
The application method of Split bolt sleeve structure provided in this embodiment, that is, formwork reinforcement method, by split bolt Screw rod outside wind heating wire, the split bolt for being wound with heating wire screw rod outside be arranged a lapping layer, After using the split bolt fixed form and after casting concrete, the lapping layer can be carried out by heating device Heating is melted so that the lapping layer is heated, thus between the screw rod and concrete for the split bolt for being wound with heating wire Gap is generated, so that the screw rod for being wound with the split bolt of heating wire can be able to extract from the concrete of solidification, it is real The recycling for not needing to make and store split bolt in the case where casing of different specifications and sizes now, saved the construction time and Occupied area solves the casing for needing to make various specifications size in the prior art, and casing needs a large amount of stacking spaces, and Casing is equally easy to roll, the problem for causing injury to personnel and casing to be damaged.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the formwork reinforcement structure (containing Split bolt sleeve structure) of one embodiment of the invention (half for illustrating only structure);
Fig. 2 is the structure sectional view of split bolt, heating wire and lapping layer;
In figure: 1, split bolt;2, heating wire;3, lapping layer;4, the extension of heating wire;5, the lumps of wood;6, template Keel;7, template;8, concrete;9, heating device.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.According to following explanation and right Claim, advantages and features of the invention will become apparent from.This hair will be described in detail by cited embodiment combination attached drawing below Bright technology contents and feature.Need in addition it illustrate, attached drawing is all made of very simplified form and uses non-accurate ratio Example, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.For sake of convenience, "upper" described below, "lower" is consistent with the upper and lower direction of attached drawing, but this can't be the limitation of technical solution of the present invention.
Embodiment one
Fig. 1 to Fig. 2 is please referred to, present embodiment discloses a kind of molding plate fixed structures to wrap for fixing the template 7 of two sides A Split bolt sleeve structure, the lumps of wood 5 and formwork keel 6 are included, is opened up in the template 7 for being enclosed with lapping layer 3 The through-hole that the screw rod of split bolt 1 passes through, the screw rod of the split bolt 1 wear translateral template 7, the outside of the template 7 The lumps of wood 5 and formwork keel 6 are set gradually, the nut of the split bolt 1 is located at the outside of the formwork keel 6.
The Split bolt sleeve structure, including split bolt 1, heating wire 2, the heating dress for fixing two side templates 7 9 and lapping layer 3 are set, the heating wire 2 is wound on the screw rod of the split bolt 1, and the heating wire 2 adds with described Thermal 9 connects, and the lapping layer 3 is wrapped in the outside of split bolt 1, and heating wire 2 be located at lapping layer 3 with it is right Between the screw rod for drawing bolt 1, i.e., the described lapping layer packet 3 is wrapped on the outside of the screw rod for being wound with the split bolt 1 of heating wire 2, The heating device 9 enables to lapping layer 3 to melt after heating heating wire 2.
After building body pours, the heating wire 2 is heated using heating device 9, is melted so that lapping layer 3 is heated Change, generates gap so that being wound between the screw rod of split bolt 1 of heating wire 2 and the concrete of building body, Jin Erke To realize the recycling of split bolt 1.Casing in the prior art is replaced using the heated lapping layer 3 that can melt, is not required to A large amount of casings of different specifications and sizes are made and be stored in advance, have not only saved material cost, and saved shared by casing Space, while casing also being avoided to roll the problem for causing injury to personnel and casing to be damaged due to being easy in cylindrical body.
Preferably, in above-mentioned Split bolt sleeve structure, the lapping layer 3 is low melting point lapping layer.
Preferably, in above-mentioned Split bolt sleeve structure, after the lapping layer 3 is melted by lapping is heated It is formed on being wrapped on the outside of the screw rod for being wound with the split bolt 2 of heating wire 3.
Preferably, in above-mentioned Split bolt sleeve structure, the lapping layer 3 is resin or paraffin.Resin It is divided into natural resin and synthetic resin.Natural resin, which can be used, in the present invention also can be used synthetic resin.Natural resin is Refer to by the resulting amorphous organic substance of animals and plants secretion in nature, such as rosin, amber, shellac.Synthetic resin refers to Resin product obtained from being chemically reacted as simple organic through chemical synthesis or certain natural products, such as phenolic resin gather Vinyl chloride resin etc., wherein synthetic resin is the main component of plastics.
Paraffin is also known as crystalline wax, usually white, tasteless waxy solid, in 47 DEG C of -64 DEG C of fusings, is dissolved in gasoline, two One kind nonpolar solvent such as nitric sulfid, dimethylbenzene, ether, benzene, chloroform, carbon tetrachloride, naphtha, the poles such as not soluble in water and methanol Property solvent.Paraffin refined wax is good insulator, and resistivity is 1013-1017 ohm meter, than removing certain plastics (especially Teflon) outer most of materials will be high.Paraffin is also good heat accumulating, and specific heat capacity is 2.14-2.9JgK, Fusing heat is 200-220Jg.
Preferably, in above-mentioned Split bolt sleeve structure, the heating wire 2 is heating alloy.Heating alloy Intensity in the high temperature environment is high, and long term high temperature operation is unlikely to deform, not malleable structure, and nichrome electric heating tube is normal Warm plasticity is good, and deformed reparation is relatively simple.In addition, the radiance height of heating alloy, not carrying magnetic, corrosion resistance Good, long service life.
Preferably, in above-mentioned Split bolt sleeve structure, the heating wire 2 is ferrum-chromium-aluminum or nichrome wire.
In order to protect heating device 9, need for heating device 9 and split bolt 1 to be separated by a distance, it is preferred that upper In the Split bolt sleeve structure stated, the heating device 9 is 2~3 meters at a distance from split bolt 1, i.e., the described heating wire Extension 4 has 2~3 meters.
Embodiment two
Please continue to refer to Fig. 1 and Fig. 2, the Split bolt sleeve structure that present embodiment discloses a kind of as described in embodiment one Application method, include the following steps:
Heating wire 2 is wound on the screw rod of split bolt 1 by step 1.
One layer of lapping layer 3 is arranged in the outside of the screw rod for the split bolt 1 for being wound with heating wire 2 in step 2;
Preferably, in step 2, it can use heating device 9 and heating wire 2 heated, so that lapping wraps up In the outside of the screw rod for the split bolt for being wound with heating wire, i.e., so that lapping is wrapped in electric heating on the screw rod of split bolt The outside for the heating wire winding layer that silk is formed, in the outside of the screw rod for the split bolt for being wound with heating wire after lapping is cooling Form the lapping layer 3.The lapping can use resin or paraffin.In the split bolt for being wound with heating wire Screw rod on the outside of be laid in the resin or paraffin of powdery or particle stake, using heating device to electric heating wire heating after, The resin or paraffin of powdery or particle stake are heated to be melted, and is formed in the outside of the screw rod for the split bolt for being wound with heating wire The lapping layer of one layer of liquid condition, the liquid lapping layer is frozen into the lapping layer of solid-like after cooling. One layer of lapping layer is set in the outside of the screw rod for the split bolt for being wound with heating wire using the above method, is avoided existing The production and preservation of different size specification entity casing, have saved construction time and occupied area in technology.
Step 3 binds the reinforcing bar of building body to be poured, using the split bolt for having heating wire 2 and lapping layer 3 1 fixed form, casting concrete 8.
Preferably, in the application method of above-mentioned Split bolt sleeve structure, the outside side of being successively arranged of the template 7 Wood 5 and formwork keel 6, the nut of the split bolt 1 are located at the outside of formwork keel 6.
Preferably, it in the application method of above-mentioned Split bolt sleeve structure, is opened up in the template 7 for being enclosed with Wrap up in the through-hole that the screw rod of the split bolt 1 of material layer 3 passes through.
Step 4 heats heating wire 2 using heating device 9 after the intensity of concrete is met the requirements, so that packet The heated thawing of material layer 3 is wrapped up in, so that gap is generated between the screw rod and concrete for the split bolt 1 for being wound with heating wire 2, into And the screw rod of the split bolt for being wound with heating wire 21 is enabled to be able to extract from the concrete eight of solidification, it realizes to drawing spiral shell The recycling of bolt 1.
Step 5 takes out the screw rod for being wound with the split bolt 1 of heating wire 2 from concrete eight;
Step 6, form removal 7.
The application method of Split bolt sleeve structure provided in this embodiment, that is, formwork reinforcement method, by split bolt Screw rod outside wind heating wire, the split bolt for being wound with heating wire screw rod outside be arranged a lapping layer, After using the split bolt fixed form and after casting concrete, the lapping layer can be carried out by heating device Heating is melted so that the lapping layer is heated, thus between the screw rod and concrete for the split bolt for being wound with heating wire Gap is generated, so that the screw rod for being wound with the split bolt of heating wire can be able to extract from the concrete of solidification, it is real The recycling for not needing to make and store split bolt in the case where casing of different specifications and sizes now, saved the construction time and Occupied area solves the casing for needing to make various specifications size in the prior art, and casing needs a large amount of stacking spaces, and Casing is equally easy to roll, the problem for causing injury to personnel and casing to be damaged.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (10)

1. a kind of Split bolt sleeve structure, which is characterized in that including for fixing two side templates split bolt, heating wire, Heating device and lapping layer, the heating wire winding on the screw rod of the split bolt, the heating wire with it is described Heating device connection, the lapping layer is wrapped in the outside of split bolt, and heating wire is located at lapping layer and to drawing Between the screw rod of bolt, lapping melting layer is enabled to after the heating devices heat heating wire.
2. Split bolt sleeve structure as described in claim 1, which is characterized in that the lapping layer is low melting point package Material layer.
3. Split bolt sleeve structure as described in claim 1, which is characterized in that the lapping layer is resin or stone Wax.
4. Split bolt sleeve structure as described in claim 1, which is characterized in that the heating wire is heating alloy.
5. Split bolt sleeve structure as described in claim 1, which is characterized in that the lapping layer by lapping by Heat is formed on being wrapped on the outside of the screw rod for being wound with the split bolt of heating wire after melting.
6. Split bolt sleeve structure as described in claim 1, which is characterized in that the heating device and split bolt away from From being 2~3 meters.
7. a kind of molding plate fixed structure, for fixing the template of two sides, which is characterized in that including any in such as claim 1-6 Split bolt sleeve structure, the lumps of wood and formwork keel described in one open up in the template for being enclosed with lapping layer Split bolt the through-hole that passes through of screw rod, the screw rod of the split bolt wears translateral template, the outside of the template according to The secondary setting lumps of wood and formwork keel, the nut of the split bolt are located at the outside of the formwork keel.
8. a kind of application method of the Split bolt sleeve structure as described in any one of claim 1-6, which is characterized in that Include the following steps:
Step 1, by heating wire winding on the screw rod of split bolt;
One layer of lapping layer is arranged in the outside of the screw rod for the split bolt for being wound with heating wire in step 2;
Step 3 binds the reinforcing bar of building body to be poured, using the split bolt stent for having heating wire and lapping layer Plate, casting concrete;
Step 4 heats heating wire using heating device, after the intensity of concrete is met the requirements so that lapping Layer is heated to be melted;
Step 5 takes out the screw rod for being wound with the split bolt of heating wire from concrete;
Step 6, form removal.
9. the application method of Split bolt sleeve structure as claimed in claim 8, which is characterized in that in the step 2, benefit Heating wire is heated with heating device, so that lapping is wrapped in the outer of the screw rod for being wound with the split bolt of heating wire Side forms the lapping layer in the outside of the screw rod for the split bolt for being wound with heating wire after lapping is cooling.
10. the application method of Split bolt sleeve structure as claimed in claim 8, which is characterized in that the outside of the template It is successively arranged the lumps of wood and formwork keel, the nut of the split bolt is located at the outside of formwork keel, opens up in the template The through-hole that screw rod for being enclosed with the split bolt of lapping layer passes through.
CN201810889322.4A 2018-08-07 2018-08-07 A kind of Split bolt sleeve structure, molding plate fixed structure and application method Pending CN109162456A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810889322.4A CN109162456A (en) 2018-08-07 2018-08-07 A kind of Split bolt sleeve structure, molding plate fixed structure and application method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810889322.4A CN109162456A (en) 2018-08-07 2018-08-07 A kind of Split bolt sleeve structure, molding plate fixed structure and application method

Publications (1)

Publication Number Publication Date
CN109162456A true CN109162456A (en) 2019-01-08

Family

ID=64895196

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810889322.4A Pending CN109162456A (en) 2018-08-07 2018-08-07 A kind of Split bolt sleeve structure, molding plate fixed structure and application method

Country Status (1)

Country Link
CN (1) CN109162456A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002167962A (en) * 2000-12-03 2002-06-11 Techno Supply Kk Synthetic resin molded plate for concrete form and concrete form using it
JP2004044186A (en) * 2002-07-11 2004-02-12 I S T Kk Method of manufacturing form fixture and form fixture
CN1837503A (en) * 2006-04-18 2006-09-27 张继红 Shell-reclaimable rock-reinforcing construction method and shelling type reinforcement body and reclaiming apparatus used thereby
JP2008251801A (en) * 2007-03-30 2008-10-16 Mitsubishi Electric Corp Coil and manufacturing method thereof
CN101898393A (en) * 2009-05-25 2010-12-01 鸿富锦精密工业(深圳)有限公司 mold
CN101994316A (en) * 2010-10-15 2011-03-30 张继红 Recyclable composite anchor rod and construction method thereof
CN103088818A (en) * 2013-02-04 2013-05-08 苏州市能工基础工程有限责任公司 Combined steel with core materials convenient to recover and recovery method thereof
CN103452103A (en) * 2013-01-18 2013-12-18 苏州市能工基础工程有限责任公司 Gripping type anchor with cores convenient to disassemble and method for recycling cores of gripping type anchor
CN204493380U (en) * 2015-01-27 2015-07-22 中国建筑土木建设有限公司 A split bolt subassembly for cast-in-place reinforced concrete construction
US20150259484A1 (en) * 2012-09-27 2015-09-17 Toyobo Co., Ltd. Polyester film
CN106062387A (en) * 2014-03-17 2016-10-26 费希尔厂有限责任两合公司 Anchors made of metal
CN209025441U (en) * 2018-08-07 2019-06-25 上海建工七建集团有限公司 A kind of Split bolt sleeve structure, molding plate fixed structure

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002167962A (en) * 2000-12-03 2002-06-11 Techno Supply Kk Synthetic resin molded plate for concrete form and concrete form using it
JP2004044186A (en) * 2002-07-11 2004-02-12 I S T Kk Method of manufacturing form fixture and form fixture
CN1837503A (en) * 2006-04-18 2006-09-27 张继红 Shell-reclaimable rock-reinforcing construction method and shelling type reinforcement body and reclaiming apparatus used thereby
JP2008251801A (en) * 2007-03-30 2008-10-16 Mitsubishi Electric Corp Coil and manufacturing method thereof
CN101898393A (en) * 2009-05-25 2010-12-01 鸿富锦精密工业(深圳)有限公司 mold
CN101994316A (en) * 2010-10-15 2011-03-30 张继红 Recyclable composite anchor rod and construction method thereof
US20150259484A1 (en) * 2012-09-27 2015-09-17 Toyobo Co., Ltd. Polyester film
CN103452103A (en) * 2013-01-18 2013-12-18 苏州市能工基础工程有限责任公司 Gripping type anchor with cores convenient to disassemble and method for recycling cores of gripping type anchor
CN103088818A (en) * 2013-02-04 2013-05-08 苏州市能工基础工程有限责任公司 Combined steel with core materials convenient to recover and recovery method thereof
CN106062387A (en) * 2014-03-17 2016-10-26 费希尔厂有限责任两合公司 Anchors made of metal
CN204493380U (en) * 2015-01-27 2015-07-22 中国建筑土木建设有限公司 A split bolt subassembly for cast-in-place reinforced concrete construction
CN209025441U (en) * 2018-08-07 2019-06-25 上海建工七建集团有限公司 A kind of Split bolt sleeve structure, molding plate fixed structure

Similar Documents

Publication Publication Date Title
CN209025441U (en) A kind of Split bolt sleeve structure, molding plate fixed structure
CN109935981A (en) A kind of 35kV--220kV pouring type cable ontology fusion splice and preparation method thereof
CN105017786B (en) Polyethylene glycol is from snow melt composite phase-change material modified pitch and preparation method thereof
WO2010084161A1 (en) High-temperature latent heat accumulator
CN109586519A (en) The fast repairing method of variable-frequency high-voltage motor winding insulation breakage
DE2003394C3 (en) Arrangement for using the solar energy radiated during the day against icing of ceilings, especially road surfaces, as well as storage mass and heat transfer medium for the arrangement
CN109162456A (en) A kind of Split bolt sleeve structure, molding plate fixed structure and application method
CN105525616A (en) Massive concrete pouring method
CN206464499U (en) The old wax circulation recycle system of precision-investment casting
DE102012000143A1 (en) Transferring heat and storing heat using specific and latent heat content of substances, comprises absorbing heat from heat source through heat storage material, storing heat, discharging heat to load, and releasing specific heat in plants
CN204884698U (en) Equipment is given as security out to electric wire
CN208247460U (en) A kind of waterproof roll film sticking apparatus
EP3260803B1 (en) Steam storage
US2135208A (en) Method and apparatus for coating and protecting metallic objects such as pipes, tanks, and the like from corrosion or other injury
CN102041919B (en) Manufacturing method of high-voltage composite material double-loop single-pole transmission tower
CN207255129U (en) A kind of rotation skeleton for processing tie hoop
CN207377240U (en) A kind of concurrent
CN105531043A (en) Process for manufacturing reclaimed alloy material and process for manufacturing reclaimed amorphous alloy ribbon
CN205929187U (en) Pitch waterproof coiled material production line auxiliary coolant system
CN104466848A (en) Multi-insulation-structure pouring type middle-high voltage bus duct
AT518828B1 (en) vapor storage
CN107508240A (en) A kind of deicer for power transmission line
CN106979431A (en) The mechanism of carried of crude oil ability is improved using solar power generation
CN207386506U (en) A kind of bismuth ingot automatic casting equipment
CN212001112U (en) A kind of thermal insulation and maintenance structure for pile foundation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190108

RJ01 Rejection of invention patent application after publication