CN107946826A
CN107946826A CN201710963731.XA CN201710963731A CN107946826A CN 107946826 A CN107946826 A CN 107946826A CN 201710963731 A CN201710963731 A CN 201710963731A CN 107946826 A CN107946826 A CN 107946826A
Authority
CN
China
Prior art keywords
switch
frame
socket
frame body
piece
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710963731.XA
Other languages
Chinese (zh)
Other versions
CN107946826B (en
Inventor
吴秋荣
申会员
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Gongniu Electric Appliances Co Ltd
Original Assignee
Ningbo Gongniu Electric Appliances Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Gongniu Electric Appliances Co Ltd filed Critical Ningbo Gongniu Electric Appliances Co Ltd
Priority to CN201710963731.XA priority Critical patent/CN107946826B/en
Publication of CN107946826A publication Critical patent/CN107946826A/en
Application granted granted Critical
Publication of CN107946826B publication Critical patent/CN107946826B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/08Distribution boxes; Connection or junction boxes
    • H02G3/14Fastening of cover or lid to box
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01RELECTRICALLY-CONDUCTIVE CONNECTIONS; STRUCTURAL ASSOCIATIONS OF A PLURALITY OF MUTUALLY-INSULATED ELECTRICAL CONNECTING ELEMENTS; COUPLING DEVICES; CURRENT COLLECTORS
    • H01R13/00Details of coupling devices of the kinds covered by groups H01R12/70 or H01R24/00 - H01R33/00
    • H01R13/46Bases; Cases
    • H01R13/516Means for holding or embracing insulating body, e.g. casing, hoods
    • H01R13/518Means for holding or embracing insulating body, e.g. casing, hoods for holding or embracing several coupling parts, e.g. frames
    • HELECTRICITY
    • H01ELECTRIC ELEMENTS
    • H01HELECTRIC SWITCHES; RELAYS; SELECTORS; EMERGENCY PROTECTIVE DEVICES
    • H01H9/00Details of switching devices, not covered by groups H01H1/00 - H01H7/00
    • H01H9/02Bases, casings, or covers

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Switch Cases, Indication, And Locking (AREA)

Abstract

本发明涉及一种连体式框架,包括框架本体,所述框架本体上设有用于安装多个开关或插座功能件的多位安装腔,所述多位安装腔上下贯通框架本体,该多位安装腔内部横向连通,本发明可以先拼装框架再接线,而本发明进一步的好处是,可以优先接线再拼装框架,本发明通过设置通框的多位安装腔,在一个或两个开关或插座功能件优先接好线的情况下,开关或插座功能件可以从框架本体的背面穿过多位安装腔到框架本体的正面,解决了先接线就会发生连体框架装不上的问题,不需要拆线返工,提高安装效率。

The invention relates to a one-piece frame, comprising a frame body, the frame body is provided with multiple mounting cavities for installing multiple switches or socket functional parts, the multiple mounting cavities penetrate the frame body up and down, the multiple mounting cavities The interior of the installation cavity is connected horizontally. The present invention can assemble the frame first and then connect the wires. The further advantage of the present invention is that the wiring can be prioritized before the frame is assembled. The present invention provides multiple installation cavities through the frame to connect one or two switches or sockets. When the functional parts are connected first, the functional parts of the switch or socket can pass through multiple installation cavities from the back of the frame body to the front of the frame body, which solves the problem that the one-piece frame cannot be installed if the wiring is done first. It needs to be removed and reworked to improve installation efficiency.

Description

一种连体式框架及其安装方法、连体式开关One-piece frame, installation method thereof, and one-piece switch

技术领域technical field

本发明涉及开关技术领域,尤其涉及一种连体式框架及其安装方法、连体式开关。The invention relates to the technical field of switches, in particular to a one-piece frame, an installation method thereof, and a one-piece switch.

背景技术Background technique

目前,市面上有多种形式的连框开关面板,主要有:(1)以单个功能件产品与连框安装固定拼装的方式,连框代替固定架,安装工艺复杂;(2)单个功能件产品与连体框架单孔拼装,即连体框架上一个孔配合一个功能件产品,安装时需要先拼装好连体框架才能上墙接线安装,安装时用户需要具备一定专业水准,不然拼装后会导致产品拼错造成返工,提高用户整体的安装成本。现有的连框产品安装繁琐且直接降低安装工作效率,影响其外观精致,安装不当或造成产品不良,甚至带来安全隐患。现有市面上销售的安装在墙体上装饰开关、插座的连体框架,一般包含2个或2个以上用来安装功能件产品的腔室,每个腔室都是相互隔开的,一个腔室安装一个功能件产品,安装的时候需要先将连体框架拼装好,然后再将墙体中预埋的电线与功能件产品连接,因为如果先接线,就会发生连体框架装不上的问题,那么就需要拆线返工,影响安装效率,而生活中确实会发生这种误把电线先接了的情况,另外,连体框架拼装好后,功能件产品接好线,功能件产品就直接紧固到连体框架的腔室上,若不紧固里面的电线多不易定位,但是后面安装第二个功能件产品或者第三个功能件产品时,整体位置有影响,就需要拆掉前面装的,返工重新安装,明显会降低安装工作效率,而且在返工过程中容易对连体框架造成损伤,提高安装成本。At present, there are various forms of frame-connected switch panels on the market, mainly including: (1) the method of installing and assembling a single functional part product with a frame, the frame replaces the fixed frame, and the installation process is complicated; (2) a single functional part The product is assembled with a single hole in the one-piece frame, that is, one hole on the one-piece frame matches a functional product. When installing, the one-piece frame needs to be assembled first before it can be installed on the wall. The user needs to have a certain professional level during installation, otherwise it will be damaged after assembly. This leads to product misspelling and rework, which increases the overall installation cost of the user. The installation of existing framed products is cumbersome and directly reduces the installation efficiency, affects its exquisite appearance, improper installation may cause defective products, and even bring safety hazards. The existing one-piece frame installed on the wall to decorate switches and sockets sold on the market generally includes two or more chambers for installing functional products. Each chamber is separated from each other. When installing a functional product in the chamber, the one-piece frame needs to be assembled first, and then the wires embedded in the wall are connected to the functional product, because if the wiring is done first, the one-piece frame will not be installed If there is a problem, then it is necessary to remove the wires and rework, which will affect the installation efficiency, and this kind of situation that the wires are connected by mistake will indeed happen in life. In addition, after the one-piece frame is assembled, the functional parts are connected. It is directly fastened to the chamber of the one-piece frame. If the wires inside are not fastened, it is difficult to locate. However, when the second or third functional product is installed later, the overall position will be affected, so it needs to be disassembled. Removing the one installed in the front, reworking and reinstalling will obviously reduce the installation efficiency, and it is easy to cause damage to the one-piece frame during the rework process, which will increase the installation cost.

发明内容Contents of the invention

针对上述现有技术的现状,本发明所要解决的技术问题在于提供一种可以先接线后拼装,避免返工重装,提高安装效率的连体式框架及其安装方法、连体式开关。Aiming at the present situation of the above-mentioned prior art, the technical problem to be solved by the present invention is to provide a one-piece frame, its installation method, and one-piece switch that can be assembled after wiring, avoiding rework and reassembly, and improving installation efficiency.

本发明解决上述技术问题所采用的技术方案为:一种连体式框架,包括框架本体,所述框架本体上设有用于安装多个开关或插座功能件的多位安装腔,所述多位安装腔上下贯通框架本体,该多位安装腔内部横向连通。The technical solution adopted by the present invention to solve the above technical problems is: a one-piece frame, including a frame body, the frame body is provided with a plurality of installation cavities for installing a plurality of switches or socket functional parts, the multi-position The installation cavity runs through the frame body up and down, and the interiors of the multiple installation cavities communicate horizontally.

进一步地,所述多位安装腔为对应安装两个开关或插座功能件的双位安装腔,在保证能让开关或插座功能件穿过的同时还能保证框架的整体强度。Further, the multi-position installation cavity is a double-position installation cavity for correspondingly installing two switch or socket functional parts, which can ensure the overall strength of the frame while allowing the switch or socket functional parts to pass through.

进一步地,所述框架本体上还设有用于安装单个开关或插座功能件的单位安装腔,增加框架整体强度。Further, the frame body is also provided with a unit installation cavity for installing a single switch or socket function, which increases the overall strength of the frame.

进一步地,所述框架本体包括平板部和自平板部四周向上延伸的侧板部,所述多位安装腔、单位安装腔的四周均由平板部构成,平板部可用来支撑开关或插座功能件,侧板部可将开关或插座功能件的周向包起来,提高安装精度与整齐度。Further, the frame body includes a flat plate and a side plate extending upward from the periphery of the flat plate. The surroundings of the multiple installation cavities and unit installation cavities are all formed by the flat plate, and the flat plate can be used to support the switch or the socket function. , The side plate part can wrap the circumference of the switch or socket functional parts, improving the installation accuracy and uniformity.

进一步地,所述平板部上设置有用于定位开关或插座功能件的扣脚,实现对开关或插座功能件进行预定位。Further, the flat plate part is provided with clasp feet for positioning the switch or socket functional parts, so as to realize the pre-positioning of the switch or socket functional parts.

进一步地,所述平板部上开有用于紧固开关或插座功能件的安装孔。Further, the flat plate part is provided with mounting holes for fastening the functional parts of the switch or the socket.

采用上述一种连体式框架的安装方法,包括如下步骤:The installation method using the above-mentioned one-piece frame includes the following steps:

a、将单个开关或插座功能件完成接线;a. Complete the wiring of a single switch or socket function;

b、将接好线的开关或插座功能件从框架本体的背面穿过多位安装腔到框架本体的正面;b. Pass the wired switch or socket functional parts from the back of the frame body through the multiple installation cavities to the front of the frame body;

c、将开关或插座功能件与扣脚相扣预定位在框架本体的正面上;c. Pre-locate the switch or socket function part and the buckle pin on the front of the frame body;

d、将第二个开关或插座功能件接好线,重复步骤c,以此类推;d. Connect the second switch or socket function, repeat step c, and so on;

e、将每个预定位的开关或插座功能件紧固在框架本体上。e. Fasten each pre-positioned switch or socket function on the frame body.

一种连体式开关,包括框架和安装在框架上的开关或插座功能件,所述开关或插座功能件包括固定架、安装于固定架中的功能模块与安装于固定架和功能模块上的面板,所述框架采用如前述所述的连体式框架,所述固定架与所述连体式框架连接。A conjoined switch, comprising a frame and a switch or socket functional part installed on the frame, the switch or socket functional part includes a fixed frame, a functional module installed in the fixed frame, and a switch mounted on the fixed frame and the functional module As for the panel, the frame adopts the one-piece frame as mentioned above, and the fixing frame is connected with the one-piece frame.

与现有技术相比,本发明的优点在于:本发明可以先拼装框架再接线,而本发明进一步的好处是,可以优先接线再拼装框架,本发明通过设置通框的多位安装腔,在一个或两个开关或插座功能件优先接好线的情况下,开关或插座功能件可以从框架本体的背面穿过多位安装腔到框架本体的正面,解决了先接线就会发生连体框架装不上的问题,不需要拆线返工,提高安装效率,另外,配合扣脚,可以对开关或插座功能件进行预定位,使得用户在上墙时可以先预安装开关或插座功能件,在开关或插座功能件安装位置不正确需要调整的情况下,可以快速地将开关或插座功能件拆下来重新定位,减少拆卸的时间,提高安装效率以及安装精度。Compared with the prior art, the advantage of the present invention is that: the present invention can assemble the frame first and then connect the wires, and the further advantage of the present invention is that it can give priority to the wiring before assembling the frame. When one or two switch or socket functional parts are wired first, the switch or socket functional parts can pass through multiple installation cavities from the back of the frame body to the front of the frame body, which solves the problem of connecting the frame first. For problems that cannot be installed, there is no need to disassemble and rework, which improves installation efficiency. In addition, with the buckle feet, the switch or socket functional parts can be pre-positioned, so that users can pre-install the switch or socket functional parts when installing on the wall. When the installation position of the switch or socket function is incorrect and needs to be adjusted, the switch or socket function can be quickly removed and repositioned, reducing the time for disassembly and improving installation efficiency and installation accuracy.

附图说明Description of drawings

图1为本发明的安装示意图;Fig. 1 is the installation schematic diagram of the present invention;

图2为本发明的一种结构示意图;Fig. 2 is a kind of structural representation of the present invention;

图3为本发明的另一种结构示意图;Fig. 3 is another kind of structural representation of the present invention;

图4为本发明的又一种结构示意图;Fig. 4 is another kind of structural representation of the present invention;

图5为本发明的再一种结构示意图;Fig. 5 is another kind of structural representation of the present invention;

如图所示,1框架本体,2单位安装腔,3多位安装腔,4扣脚,5安装孔,6开关或插座功能件。As shown in the figure, 1 frame body, 2 unit installation cavity, 3 multi-position installation cavity, 4 buckle feet, 5 installation holes, 6 switch or socket functional parts.

具体实施方式Detailed ways

下面结合附图和具体实施例对本发明作进一步地说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.

如图1-5所示,一种连体式框架,包括框架本体1,所述框架本体1上设有用于安装多个开关或插座功能件6的多位安装腔3,所述多位安装腔3上下贯通框架本体1,该多位安装腔3内部横向连通,多位安装腔3方便开关或插座功能件6自由穿过,在一个或两个开关或插座功能件6优先接好线的情况下,开关或插座功能件6可以从框架本体1的背面穿过多位安装腔3到框架本体1的正面,避免因为先接线而要拆除接线返工的情况,弥补安装失误造成的损失,所述多位安装腔3为对应安装两个开关或插座功能件6的双位安装腔,在保证能让开关或插座功能件6穿过的同时还能保证框架的整体强度,所述框架本体1上还设有用于安装单个开关或插座功能件6的单位安装腔2,增加框架整体强度,本发明的框架可以只包括一个双位安装腔,用于安装两个开关或插座功能件6,如图2所示;也可以包括一个双位安装腔和一个单位安装腔2,用于安装三个开关或插座功能件6,如图3所示;也可以包括两个双位安装腔或者一个双位安装腔配合两个单位安装腔2,用于安装四个开关或插座功能件6,如图4所示;还可以包括两个双位安装腔配合一个单位安装腔2或者一个双位安装腔配合三个单位安装腔2,用于安装五个开关或插座功能件6,如图5所示;所述框架本体1包括平板部和自平板部四周向上延伸的侧板部,所述多位安装腔3、单位安装腔2的四周均由平板部构成,平板部可用来支撑开关或插座功能件6,侧板部可将开关或插座功能件6的周向包起来,提高安装精度与整齐度,所述平板部上设置有用于定位开关或插座功能件6的扣脚4,扣脚4的设置使得用户在上墙时可以先预安装开关或插座功能件6,即开关或插座功能件6与扣脚4相扣预定位在框架本体1的正面,在开关或插座功能件6安装位置不正确需要调整的情况下,可以快速地将开关或插座功能件6拆下来重新定位,减少拆卸的时间,所述扣脚4两个为一组与开关或插座功能件6配合,该扣脚4在开关或插座功能件6对角线方向上进行定位,可以利用最少数量的扣脚4实现对开关或插座功能件6的定位,而且两点定位,安装、拆卸较快,提高工作效率,所述平板部上开有用于紧固开关或插座功能件6的安装孔5,在开关或插座功能件6预定位后,检查安装位置无误后,通过安装孔5将开关或插座功能件6紧固在框架上。As shown in Figures 1-5, a one-piece frame includes a frame body 1, and the frame body 1 is provided with a multi-position installation cavity 3 for installing a plurality of switch or socket functional parts 6, and the multi-position installation The cavity 3 runs through the frame body 1 up and down, and the interior of the multi-position installation cavity 3 is connected horizontally. The multi-position installation cavity 3 facilitates the free passage of the switch or socket function parts 6, and one or two switch or socket function parts 6 are preferentially connected. Under normal circumstances, the switch or socket functional part 6 can pass through the multi-position installation cavity 3 to the front of the frame body 1 from the back of the frame body 1, avoiding the situation of dismantling the wiring and reworking due to the wiring first, and making up for the loss caused by the installation error. The multi-position installation cavity 3 is a double-position installation cavity corresponding to the installation of two switches or socket function parts 6, which can ensure the overall strength of the frame while ensuring that the switch or socket function parts 6 can pass through. There is also a unit installation cavity 2 for installing a single switch or socket function 6, which increases the overall strength of the frame. The frame of the present invention can only include a double-position installation cavity for installing two switches or socket functions 6, such as As shown in Figure 2; it may also include a double-position installation chamber and a unit installation chamber 2 for installing three switch or socket functional parts 6, as shown in Figure 3; it may also include two double-position installation chambers or a double-position installation chamber The one-position installation cavity cooperates with two unit installation cavities 2 for installing four switch or socket functional parts 6, as shown in Figure 4; it can also include two double-position installation cavities matched with one unit installation cavity 2 or one double-position installation cavity Cooperate with three unit installation cavities 2 for installing five switch or socket functional parts 6, as shown in Figure 5; The installation cavity 3 and the unit installation cavity 2 are surrounded by flat plates, which can be used to support the switch or socket functional parts 6, and the side plates can wrap the circumference of the switch or socket functional parts 6 to improve installation accuracy and neatness The flat part is provided with buckle feet 4 for positioning switch or socket function parts 6. The setting of buckle feet 4 enables users to pre-install switch or socket function parts 6 when they are on the wall, that is, switch or socket function parts 6 is interlocked with the pin 4 and pre-positioned on the front of the frame body 1. When the installation position of the switch or socket function part 6 is incorrect and needs to be adjusted, the switch or socket function part 6 can be quickly removed and repositioned to reduce disassembly During the time, two of the buckle feet 4 are used as a group to cooperate with the switch or socket function part 6, and the buckle feet 4 are positioned in the diagonal direction of the switch or socket function part 6, which can be realized by using a minimum number of buckle feet 4 For the positioning of the switch or socket functional part 6, and two-point positioning, the installation and disassembly are quicker, and the work efficiency is improved. The mounting hole 5 for fastening the switch or socket functional part 6 is opened on the said flat part. After the functional part 6 is pre-positioned, after checking that the installation position is correct, fasten the switch or socket functional part 6 on the frame through the mounting hole 5 .

采用上述一种连体式框架的安装方法,包括如下步骤:The installation method using the above-mentioned one-piece frame includes the following steps:

a、将单个开关或插座功能件6完成接线,即开关或插座功能件6与墙体内预埋的电线连接;a. Complete the wiring of a single switch or socket functional part 6, that is, the switch or socket functional part 6 is connected to the wire embedded in the wall;

b、将接好线的开关或插座功能件6从框架本体1的背面穿过多位安装腔3到框架本体1的正面;b. Pass the wired switch or socket functional part 6 from the back of the frame body 1 through the multi-position installation cavity 3 to the front of the frame body 1;

c、将开关或插座功能件6与扣脚4相扣预定位在框架本体1的正面上;c. The switch or socket functional part 6 is interlocked with the buckle pin 4 and pre-positioned on the front of the frame body 1;

d、将第二个开关或插座功能件6接好线,此时第二个开关或插座功能件6是直接在框架本体1的正面完成接线,然后重复步骤c,以此类推,直到安装完相应数量的开关或插座功能件6;d. Connect the second switch or socket functional part 6, at this time, the second switch or socket functional part 6 is connected directly on the front of the frame body 1, then repeat step c, and so on, until the installation is complete A corresponding number of switch or socket functional parts 6;

e、将每个预定位的开关或插座功能件6紧固在框架本体1上,即开关或插座功能件6通过安装孔5紧固在框架本体1上。e. Fasten each pre-positioned switch or socket function part 6 on the frame body 1 , that is, the switch or socket function part 6 is fastened on the frame body 1 through the installation hole 5 .

本发明的安装方法也可以是如下步骤:Installation method of the present invention also can be following steps:

a、将两个开关或插座功能件6优先完成接线,即开关或插座功能件6与墙体内预埋的电线连接;a. Prioritize the wiring of the two switch or socket functional parts 6, that is, connect the switch or socket functional parts 6 to the wires embedded in the wall;

b、将接好线的开关或插座功能件6逐个从框架本体1的背面穿过多位安装腔3到框架本体1的正面;b. Pass the connected switch or socket functional parts 6 from the back of the frame body 1 through the multi-position installation cavity 3 to the front of the frame body 1;

c、将两个开关或插座功能件6分别与相对应的扣脚4相扣预定位在框架本体1的正面上,如果只有两个位的,则将两个预定位的开关或插座功能件6紧固在框架本体1上即可,如果超过两个位的,则进行步骤d;c. Buckle the two switch or socket function parts 6 with the corresponding buckle feet 4 and pre-position them on the front of the frame body 1. If there are only two positions, place the two pre-positioned switch or socket function parts 6 Just fasten it on the frame body 1, if there are more than two positions, proceed to step d;

d、将第三个开关或插座功能件6接好线,此时第三个开关或插座功能件6是直接在框架本体1的正面完成接线,然后将开关或插座功能件6与扣脚4相扣预定位在框架本体1的正面上,以此类推,直到安装完相应数量的开关或插座功能件6;d. Connect the third switch or socket functional part 6 to the wire. At this time, the third switch or socket functional part 6 is directly connected on the front of the frame body 1, and then connect the switch or socket functional part 6 to the pin 4 Interlocking is pre-positioned on the front of the frame body 1, and so on, until a corresponding number of switches or socket functional parts 6 are installed;

e、将每个预定位的开关或插座功能件6紧固在框架本体1上,即开关或插座功能件6通过安装孔5紧固在框架本体1上。e. Fasten each pre-positioned switch or socket function part 6 on the frame body 1 , that is, the switch or socket function part 6 is fastened on the frame body 1 through the installation hole 5 .

以上所述的相应数量的开关或插座功能件,是指开关或插座功能件的数量与框架上的安装位数量一致,单位安装腔2包括一个安装位,双位安装腔包括两个安装位,多位安装腔3包括多个安装位,多位安装腔3与单位安装腔2之间、单位安装腔2与单位安装腔2之间、多位安装腔3与多位安装腔3之间隔着平板部,彼此都是相隔状态,而多位安装腔3内部是通框设计,所以可以穿过开关或插座功能件6,而单位安装腔2是不能穿过开关或插座功能件6的,开关或插座功能件6可以优先接线的数量取决于多位安装腔3内部包含的安装位的数量,双位安装腔可以优先接线1-2个开关或插座功能件6,三位安装腔可以优先接线1-3个开关或插座功能件6,以此类推。The corresponding number of switch or socket functional parts mentioned above means that the number of switch or socket functional parts is consistent with the number of installation positions on the frame. The unit installation cavity 2 includes one installation position, and the double-position installation cavity includes two installation positions. The multi-position installation cavity 3 includes a plurality of installation positions, between the multi-position installation cavity 3 and the unit installation cavity 2, between the unit installation cavity 2 and the unit installation cavity 2, and between the multi-position installation cavity 3 and the multi-position installation cavity 3 The flat parts are all separated from each other, and the interior of the multi-position installation cavity 3 is designed through the frame, so it can pass through the switch or socket function 6, while the unit installation cavity 2 cannot pass through the switch or socket function 6, the switch Or the number of socket function parts 6 that can be wired preferentially depends on the number of installation positions contained in the multi-position installation cavity 3. The double-position installation cavity can preferentially connect 1-2 switches or socket function parts 6, and the three-position installation cavity can be preferentially wired. 1-3 switch or socket functional parts 6, and so on.

以上安装方法只是使用顺序的不同,拼装原理是一样的,在优先接线的情况下,都需要开关或插座功能件从框架本体的背面穿过多位安装腔到框架本体的正面。The above installation methods are only different in order of use, and the assembly principle is the same. In the case of priority wiring, the switch or socket functional parts need to pass through the multi-position installation cavity from the back of the frame body to the front of the frame body.

一种连体式开关,包括框架和安装在框架上的开关或插座功能件6,所述开关或插座功能件6包括固定架、安装于固定架中的功能模块与安装于固定架和功能模块上的面板,所述框架采用如前述所述的连体式框架,所述固定架与所述连体式框架连接,该固定架通过与扣脚4相扣预定位,使用时,先将开关或插座功能件6组装完毕,并按照如前述所述的安装方法进行安装,即可,如图1所示。A conjoined switch, comprising a frame and a switch or socket functional part 6 installed on the frame, the switch or socket functional part 6 includes a fixing frame, a functional module installed in the fixing frame, and a function module installed in the fixing frame and the functional module The panel above, the frame adopts the one-piece frame as mentioned above, the fixed frame is connected with the one-piece frame, the fixed frame is pre-positioned by interlocking with the buckle foot 4, when in use, first switch the Or the socket functional part 6 is assembled, and installed according to the above-mentioned installation method, as shown in FIG. 1 .

最后应说明的是:以上实施例仅用以说明本发明的技术方案,而非对其限制;尽管参照前述实施例对本发明进行了详细的说明,本领域的技术人员应当理解,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行同等替换;而这些修改或者替换,并不使相应技术方案的本质脱离本发明各实施例技术方案的精神与范围。Finally, it should be noted that: the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them; although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that it still can The technical solutions described in the foregoing embodiments are modified, or some of the technical features are replaced equivalently; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the various embodiments of the present invention.

Claims (8)

1.一种连体式框架,包括框架本体(1),其特征在于,所述框架本体(1)上设有用于安装多个开关或插座功能件(6)的多位安装腔(3),所述多位安装腔(3)上下贯通框架本体(1),该多位安装腔(3)内部横向连通。1. A one-piece frame, comprising a frame body (1), characterized in that, the frame body (1) is provided with multiple installation cavities (3) for installing multiple switches or socket functional parts (6) , the multiple installation cavities (3) pass through the frame body (1) up and down, and the multiple installation cavities (3) communicate horizontally inside. 2.根据权利要求1所述的一种连体式框架,其特征在于,所述多位安装腔(3)为对应安装两个开关或插座功能件(6)的双位安装腔。2 . The one-piece frame according to claim 1 , characterized in that, the multi-position installation cavity ( 3 ) is a double-position installation cavity for correspondingly installing two switch or socket functional parts ( 6 ). 3.根据权利要求1或2所述的一种连体式框架,其特征在于,所述框架本体(1)上还设有用于安装单个开关或插座功能件(6)的单位安装腔(2)。3. A one-piece frame according to claim 1 or 2, characterized in that, the frame body (1) is also provided with a unit installation cavity (2) for installing a single switch or socket function (6) ). 4.根据权利要求3所述的一种连体式框架,其特征在于,所述框架本体(1)包括平板部和自平板部四周向上延伸的侧板部,所述多位安装腔(3)、单位安装腔(2)的四周均由平板部构成。4. A one-piece frame according to claim 3, characterized in that, the frame body (1) includes a flat plate and side plates extending upward from around the flat plate, and the multi-position installation cavity (3 ), the surroundings of the unit installation cavity (2) are all made of flat plate parts. 5.根据权利要求4所述的一种连体式框架,其特征在于,所述平板部上设置有用于定位开关或插座功能件(6)的扣脚(4)。5 . The one-piece frame according to claim 4 , characterized in that, the flat plate part is provided with buckle feet ( 4 ) for positioning switch or socket functional parts ( 6 ). 6 . 6.根据权利要求4所述的一种连体式框架,其特征在于,所述平板部上开有用于紧固开关或插座功能件(6)的安装孔(5)。6 . The one-piece frame according to claim 4 , characterized in that, the flat plate portion is provided with mounting holes ( 5 ) for fastening the functional parts ( 6 ) of switches or sockets. 7 . 7.根据权利要求1所述的一种连体式框架的安装方法,其特征在于,包括如下步骤:7. The installation method of a one-piece frame according to claim 1, characterized in that it comprises the following steps: a、将单个开关或插座功能件(6)完成接线;a. Complete the wiring of a single switch or socket function (6); b、将接好线的开关或插座功能件(6)从框架本体(1)的背面穿过多位安装腔(3)到框架本体(1)的正面;b. Pass the wired switch or socket functional part (6) from the back of the frame body (1) through the multi-position installation cavity (3) to the front of the frame body (1); c、将开关或插座功能件(6)与扣脚(4)相扣预定位在框架本体(1)的正面上;c. Buckle the switch or socket functional part (6) with the buckle pin (4) and pre-position it on the front of the frame body (1); d、将第二个开关或插座功能件(6)接好线,重复步骤c,以此类推;d. Connect the second switch or socket function (6), repeat step c, and so on; e、将每个预定位的开关或插座功能件(6)紧固在框架本体(1)上。e. Fasten each pre-positioned switch or socket function (6) on the frame body (1). 8.一种连体式开关,包括框架和安装在框架上的开关或插座功能件(6),所述开关或插座功能件(6)包括固定架、安装于固定架中的功能模块与安装于固定架和功能模块上的面板,其特征在于,所述框架采用如权利要求1-6之一所述的连体式框架,所述固定架与所述连体式框架连接。8. A one-piece switch, comprising a frame and a switch or socket functional part (6) mounted on the frame, said switch or socket functional part (6) comprising a fixing frame, a functional module installed in the fixing frame and a mounting The panel on the fixing frame and the functional module is characterized in that the frame adopts the one-piece frame according to any one of claims 1-6, and the fixing frame is connected to the one-piece frame.
CN201710963731.XA 2017-10-17 2017-10-17 A conjoined frame and installation method thereof, and conjoined switch Active CN107946826B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710963731.XA CN107946826B (en) 2017-10-17 2017-10-17 A conjoined frame and installation method thereof, and conjoined switch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710963731.XA CN107946826B (en) 2017-10-17 2017-10-17 A conjoined frame and installation method thereof, and conjoined switch

Publications (2)

Publication Number Publication Date
CN107946826A true CN107946826A (en) 2018-04-20
CN107946826B CN107946826B (en) 2019-04-05

Family

ID=61935384

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710963731.XA Active CN107946826B (en) 2017-10-17 2017-10-17 A conjoined frame and installation method thereof, and conjoined switch

Country Status (1)

Country Link
CN (1) CN107946826B (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2829130Y (en) * 2005-07-13 2006-10-18 佛山市维皓电气贸易有限公司 Electrical equipment plug socket
CN201004381Y (en) * 2006-12-14 2008-01-09 惠州雷士光电科技有限公司 A connected switch socket
CN201032656Y (en) * 2007-01-23 2008-03-05 冯华雄 Switch socket
US20160054717A1 (en) * 2014-03-26 2016-02-25 Elbex Video Ltd. Method and apparatus for setting and integrating home automation grid or network with electrical grid
CN205104659U (en) * 2015-11-09 2016-03-23 淳安千岛湖炎农电子商务有限公司 A support socket backplate charges
CN205752814U (en) * 2016-05-13 2016-11-30 深圳市智远能科技有限公司 A kind of intelligent switch socket
CN206313235U (en) * 2016-10-22 2017-07-07 浙江诺金电器有限公司 A kind of three wall sockets
CN206558758U (en) * 2017-02-24 2017-10-13 宁波公牛电器有限公司 A kind of multidigit fixing type socket with integrated plug bush

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2829130Y (en) * 2005-07-13 2006-10-18 佛山市维皓电气贸易有限公司 Electrical equipment plug socket
CN201004381Y (en) * 2006-12-14 2008-01-09 惠州雷士光电科技有限公司 A connected switch socket
CN201032656Y (en) * 2007-01-23 2008-03-05 冯华雄 Switch socket
US20160054717A1 (en) * 2014-03-26 2016-02-25 Elbex Video Ltd. Method and apparatus for setting and integrating home automation grid or network with electrical grid
CN205104659U (en) * 2015-11-09 2016-03-23 淳安千岛湖炎农电子商务有限公司 A support socket backplate charges
CN205752814U (en) * 2016-05-13 2016-11-30 深圳市智远能科技有限公司 A kind of intelligent switch socket
CN206313235U (en) * 2016-10-22 2017-07-07 浙江诺金电器有限公司 A kind of three wall sockets
CN206558758U (en) * 2017-02-24 2017-10-13 宁波公牛电器有限公司 A kind of multidigit fixing type socket with integrated plug bush

Also Published As

Publication number Publication date
CN107946826B (en) 2019-04-05

Similar Documents

Publication Publication Date Title
US11231164B2 (en) Holiday decorative lamp
CN107946826A (en) A kind of Contiuum type frame and its installation method, connected switch
US10617024B2 (en) Locking spring structure and power apparatus having the same
CN206263826U (en) Circuit board mounting jig
CN106711574A (en) Antenna installing part, installing assembly and installing method
CN216488682U (en) Novel wall socket panel dismounting structure
CN106426996B (en) A kind of tire-mold
KR101719055B1 (en) Fixing and taking away device of cover for light
CN106568038A (en) Bracket of flush light panel and flush light panel
CN208920533U (en) A net cover installation structure and an air conditioner
CN210508116U (en) A stainless steel casting for support
JP3224578U (en) Surface mount type LED lamp
CN209540678U (en) Lamps and lanterns
CN223375671U (en) Lamp capable of being rapidly assembled and disassembled
CN206116800U (en) Machine square frame rectangular connector assembly quality
CN207159609U (en) Assemble mechanism and washing machine for washing machine
CN216047228U (en) Simple and convenient installation component
CN106057091A (en) Display screen assembly
CN223242724U (en) Split type fan lamp structure
CN212902041U (en) A buckle structure for hanging stove
JP2572887B2 (en) lighting equipment
CN102411222B (en) The fixing means of a kind of liquid crystal display and internal component thereof
CN104110610A (en) Indicator lamp
CN219915791U (en) Antenna port impedance mismatch simulator
CN214948526U (en) Positioning jig and lamp panel assembly

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant