CN107103078A - 基于bim的变电站建设全周期数字化管控系统 - Google Patents
基于bim的变电站建设全周期数字化管控系统 Download PDFInfo
- Publication number
- CN107103078A CN107103078A CN201710278066.0A CN201710278066A CN107103078A CN 107103078 A CN107103078 A CN 107103078A CN 201710278066 A CN201710278066 A CN 201710278066A CN 107103078 A CN107103078 A CN 107103078A
- Authority
- CN
- China
- Prior art keywords
- bim
- data
- 3dgis
- module
- management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F16/00—Information retrieval; Database structures therefor; File system structures therefor
- G06F16/20—Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
- G06F16/26—Visual data mining; Browsing structured data
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING OR CALCULATING; COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Strategic Management (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Economics (AREA)
- Physics & Mathematics (AREA)
- Tourism & Hospitality (AREA)
- Databases & Information Systems (AREA)
- Health & Medical Sciences (AREA)
- Marketing (AREA)
- General Business, Economics & Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Data Mining & Analysis (AREA)
- Quality & Reliability (AREA)
- General Engineering & Computer Science (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
本发明公开了一种基于BIM的变电站建设全周期数字化管控系统,包括变电站三维模型和协同管理平台,所述协同管理平台包括数据输入模块、数据采集模块、数据库、3DGIS+BIM平台、交互模块和综合应用模块;所述数据输入模块用于输入变电站建设用输入类数据;所述数据采集模块用于采集变电站建设用采集类数据;所述3DGIS+BIM平台利用所述数据库中存储的各类数据搭建所述变电站三维模型;所述交互模块实现与所述3DGIS+BIM平台之间的信息交互和指令交互;所述3DGIS+BIM平台根据控制指令调取所述综合应用模块进行相应操作。从而对变电站整个建设过程实现可靠而准确的控制和管理。
Description
技术领域
本发明涉及变电站建设管控系统。
背景技术
近年来,公司输变电工程投资逐年增加,电网建设任务很重。从500千伏、220千伏高电压等级到110千伏及以下电压等级,每年都有几十个输变电工程项目施工建设。输变电工程项目具有公用事业的特殊性,项目能否按照计划建成投运,将直接影响到社会用电,所以输变电工程在建设工期上往往很紧。同时,由于新建变电站体现出小型化、非典型化的技术特点。一方面,要在狭小的工程场地内安排土建、电气之间的交叉作业,对施工工序、大型设备吊装等进行精细的事前筹谋和策划;另一方面,要综合处理噪声、粉尘、垃圾、污水等环境问题,在规划设计之初就对选址方案进行细致的评估和分析。
电力设计院普遍采用的二维设计手段来完成设计工作,单纯依靠工程师的空间想象力和基本制图技能完成空间设计,带有局限性和特殊性,尤其对详细布置的经济性和优化缺乏控制,不能很好地满足电力公司变电站全寿命周期管理的需求。此外,目前计师50%以上的工作量用在施工图阶段,以至于设计师被称为“画图匠”,而无法将主要精力放在初步设计阶段,这导致后期需要通过设计变更优化方案,造成工期延误、质量难以保障。
公司参与输变电工程项目管理的机构和部门众多,造成工程建设管理的信息零碎化,使工程进度、质量、风险难以把控。在工程项目的建设过程中,设计、施工和运营过程基本相互隔绝,缺少一种共同的交互平台,形成一个个信息孤岛,造成信息无序流动,引起信息流失与失真,严重阻碍工程建设。此外,工程建设管理工作繁杂、覆盖面广,目前项目进展主要依赖以文字、图表形式表达的周报、月报体现,难以全面、直观地反映现场作业信息,难以方便、快捷地获取项目投资、质量、安全等信息,依赖人工的跟踪检查也难以保障信息被及时高效地处理,严重影响了工作的效率和成效。
综上,传统的工程管理方法难以应对变电站建设的这些新特点,进行改革与创新势在必行。
发明内容
本发明的目的在于提供基于BIM(建筑信息模型)的变电站建设全周期数字化管控系统,对变电站整个建设过程实现可靠而准确的控制和管理。
实现上述目的的技术方案是:
一种基于BIM的变电站建设全周期数字化管控系统,包括变电站三维模型和协同管理平台,所述协同管理平台包括数据输入模块、数据采集模块、数据库、3DGIS(三维GIS,GIS表示地理信息系统)+BIM平台、交互模块和综合应用模块;
所述数据输入模块用于输入变电站建设用输入类数据至所述数据库;
所述数据采集模块用于采集变电站建设用采集类数据至所述数据库;
所述3DGIS+BIM平台利用所述数据库中存储的各类数据搭建所述变电站三维模型;
所述交互模块一方面通过所述3DGIS+BIM平台调取所述变电站三维模型的各类信息进行显示,另一方面发送各类控制指令给所述3DGIS+BIM平台;
所述3DGIS+BIM平台根据控制指令调取所述综合应用模块进行相应操作。
在上述的基于BIM的变电站建设全周期数字化管控系统中,还包括连接所述3DGIS+BIM平台的通信模块,以及无线连接所述通信模块的移动终端,
所述移动终端一方面通过所述通信模块和所述3DGIS+BIM平台调取所述变电站三维模型的各类信息进行显示,另一方面通过所述通信模块发送各类控制指令给所述3DGIS+BIM平台;
所述3DGIS+BIM平台根据控制指令调取所述综合应用模块进行相应操作。
在上述的基于BIM的变电站建设全周期数字化管控系统中,所述数据库中存储的数据包括地理空间数据、动态监测数据和应用业务数据;
所述变电站建设用输入类数据包括地理空间数据和应用业务数据;
所述变电站建设用采集类数据包括动态监测数据。
在上述的基于BIM的变电站建设全周期数字化管控系统中,所述综合应用模块包括以下功能:项目总览、设计管理、施工组织、进度管理、安全管理、质量管理、风险管理、投资管理、系统管理和移动端管理。
本发明的有益效果是:本发明以统一规范的数字化标准和物联网、云计算、大数据等技术为基础,通过构建变电站三维模型和协同管理平台,有力支撑项目进度、质量、安全、技术、成本的管理控制,实现三维的、集成的、智能的、实时的项目管理新模式,以保障工程项目按时保质保量完成。
附图说明
图1是本发明的变电站建设全周期数字化管控系统的结构图。
具体实施方式
下面将结合附图对本发明作进一步说明。
本发明的基于BIM的变电站建设全周期数字化管控系统,以“数字化标准”和“先进技术”为基础,以“变电站建模”和“协同管理平台”为支撑,以“三维的、集成的、智能的、实时的”为特征,能够有效提高工程建设的数字化水平,使各参建方在统一的平台上,基于全面共享的信息进行协同项目管理,有利于促进项目效率和质量的提高。
请参阅图1,基于BIM的变电站建设全周期数字化管控系统包括变电站三维模型1和协同管理平台2,协同管理平台2包括数据输入模块21、数据采集模块22、数据库23、3DGIS+BIM平台24、交互模块25、综合应用模块26、通信模块27和移动终端28。
数据输入模块21用于输入变电站建设用输入类数据至数据库23,变电站建设用输入类数据包括地理空间数据和应用业务数据。地理空间数据包括构建整个数字地球三维场景的各类基础数据:遥感影像数据,矢量地图数据,数字高程模型数据,BIM模型数据库,建筑三维数据库等。应用业务数据包括系统管理和业务应用产生的各类数据。
数据采集模块22用于采集变电站建设用采集类数据至数据库23,变电站建设用采集类数据包括动态监测数据,具体指各类传感器、二维码信息的采集获取等。
3DGIS+BIM平台24利用数据库23中存储的各类数据搭建变电站三维模型1。
交互模块25一方面通过3DGIS+BIM平台24调取变电站三维模型1的各类信息进行显示,另一方面发送各类控制指令给3DGIS+BIM平台24。
移动终端28一方面通过通信模块27和3DGIS+BIM平台24调取变电站三维模型1的各类信息进行显示,另一方面通过通信模块27发送各类控制指令给3DGIS+BIM平台24。
3DGIS+BIM平台24根据控制指令调取综合应用模块26进行相应操作。综合应用模块26能够调用以下功能:项目总览、设计管理、施工组织、进度管理、安全管理、质量管理、风险管理、投资管理、系统管理和移动端管理。
综上,贯穿于变电站建设全周期,实现整体的数字化管控,使各参建方在统一的平台上,基于全面共享的信息进行协同项目管理,有利于促进项目效率和质量的提高。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。
Claims (4)
1.一种基于BIM的变电站建设全周期数字化管控系统,其特征在于,包括变电站三维模型和协同管理平台,所述协同管理平台包括数据输入模块、数据采集模块、数据库、3DGIS+BIM平台、交互模块和综合应用模块;
所述数据输入模块用于输入变电站建设用输入类数据至所述数据库;
所述数据采集模块用于采集变电站建设用采集类数据至所述数据库;
所述3DGIS+BIM平台利用所述数据库中存储的各类数据搭建所述变电站三维模型;
所述交互模块一方面通过所述3DGIS+BIM平台调取所述变电站三维模型的各类信息进行显示,另一方面发送各类控制指令给所述3DGIS+BIM平台;
所述3DGIS+BIM平台根据控制指令调取所述综合应用模块进行相应操作。
2.根据权利要求1所述的基于BIM的变电站建设全周期数字化管控系统,其特征在于,还包括连接所述3DGIS+BIM平台的通信模块,以及无线连接所述通信模块的移动终端,
所述移动终端一方面通过所述通信模块和所述3DGIS+BIM平台调取所述变电站三维模型的各类信息进行显示,另一方面通过所述通信模块发送各类控制指令给所述3DGIS+BIM平台;
所述3DGIS+BIM平台根据控制指令调取所述综合应用模块进行相应操作。
3.根据权利要求1或2所述的基于BIM的变电站建设全周期数字化管控系统,其特征在于,所述数据库中存储的数据包括地理空间数据、动态监测数据和应用业务数据;
所述变电站建设用输入类数据包括地理空间数据和应用业务数据;
所述变电站建设用采集类数据包括动态监测数据。
4.根据权利要求1或2所述的基于BIM的变电站建设全周期数字化管控系统,其特征在于,所述综合应用模块包括以下功能:项目总览、设计管理、施工组织、进度管理、安全管理、质量管理、风险管理、投资管理、系统管理和移动端管理。
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710278066.0A CN107103078A (zh) | 2017-04-25 | 2017-04-25 | 基于bim的变电站建设全周期数字化管控系统 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710278066.0A CN107103078A (zh) | 2017-04-25 | 2017-04-25 | 基于bim的变电站建设全周期数字化管控系统 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN107103078A true CN107103078A (zh) | 2017-08-29 |
Family
ID=59657683
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710278066.0A Pending CN107103078A (zh) | 2017-04-25 | 2017-04-25 | 基于bim的变电站建设全周期数字化管控系统 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN107103078A (zh) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107527155A (zh) * | 2017-09-06 | 2017-12-29 | 北京北控建设发展有限公司 | 建设项目监管系统 |
| CN107562962A (zh) * | 2017-10-12 | 2018-01-09 | 国网上海市电力公司 | 一种基于bim的变电站信息监测管理系统 |
| CN107680002A (zh) * | 2017-09-27 | 2018-02-09 | 国网上海市电力公司 | 一种基于gis和bim的电力设施信息化系统 |
| CN107862153A (zh) * | 2017-11-23 | 2018-03-30 | 国网上海市电力公司 | 一种变电站数字化管控系统 |
| CN109345209A (zh) * | 2018-11-21 | 2019-02-15 | 国网河北省电力有限公司建设公司 | 一种500kV变电站的可视化施工管理方法及装置 |
| CN111126838A (zh) * | 2019-12-23 | 2020-05-08 | 广东电网有限责任公司 | 一种智慧工程管理系统 |
| CN111597666A (zh) * | 2020-05-20 | 2020-08-28 | 佛山电力设计院有限公司 | 一种将bim应用到变电站建设过程的方法 |
| CN111709123A (zh) * | 2020-05-26 | 2020-09-25 | 国网江苏省电力有限公司南通供电分公司 | 基于bim技术的变电站工程实施现场物料数字化管理系统 |
| CN112769237A (zh) * | 2020-12-31 | 2021-05-07 | 长园深瑞继保自动化有限公司 | 变电站数字孪生系统 |
| CN114372307A (zh) * | 2021-12-30 | 2022-04-19 | 国网江苏省电力工程咨询有限公司 | 一种面向电力变电站基于bim+gis技术的施工管理系统及方法 |
| CN114969908A (zh) * | 2022-05-17 | 2022-08-30 | 武汉联动设计股份有限公司 | 一种基于BIM模型的220kv全户内变电站数字化模拟测试系统 |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
| US20140214220A1 (en) * | 2011-06-15 | 2014-07-31 | Expanergy, Llc | Systems and methods to assess and optimize energy usage for a facility |
| CN104680331A (zh) * | 2015-03-18 | 2015-06-03 | 国网上海市电力公司 | 一种基于ifc的输变电工程三维数字化管理平台 |
| CN104835079A (zh) * | 2015-04-28 | 2015-08-12 | 国网上海市电力公司 | 一种基于bim和gis的变电站模型构建方法 |
| CN105938613A (zh) * | 2016-06-27 | 2016-09-14 | 锐创(唐山)生态建筑科技有限公司 | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 |
| CN106022979A (zh) * | 2016-05-13 | 2016-10-12 | 郑州双杰科技股份有限公司 | 基于bim的水利水电工程管理云平台及应用方法 |
-
2017
- 2017-04-25 CN CN201710278066.0A patent/CN107103078A/zh active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20140214220A1 (en) * | 2011-06-15 | 2014-07-31 | Expanergy, Llc | Systems and methods to assess and optimize energy usage for a facility |
| CN103699731A (zh) * | 2013-12-19 | 2014-04-02 | 中铁第一勘察设计院集团有限公司 | 一种铁道工程真实场景模型协同设计平台的构建方法 |
| CN104680331A (zh) * | 2015-03-18 | 2015-06-03 | 国网上海市电力公司 | 一种基于ifc的输变电工程三维数字化管理平台 |
| CN104835079A (zh) * | 2015-04-28 | 2015-08-12 | 国网上海市电力公司 | 一种基于bim和gis的变电站模型构建方法 |
| CN106022979A (zh) * | 2016-05-13 | 2016-10-12 | 郑州双杰科技股份有限公司 | 基于bim的水利水电工程管理云平台及应用方法 |
| CN105938613A (zh) * | 2016-06-27 | 2016-09-14 | 锐创(唐山)生态建筑科技有限公司 | 一种基于bim和vr智慧城市管网综合平台及其管理方法和构建方法 |
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107527155A (zh) * | 2017-09-06 | 2017-12-29 | 北京北控建设发展有限公司 | 建设项目监管系统 |
| CN107680002A (zh) * | 2017-09-27 | 2018-02-09 | 国网上海市电力公司 | 一种基于gis和bim的电力设施信息化系统 |
| CN107562962A (zh) * | 2017-10-12 | 2018-01-09 | 国网上海市电力公司 | 一种基于bim的变电站信息监测管理系统 |
| CN107862153A (zh) * | 2017-11-23 | 2018-03-30 | 国网上海市电力公司 | 一种变电站数字化管控系统 |
| CN109345209A (zh) * | 2018-11-21 | 2019-02-15 | 国网河北省电力有限公司建设公司 | 一种500kV变电站的可视化施工管理方法及装置 |
| CN111126838B (zh) * | 2019-12-23 | 2022-07-12 | 广东电网有限责任公司 | 一种智慧工程管理系统 |
| CN111126838A (zh) * | 2019-12-23 | 2020-05-08 | 广东电网有限责任公司 | 一种智慧工程管理系统 |
| CN111597666A (zh) * | 2020-05-20 | 2020-08-28 | 佛山电力设计院有限公司 | 一种将bim应用到变电站建设过程的方法 |
| CN111597666B (zh) * | 2020-05-20 | 2021-01-26 | 佛山电力设计院有限公司 | 一种将bim应用到变电站建设过程的方法 |
| CN111709123A (zh) * | 2020-05-26 | 2020-09-25 | 国网江苏省电力有限公司南通供电分公司 | 基于bim技术的变电站工程实施现场物料数字化管理系统 |
| CN112769237A (zh) * | 2020-12-31 | 2021-05-07 | 长园深瑞继保自动化有限公司 | 变电站数字孪生系统 |
| CN112769237B (zh) * | 2020-12-31 | 2023-04-21 | 长园深瑞继保自动化有限公司 | 变电站数字孪生系统 |
| CN114372307A (zh) * | 2021-12-30 | 2022-04-19 | 国网江苏省电力工程咨询有限公司 | 一种面向电力变电站基于bim+gis技术的施工管理系统及方法 |
| CN114969908A (zh) * | 2022-05-17 | 2022-08-30 | 武汉联动设计股份有限公司 | 一种基于BIM模型的220kv全户内变电站数字化模拟测试系统 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107103078A (zh) | 基于bim的变电站建设全周期数字化管控系统 | |
| CN102722764B (zh) | 一体化电网优化辅助决策分析系统 | |
| CN109165394B (zh) | 一种标准化bim模型轻量化实现方法 | |
| CN103093007B (zh) | 输电铁塔三维虚拟装配方法 | |
| CN102832703B (zh) | 基于模型转换机的变电站与调度主站模型快速转换方法 | |
| CN102411764B (zh) | 电网设备的数据管理系统及管理方法 | |
| CN112035983A (zh) | 一种基于三维实景的城市中压电网规划设计平台 | |
| CN104835079A (zh) | 一种基于bim和gis的变电站模型构建方法 | |
| CN101964542B (zh) | 一种iec61970调度ems系统接入iec61850数字化变电站的方法 | |
| CN102096759A (zh) | 一种土地实时集群调查方法 | |
| CN106056349A (zh) | 一种省地县三级电网规划gis绘图系统及方法 | |
| CN110570009A (zh) | 一种配电网分析与规划系统 | |
| CN102750359A (zh) | 基于输电线路三维模型的空间信息提取与格式转换方法 | |
| CN105528497A (zh) | 一种三维变电站设计平台 | |
| CN104008218A (zh) | 电力工程三维一体化设计平台 | |
| CN104866613A (zh) | 一种电网设备设施三维组件化模型数据库的建立方法 | |
| CN104778551A (zh) | 一种可视化电网设计与分析方法 | |
| CN115409652A (zh) | 一种基于bim的集成整合数据中台管理系统 | |
| CN118797783A (zh) | 一种基于bim的水利工程信息管理方法及系统 | |
| CN105354613A (zh) | 一种分布式光伏运维模式选择系统 | |
| CN104104146A (zh) | 一种大电网变电设备在线监测数据模型建立方法 | |
| CN103065267B (zh) | 基于用户集的营销、生产数据共享及业务融合方法 | |
| CN204290485U (zh) | 变电站运维一体化现场工作信息采集系统 | |
| CN112347168A (zh) | 一种cad-gis系统数据自动处理与转换方法 | |
| CN110991070A (zh) | 一种变电站二次设备三维数字化建设方法 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170829 |