CN107366303A - Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template - Google Patents

Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template Download PDF

Info

Publication number
CN107366303A
CN107366303A CN201710650272.XA CN201710650272A CN107366303A CN 107366303 A CN107366303 A CN 107366303A CN 201710650272 A CN201710650272 A CN 201710650272A CN 107366303 A CN107366303 A CN 107366303A
Authority
CN
China
Prior art keywords
retaining wall
template
wall
highway
aluminum alloy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710650272.XA
Other languages
Chinese (zh)
Inventor
戚成建
马培松
郭清
焦成林
李光选
时亮
张丹瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Yearning Construction Co Ltd
Original Assignee
Jiangsu Yearning Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Yearning Construction Co Ltd filed Critical Jiangsu Yearning Construction Co Ltd
Priority to CN201710650272.XA priority Critical patent/CN107366303A/en
Publication of CN107366303A publication Critical patent/CN107366303A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0258Retaining or protecting walls characterised by constructional features
    • E02D29/0275Retaining or protecting walls characterised by constructional features cast in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0035Aluminium

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)

Abstract

The present invention discloses construction method and retaining wall of a kind of aluminum alloy mould plate as highway gravity retaining wall template, it is related to technical field of building construction, it can not meet construction quality requirement in mountain highway Lin Ya or the section that borders on the river structure gravity retaining wall to improve conventional template, and potential safety hazard be present and technical problem that the forest reserves excessively consume.Construction method of the aluminum alloy mould plate of the present invention as highway gravity retaining wall template, using aluminum alloy mould plate in spacious place elder generation merogenesis assembling earth-retaining wall form, then by retaining wall formwork hoisting to design attitude, fix after-pouring concrete, the construction quality requirement in mountain highway Lin Ya or the section that borders on the river structure gravity retaining wall can either be met, and can enough reduces the generation of security incident to greatest extent, construction speed can also be improved, shorten construction period, phenomenon of caving in can be avoided simultaneously, and timber resources need not be consumed, the beneficial effect with energy-conserving and environment-protective.Retaining wall of the present invention can realize the effect of permanent bank protection safe edge.

Description

Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template
Technical field
The present invention relates to technical field of building construction, in particular to a kind of aluminum alloy mould plate as highway gravity type The construction method and retaining wall of earth-retaining wall form.
Background technology
Gravity retaining wall is to resist the retaining wall of soil body lateral pressure by wall self gravitation, the slope carried on the back according to its wall Degree be divided into face upward inclined, bow inclined and vertical type three types.The stratum of this kind of retaining wall is stable, not entail dangers to during earth and stone digging The location of adjacent buildings safety, its economic benefit is obvious, is widely used in China.Lead to for mountain highway Lin Ya or the section that borders on the river Often need to set retaining wall, but the construction height difference of respective stretch is larger, narrow field, constructional difficulties and potential safety hazard be present The problem of big.Therefore, template is needed to use when building gravity retaining wall for mountain highway Lin Ya or the section that borders on the river.
Template in construction industry is a kind of temporary supporting structure, is made by design requirement, makes concrete structure or component It is molded according to the position of regulation and physical dimension, and keeps its correct position, is can be used in bearing building template deadweight and make Used in external load thereon.In existing engineering construction, using it is more be conventional template, typically steel form or wooden model Plate.Wherein steel form is customized with steel and is molded, and has the advantages of intensity is big, concrete apparent mass is good after form removal, but weight mistake Weight, construction need plant equipment to assist, easily got rusty, and in concreting process easily together with concrete binding, take off Mould is difficult;Plank sheathing uses timber machine-shaping, and this template is relatively affectedly unconventional, and cost is slightly lower, but its low strength, no waterproof Performance, easily go mouldy rotten, repeat usage is low, it is necessary to consume timber resources, is unfavorable for the protection of ecological environment and the forest reserves. Aluminum alloy mould plate has in light weight as a kind of new building template, and construction quality is good and the advantages of energy-conserving and environment-protective, but mainly Applied to industry or civil buildings, using less in terms of Road Retaining Walls.Therefore a kind of aluminum alloy mould plate conduct how is provided The construction method and retaining wall of highway gravity retaining wall template, it can either meet in mountain highway Lin Ya or the section that borders on the river structure weight The construction quality requirement of power formula retaining wall, and can enough reduce the generation of security incident to greatest extent, additionally it is possible to realize energy-saving ring The effect of guarantor turns into the technical problem of those skilled in the art's urgent need to resolve.
In view of this, it is special to propose the present invention.
The content of the invention
First purpose of the present invention is to provide a kind of aluminum alloy mould plate applying as highway gravity retaining wall template Work method, the construction quality that gravity retaining wall is built in mountain highway Lin Ya or the section that borders on the river to improve conventional template not meet It is required that and potential safety hazard be present and technical problem that the forest reserves excessively consume.
Second object of the present invention is to provide one kind using aluminum alloy mould plate of the present invention as highway gravity type earth-retaining The retaining wall that the construction method of wall form is constructed, the retaining wall disclosure satisfy that construction quality requirement, and it is relatively low to construct cost, Neng Goufa Wave permanent bank protection safe edge effect.
In order to realize the above-mentioned purpose of the present invention, spy uses following technical scheme:
The present invention provides a kind of construction method of aluminum alloy mould plate as highway gravity retaining wall template, including following step Suddenly:Random sample unwrapping wire step, the center line and horizontal stroke, longitudinal axis of retaining wall are released according to design requirement, and are carried out with total powerstation, steel ruler Foundation ditch setting-out;Excavation of foundation pit step, using the artificial digging mode for combining excavator, excavator first excavates, then manual cleaning Bottom land carries out bearing capacity examination to designed elevation after cleaning out;Retaining wall construction procedure, by the aluminum alloy mould plate of acceptance(check) Respectively as wall body Side shuttering, wall body front face template and end head formwork after cleaning out, then each corresponding template is propped up and stood simultaneously Merogenesis is assembled into earth-retaining wall form, then is lifted at design attitude, fixation after-pouring concrete;Wall carries on the back refilling step, Concrete strength backfills the wall back of the body in time after reaching design requirement.
Alternatively, in retaining wall construction procedure, the both sides of the wall body Side shuttering are fixed using steel pipe support, and Steel pipe support is linked to be entirety, and the inside of the wall body Side shuttering is fixed using wall-through pull rod.
Alternatively, the cross bar spacing of the steel pipe support is 45-55cm, and montant spacing is 75-85cm;The steel pipe support On be provided with bridging, the spacing of the bridging is 1.5-2.5m.
Alternatively, the wall-through pull rod is fed through pvc pipe and both ends are connected on the wall body Side shuttering, institute The spacing for stating wall-through pull rod is 45-55cm;The both ends of the pvc pipe pass the wall body Side shuttering 1-2cm and the PVC Manage and cemented with the junction of the wall body Side shuttering with adhesive tape.
Alternatively, the end head formwork and the wall body front face template and the wall body Side shuttering jam-packed and connector is used It is fixed, the junction patch double faced adhesive tape of two neighboring template;Steel is used after the wall body front face template and end head formwork installation Pipe holder supports.
Alternatively, in retaining wall construction procedure, built-in fitting, the wall body Side shuttering, the wall body are set on ground Front face template and the end head formwork are connected with the built-in fitting;The wall body Side shuttering, the wall body front face template and After the end head formwork is spliced into earth-retaining wall form and installation, in the external coating releasing agent of the earth-retaining wall form.
Alternatively, the inside of the earth-retaining wall form is additionally provided with passage template, and the passage template is used for the gear Section gap inside cob wall template;During the passage formwork support arrangement, the upper strata subsiding crack of retaining wall is seamed with its foundation settlement Put on same vertical curve;Separated in the upper strata subsiding crack and in the settlement joints with bamboo slab rubber.
Alternatively, in retaining wall construction procedure, the earth-retaining wall form is fixed into after-pouring concrete;By the earth-retaining One end of wall form is to other end layer and section casting concrete in the horizontal direction, lift height≤30cm;Lay first layer stone Before block, the thick concrete of 10-15cm is first poured, lays stone, then casting concrete then up;The spacing of adjacent stone is 8- 12cm, the spacing >=15cm, thickness >=10cm of the top surface oversite concrete of the superiors' stone of stone and earth-retaining wall form;Wait to mix Coagulate after native intensity reaches requirement and remove correlate template.
Alternatively, in wall carries on the back refilling step, backfilled using placement in layers compacting mode.
The present invention also provides a kind of retaining wall, and the retaining wall is using above-mentioned aluminum alloy mould plate as highway gravity retaining wall The construction method of template obtains.
Compared with prior art, the present invention has following advantage:
(1) construction method of the aluminum alloy mould plate of the present invention as highway gravity retaining wall template, by random sample unwrapping wire and Excavation of foundation pit can be that adequate preparation is carried out in the construction of gravity retaining wall, then first in the place of spaciousness using aluminum alloy mould plate Merogenesis assembles earth-retaining wall form, then by retaining wall formwork hoisting to design attitude, fixes after-pouring concrete, can either expire Construction quality of the foot in mountain highway Lin Ya or the section that borders on the river structure gravity retaining wall requires that and can enough reduces peace to greatest extent The generation of full accident, additionally it is possible to improve construction speed, shorten construction period, additionally due to aluminum alloy mould plate have it is in light weight, by force Degree is big, the easily advantage such as moulding and energy-conserving and environment-protective, therefore make the convenient construction of highway gravity retaining wall, and construction quality is high, avoids Cave in phenomenon, and timber resources need not be consumed, the beneficial effect with energy-conserving and environment-protective.The inventive method process is simple, easily In construction, suitable for the popularization and application in highway engineering.
(2) retaining wall of the present invention both has firm solid internal structure, has smooth appearance attractive in appearance again, outside interior reality U.S., disclosure satisfy that mountain highway Lin Ya or a section requirement for gravity retaining wall construction quality of bordering on the river, and it is relatively low to construct cost, realizes length The effect of long bank protection safe edge.
Embodiment
Embodiment of the present invention is described in detail below in conjunction with embodiment or embodiment, but this area skill Art personnel will be understood that following embodiments or embodiment are merely to illustrate the present invention, and be not construed as the model of the limitation present invention Enclose.Unreceipted actual conditions person in embodiment or embodiment, the condition suggested according to normal condition or manufacturer are carried out.It is used Reagent or the unreceipted production firm person of instrument, it is the conventional products that can be obtained by commercially available purchase.
The present invention provides a kind of construction method of aluminum alloy mould plate as highway gravity retaining wall template, including following step Suddenly:Random sample unwrapping wire step, the center line and horizontal stroke, longitudinal axis of retaining wall are released according to design requirement, and are carried out with total powerstation, steel ruler Foundation ditch setting-out;Excavation of foundation pit step, using the artificial digging mode for combining excavator, excavator first excavates, then manual cleaning Bottom land carries out bearing capacity examination to designed elevation after cleaning out;Retaining wall construction procedure, by the aluminum alloy mould plate of acceptance(check) Respectively as wall body Side shuttering, wall body front face template and end head formwork after cleaning out, then each corresponding template is propped up and stood simultaneously Merogenesis is assembled into earth-retaining wall form, then is lifted at design attitude, fixation after-pouring concrete;Wall carries on the back refilling step, Concrete strength backfills the wall back of the body in time after reaching design requirement.
Compared with prior art, the aluminum alloy mould plate that embodiment of the present invention provides is as highway gravity retaining wall template Construction method have the beneficial effect that:
Construction method of the aluminum alloy mould plate that embodiment of the present invention provides as highway gravity retaining wall template, passes through Random sample unwrapping wire and excavation of foundation pit can be that adequate preparation is carried out in the construction of gravity retaining wall, then using aluminum alloy mould plate in width Spacious place elder generation merogenesis assembling earth-retaining wall form, then by retaining wall formwork hoisting to design attitude, fixes after-pouring coagulation Soil, the construction quality requirement in mountain highway Lin Ya or the section that borders on the river structure gravity retaining wall, the enough maximums of and can either be met The generation of the reduction security incident of limit, additionally it is possible to improve construction speed, shorten construction period, additionally due to aluminum alloy mould plate has There is in light weight, the advantage such as big, easy moulding and energy-conserving and environment-protective of intensity, therefore make the convenient construction of highway gravity retaining wall, engineering Quality is high, avoids phenomenon of caving in, and need not consume timber resources, has the beneficial effect of energy-conserving and environment-protective.The present invention is implemented Mode methods described process is simple, is easy to construct, suitable for the popularization and application in highway engineering.
Alternatively, it is corresponding according to the center line and longitudinal and transverse axis of design drawing and slab culvert in random sample unwrapping wire step The orientation axis (i.e. center line and longitudinal and transverse axis) of actual retaining wall is released, foundation ditch setting-out is carried out with total powerstation, steel ruler.Foundation ditch Control stake is set before excavation, on longitudinal and transverse axis and beyond foundation ditch side column, and often place sets at least two, checks during for constructing Setting-out, after each orientation axis is qualified by inspection, then carry out excavation of foundation pit step.
Alternatively, in excavation of foundation pit step, first excavated using excavator, excavation slope 1:1, the earthwork is dug to distance and designed During bottom of foundation ditch 20-30cm, manual cleaning is used instead to the elevation location for designing bottom of foundation ditch, so as to prevent ground soil property quilt Disturbance.After manual cleaning, a small amount of rock excavation is cleared up using machine gun head is excavated, then smooth to setting with gravel place mat Count elevation location.It is compacted with Small Tamping Machine, then examines foundation bearing capacity, subsequent construction is carried out again after qualified.
Alternatively, retaining wall substrate sets 1:5 adverse grade, strict slope during construction, retaining wall buried depth are at wall location After clear table below above-ground route >=1m, so as to ensure the stability of retaining wall side slope.
Alternatively, before base concrete pours after foundation ditch is dug, along retaining walls line embedded bar or slabstone at one's side, from And positioning action can be played to earth-retaining wall form;Construction joint does dabbing processing, treats that base concrete intensity reaches more than 75% When, then erect earth-retaining wall form.
Alternatively, in order to ensure wall body Side shuttering Zhi Li stability, aluminium alloy mould that embodiment of the present invention provides Construction method of the plate as highway gravity retaining wall template, in retaining wall construction procedure, the both sides of wall body Side shuttering are equal Fixed using steel pipe support, and steel pipe support is linked to be entirety, the inside of wall body Side shuttering is fixed using wall-through pull rod.
Alternatively, a diameter of 14mm of wall-through pull rod, arranged according to spacing 50cm blossom type.
Alternatively, in order to ensure even support wall body Side shuttering, template local deformation amount, embodiment of the present invention are reduced In construction method of the aluminum alloy mould plate of offer as highway gravity retaining wall template, the cross bar spacing of steel pipe support is 45- 55cm, montant spacing are 75-85cm;Bridging is provided with steel pipe support, the spacing of bridging is 1.5-2.5m.Specifically, Bridging is arranged on base concrete face.Because the cross bar spacing and montant spacing of steel pipe support are fixed dimension, therefore energy Enough ensure to play a part of even support to wall body Side shuttering between steel pipe, simultaneously because being provided with the scissors of constant spacing Support, therefore the effect for strengthening the support of steel pipe support longitudinal rigid can be realized.
Alternatively, the cross bar spacing of steel pipe support it is typical but it is non-limiting for 45cm, 46cm, 47cm, 48cm, 49cm, 50cm, 51cm, 52cm, 53cm, 54cm or 55cm;The montant spacing of steel pipe support it is typical but it is non-limiting for 75cm, 76cm, 77cm, 78cm, 79cm, 80cm, 81cm, 82cm, 83cm, 84cm or 85cm;The spacing of bridging be 1.5m, 1.7m, 1.9m, 2.0m, 2.2m, 2.4m or 2.5m.
Preferably, the cross bar spacing of steel pipe support is 50cm, and the montant spacing of steel pipe support is 80cm;The spacing of bridging For 2.0m.
In the present invention, bridging refers to playing steel pipe support the structure of longitudinal stability effect, shape and scissors phase Seemingly.Specifically, bridging, which must prop up, stands on base concrete face, and steel pipe support branch stands in stable position, it is impossible to directly props up Stand on the soil body.
Alternatively, in order to improve the stability of wall body Side shuttering internal structure, earth-retaining wall thickness uniformity is ensured, together When preventing casting concrete spillage dusting phenomenon, the aluminum alloy mould plate that embodiment of the present invention provides is as highway gravity type In the construction method of earth-retaining wall form, wall-through pull rod is fed through pvc pipe and both ends are connected on wall body Side shuttering, wears The spacing of wall pull bar is 45-55cm;The both ends of pvc pipe pass wall body Side shuttering 1-2cm and pvc pipe and wall body Side shuttering Junction cemented with adhesive tape.During installation, according to the setting spacing of wall-through pull rod, bored in position corresponding to wall body Side shuttering 1mm bigger than pvc pipe circular hole is taken, the internal diameter of pvc pipe is bigger 2-3mm than wall-through pull rod, therefore is easy to wall-through pull rod to be fed through PVC Pipe.Because the both ends of pvc pipe pass wall body Side shuttering 1-2cm, junction is cemented with adhesive tape, and adhesive tape avoids wrinkling, because The both ends of this pvc pipe can be fixed on wall body Side shuttering, while the problem of can effectively avoid spillage dusting.
Alternatively, the spacing of wall-through pull rod it is typical but it is non-limiting for 45cm, 46cm, 47cm, 48cm, 49cm, 50cm, 51cm, 52cm, 53cm, 54cm or 55cm.
Alternatively, in order to realize firmly assembling earth-retaining wall form purpose, embodiment of the present invention provide aluminium alloy mould In construction method of the plate as highway gravity retaining wall template, end head formwork squeezes with wall body front face template and wall body Side shuttering Fixed tightly and with connector, the junction patch double faced adhesive tape of two neighboring template;After wall body front face template and end head formwork installation Supported with steel pipe support.Specifically, the wall body overlap joint certain length with having poured is needed when wall body front face template is installed, first to taking Junction is handled so that surfacing, ensures that wall body vertically and without cut, is then being installed just in new walling body overlap joint incline angle of pouring Face die plate, and supported with steel pipe support.End head formwork is assembled using aluminum alloy mould plate, and with wall body front face template and wall body side Template jam-packed, because double faced adhesive tape is pasted in the junction of two neighboring template, therefore it is capable of the phenomenon of effective mortar leakage prevention, so as to avoid Voids and pits or undisguised phenomenon;Supported after end head formwork installation with steel pipe support, can ensure that end head formwork Zhi Li get is firm vertically Gu.
Alternatively, in order to prevent phenomenon that earth-retaining wall form floats in work progress, what embodiment of the present invention provided Construction method of the aluminum alloy mould plate as highway gravity retaining wall template, in retaining wall construction procedure, is provided with ground Built-in fitting, wall body Side shuttering, wall body front face template and end head formwork are connected with built-in fitting by steel wire rope;Wall body side mould After plate, wall body front face template and end head formwork are spliced into earth-retaining wall form and installation, in the external coating of earth-retaining wall form Releasing agent.
Alternatively, it is reinforcing bar earth anchor that built-in fitting is typical but non-limiting.
Alternatively, it is easy to the purpose of layer and section casting concrete to realize, the aluminium that embodiment of the present invention provides closes In construction method of the golden template as highway gravity retaining wall template, the inside of earth-retaining wall form is also provided with passage mould Plate, passage template be used for by earth-retaining wall form inside points it is intersegmental every;During passage formwork support arrangement, by the upper strata subsiding crack of retaining wall with Its settlement joints is arranged on same vertical curve;Separated in the subsiding crack of upper strata and in settlement joints with bamboo slab rubber.It is optional Ground, passage template are plane template, are advantageously implemented the effect of layer and section casting concrete;Because the upper strata of retaining wall settles Seam is arranged on same vertical curve with its settlement joints, and in the subsiding crack of upper strata and in settlement joints with bamboo slab rubber every Open, therefore can ensure that retaining wall has independent free settling unit after the completion of construction, avoid the inequality in vertical direction Even sedimentation causes to have a strong impact on to retaining wall structure.
Alternatively, it is mixed being poured into earth-retaining wall form in order to prevent the wall body bottom of retaining wall from cellular phenomenon occur Template bottom is blocked with cement mortar before solidifying soil, casting concrete again after after cement mortar solidification and there is some strength.
Alternatively, after the completion of retaining wall model sheetinstallat, it is necessary to the stability of close inspection steel pipe support and each template, together When check inside dimension, vertical degree and the flatness of template, adjustment amendment in time to carrying out subsequent construction after qualified again.
Alternatively, in order to ensure retaining wall has a preferable construction quality, and embodiment of the present invention provides aluminium alloy mould Construction method of the plate as highway gravity retaining wall template, in retaining wall construction procedure, poured after earth-retaining wall form is fixed Build concrete;From one end of earth-retaining wall form to other end layer and section casting concrete in the horizontal direction, lift height≤ 30cm;Before laying first layer stone, the thick concrete of 10-15cm is first poured, lays stone, then casting concrete then up; The spacing of adjacent stone is 8-12cm, stone and earth-retaining wall form spacing >=15cm, and the top surface of the superiors' stone covers coagulation Thickness >=10cm of soil;Correlate template is removed after concrete strength reaches requirement.
Alternatively, concrete is uniform by concentrated compactness in mixing plant, and job site is transported to by concrete tank.Coagulation Soil is vibrated after pouring using plug-in type vibrating rod, and the mobile spacing of vibrating head is not less than 1.5 times of vibrating head operating radius, vibration The depth of rod insertion lower-layer concrete is 50-100mm.The distance of vibrating head and earth-retaining wall form is 50-100mm when vibrating, with Prevent from hitting earth-retaining wall form.Sinking and effervescent are occurred without with concrete surface during concrete vibrating, surface is flat to be advisable, and one Place slowly lifts vibrating head after the completion of vibrating in region and moves on to next place region again.In concreting process, workmen should and When make an inspection tour earth-retaining wall form, if casting concrete should be stopped immediately by anomaly occur, be further continued for constructing after problem to be solved.
Alternatively, when retaining wall is constructed, free from flaw, the stone without interlayer and non-strip of sheet, the compressive ultimate of stone are selected Intensity is not less than 30MPa, and the size of stone is preferably 15-30cm, needs to rinse stone well before use.Into earth-retaining wall form When inserting stone, make the big face-down of stone.Stone at horizontal joint exposes about the 1/2 of its area, to ensure that interlayer is preferable Connection effect.
Alternatively, start covering watering maintenance after the concrete final set in earth-retaining wall form, set special messenger to pinpoint watering, support Protect at least 7 days time.Treat that concrete strength reaches more than the 75% of design requirement again by form removable.Acted to the greatest extent during form removal Amount is treated without proper respect, to avoid the surface of wall body concrete from being collided, ensures the integrality of corner angle.Pvc pipe outside wall-through pull rod exists Both ends finishing is concordant after form removal, first with reinforcing bar through hole, then clogs the cement mortar with wall body concrete with label, and smash with reinforcing bar It is real.The outside 2-3cm cement mortar in hole corresponding to wall-through pull rod is floating on retaining wall, makes surfacing closely knit, then by hole Cement mortar around hole is cleaned out.After the concreting of every section of wall body terminates, the necessary fixation of built-in fitting, retaining wall Top surface receive slurry plucking after sprinkle water covering curing.Wall is covered with geotextiles in time after retaining wall form removable, it is complicated by special messenger Watering health.
Alternatively, construction party of the aluminum alloy mould plate that embodiment of the present invention provides as highway gravity retaining wall template Method, in wall carries on the back refilling step, backfilled using placement in layers compacting mode.Specifically, design requirement is reached in concrete strength When, the wall back of the body is backfilled in time.Backfilling material uses coarse grain dank material, it is typical but it is non-limiting be gravel, rubble or slag.Return Filling chock material avoids being mingled with wood chip, tree root or weeds, forbids to use mud, fertile soil or swelled ground.
Embodiment of the present invention also provides a kind of retaining wall, and the retaining wall is using above-mentioned aluminum alloy mould plate as highway gravity The construction method of formula earth-retaining wall form obtains.
The retaining wall that embodiment of the present invention provides both has firm solid internal structure, have again it is smooth it is attractive in appearance outside Table, interior reality are outer beautiful, disclosure satisfy that mountain highway Lin Ya or a section requirement for gravity retaining wall construction quality of bordering on the river, construct cost compared with It is low, realize the effect of permanent bank protection safe edge.
With reference to concrete engineering example, to aluminum alloy mould plate provided by the invention as highway gravity retaining wall template Construction method elaborate.
It is mainly slabstone concrete retaining wall that somewhere highway, which faces precipice danger section subgrade protection project, the construction length of retaining wall For 88m, walls concrete includes C15 piece stone concretes 553.8m3, C20 piece stone concretes 2535.8m3
Earth-retaining is constructed according to construction method of the aluminum alloy mould plate provided by the invention as highway gravity retaining wall template Wall, comprise the following steps:
(1) random sample unwrapping wire step, it is corresponding to release reality according to the center line and longitudinal and transverse axis of design drawing and slab culvert The orientation axis (i.e. center line and longitudinal and transverse axis) of retaining wall, foundation ditch setting-out is carried out with total powerstation, steel ruler;On longitudinal and transverse axis And control stake is set beyond foundation ditch side column, often place sets at least two, checks setting-out during for constructing, by inspection each orientation axis After qualified, then carry out excavation of foundation pit step;
(2) excavation of foundation pit step, first excavated using excavator, excavation slope 1:1, the earthwork is dug to distance design foundation ditch bottom During portion 20-30cm, the elevation location that manual cleaning extremely designs bottom of foundation ditch is used instead,;After manual cleaning, a small amount of rock excavation Cleared up using machine gun head is excavated, it is then smooth to designed elevation position with gravel place mat;Pressed with Small Tamping Machine It is real, foundation bearing capacity is then examined, subsequent construction is carried out again after qualified;
(3) retaining wall construction procedure, the quality of aluminum alloy mould plate is first examined, it is desirable to any surface finish, smooth, all lines horizontal strokes Flat vertical, panel flatness meets to require, prior assembled aluminum alloy mould plate simultaneously checks the situation of connecting sewing, is lifted after passed examination To design attitude;Multiple reinforcing bar earth anchors are set on the ground of retaining wall, are respectively used to anchor connection end head formwork, wall body front Template and wall body Side shuttering;According to the design spacing of wall-through pull rod, drilled through in the relevant position of wall body Side shuttering and compare pvc pipe Big 1mm circular hole;Wall body Side shuttering is fixed using the method for " being supportted outside interior drawing ", and steel pipe support, and steel are set up on the outside of template Pipe holder is linked to be entirety, and the cross bar spacing of steel pipe support is 50cm, and montant spacing is 80cm, and one of bridging is set every 2m; The inside of wall body Side shuttering is fixed using wall-through pull rod, a diameter of 14mm of wall-through pull rod, according to spacing 50cm blossom type Arrangement, wall-through pull rod are fed through pvc pipe, and the length of pvc pipe passes template both sides 1-2cm, and junction is used around pvc pipe and template Adhesive tape cements, and avoids adhesive tape from wrinkling;The wall body overlap joint certain length with having poured is needed when wall body front face template is installed, first Faying surface is handled, makes surfacing, and overlaps incline angle vertically without cut, wall body front face template is then assembled, is used in combination Steel pipe support supports;End head formwork is assembled using aluminum alloy mould plate, and with wall body front face template and wall body Side shuttering jam-packed, use Connector locks, and the junction patch double faced adhesive tape of two neighboring template, is also supported after end head formwork installation using steel pipe support;Wall body Side shuttering, wall body front face template and end head formwork are connected with reinforcing bar earth anchor by steel wire rope;Wall body Side shuttering, wall body are just After face die plate and end head formwork are spliced into earth-retaining wall form and installation, in the external coating releasing agent of earth-retaining wall form;Gear The inside of cob wall template also sets up passage template, during passage formwork support arrangement, by the upper strata subsiding crack of retaining wall and its foundation settlement Seam is arranged on same vertical curve, is separated in the subsiding crack of upper strata and in settlement joints with the thick bamboo slab rubbers of 2cm;Model sheetinstallat Pacify into the stability of rear inspection support and template, while check inside dimension, vertical degree and the flatness of template, meet after requiring Subsequent construction is carried out again;Earth-retaining wall form is fixed into after-pouring concrete, it is horizontal from one end of earth-retaining wall form to other end edge Direction layer and section casting concrete, lift height≤30cm, before laying first layer stone, first pour the thick coagulations of 10-15cm Soil, stone, then casting concrete is laid then up, the spacing of adjacent stone is 8-12cm, between stone and earth-retaining wall form Away from >=15cm, thickness >=10cm of the top surface oversite concrete of the superiors' stone, phase is removed after concrete strength reaches requirement Close template;
(4) in wall back of the body refilling step, wall is backfilled by the way of gravel, rubble and slag carry out placement in layers and are compacted The back of the body.
To being tested after the completion of engineering, it is as shown in table 1 that measured result is carried out to cast-in-place retaining wall.
1 cast-in-place retaining wall of table surveys project and testing result
It is actually detected by being carried out to cast-in-place retaining wall, the results showed that aluminum alloy mould plate of the present invention is kept off as highway gravity type The scientific construction of cob wall template is reasonable, and the Retaining Wall Engineering quality constructed using this method disclosure satisfy that requirement.
In addition, it is to the outward appearance qualification result of retaining wall:1) concrete construction joint smoothes out, and honeycomb and pitted skin area do not surpass Cross the 0.5% of the face area;2) concrete surface is without nonconservative scheme;3) subsiding crack is neatly vertical, up/down perforation.Outward appearance is identified As a result further demonstrate that construction quality meets to require.
Although illustrate and describing the present invention with embodiment and embodiment, but it will be appreciated that and do not carrying on the back In the case of from the spirit and scope of the present invention, many other change and modification can be made.It is, therefore, intended that appended Claim includes belonging to all such changes and modifications in the scope of the invention.

Claims (10)

1. construction method of a kind of aluminum alloy mould plate as highway gravity retaining wall template, it is characterised in that including following step Suddenly:
Random sample unwrapping wire step, the center line and horizontal stroke, longitudinal axis of retaining wall are released according to design requirement, and are entered with total powerstation, steel ruler Row foundation ditch setting-out;
Excavation of foundation pit step, using the artificial digging mode for combining excavator, excavator first excavates, and then manual cleaning bottom land is extremely Designed elevation, bearing capacity examination is carried out after cleaning out;
Retaining wall construction procedure, as wall body Side shuttering, wall body after the aluminum alloy mould plate of acceptance(check) is cleaned out Front face template and end head formwork, each corresponding template is then propped up into vertical and merogenesis and is assembled into earth-retaining wall form, then be lifted into design position Put place, fixation after-pouring concrete;
Wall carries on the back refilling step, and backfill wall is carried on the back in time after concrete strength reaches design requirement.
2. construction method of the aluminum alloy mould plate according to claim 1 as highway gravity retaining wall template, its feature It is, in retaining wall construction procedure, the both sides of the wall body Side shuttering are fixed using steel pipe support, and steel pipe support connects Integral, the inside of the wall body Side shuttering is fixed using wall-through pull rod.
3. construction method of the aluminum alloy mould plate according to claim 2 as highway gravity retaining wall template, its feature It is, the cross bar spacing of the steel pipe support is 45-55cm, and montant spacing is 75-85cm;
Bridging is provided with the steel pipe support, the spacing of the bridging is 1.5-2.5m.
4. construction method of the aluminum alloy mould plate according to claim 3 as highway gravity retaining wall template, its feature It is, the wall-through pull rod is fed through pvc pipe and both ends are connected on the wall body Side shuttering, the wall-through pull rod Spacing be 45-55cm;
The both ends of the pvc pipe pass the wall body Side shuttering 1-2cm and the pvc pipe and the wall body Side shuttering Junction is cemented with adhesive tape.
5. construction method of the aluminum alloy mould plate as highway gravity retaining wall template according to claim 1 or 4, it is special Sign is, the end head formwork and the wall body front face template and the wall body Side shuttering jam-packed are simultaneously fixed, phase with connector The junction patch double faced adhesive tape of adjacent two templates;
Supported after the wall body front face template and end head formwork installation with steel pipe support.
6. construction method of the aluminum alloy mould plate according to claim 5 as highway gravity retaining wall template, its feature Be, in retaining wall construction procedure, built-in fitting be set on ground, the wall body Side shuttering, the wall body front face template and The end head formwork is connected with the built-in fitting;
The wall body Side shuttering, the wall body front face template and the end head formwork are spliced into earth-retaining wall form and installation Afterwards, in the external coating releasing agent of the earth-retaining wall form.
7. construction method of the aluminum alloy mould plate according to claim 6 as highway gravity retaining wall template, its feature It is, the inside of the earth-retaining wall form is additionally provided with passage template, and the passage template is used in the earth-retaining wall form Segment section interval;
During the passage formwork support arrangement, the upper strata subsiding crack of retaining wall and its settlement joints are arranged on same vertical curve;
Separated in the upper strata subsiding crack and in the settlement joints with bamboo slab rubber.
8. construction method of the aluminum alloy mould plate according to claim 7 as highway gravity retaining wall template, its feature It is, in retaining wall construction procedure, the earth-retaining wall form is fixed into after-pouring concrete;By the one of the earth-retaining wall form Hold to other end layer and section casting concrete in the horizontal direction, lift height≤30cm;
Before laying first layer stone, the thick concrete of 10-15cm is first poured, lays stone, then casting concrete then up;Phase The spacing of adjacent stone is 8-12cm, spacing >=15cm of stone and earth-retaining wall form, the top surface oversite concrete of the superiors' stone Thickness >=10cm;
Correlate template is removed after concrete strength reaches requirement.
9. construction method of the aluminum alloy mould plate according to claim 1 as highway gravity retaining wall template, its feature It is, in wall carries on the back refilling step, is backfilled using placement in layers compacting mode.
10. a kind of retaining wall, it is characterised in that using any one of the claim 1-9 aluminum alloy mould plates as highway gravity The construction method of formula earth-retaining wall form obtains.
CN201710650272.XA 2017-08-01 2017-08-01 Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template Pending CN107366303A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710650272.XA CN107366303A (en) 2017-08-01 2017-08-01 Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710650272.XA CN107366303A (en) 2017-08-01 2017-08-01 Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template

Publications (1)

Publication Number Publication Date
CN107366303A true CN107366303A (en) 2017-11-21

Family

ID=60309422

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710650272.XA Pending CN107366303A (en) 2017-08-01 2017-08-01 Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template

Country Status (1)

Country Link
CN (1) CN107366303A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859058A (en) * 2017-12-17 2018-03-30 北京市政路桥股份有限公司 A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN111663564A (en) * 2020-06-03 2020-09-15 安徽省交通规划设计研究总院股份有限公司 UHPC-C environment-friendly retaining wall and construction method thereof
CN112431220A (en) * 2020-11-12 2021-03-02 中国铁道科学研究院集团有限公司铁道建筑研究所 Retaining wall using waste concrete sleeper and construction method thereof
CN114059582A (en) * 2021-11-19 2022-02-18 北京城建集团有限责任公司 Construction process of irregular-shaped gravity retaining wall

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5078360A (en) * 1989-12-22 1992-01-07 Speral Aluminium Inc. Prefabricated assembly for poured concrete forming structures
CN103206089A (en) * 2013-04-18 2013-07-17 成军 Fabricated aluminum alloy formwork system construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5078360A (en) * 1989-12-22 1992-01-07 Speral Aluminium Inc. Prefabricated assembly for poured concrete forming structures
CN103206089A (en) * 2013-04-18 2013-07-17 成军 Fabricated aluminum alloy formwork system construction method

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
徐冬雪等: "地铁深基坑高模架单侧模板施工设计分析", 《现代城市轨道交通》 *
汪孟雷等: "浅谈道路挡土墙的施工", 《黑龙江科技信息》 *
王芝兴: "高速公路大型挡土墙的施工", 《中国西部科技》 *
甘钊南: "水工挡土墙设计体会", 《黑龙江科技信息》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107859058A (en) * 2017-12-17 2018-03-30 北京市政路桥股份有限公司 A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN111663564A (en) * 2020-06-03 2020-09-15 安徽省交通规划设计研究总院股份有限公司 UHPC-C environment-friendly retaining wall and construction method thereof
CN112431220A (en) * 2020-11-12 2021-03-02 中国铁道科学研究院集团有限公司铁道建筑研究所 Retaining wall using waste concrete sleeper and construction method thereof
CN112431220B (en) * 2020-11-12 2022-06-10 中国铁道科学研究院集团有限公司铁道建筑研究所 Retaining wall using waste concrete sleeper and construction method thereof
CN114059582A (en) * 2021-11-19 2022-02-18 北京城建集团有限责任公司 Construction process of irregular-shaped gravity retaining wall

Similar Documents

Publication Publication Date Title
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104846810B (en) Self-circulating posterior grouting bored pile construction method
CN104264688B (en) Manually digging hole non-uniform pile support construction process
CN106958256B (en) A caisson construction technology with layered pouring and multiple subsidence
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN106088127A (en) Open caisson construction method
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN109505229A (en) Highway high gradient slope stress equilibrium and vibration damping are taken precautions against natural calamities high bridge pier structure and construction method
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN102071698B (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN102926398A (en) Construction method of inclined column type corrosion resistant foundation for power line in salt lake area
CN111119128B (en) A kind of natural rockfill dam in dammed lake, reinforcement and anti-seepage method
CN110106889A (en) A kind of deep basal pit perfusion slope protection pile adds cable bolting construction
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN118110193A (en) The whole process construction method of large diameter caisson in complex geological conditions
CN106013171A (en) Semi-rigid and semi-flexible support structure and method for deep foundation pit side wall
CN109706952A (en) Large-scale well-sinking construction method
CN107366303A (en) Construction method and retaining wall of the aluminum alloy mould plate as highway gravity retaining wall template
CN107964980A (en) Lattice counterfort wall and construction method with earth anchor
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN109653223A (en) River anti-floating weighting board construction method
CN105926667A (en) Retaining wall
CN108952766A (en) The construction method of Tunnel Passing karst location punishment
CN104963348B (en) Soft soil area tower crane foundation construction supporting structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 210000 4, building 223, Shui Simen street, Jianye District, Nanjing, Jiangsu.

Applicant after: Jiangsu Yan Ning Engineering Science and Technology Group Co., Ltd.

Address before: 210000 4, building 223, Shui Simen street, Jianye District, Nanjing, Jiangsu.

Applicant before: Jiangsu Yearning Construction Co., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20171121