CN107023002A - Down-the-hole impacts churning composite pile pile making method - Google Patents
Down-the-hole impacts churning composite pile pile making method Download PDFInfo
- Publication number
- CN107023002A CN107023002A CN201710346370.4A CN201710346370A CN107023002A CN 107023002 A CN107023002 A CN 107023002A CN 201710346370 A CN201710346370 A CN 201710346370A CN 107023002 A CN107023002 A CN 107023002A
- Authority
- CN
- China
- Prior art keywords
- pile
- hole
- churning
- composite
- stake
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/48—Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/50—Piles comprising both precast concrete portions and concrete portions cast in situ
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/56—Screw piles
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
本发明要求专利号为:201620969302.4,发明名称为:潜孔冲击旋喷复合桩,的中国专利的优先权。The present invention requires the patent number: 201620969302.4, and the title of the invention is: down-the-hole impact rotary grouting composite pile, the priority of the Chinese patent.
技术领域technical field
本发明涉及岩土工程领域,具体涉及一种潜孔冲击旋喷复合桩成桩方法。The invention relates to the field of geotechnical engineering, in particular to a method for forming a down-the-hole impact rotary spraying composite pile.
背景技术Background technique
在岩土工程领域,按用途可将桩分为基础工程中的抗压桩和抗拔桩、基坑支护中的支护桩和帷幕桩、复合地基中的刚性增强体等几大类;按施工工艺可分为灌注桩和预制桩两大类,其中预制桩又包括混凝土预制桩和钢桩。桩基础领域目前所采用的最多的两种类型的桩分别为钻孔灌注桩和预应力混凝土管桩;前者适用地层广泛、承载力大,后者质量可控、施工效率高。但经过多年的实践运用,两者都出现了诸多问题,分述如下。In the field of geotechnical engineering, according to the purpose, piles can be divided into several categories such as compression piles and uplift piles in foundation engineering, support piles and curtain piles in foundation pit support, and rigid reinforcements in composite foundations; According to the construction technology, it can be divided into two categories: cast-in-place piles and prefabricated piles, among which prefabricated piles include concrete prefabricated piles and steel piles. The two types of piles currently used most in the field of pile foundations are bored piles and prestressed concrete pipe piles; the former is applicable to a wide range of strata and has a large bearing capacity, while the latter has controllable quality and high construction efficiency. However, after many years of practical use, both of them have many problems, which are described as follows.
钻孔灌注桩一般可分为干作业和泥浆护壁两种类型,前者适用于地下水位以上、孔壁稳定性较好的地层,后者适用于地下水位以下、孔壁稳定性差的地层。随着承载力要求的提高,桩的深度不断加大,一般要穿越多种地层进入基岩,泥浆护壁的做法占了很大比例。这种成孔方法可解决孔壁稳定性的问题,但对泥浆材料的比重控制和施工技术的要求均比较高,实际工程中容易出现泥浆比重不够、含砂量高、清孔不到位导致桩底沉渣过厚等不利于桩基质量控制的问题。为解决这一问题又衍生灌注桩后注浆技术,弥补桩端沉渣造成的端阻不足或进一步提高桩侧摩阻力。但工艺更为复杂,工期相应增加,造价也增幅较大。Bored cast-in-situ piles can generally be divided into two types: dry operation and mud retaining wall. The former is suitable for formations above the groundwater level and with good hole wall stability, and the latter is suitable for formations below the groundwater level and with poor hole wall stability. With the improvement of bearing capacity requirements, the depth of piles is continuously increased. Generally, it is necessary to pass through various strata to enter the bedrock, and the practice of mud retaining walls accounts for a large proportion. This hole-forming method can solve the problem of hole wall stability, but it has relatively high requirements on the specific gravity control of the mud material and construction technology. The bottom sediment is too thick and other problems that are not conducive to the quality control of the pile foundation. In order to solve this problem, the post-grouting technology of cast-in-place piles is derived to make up for the insufficient end resistance caused by the sediment at the pile end or to further increase the pile side frictional resistance. But the process is more complicated, the construction period increases accordingly, and the cost also increases greatly.
混凝土预制桩和钢桩接近于预制装配式的理念,将工厂内预制生产的、质量可控的成品桩在现场通过特定的设备沉入地层中,工艺简单、施工快速。但此类桩对地层的要求较高,且桩身抗弯刚度较灌注桩相比偏低,不适用于抗震烈度较大的地区。Concrete prefabricated piles and steel piles are close to the concept of prefabricated assembly. The finished piles prefabricated in the factory and with controllable quality are sunk into the ground through specific equipment on site. The process is simple and the construction is fast. However, this type of pile has higher requirements on the stratum, and the bending stiffness of the pile body is lower than that of cast-in-situ piles, so it is not suitable for areas with high seismic intensity.
复合桩是一种新的解决思路,即先施工水泥土外桩,然后内插芯桩,形成外部柔性、内部刚性的复合桩。水泥土外桩的施工方法一般为传统高压旋喷或水泥搅拌,在成桩后根据不同要求的时间内采用沉入、钻孔或锤击等方法将芯桩插入,形成复合桩。但由于传统高压旋喷工艺和水泥搅拌工艺对地层的适应性有较大局限,一般可用于黏性土、粉土、松散砂土等地层,无法用于密实砂层、卵石、砾石、含抛石的杂填地层,限制了此类工艺的进一步推广和实施。Composite piles are a new solution, that is, constructing cement-soil external piles first, and then inserting core piles to form composite piles with external flexibility and internal rigidity. The construction method of the cement-soil external pile is generally the traditional high-pressure rotary spraying or cement mixing. After the pile is formed, the core pile is inserted by sinking, drilling or hammering according to different requirements to form a composite pile. However, due to the relatively limited adaptability of the traditional high-pressure rotary spraying process and cement mixing process to the stratum, it can generally be used in cohesive soil, silt, loose sand and other strata, and cannot be used in dense sand, pebbles, gravels, sandy soils, etc. The miscellaneous filling formations of rocks limit the further promotion and implementation of this kind of technology.
综上所述,现有技术中存在以下问题:现有的复合桩适用的地层范围小、与芯桩的适应性弱。To sum up, the following problems exist in the prior art: the existing composite piles are applicable to a small stratum range, and have weak adaptability to core piles.
发明内容Contents of the invention
本发明提供一种潜孔冲击旋喷复合桩成桩方法,以解决现有的复合桩适用的地层范围小、与芯桩的适应性弱的问题。The invention provides a method for forming a down-the-hole impact rotary grouting composite pile to solve the problems that the existing composite pile is applicable to a small stratum range and has weak adaptability to core piles.
为此,本发明提出一种潜孔冲击旋喷复合桩成桩方法,所述潜孔冲击旋喷复合桩成桩方法包括以下步骤:For this reason, the present invention proposes a kind of down-the-hole impact rotary grouting composite pile forming method, described down-the-hole impact rotary grouting composite pile forming method comprises the following steps:
步骤A:先采用潜孔冲击高压旋喷桩施工工艺形成水泥土外桩;Step A: first use the down-the-hole impact high-pressure rotary grouting pile construction technology to form the cement-soil outer pile;
步骤B:然后在所述水泥土外桩内设置芯桩,形成潜孔冲击旋喷复合桩;Step B: then core piles are set in the cement-soil outer piles to form down-the-hole impact rotary grouting composite piles;
其中,所述芯桩是灌注桩、混凝土预制桩或钢桩。Wherein, the core pile is cast-in-place pile, concrete prefabricated pile or steel pile.
进一步地,所述水泥土外桩的桩体是等直径或不等直径。Further, the pile bodies of the cement-soil external piles have equal diameters or unequal diameters.
进一步地,所述步骤A包括对水泥土外桩进行扩径或扩底。Further, the step A includes expanding the diameter or bottom of the cement-soil external pile.
进一步地,所述灌注桩包括:沉管灌注桩、内夯沉管灌注桩、螺旋钻孔压灌桩和螺纹灌注桩。Further, the cast-in-situ piles include: cast-in-place piles with immersed tubes, internally rammed cast-in-place piles, auger-drilled cast-in-situ piles and threaded cast-in-place piles.
进一步地,所述芯桩为螺旋钻孔压灌桩,所述步骤B包括:采用螺旋钻机成孔,达到设计深度后,在孔中心压灌混凝土,反插钢筋笼成桩。Further, the core pile is an auger drilled grouting pile, and the step B includes: using an auger drill to form a hole, and after reaching the design depth, pouring concrete in the center of the hole, and inserting a steel cage in reverse to form a pile.
进一步地,所述芯桩为沉管灌注桩,所述步骤B包括:采用锤击、振动等沉管法进行成孔,宜采用预制桩尖,插入钢筋笼后灌注混凝土成桩。Further, the core pile is a cast-in-situ pile, and the step B includes: forming a hole by hammering, vibrating and other sinking methods, preferably using a prefabricated pile tip, inserting a steel cage and pouring concrete to form a pile.
进一步地,所述芯桩为内夯沉管灌注桩,所述步骤B包括:采用内夯钻机套管跟进冲击成孔,冲击成孔的同时对水泥土外桩产生挤密作用,桩端内夯扩大头,下放钢筋笼,浇筑芯桩混凝土,提拔套管成桩。Further, the core pile is an internally rammed cast-in-place pile, and the step B includes: using an internally rammed drilling rig casing to follow up and impact to form a hole, while impacting to form a hole, the cement-soil outer pile is compacted, and the pile end The expansion head is internally rammed, the steel cage is lowered, the core pile concrete is poured, and the casing is lifted to form a pile.
进一步地,所述芯桩为螺纹灌注桩,所述步骤B包括:采用螺纹桩机成孔,螺纹钻杆成孔的同时,依靠螺纹的挤压,对水泥土外桩产生挤密作用。Further, the core pile is a threaded cast-in-place pile, and the step B includes: using a threaded pile machine to form a hole, while forming a hole with a threaded drill rod, and relying on the extrusion of the thread to produce a compacting effect on the cement-soil outer pile.
进一步地,所述芯桩为混凝土预制桩,所述混凝土预制桩包括:混凝土实心方桩、预应力混凝土管桩、预应力混凝土空心方桩和预制螺纹桩,所述步骤B包括:采用振锤吊放、静压、锤击、回转方式将预应力混凝土管桩、预应力混凝土空心方桩、或预制螺纹桩下放至设计深度。Further, the core pile is a concrete prefabricated pile, and the concrete prefabricated pile includes: a concrete solid square pile, a prestressed concrete pipe pile, a prestressed concrete hollow square pile and a prefabricated threaded pile, and the step B includes: using a vibrating hammer Lower prestressed concrete pipe piles, prestressed concrete hollow square piles, or prefabricated threaded piles to the design depth by means of hanging, static pressure, hammering, and rotation.
进一步地,所述芯桩为钢桩,所述钢桩包括:钢管桩、H型钢桩或其他异型钢桩,所述步骤B包括:采用振锤吊放、静压、锤击、回转方式将钢管桩、H型钢桩或其他异型钢桩下放至设计深度。Further, the core piles are steel piles, and the steel piles include: steel pipe piles, H-shaped steel piles or other special-shaped steel piles, and the step B includes: lifting by vibrating hammer, static pressure, hammering, and turning Lower steel pipe piles, H-shaped steel piles or other special-shaped steel piles to the design depth.
本发明先采用潜孔冲击高压旋喷桩施工工艺和设备形成水泥土外桩,后可根据实际需要采用不同工艺施工不同类型的芯桩。通过水泥土外桩与芯桩的有机结合与共同作用,提高芯桩侧摩阻力及桩端的端阻力;同时,水泥土外桩还可增加桩体的抵抗水平荷载的能力,提高桩基础的抗震性能。该桩适用于黏性土、粉土、砂土等一般地层,也适用于淤泥质土、卵石、砾石、漂石、抛石、人工填海地区等复杂地层;可用作桩基础中的抗压桩或抗拔桩,也可用作复合地基的增强体或基坑工程中的支护桩。The invention adopts the construction technology and equipment of submerged hole impact high-pressure rotary grouting piles to form cement-soil outer piles, and then adopts different techniques to construct different types of core piles according to actual needs. Through the organic combination and interaction of the cement-soil outer pile and the core pile, the side friction resistance of the core pile and the end resistance of the pile end can be improved; at the same time, the cement-soil outer pile can also increase the ability of the pile to resist horizontal loads and improve the seismic resistance of the pile foundation performance. The pile is suitable for general formations such as cohesive soil, silt, sandy soil, etc., and also for complex formations such as muddy soil, pebbles, gravels, boulders, riprap, and artificial reclamation areas; it can be used as an anti-corrosion pile in pile foundations Pressure piles or uplift piles can also be used as reinforcements for composite foundations or support piles in foundation pit engineering.
附图说明Description of drawings
图1为本发明的潜孔冲击旋喷复合桩成桩方法的工作原理示意图,其中,芯桩是螺旋钻孔压灌桩或沉管灌注桩或内夯沉管灌注桩;Fig. 1 is the schematic diagram of the working principle of the pile-forming method of the down-the-hole impact rotary grouting composite pile of the present invention, wherein, the core pile is an auger bored pressure-grown pile or a sinking-pipe cast-in-place pile or an internally rammed sinker-pipe cast-in-situ pile;
图2为本发明的潜孔冲击旋喷复合桩成桩方法的工作原理示意图,其中,芯桩是预应力混凝土管桩或混凝土空心方桩;Fig. 2 is a schematic diagram of the working principle of the pile-forming method of the down-the-hole impact rotary grouting composite pile of the present invention, wherein the core pile is a prestressed concrete pipe pile or a concrete hollow square pile;
图3为本发明的潜孔冲击旋喷复合桩成桩方法的工作原理示意图,其中,芯桩是螺纹灌注桩或预制螺杆桩;Fig. 3 is a schematic diagram of the working principle of the pile-forming method of the down-the-hole impact rotary grouting composite pile of the present invention, wherein the core pile is a threaded cast-in-place pile or a prefabricated screw pile;
图4为本发明的潜孔冲击旋喷复合桩成桩方法进行水泥土外桩扩径的结构示意图,其中,芯桩是螺旋钻孔压灌桩或沉管灌注桩或内夯沉管灌注桩;Fig. 4 is a structural schematic diagram of expanding the diameter of cement-soil outer piles by the pile-forming method of submerged-hole impact rotary grouting composite piles of the present invention, wherein the core piles are auger-drilled grouting piles or sinking tube grouting piles or internally rammed sinking tube grouting piles ;
图5为本发明的潜孔冲击旋喷复合桩成桩方法进行水泥土外桩扩径的结构示意图,其中,芯桩是预应力混凝土管桩或混凝土空心方桩;Fig. 5 is the structure schematic diagram of expanding the diameter of the cement-soil outer pile by the pile forming method of the down-the-hole impact rotary grouting composite pile of the present invention, wherein, the core pile is a prestressed concrete pipe pile or a concrete hollow square pile;
图6为本发明的潜孔冲击旋喷复合桩成桩方法进行水泥土外桩扩径的结构示意图,其中,芯桩是螺纹灌注桩或预制螺杆桩。Fig. 6 is a structural schematic diagram of expanding the diameter of cement-soil outer piles by the pile-forming method of the down-the-hole impact rotary grouting composite pile of the present invention, wherein the core pile is a threaded cast-in-place pile or a prefabricated screw pile.
附图标号说明:Explanation of reference numbers:
1-水泥土外桩;2-芯桩;5-水泥土外桩扩径;6-水泥土外桩扩底;1-Cement-soil outer pile; 2-Core pile; 5-Cement-soil outer pile diameter expansion; 6-Cement-soil outer pile bottom expansion;
具体实施方式detailed description
为了对本发明的技术特征、目的和效果有更加清楚的理解,现对照附图说明本发明。In order to have a clearer understanding of the technical features, purposes and effects of the present invention, the present invention will now be described with reference to the accompanying drawings.
本发明一种潜孔冲击旋喷复合桩成桩方法,所述潜孔冲击旋喷复合桩成桩方法包括以下步骤:The invention discloses a pile-forming method of a submerged-hole impact rotary-grouting composite pile, which comprises the following steps:
步骤A:先采用潜孔冲击高压旋喷桩施工工艺形成水泥土外桩1;潜孔冲击高压旋喷桩施工工艺既能实现对潜孔冲击,实现底部的钻进,同时还能实现高压旋喷,即在潜孔冲击器底部的上方进行水平高压喷射,钻进的同时向喷射器提供不小于15MPa压力的高压水(浆)切割软化土体,保证钻进时的径向孔径;除可在黏性土、粉土和松散砂土施工旋喷桩外,还可在密实砂层、卵石、砾石、含抛石的杂填地层中形成大直径的旋喷桩;且成桩垂直度偏差控制值小于1%;具体的潜孔冲击高压旋喷桩施工工艺可以参考现有成熟的技术;Step A: first use the down-the-hole impact high-pressure rotary grouting pile construction technology to form the cement-soil outer pile 1; Spraying, that is, horizontal high-pressure spraying above the bottom of the down-the-hole impactor. While drilling, provide high-pressure water (slurry) with a pressure of not less than 15MPa to the injector to cut and soften the soil to ensure the radial aperture during drilling; In addition to the construction of rotary grouting piles in cohesive soil, silt and loose sand, large diameter rotary grouting piles can also be formed in dense sand layers, pebbles, gravels, and miscellaneous fill formations containing riprap; and the verticality of piles is deviated The control value is less than 1%; the specific construction technology of down-the-hole impact high-pressure rotary grouting pile can refer to the existing mature technology;
步骤B:然后在所述水泥土外桩内设置芯桩2,形成潜孔冲击旋喷复合桩;所述的水泥土外桩施工完成后,根据芯桩类型的不同可选取不同的时间进行芯桩施工;所述的芯桩2可选用灌注桩、混凝土预制桩、钢桩或其他任意一种类型的桩。Step B: set core pile 2 in described cement-soil outer pile then, form down-the-hole impact rotary grouting compound pile; After described cement-soil outer pile construction is finished, can choose different time to carry out core according to the difference of core pile type Pile construction; the core pile 2 can be cast-in-situ pile, concrete prefabricated pile, steel pile or any other type of pile.
进一步地,如图1、图2和图3所示,所述水泥土外桩1的桩体是等直径的,形成直径较大、较均匀的水泥土外桩;如图4、图5和图6所示,所述水泥土外桩1的桩体是不等直径,也可以根据设计要求进行扩径或扩底,形成水泥土外桩扩径5和水泥土外桩扩底6。Further, as shown in Fig. 1, Fig. 2 and Fig. 3, the pile bodies of the cement-soil outer pile 1 are equal in diameter, forming a larger and more uniform cement-soil outer pile; as shown in Fig. 4, Fig. 5 and As shown in Fig. 6, the pile bodies of the cement-soil outer pile 1 are unequal diameters, and can also be expanded in diameter or bottom according to design requirements, forming the expanded diameter 5 of the cement-soil outer pile and the enlarged bottom 6 of the cement-soil outer pile.
进一步地,所述灌注桩包括:沉管灌注桩、内夯沉管灌注桩、螺旋钻孔压灌桩和螺纹灌注桩。Further, the cast-in-situ piles include: cast-in-place piles with immersed tubes, internally rammed cast-in-place piles, auger-drilled cast-in-situ piles and threaded cast-in-place piles.
进一步地,如图1和图4所示,所述芯桩2为螺旋钻孔压灌桩,所述步骤B包括:采用螺旋钻机成孔,达到设计深度后,在孔中心压灌混凝土,反插钢筋笼成桩。Further, as shown in Figures 1 and 4, the core pile 2 is an auger-drilled grouting pile, and the step B includes: using an auger drill to form a hole, and after the designed depth is reached, concrete is poured in the center of the hole, and then Insert reinforcement cages into piles.
进一步地,如图1和图4所示,所述芯桩2为沉管灌注桩,所述步骤B包括:采用锤击、振动等沉管法进行成孔,宜采用预制桩尖,插入钢筋笼后灌注混凝土成桩。Further, as shown in Fig. 1 and Fig. 4, the core pile 2 is a pipe sinking cast-in-situ pile, and the step B includes: using hammering, vibration and other sinking methods to form holes, preferably using prefabricated pile tips, inserting steel bars Concrete is poured after the cage to form a pile.
进一步地,如图1和图4所示,所述芯桩2为内夯沉管灌注桩,所述步骤B包括:采用内夯钻机套管跟进冲击成孔,冲击成孔的同时对水泥土外桩产生挤密作用,桩端内夯扩大头,下放钢筋笼,浇筑芯桩混凝土,提拔套管成桩。Further, as shown in Fig. 1 and Fig. 4, the core pile 2 is an internally rammed cast-in-situ pile, and the step B includes: using an internally rammed drilling rig casing to follow up and impact the hole, and impact the cement while forming the hole. The pile outside the soil produces a compaction effect, the pile end is internally rammed to expand the head, the steel cage is lowered, the core pile concrete is poured, and the casing is lifted to form a pile.
进一步地,如图3和图6所示,所述芯桩2为螺纹灌注桩,所述步骤B包括:采用螺纹桩机成孔,螺纹钻杆成孔的同时,依靠螺纹的挤压,对水泥土外桩产生挤密作用。Further, as shown in Fig. 3 and Fig. 6, the core pile 2 is a threaded cast-in-situ pile, and the step B includes: using a threaded pile driver to form a hole, and while the threaded drill rod is forming a hole, relying on the extrusion of the thread, the The cement-soil external pile produces compaction.
进一步地,如图2和图5所示,所述芯桩2为混凝土预制桩,所述混凝土预制桩包括:混凝土实心方桩、预应力混凝土管桩、预应力混凝土空心方桩和预制螺纹桩,所述步骤B包括:采用振锤吊放、静压、锤击、回转方式将预应力混凝土管桩、预应力混凝土空心方桩、或预制螺纹桩下放至设计深度。Further, as shown in Figure 2 and Figure 5, the core pile 2 is a concrete prefabricated pile, and the concrete prefabricated pile includes: a concrete solid square pile, a prestressed concrete pipe pile, a prestressed concrete hollow square pile and a prefabricated threaded pile , the step B includes: lowering the prestressed concrete pipe pile, the prestressed concrete hollow square pile, or the prefabricated threaded pile to the design depth by means of vibrating hammer lifting, static pressure, hammering, and rotation.
进一步地,所述芯桩为钢桩,所述钢桩包括:钢管桩、H型钢桩或其他异型钢桩,所述步骤B包括:采用振锤吊放、静压、锤击、回转方式将钢管桩、H型钢桩或其他异型钢桩下放至设计深度。在潜孔冲击高压旋喷桩形成水泥土外桩后进行施工;用于基坑工程的支护桩或支护帷幕一体桩时,可拔出芯桩回收利用。Further, the core piles are steel piles, and the steel piles include: steel pipe piles, H-shaped steel piles or other special-shaped steel piles, and the step B includes: lifting by vibrating hammer, static pressure, hammering, and turning Lower steel pipe piles, H-shaped steel piles or other special-shaped steel piles to the design depth. The construction is carried out after the submerged hole impacts the high-pressure rotary grouting pile to form the cement-soil outer pile; when it is used for the support pile of the foundation pit project or the support curtain integrated pile, the core pile can be pulled out for recycling.
本发明的具体作业过程例如为:Concrete operating process of the present invention is for example:
(1)桩位测放:按照设计桩位,采用传统测量仪器或高精度自动定位测量技术进行桩位测量及定位。(1) Pile position measurement and placement: According to the designed pile position, traditional measuring instruments or high-precision automatic positioning measurement technology are used to measure and locate the pile position.
(2)外桩作业:潜孔冲击旋喷搅拌桩机就位后,冲击器开始工作,钻进的同时向喷射器提供不小于15MPa压力的高压水(浆)切割软化土体。成孔至设计深度后,喷射高压水泥浆,根据施工需要提升、下放钻头进行重复旋喷,形成直径较大、较均匀的水泥土外桩。(2) External pile operation: After the submersible impact rotary jet mixing pile machine is in place, the impactor starts to work. While drilling, provide high-pressure water (slurry) with a pressure of not less than 15MPa to the injector to cut and soften the soil. After the hole is formed to the designed depth, high-pressure cement slurry is sprayed, and the drill bit is lifted and lowered according to the construction needs for repeated rotary spraying to form a larger diameter and more uniform cement-soil external pile.
(3)芯桩作业:(3) Core pile operation:
①当芯桩采用长螺旋钻孔压灌桩时,在水泥土外桩成桩后的一定时间内,采用长螺旋钻机成孔,达到设计深度后,中心压灌混凝土,反插钢筋笼成桩。① When the core pile adopts long auger drilling and grouting piles, within a certain period of time after the cement-soil outer pile is formed, the long auger drilling machine is used to form the hole. After the design depth is reached, the concrete is poured in the center, and the steel cage is inserted reversely to form the pile .
②当芯桩为沉管灌注桩时,在水泥土外桩成桩后的一定时间内,采用锤击、振动等沉管法进行成孔,宜采用预制桩尖,插入钢筋笼后灌注混凝土成桩。② When the core piles are cast-in-place piles, within a certain period of time after the cement-soil outer piles are piled, pipe sinking methods such as hammering and vibration are used to form holes. pile.
③当芯桩为内夯沉管灌注桩时,在水泥土外桩成桩后的一定时间内,采用内夯钻机套管跟进冲击成孔,冲击成孔的同时,对水泥土外桩产生挤密作用,桩端内夯扩大头,下放钢筋笼,浇筑芯桩混凝土,提拔套管成桩。③ When the core pile is an internally rammed sinking pipe pouring pile, within a certain period of time after the cement-soil outer pile is formed, the casing of the internal ramming drilling rig is used to follow up and impact the hole. Compacting effect, internally ramming and expanding the pile end, lowering the reinforcement cage, pouring concrete for the core pile, and lifting the casing to form a pile.
④当芯桩为螺纹灌注桩时,在水泥土成桩后的一定时间内,采用螺纹桩机成孔,螺纹钻杆成孔的同时,依靠螺纹的挤压,对水泥土外桩产生挤密作用,以增强外桩的桩身强度及芯桩与外桩的整体性。④ When the core pile is a threaded cast-in-situ pile, within a certain period of time after the cement soil pile is formed, a threaded pile machine is used to form a hole. While the threaded drill pipe is forming a hole, relying on the extrusion of the thread, the cement soil outer pile is compacted To enhance the pile body strength of the outer pile and the integrity of the core pile and the outer pile.
⑤当芯桩为预制桩时,在水泥土外桩成桩后的一定时间内,采用振锤吊放、静压、锤击、回转等方式将预应力混凝土管桩、预制混凝土空心方桩、预制螺纹桩下放至设计深度。⑤ When the core pile is a prefabricated pile, the prestressed concrete pipe pile, precast concrete hollow square pile, precast concrete hollow square pile, The prefabricated threaded piles are lowered to the design depth.
⑥当芯桩为钢桩时,在水泥土外桩成桩成桩后的一定时间内,采用振锤吊放、静压、锤击、回转等方式将钢管桩、H型钢桩或其他异型钢桩下放至设计深度。⑥When the core pile is a steel pile, within a certain period of time after the cement-soil outer pile is formed, the steel pipe pile, H-shaped steel pile or other special-shaped The steel piles are lowered to the design depth.
以上所述仅为本发明示意性的具体实施方式,并非用以限定本发明的范围。为本发明的各组成部分在不冲突的条件下可以相互组合,任何本领域的技术人员,在不脱离本发明的构思和原则的前提下所作出的等同变化与修改,均应属于本发明保护的范围。The above descriptions are only illustrative specific implementations of the present invention, and are not intended to limit the scope of the present invention. Because the various components of the present invention can be combined with each other under the condition of no conflict, any equivalent changes and modifications made by any person skilled in the art without departing from the concept and principle of the present invention shall belong to the protection of the present invention. range.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| PCT/CN2018/075793 WO2018210019A1 (en) | 2016-08-30 | 2018-02-08 | Pile formation method for down-the-hole impact rotary jet composite piles |
Applications Claiming Priority (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201620969302 | 2016-08-30 | ||
| CN2016209693024 | 2016-08-30 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN107023002A true CN107023002A (en) | 2017-08-08 |
Family
ID=59529880
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710346370.4A Pending CN107023002A (en) | 2016-08-30 | 2017-05-17 | Down-the-hole impacts churning composite pile pile making method |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN107023002A (en) |
| WO (1) | WO2018210019A1 (en) |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN108104118A (en) * | 2018-01-03 | 2018-06-01 | 上海智平基础工程有限公司 | A kind of cast-in-place composite pile foundation structure and its construction method |
| CN108179741A (en) * | 2018-03-26 | 2018-06-19 | 卓典机器人(海南)有限公司 | A kind of screw rod pile and combined drilling tool and its engineering method |
| CN108487236A (en) * | 2018-03-21 | 2018-09-04 | 中国建筑第六工程局有限公司 | A kind of cast-in-situ bored pile collapse hole in-situ treatment method |
| WO2018210019A1 (en) * | 2016-08-30 | 2018-11-22 | 北京荣创岩土工程股份有限公司 | Pile formation method for down-the-hole impact rotary jet composite piles |
| CN109113058A (en) * | 2018-08-15 | 2019-01-01 | 绿山高科建设科技有限公司 | A kind of new type cement soil composite pile |
| CN110485410A (en) * | 2019-08-21 | 2019-11-22 | 天津建岩岩土工程有限公司 | Foundation pile pile making method |
| CN110847205A (en) * | 2019-11-08 | 2020-02-28 | 中煤江南建设发展有限公司 | A composite pile foundation structure and its construction method |
| CN113216155A (en) * | 2021-06-02 | 2021-08-06 | 刘守进 | Novel composite pile |
| CN113279395A (en) * | 2021-06-11 | 2021-08-20 | 隋付仁 | High-grouting-slurry-body built-in prestressed concrete pile construction process |
| CN113293756A (en) * | 2021-06-01 | 2021-08-24 | 北京建材地质工程有限公司 | Construction method of steel pipe inserted composite foundation and pile foundation of pneumatic down-the-hole hammer vibration jet grouting pile |
| CN113550303A (en) * | 2021-07-28 | 2021-10-26 | 建材桂林地质工程勘察院有限公司 | Pile-forming method of DTH impact high-pressure jetting composite pile |
| CN114169064A (en) * | 2021-12-28 | 2022-03-11 | 中国铁道科学研究院集团有限公司 | Size optimization combination method for down-the-hole impact cement-soil composite precast pile and application thereof |
| CN116752522A (en) * | 2023-07-05 | 2023-09-15 | 江苏建院营造股份有限公司 | Free-angle high-bearing composite expansion pile |
Families Citing this family (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111455981B (en) * | 2020-04-05 | 2021-11-16 | 上海民航新时代机场设计研究院有限公司 | Concrete cast-in-place pile of sludge texture foundation and construction method thereof |
| CN112252310A (en) * | 2020-10-24 | 2021-01-22 | 武汉安振岩土工程有限公司 | Method for deep foundation pit waterproof curtain construction by adopting high-pressure jet grouting pile machine |
| CN116856420A (en) * | 2023-05-25 | 2023-10-10 | 深圳市综合交通与市政工程设计研究总院有限公司 | Foundation pit supporting structure of deep silt stratum and construction method thereof |
| CN116856853A (en) * | 2023-07-07 | 2023-10-10 | 山东省建筑科学研究院有限公司 | Construction device and construction method for complex stratum composite pile |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2336006Y (en) * | 1998-08-21 | 1999-09-01 | 中国建筑科学研究院地基基础研究所 | Dry contruction composite driven cast-in-place pile |
| CN101942830A (en) * | 2010-08-19 | 2011-01-12 | 上海强劲基础工程有限公司 | Combined concrete soil pile with core pile and construction method as well as construction device thereof |
| JP4670101B2 (en) * | 2006-10-23 | 2011-04-13 | 日本ヒューム株式会社 | Pre-boring precast concrete pile burying method. |
| CN102251520A (en) * | 2011-05-27 | 2011-11-23 | 岳建伟 | Novel cement soil composite mixing pile and pile formation method thereof |
| CN102787595A (en) * | 2012-08-16 | 2012-11-21 | 岳建伟 | Double-acting self-stressing combined uplift pile and pile forming method |
| CN102839657A (en) * | 2012-09-12 | 2012-12-26 | 江苏兴鹏基础工程有限公司 | Cast-in-place pedestal tubular pile and construction method thereof |
| CN103015435A (en) * | 2012-12-04 | 2013-04-03 | 北京建材地质工程公司 | Long auger down hole hammer vibration rotary-jet steel reinforced cement-soil pile foundation pit water-resisting and supporting method |
Family Cites Families (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2565870Y (en) * | 2002-08-08 | 2003-08-13 | 青岛市勘察测绘研究院 | Reinforced concrete cross-section-changeable composite pile |
| JP4027264B2 (en) * | 2003-05-09 | 2007-12-26 | 株式会社テノックス | How to construct soil cement composite piles |
| JP4796477B2 (en) * | 2006-11-08 | 2011-10-19 | 山伸工業株式会社 | Steel pipe soil cement pile construction method and composite pile construction method |
| CN101148875A (en) * | 2007-11-05 | 2008-03-26 | 山东省机械施工有限公司 | Composite pile and construction method thereof |
| CN202337979U (en) * | 2011-06-17 | 2012-07-18 | 北京荣创科宏岩土工程有限公司 | Air slurry separation device and drill rod combination structure with same |
| CN202227336U (en) * | 2011-09-09 | 2012-05-23 | 管自立 | Rigid flexible composite foundation pile |
| CN107023002A (en) * | 2016-08-30 | 2017-08-08 | 北京荣创岩土工程股份有限公司 | Down-the-hole impacts churning composite pile pile making method |
-
2017
- 2017-05-17 CN CN201710346370.4A patent/CN107023002A/en active Pending
-
2018
- 2018-02-08 WO PCT/CN2018/075793 patent/WO2018210019A1/en not_active Ceased
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN2336006Y (en) * | 1998-08-21 | 1999-09-01 | 中国建筑科学研究院地基基础研究所 | Dry contruction composite driven cast-in-place pile |
| JP4670101B2 (en) * | 2006-10-23 | 2011-04-13 | 日本ヒューム株式会社 | Pre-boring precast concrete pile burying method. |
| CN101942830A (en) * | 2010-08-19 | 2011-01-12 | 上海强劲基础工程有限公司 | Combined concrete soil pile with core pile and construction method as well as construction device thereof |
| CN102251520A (en) * | 2011-05-27 | 2011-11-23 | 岳建伟 | Novel cement soil composite mixing pile and pile formation method thereof |
| CN102787595A (en) * | 2012-08-16 | 2012-11-21 | 岳建伟 | Double-acting self-stressing combined uplift pile and pile forming method |
| CN102839657A (en) * | 2012-09-12 | 2012-12-26 | 江苏兴鹏基础工程有限公司 | Cast-in-place pedestal tubular pile and construction method thereof |
| CN103015435A (en) * | 2012-12-04 | 2013-04-03 | 北京建材地质工程公司 | Long auger down hole hammer vibration rotary-jet steel reinforced cement-soil pile foundation pit water-resisting and supporting method |
Non-Patent Citations (1)
| Title |
|---|
| 北京土木建筑学会编: "《地基基础工程 施工技术、质量控制、实例手册》", 31 January 2008, 北京:中国电力出版社 * |
Cited By (13)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2018210019A1 (en) * | 2016-08-30 | 2018-11-22 | 北京荣创岩土工程股份有限公司 | Pile formation method for down-the-hole impact rotary jet composite piles |
| CN108104118A (en) * | 2018-01-03 | 2018-06-01 | 上海智平基础工程有限公司 | A kind of cast-in-place composite pile foundation structure and its construction method |
| CN108487236A (en) * | 2018-03-21 | 2018-09-04 | 中国建筑第六工程局有限公司 | A kind of cast-in-situ bored pile collapse hole in-situ treatment method |
| CN108179741A (en) * | 2018-03-26 | 2018-06-19 | 卓典机器人(海南)有限公司 | A kind of screw rod pile and combined drilling tool and its engineering method |
| CN109113058A (en) * | 2018-08-15 | 2019-01-01 | 绿山高科建设科技有限公司 | A kind of new type cement soil composite pile |
| CN110485410A (en) * | 2019-08-21 | 2019-11-22 | 天津建岩岩土工程有限公司 | Foundation pile pile making method |
| CN110847205A (en) * | 2019-11-08 | 2020-02-28 | 中煤江南建设发展有限公司 | A composite pile foundation structure and its construction method |
| CN113293756A (en) * | 2021-06-01 | 2021-08-24 | 北京建材地质工程有限公司 | Construction method of steel pipe inserted composite foundation and pile foundation of pneumatic down-the-hole hammer vibration jet grouting pile |
| CN113216155A (en) * | 2021-06-02 | 2021-08-06 | 刘守进 | Novel composite pile |
| CN113279395A (en) * | 2021-06-11 | 2021-08-20 | 隋付仁 | High-grouting-slurry-body built-in prestressed concrete pile construction process |
| CN113550303A (en) * | 2021-07-28 | 2021-10-26 | 建材桂林地质工程勘察院有限公司 | Pile-forming method of DTH impact high-pressure jetting composite pile |
| CN114169064A (en) * | 2021-12-28 | 2022-03-11 | 中国铁道科学研究院集团有限公司 | Size optimization combination method for down-the-hole impact cement-soil composite precast pile and application thereof |
| CN116752522A (en) * | 2023-07-05 | 2023-09-15 | 江苏建院营造股份有限公司 | Free-angle high-bearing composite expansion pile |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2018210019A1 (en) | 2018-11-22 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107023002A (en) | Down-the-hole impacts churning composite pile pile making method | |
| CN105780763B (en) | Mesoporous vibrates the construction method of casing retaining wall long auger guncreting pile | |
| US20060088388A1 (en) | Method and apparatus for providing a rammed aggregate pier | |
| CN104329020B (en) | A kind of reinforced long spire embedding rock construction equipment and technique thereof | |
| CN112281829A (en) | Composite pile foundation structure and construction method thereof | |
| CN112392400B (en) | Hole forming construction process for slope protection pile in complex geological environment | |
| CN109488202A (en) | A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed | |
| CN216239904U (en) | An existing building underpinning reinforcement connection structure | |
| CN101200893A (en) | Construction method of pile with bearing base | |
| CN107642041A (en) | Super large diameter hollow pile group anchorage | |
| CN105672307A (en) | Expanded-base combination end pile bearing foundation | |
| CN102400462A (en) | Secondary grouting small pile construction process in foundation anti-seismic reinforcement treatment | |
| CN105019431B (en) | Crush and complete alternate steep dip stratified rock masses Large Diameter Super-long Bored Piles construction method | |
| WO2022021469A1 (en) | Method for constructing pipeline sinking rammed and expanded cast-in-situ pile in sand or gravel layer | |
| CN107268608A (en) | Building waste earth-boring stake forming hole method | |
| KR100762991B1 (en) | Ready-made pile filling method to fill high strength mortar | |
| CN211421112U (en) | Double-casing pore-forming structure of karst geological pile foundation | |
| CN108071110A (en) | Rotary drilling rig Pile method under complex geological condition | |
| CN207484290U (en) | Super large diameter hollow pile group anchorage | |
| CN105714832B (en) | A kind of large size prefabricated building enclosure of deep basal pit and construction method | |
| CN105064332A (en) | Construction method for bearing base piles of square pile bodies | |
| CN108049401A (en) | A kind of screw thread rammed bulb pile and its construction method | |
| CN112523253A (en) | Construction method of reusable retaining wall | |
| CN106759296A (en) | Drainable irregular-section bamboo joint pipe pile and root planting type construction method thereof | |
| CN111926821A (en) | Construction method of novel slope protection pile |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170808 |
|
| RJ01 | Rejection of invention patent application after publication |