CN106836244A - Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall - Google Patents
Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall Download PDFInfo
- Publication number
- CN106836244A CN106836244A CN201710034318.5A CN201710034318A CN106836244A CN 106836244 A CN106836244 A CN 106836244A CN 201710034318 A CN201710034318 A CN 201710034318A CN 106836244 A CN106836244 A CN 106836244A
- Authority
- CN
- China
- Prior art keywords
- gabion
- pile
- retaining wall
- concrete
- cage
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G2/00—Vegetative propagation
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/02—Retaining or protecting walls
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- Civil Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Botany (AREA)
- Developmental Biology & Embryology (AREA)
- Environmental Sciences (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
Abstract
一种抗滑桩与格宾高挡墙联合防护陡坡路基的方法,包括以下步骤:(1)挖方弃碴再生各级料源;(2)抗滑桩施工(3);安装混凝土挡土板;(4)格宾高挡墙施工;(5)工序循环;(6)格宾高挡墙表面绿化。本发明的抗滑桩、格宾网箱与压实填土共同作用,构成一个共同承担荷载的整体结构,由此可使陡坡路基边坡保持持久稳定和长期安全运行;且本发明联合护坡可使格宾高挡墙呈陡立台阶式,减少了削坡土石方量和地表破坏,节约了填料、土地和植被资源。同时,格宾挡墙石料孔隙可植入土壤与植被,利于边坡绿化和生态恢复,产生了景观和生态、环保效益。
A method for protecting steep slope roadbed by combining anti-slip piles and gabion high retaining walls, comprising the following steps: (1) excavating waste slag to regenerate various levels of material sources; (2) anti-slip pile construction; (3) installation of concrete retaining plates; (4) gabion high retaining wall construction; (5) process cycle; (6) greening of the surface of the gabion high retaining wall. The anti-slip piles, gabion boxes and compacted fill of the present invention work together to form an integral structure that bears the load together, thereby maintaining the long-term stability and long-term safe operation of the steep slope roadbed slope; and the combined slope protection of the present invention can make the gabion high retaining wall steep and stepped, reducing the amount of earth and stone cut and surface damage, and saving filler, land and vegetation resources. At the same time, the pores in the gabion retaining wall stone can be implanted with soil and vegetation, which is beneficial to the greening of the slope and ecological restoration, and produces landscape, ecological and environmental benefits.
Description
技术领域technical field
本发明属于岩土工程中边坡防护技术领域,具体涉及一种抗滑桩与格宾高挡墙联合防护陡坡路基施工方法。The invention belongs to the technical field of slope protection in geotechnical engineering, and in particular relates to a construction method for combined protection of steep slope subgrades with anti-slide piles and gabion high retaining walls.
背景技术Background technique
在山区或丘陵地区兴建公路时,由于地质、地形和地貌条件复杂,使得高填方陡坡路基常常出现边坡滑塌等地质灾害。为此常用加筋高挡墙进行陡坡路基边坡防护。而加筋高挡墙存在较多缺陷,包括:①排水不畅产生渗透破坏;②格栅蠕变发生面墙“鼓肚”;③圬工防护造成的环境不协调。When building roads in mountainous or hilly areas, due to complex geological, topographical and topographical conditions, geological disasters such as side slope landslides often occur on high-fill steep slope subgrades. For this reason, reinforced high retaining walls are commonly used for steep slope subgrade slope protection. However, there are many defects in the reinforced high retaining wall, including: (1) seepage damage due to poor drainage; (2) “bulging” of the surface wall due to grid creep; (3) environmental incongruity caused by masonry protection.
在发明公开号为CN104612107A的《河道加筋格宾透水土工布复合生态护坡挡墙施工方法》发明专利中,公开了一种河道加筋格宾透水土工布复合生态护坡挡墙施工方法。格宾构件需符合工程要求由防腐处理的低碳钢丝编织而成的六边形双绞合钢丝网制成;依次进行格宾组装、格宾安装、石料填充、盖板绞合、碎石回填、土工格珊的铺设、透水无纺土工布的铺设、填土压实等工序。该发明提供的河道加筋格宾透水土工布复合生态护坡挡墙施工方法,可广泛应用于水利、航运、海岸、护坡、河堤、渠道、市政、道路、铁路、涵洞、园林、公园、地产小区等护坡挡墙施工,抗压强度大、抗冻型好、经济美观、安全可靠,但是该发明仅适用于河道护坡,不适用于山地、丘陵地区,且格宾构件中填充的石料需要从它处开采、运输。In the invention patent of "Construction method of river reinforced gabion permeable geotextile composite ecological slope protection and retaining wall" with the invention publication number CN104612107A, a construction method of river reinforced gabion permeable geotextile composite ecological slope protection and retaining wall is disclosed. The gabion components must meet the engineering requirements and are made of hexagonal double-stranded steel wire mesh woven by anti-corrosion treated low-carbon steel wires; the gabion assembly, gabion installation, stone filling, cover plate stranding, and gravel backfilling are carried out in sequence , Geogrid laying, permeable non-woven geotextile laying, filling compaction and other processes. The construction method of river reinforced gabion permeable geotextile composite ecological slope protection and retaining wall provided by the invention can be widely used in water conservancy, shipping, coast, slope protection, embankment, channel, municipal administration, road, railway, culvert, garden, park, real estate The construction of slope protection and retaining walls in residential areas has high compressive strength, good frost resistance, economical appearance, safety and reliability, but this invention is only suitable for river slope protection, not suitable for mountainous and hilly areas, and the stones filled in gabion components need to be obtained from It is mined and transported.
在发明公开号为CN204435395U的《一种重轨式挡墙与抗滑桩结合的边坡抗滑支挡结构》实用新型专利中,公开了一种重轨式挡墙与抗滑桩结合的边坡抗滑支挡结构。该实用新型涉及的支挡结构由设置重轨的挡土墙、配置重轨笼的抗滑桩组成。该实用新型在边坡上形成连续、易于施工的抗滑能力强的支挡结构,保证多道抗滑重轨插入边坡稳定地层以起到边坡整体抗滑作用,但是该实用新型中涉及的挡土墙会引发由于排水不畅导致的渗透破坏,且具有施工速度慢工期长、圬工防护造成环境不协调的缺点。In the utility model patent of "A Slope Anti-sliding Retaining Structure Combining Heavy Rail Retaining Wall and Anti-slide Pile" with the invention publication number CN204435395U, a side slope combined with heavy rail retaining wall and anti-slide pile is disclosed. Slope anti-skid retaining structure. The support and retaining structure involved in the utility model is composed of a retaining wall provided with heavy rails and anti-sliding piles equipped with heavy rail cages. This utility model forms a continuous and easy-to-construct support structure with strong anti-sliding ability on the slope to ensure that multiple anti-sliding heavy rails are inserted into the stable stratum of the slope to play the role of overall anti-sliding of the slope. However, the utility model involves The retaining wall will cause seepage damage due to poor drainage, and has the disadvantages of slow construction speed and long construction period, and masonry protection will cause uncoordinated environment.
抗滑桩与格宾高挡墙联合护坡结构可克服加筋高挡墙的固有缺陷。在该结构中,抗滑桩与格宾高挡墙(包括格宾网箱、拉筋网面与压实填土)共同作用,构成了一个可共同承载土压力的整体结构,从而实现陡坡路基边坡联合防护。抗滑桩不仅可支挡土体,还能收缩坡脚、少占土地;而格宾高挡墙具有支挡与填方双重功能。The combined slope protection structure of anti-sliding piles and gabion high retaining walls can overcome the inherent defects of reinforced high retaining walls. In this structure, the anti-slide piles and the high gabion retaining wall (including the gabion cage, the reinforcement mesh surface and the compacted fill) work together to form an overall structure that can jointly bear the earth pressure, thereby realizing the steep slope subgrade Joint slope protection. Anti-slide piles can not only support the retaining soil, but also shrink the slope toe and occupy less land; while the gabion high retaining wall has dual functions of retaining and filling.
格宾高挡墙具有安全稳定、排水通畅、经济耐久和生态环保等优点,可为复杂地质条件下陡坡路基边坡防护提供施工快捷、长期稳定和安全可靠的新型支挡结构,尤其适用于渗流条件复杂和渗透强度较高条件下景观道路陡坡路基防护工程施工。The gabion high retaining wall has the advantages of safety and stability, smooth drainage, economical durability and ecological environmental protection. It can provide a new retaining structure with fast construction, long-term stability, safety and reliability for the protection of steep slope subgrade slopes under complex geological conditions, especially for seepage Under the conditions of complex conditions and high seepage strength, the construction of steep slope subgrade protection works for landscape roads.
此外,陡坡路基施工过程中会产生大量的挖方弃碴,而弃碴堆放则会破坏地表植被、诱发水土流失,最终危害周边生态环境。因此,对挖方弃碴进行分选、破碎和筛分再生处理,可获得格宾网箱填充石料,这既可缓解天然建材紧缺问题,又能避免弃碴堆放造成的土地占用和环境污染问题。In addition, during the construction of steep slope subgrades, a large amount of excavation and waste dregs will be generated, and the accumulation of waste dregs will destroy surface vegetation, induce water and soil erosion, and ultimately endanger the surrounding ecological environment. Therefore, sorting, crushing, screening and recycling the excavated dregs can obtain the filling stones for gabion cages, which can not only alleviate the shortage of natural building materials, but also avoid land occupation and environmental pollution caused by dregs piled up.
发明内容Contents of the invention
本发明的目的在于克服现有技术之不足,提供一种抗滑桩与格宾高挡墙联合防护陡坡路基的方法,为陡坡路基加固和挖方弃碴处置提供一条切实可行的技术途径。The purpose of the present invention is to overcome the deficiencies of the prior art, provide a method for combined protection of steep slope subgrades with anti-slide piles and gabion high retaining walls, and provide a feasible technical approach for steep slope subgrade reinforcement and excavation disposal.
为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:
一种抗滑桩与格宾高挡墙联合防护陡坡路基的方法,包括以下步骤:A method for combined protection of steep slope subgrades with anti-slide piles and Gabion high retaining walls, comprising the following steps:
(1)挖方弃碴再生各级料源(1) Excavation and disposal of dregs to regenerate material sources at all levels
在陡坡路基施工现场,依次采用分选、破碎和筛分技术手段,对挖方弃碴进行就地再生,获得格宾网箱填充用石料和陡坡路基用回填料源,所述石料和所述回填料源均包括不同粒径范围的各类再生材料;At the construction site of the steep slope subgrade, sorting, crushing and screening techniques are used sequentially to regenerate the excavated muck on site to obtain stone materials for filling gabion cages and backfill sources for steep slope subgrades. Filler sources include various recycled materials in different particle size ranges;
(2)抗滑桩施工(2) Anti-slide pile construction
在完成场地平整、桩位测定和井架安装准备工作后,即可正式开展抗滑桩施工工作,包括:地下桩孔开挖、桩身混凝土浇筑和地上桩柱施工;After completing the site leveling, pile position measurement and derrick installation preparations, the anti-slide pile construction work can be officially carried out, including: underground pile hole excavation, pile body concrete pouring and ground pile construction;
1)地下桩孔开挖1) Excavation of underground pile holes
①锁口①Lock
为了保证地下桩孔孔口稳定,在地下桩孔挖至2m深时,立模浇注壁厚为20cm±5cm的C25钢筋混凝土锁口护壁,锁口顶面平整,且高出施工场地的地面55cm;In order to ensure the stability of the underground pile hole opening, when the underground pile hole is dug to a depth of 2m, a C25 reinforced concrete locking wall with a wall thickness of 20cm±5cm is cast in the vertical form, and the top surface of the locking hole is flat and 55cm above the ground of the construction site ;
②开挖与出碴② Excavation and ballasting
从上到下逐层开挖地下桩孔,先挖地下桩孔中间的土方,再扩及地下桩孔的边界处;在地下桩孔内人工装碴,再使用提升设备运碴,并将弃碴运至堆场堆放;在地下桩孔开挖过程中,要求边开挖地下桩孔边护壁,且地下桩孔每挖入2m深时护壁1次;Excavate the underground pile holes layer by layer from top to bottom, first dig the earthwork in the middle of the underground pile holes, and then expand to the boundary of the underground pile holes; manually load the ballast in the underground pile holes, then use the lifting equipment to transport the ballast, and put The ballast is transported to the storage yard for stacking; during the excavation of the underground pile hole, it is required to excavate the underground pile hole while retaining the wall, and the wall should be protected once every time the underground pile hole is dug into a depth of 2m;
③护壁③ retaining wall
首先,在地下桩孔内安装护壁钢模,并依据地下桩孔的中轴线校正护壁钢模的位置,且上下两相邻护壁之间搭接50mm长;护壁钢模安装好后浇注护壁混凝土,并在护壁混凝土强度达到设计强度后拆掉护壁钢模;Firstly, install the retaining wall steel form in the underground pile hole, and correct the position of the retaining wall steel form according to the central axis of the underground pile hole, and the overlap between the upper and lower two adjacent retaining walls is 50mm long; after the retaining wall steel form is installed, pour the retaining wall concrete, And remove the retaining wall steel mold after the strength of retaining wall concrete reaches the design strength;
2)桩身混凝土浇筑2) Pile body concrete pouring
①下放钢筋笼:首先,按照设计要求配筋,并在地表绑扎、焊接成钢筋笼;最后,采用卷扬机将钢筋笼放入地下桩孔内;① Lowering the reinforcement cage: firstly, according to the design requirements, reinforce the reinforcement, tie and weld the reinforcement cage on the surface; finally, use the winch to put the reinforcement cage into the underground pile hole;
②浇筑桩身混凝土:使用串筒或吊车将混凝土输送至地下桩孔内,然后向地下桩孔浇筑桩身混凝土,桩身混凝土分层进行浇筑,且每层桩身混凝土捣固后的厚度≤30cm;②Pouring concrete for pile body: Use string tube or crane to transport concrete to the underground pile hole, then pour concrete for pile body into the underground pile hole, pour concrete for pile body in layers, and the thickness of concrete for each layer of pile body after tamping is ≤ 30cm;
③成桩质检:桩身混凝土与钢筋笼形成地下桩后,采用无损法测地下桩质量;③Pile quality inspection: After the concrete of the pile body and the steel cage form an underground pile, the quality of the underground pile is measured by a non-destructive method;
3)地上桩柱施工3) Ground pile construction
①连接桩头① Connect the pile head
首先,破除和清理地下桩的桩头;而后,顺直和焊接地下桩的桩头中的竖向钢筋、箍筋;First, break and clean the pile head of the underground pile; then, straighten and weld the vertical steel bars and stirrups in the pile head of the underground pile;
②搭设脚手架②Set up scaffolding
脚手架长与宽均超出地上桩柱模板的边缘2.0m,且脚手架的高度超出地上桩柱模板高度1.2m;Both the length and width of the scaffold exceed the edge of the pile formwork on the ground by 2.0m, and the height of the scaffold exceeds the height of the pile formwork on the ground by 1.2m;
③架设钢筋笼③Establish the reinforcement cage
地上桩柱高6~8m;地上桩柱钢筋笼一次焊接成型;分批次浇筑地上桩柱混凝土,且一次浇筑高度为3.0m;The height of the above-ground pile is 6-8m; the steel cage of the above-ground pile is welded and formed at one time; the concrete of the above-ground pile is poured in batches, and the height of one-time pouring is 3.0m;
④配置模板④Configuration template
为加快施工进度,配备桩柱模板;地上桩柱钢筋笼外挂垫块作为保护层;In order to speed up the construction progress, the pile formwork is equipped; the external pads of the pile reinforcement cage on the ground are used as a protective layer;
⑤浇筑混凝土⑤Pouring concrete
采用吊车吊运混凝土,向地上桩柱钢筋笼内持续浇筑混凝土,以构成地上桩柱;The concrete is hoisted by a crane, and the concrete is continuously poured into the reinforcement cage of the above-ground piles to form the above-ground piles;
(3)安装混凝土挡土板(3) Install concrete retaining board
沿道路走向按上述步骤(1)-(2)间隔设置若干个所述抗滑桩,在抗滑桩靠近陡坡路基一侧,分段安装预制的混凝土挡土板,并使混凝土挡土板连接成一体;Along the road direction, several anti-slide piles are arranged at intervals according to the above steps (1)-(2). On the side of the anti-slide piles close to the steep slope subgrade, install prefabricated concrete retaining boards in sections, and connect the concrete retaining boards into one;
(4)格宾高挡墙施工(4) Construction of gabion high retaining wall
地上桩柱与路基顶面围合成填方区域,在填方区域进行多级台阶式格宾高挡墙施工;The piles on the ground and the top surface of the subgrade form a filling area, and the multi-level stepped Gabion high retaining wall construction is carried out in the filling area;
1)格宾网箱安装1) Gabion cage installation
①格宾网箱拼装① Gabion cage assembly
展开格宾网箱,拉伸褶皱,采用不锈钢钢丝系扣环连接格宾网箱;Expand the gabion cage, stretch the folds, and connect the gabion cage with a stainless steel wire buckle ring;
②格宾网箱码砌② Gabion cage code construction
将格宾网箱分层安放于指定位置;并在格宾网箱码砌时校正扭曲变形,并校正折起尺寸;Lay the gabion cages in the designated position in layers; and correct the distortion and deformation when the gabion cages are stacked, and correct the folded size;
③格宾网箱连接③ Gabion cage connection
使用直径不小于3.0mm的捆绑钢丝采用连续缠绕法,将各个格宾网箱连接成整体;Use the bundled steel wire with a diameter of not less than 3.0mm to connect each gabion cage into a whole by continuous winding method;
2)格宾网箱填充2) Gabion cage filling
用所述石料填充码放好的格宾网箱,且石料分层投放,每层厚度为1/3倍的格宾网箱高度,为防格宾网箱扭曲变形,相邻两格宾网箱的石料表层高度差≤35cm;每投放一层石料,进行人工捣实调整,确保密实度和平整度;Use the stones to fill the stacked gabion cages, and put the stones in layers. The thickness of each layer is 1/3 times the height of the gabion cages. In order to prevent the gabion cages from twisting and deforming, two adjacent gabion cages The height difference of the surface layer of stone materials is ≤35cm; each layer of stone materials is put in and adjusted by manual tamping to ensure the compactness and flatness;
在每层石料的上表面处,加设加强筋以防格宾网箱鼓胀;加强筋为不锈钢钢丝线,绑扎时必须穿过两个及以上的格宾网箱的网眼;对于位处边缘的两个格宾网箱,应用45°的斜交加强筋;On the upper surface of each layer of stone, add reinforcing ribs to prevent the gabion cages from bulging; the reinforcing ribs are stainless steel wires, which must pass through the meshes of two or more gabion cages when binding; For two gabion cages, 45° oblique ribs shall be applied;
3)墙后回填3) Backfilling behind the wall
首先,为阻止陡坡路基回填料源随水流而渗入格宾网箱内部,每施工完1层格宾网箱后,必须在格宾高挡墙靠近路基一侧的背部与填方区域间铺设反滤无纺土工布,且反滤无纺土工布应在每层格宾网箱上表面与拉筋网面上各折入长度为m的一段,m取值30cm;First of all, in order to prevent the backfill source of the steep slope roadbed from infiltrating into the gabion cage with the water flow, after each layer of gabion cage is constructed, a reverse wall must be laid between the back of the gabion high retaining wall near the roadbed and the filling area. Filter non-woven geotextiles, and anti-filter non-woven geotextiles should be folded into a section of length m on the upper surface of each layer of gabion cages and the reinforcement mesh surface, and the value of m is 30cm;
而后,采用由边缘向中间、逐步推进的顺序,在拉筋网面上分层摊铺、压实填料,层厚为20~30cm;Then, step by step from the edge to the middle, pave and compact the filler layer by layer on the reinforcement mesh surface, with a layer thickness of 20-30cm;
同时分层填筑陡坡路基,所述回填料源是再生弃碴和挖方弃土,并以如砂、砂砾和黏性土等天然填料作为有效补充;At the same time, the steep slope subgrade is filled in layers, and the backfill source is recycled spoil and excavation spoil, and natural fillers such as sand, gravel and clay are used as effective supplements;
(5)工序循环(5) Process cycle
重复(4)所述施工工序,直至格宾高挡墙及其墙后回填达到设计高程;Repeat the construction process described in (4) until the backfilling of the Gabion high retaining wall and its wall reaches the design elevation;
在施工过程中,上、下两层格宾网箱应错开码砌、并绑扎固定,以防通缝出现和水平错动;During the construction process, the upper and lower layers of gabion cages should be staggered and fixed, so as to prevent through joints and horizontal displacement;
为保持结构稳定,对于高度>12m的格宾高挡墙,每隔6m高度位置设置1个平台,使整个格宾挡墙分隔成多级台阶形式,每级格宾挡墙坡度由下而上渐进增加,格宾网箱按照阶梯形状码砌形成多级台阶式格宾高挡墙,且每级格宾高挡墙的坡度由下而上递增;In order to keep the structure stable, for the high gabion retaining wall with a height of >12m, set up a platform every 6m height, so that the whole gabion retaining wall is divided into multi-level steps, and the slope of each level of gabion retaining wall is from bottom to top Gradual increase, the gabion cages are stacked according to the shape of the ladder to form a multi-level stepped gabion high retaining wall, and the slope of each level of the gabion high retaining wall increases from bottom to top;
(6)格宾高挡墙表面绿化(6) Surface greening of Gabion high retaining wall
格宾高挡墙施工至设计标高后,根据土壤、气候和景观要求,优选确定所需草种或灌木类型,尽早实施边坡绿化工作:①在格宾网箱临空一侧进行喷播植草处理;②在各层格宾网箱搭接空余位置铺设植生袋;③在格宾高挡墙顶部边坡位置进行草灌混种绿化坡面;After the construction of the gabion high retaining wall reaches the design elevation, according to the soil, climate and landscape requirements, the required grass species or shrub types are optimally determined, and the slope greening work is carried out as soon as possible: ① Spray and plant grass on the empty side of the gabion cage treatment; ② Lay planting bags in the vacant positions where the gabion cages overlap on each layer; ③ Carry out grass-shrub mixed planting greening slopes at the top slope of the gabion high retaining wall;
进一步,步骤(1)中所述的再生材料是粗骨料、细骨料和细粒土。Further, the recycled materials described in step (1) are coarse aggregate, fine aggregate and fine-grained soil.
本发明的有益效果主要表现在:The beneficial effects of the present invention are mainly manifested in:
(1)安全稳定(1) Safe and stable
抗滑桩与格宾高挡墙联合使用,可使陡坡路基保持持久性的边坡稳定和运营安全。The combination of anti-slide piles and high gabion retaining wall can make the steep slope subgrade maintain permanent slope stability and operational safety.
(2)排水顺畅(2) smooth drainage
格宾网箱内的石料渗透性能良好,可有效疏导静/动水压力,克服了加筋挡墙因排水不畅而诱发渗透破坏的固有缺陷。The stone material in the gabion cage has good permeability, which can effectively relieve the static/dynamic water pressure, and overcome the inherent defect of seepage damage induced by the poor drainage of the reinforced retaining wall.
(3)生态环保(3) Ecological and environmental protection
格宾网箱顶面可铺设植生袋,内部石料孔隙可喷播植草,利于水土保持、边坡绿化和生态恢复,具有经济、环保和景观等多重功效。Vegetation bags can be laid on the top surface of the gabion cage, and grass can be sprayed and planted in the internal stone pores, which is beneficial to water and soil conservation, slope greening and ecological restoration, and has multiple functions such as economy, environmental protection and landscape.
(4)施工快捷(4) Fast construction
格宾高挡墙部件成品化率高,现场拼接安装操作简单、快捷,施工要求较低(既可完全机械化施工,亦可于局部人工辅助施工),由此可以有效缩短施工工期。Gabion high retaining wall components have a high rate of finished products, on-site splicing and installation operations are simple and fast, and construction requirements are low (either fully mechanized construction or partially artificially assisted construction), which can effectively shorten the construction period.
附图说明Description of drawings
图1是格宾网箱的结构示意图。Fig. 1 is a structural schematic diagram of a gabion cage.
图2是按本发明施工的施工状态侧视图。Fig. 2 is a construction state side view of construction according to the present invention.
图3是按本发明施工的施工状态俯视图。Fig. 3 is the top view of the construction state of construction according to the present invention.
图4是反滤无纺土工布施工状态示意图。Figure 4 is a schematic diagram of the construction state of the reverse filter non-woven geotextile.
具体实施方式detailed description
参照附图,一种抗滑桩与格宾高挡墙联合防护陡坡路基的方法,包括以下步骤:With reference to the accompanying drawings, a method for jointly protecting steep slope subgrades with anti-slide piles and high gabion retaining walls comprises the following steps:
(1)挖方弃碴再生各级料源(1) Excavation and disposal of dregs to regenerate material sources at all levels
在陡坡路基施工现场,依次采用分选、破碎和筛分技术手段,对挖方弃碴进行就地再生,获得格宾网箱填充用石料和陡坡路基用回填料源,所述石料和所述回填料源均包括不同粒径范围的各类再生材料;At the construction site of the steep slope subgrade, sorting, crushing and screening techniques are used sequentially to regenerate the excavated muck on site to obtain stone materials for filling gabion cages and backfill sources for steep slope subgrades. Filler sources include various recycled materials in different particle size ranges;
所述石料:要求质地坚硬,表面洁净,具备一定的耐久性,抗压强度不小于30MPa,表观密度>2.5g/cm3,孔隙率<20%,粒径控制在12~30cm,料径大于30cm或小于12cm的石料含量控制在4.5%-5.5%之间;The stone material: requires hard texture, clean surface, certain durability, compressive strength not less than 30MPa, apparent density > 2.5g/cm 3 , porosity < 20%, particle size controlled at 12-30cm, material diameter The stone content greater than 30cm or less than 12cm is controlled between 4.5% and 5.5%;
所述回填料源,对挖方弃碴采用Talbot级配理论设计获得具有连续密级配的陡坡路基回填所需料源,从而达到减小孔隙比和增加压实度,以及控制工后沉降的目的;The backfill source is designed using the Talbot gradation theory to obtain the material source required for backfilling the steep slope roadbed with continuous dense gradation, so as to achieve the purpose of reducing the void ratio and increasing the compaction degree, as well as controlling post-construction settlement;
(2)抗滑桩200施工(2) Construction of anti-slide pile 200
在完成场地平整、桩位测定和井架安装准备工作后,即可正式开展抗滑桩200施工工作,包括:地下桩孔开挖、桩身混凝土浇筑和地上桩柱施工;After completing the site leveling, pile position measurement and derrick installation preparations, the anti-slide pile 200 construction work can be officially carried out, including: underground pile hole excavation, pile body concrete pouring and ground pile construction;
1)地下桩孔开挖1) Excavation of underground pile holes
①锁口①Lock
为了保证地下桩孔孔口稳定,在地下桩孔挖至2m深时,立模浇注壁厚为20cm±5cm的C25钢筋混凝土锁口护壁,锁口顶面平整,且高出施工场地的地面55cm;In order to ensure the stability of the underground pile hole opening, when the underground pile hole is dug to a depth of 2m, a C25 reinforced concrete locking wall with a wall thickness of 20cm±5cm is cast in the vertical form, and the top surface of the locking hole is flat and 55cm above the ground of the construction site ;
②开挖与出碴② Excavation and ballasting
从上到下逐层开挖地下桩孔,先挖地下桩孔中间的土方,再扩及地下桩孔的边界处;在地下桩孔内人工装碴,再使用提升设备运碴,并将弃碴运至堆场堆放;在地下桩孔开挖过程中,要求边开挖地下桩孔边护壁,且地下桩孔每挖入2m深时护壁1次;Excavate the underground pile holes layer by layer from top to bottom, first dig the earthwork in the middle of the underground pile holes, and then expand to the boundary of the underground pile holes; manually load the ballast in the underground pile holes, then use the lifting equipment to transport the ballast, and put The ballast is transported to the storage yard for stacking; during the excavation of the underground pile hole, it is required to excavate the underground pile hole while retaining the wall, and the wall should be protected once every time the underground pile hole is dug into a depth of 2m;
③护壁③ retaining wall
首先,在地下桩孔内安装护壁钢模,并依据地下桩孔的中轴线校正护壁钢模的位置,且上下两相邻护壁之间搭接50mm长;护壁钢模安装好后浇注护壁混凝土,并在护壁混凝土强度达到设计强度后拆掉护壁钢模;Firstly, install the retaining wall steel form in the underground pile hole, and correct the position of the retaining wall steel form according to the central axis of the underground pile hole, and the overlap between the upper and lower two adjacent retaining walls is 50mm long; after the retaining wall steel form is installed, pour the retaining wall concrete, And remove the retaining wall steel mold after the strength of retaining wall concrete reaches the design strength;
2)桩身混凝土浇筑2) Pile body concrete pouring
①下放钢筋笼:首先,按照设计要求配筋,并在地表绑扎、焊接成钢筋笼;最后,采用卷扬机将钢筋笼放入地下桩孔内;① Lowering the reinforcement cage: firstly, according to the design requirements, reinforce the reinforcement, tie and weld the reinforcement cage on the surface; finally, use the winch to put the reinforcement cage into the underground pile hole;
②浇筑桩身混凝土:使用串筒或吊车将混凝土输送至地下桩孔内,然后向地下桩孔浇筑桩身混凝土,桩身混凝土分层进行浇筑,且每层桩身混凝土捣固后的厚度≤30cm;②Pouring concrete for pile body: Use string tube or crane to transport concrete to the underground pile hole, then pour concrete for pile body into the underground pile hole, pour concrete for pile body in layers, and the thickness of concrete for each layer of pile body after tamping is ≤ 30cm;
③成桩质检:桩身混凝土与钢筋笼形成地下桩后,采用无损法测地下桩质量,要求地下桩的桩身混凝土质量达到Ⅱ类桩以上标准,其中Ⅰ类桩达90%以上,严禁出现Ⅲ类桩;③ Pile Quality Inspection: After the pile body concrete and the steel cage form an underground pile, the quality of the underground pile is measured by a non-destructive method. Class III piles appear;
3)地上桩柱施工3) Ground pile construction
①连接桩头① Connect the pile head
首先,破除和清理地下桩的桩头;而后,顺直和焊接地下桩的桩头中的竖向钢筋、箍筋;First, break and clean the pile head of the underground pile; then, straighten and weld the vertical steel bars and stirrups in the pile head of the underground pile;
②搭设脚手架②Set up scaffolding
脚手架长与宽均超出地上桩柱模板的边缘2.0m,且脚手架的高度超出地上桩柱模板高度1.2m;Both the length and width of the scaffold exceed the edge of the pile formwork on the ground by 2.0m, and the height of the scaffold exceeds the height of the pile formwork on the ground by 1.2m;
③架设钢筋笼③Establish the reinforcement cage
地上桩柱高6~8m;地上桩柱钢筋笼一次焊接成型;分批次浇筑地上桩柱混凝土,且一次浇筑高度为3.0m;The height of the above-ground pile is 6-8m; the steel cage of the above-ground pile is welded and formed at one time; the concrete of the above-ground pile is poured in batches, and the height of one-time pouring is 3.0m;
④配置模板④Configuration template
为加快施工进度,配备3套桩柱模板,每套长22m(包括5m和6m各两节);地上桩柱钢筋笼外挂垫块作为保护层;In order to speed up the construction progress, 3 sets of pile templates are equipped, each set is 22m long (including two sections of 5m and 6m); the external pads of the pile reinforcement cage on the ground are used as a protective layer;
⑤浇筑混凝土⑤Pouring concrete
采用吊车吊运混凝土,向地上桩柱钢筋笼内持续浇筑混凝土,以构成地上桩柱;The concrete is hoisted by a crane, and the concrete is continuously poured into the reinforcement cage of the above-ground piles to form the above-ground piles;
(3)安装混凝土挡土板300(3) Install concrete retaining board 300
沿道路走向d按上述步骤(1)-(2)间隔设置若干个所述抗滑桩200,在抗滑桩200靠近陡坡路基一侧,分段安装预制的混凝土挡土板300,并使混凝土挡土板300连接成一体;Along the road direction d, several described anti-slide piles 200 are arranged at intervals according to the above steps (1)-(2). On the side of the anti-slide pile 200 near the steep slope subgrade, install prefabricated concrete retaining boards 300 in sections, and make the concrete The retaining plate 300 is connected into one;
(4)格宾高挡墙施工(4) Construction of gabion high retaining wall
地上桩柱与路基顶面500围合成填方区域600,在填方区域600进行多级台阶式格宾高挡墙施工;The piles on the ground and the top surface of the subgrade 500 surround the composite filling area 600, and the multi-level stepped gabion high retaining wall construction is carried out in the filling area 600;
1)格宾网箱安装1) Gabion cage installation
①格宾网箱100拼装①Assembly of 100 gabion cages
展开格宾网箱100,拉伸褶皱,采用不锈钢钢丝系扣环连接格宾网箱100;Unfold the gabion cage 100, stretch the folds, and connect the gabion cage 100 with stainless steel wire fastening rings;
②格宾网箱100码砌② 100 yards of gabion cage
将格宾网箱100分层安放于指定位置;并在格宾网箱100码砌时校正扭曲变形,并用卷尺校正折起尺寸;Lay the gabion cage 100 in layers at the designated location; and correct the distortion when the gabion cage is 100 yards in size, and correct the folded size with a tape measure;
③格宾网箱100连接③ Gabion cage 100 connection
使用直径不小于3.0mm的捆绑钢丝采用连续缠绕法,将各个格宾网箱100连接成整体;Use a bundled steel wire with a diameter of not less than 3.0mm and adopt a continuous winding method to connect each gabion cage 100 into a whole;
2)格宾网箱100填充2) Gabion cage 100 filling
用所述石料填充码放好的格宾网箱100,且石料分层投放,每层厚度为1/3倍的格宾网箱100高度,为防格宾网箱扭曲变形,相邻两格宾网箱100的石料表层高度差≤35cm;每投放一层石料,进行人工捣实调整,确保密实度和平整度;Fill the gabion cage 100 that has been placed with the stone material, and put the stone material in layers, and the thickness of each layer is 1/3 times the height of the gabion cage 100. In order to prevent the gabion cage from twisting and deforming, two adjacent gabion cages The height difference of the stone surface layer of the net cage 100 is ≤ 35cm; every layer of stone is put in, and manual tamping is carried out to ensure the compactness and flatness;
在每层石料的上表面处,加设加强筋以防格宾网箱100鼓胀;加强筋为不锈钢钢丝线,绑扎时必须穿过两个及以上的格宾网箱的网眼;对于位处边缘的两个格宾网箱100,应用45°的斜交加强筋;On the upper surface of each layer of stone, add reinforcing ribs to prevent the gabion cages from bulging; the reinforcing ribs are stainless steel wires, which must pass through the meshes of two or more gabion cages when binding; For the two gabion cages 100, 45° oblique reinforcing ribs shall be applied;
3)墙后回填3) Backfilling behind the wall
首先,为阻止陡坡路基回填料源随水流而渗入格宾网箱内部,每施工完1层格宾网箱后,必须在格宾高挡墙靠近路基一侧的背部与填方区域间铺设反滤无纺土工布700,且反滤无纺土工布700应在每层格宾网箱上表面与拉筋网面103上各折入长度为m的一段,m取值30cm;First of all, in order to prevent the backfill source of the steep slope roadbed from infiltrating into the gabion cage with the water flow, after each layer of gabion cage is constructed, a reverse wall must be laid between the back of the gabion high retaining wall near the roadbed and the filling area. The filter non-woven geotextile 700, and the reverse filter non-woven geotextile 700 should be folded into a section with a length of m on the upper surface of each layer of the gabion cage and the reinforcement mesh surface 103, and the value of m is 30cm;
而后,采用由边缘向中间、逐步推进的顺序,在拉筋网面上分层摊铺、压实填料,层厚为20~30cm;Then, step by step from the edge to the middle, pave and compact the filler layer by layer on the reinforcement mesh surface, with a layer thickness of 20-30cm;
同时分层填筑陡坡路基,所述回填料源是再生弃碴和挖方弃土,并以如砂、砂砾和黏性土等天然填料作为有效补充;At the same time, the steep slope subgrade is filled in layers, and the backfill source is recycled spoil and excavation spoil, and natural fillers such as sand, gravel and clay are used as effective supplements;
(5)工序循环(5) Process cycle
重复(4)所述施工工序,直至格宾高挡墙及其墙后回填达到设计高程;Repeat the construction process described in (4) until the backfilling of the Gabion high retaining wall and its wall reaches the design elevation;
在施工过程中,上、下两层格宾网箱100应错开码砌、并绑扎固定,以防通缝出现和水平错动;During the construction process, the upper and lower layers of gabion cages 100 should be staggered and fixed, so as to prevent through joints and horizontal displacement;
为保持结构稳定,对于高度>12m的格宾高挡墙,每隔6m高度位置设置1个平台a、b,使整个格宾挡墙分隔成多级台阶形式,每级格宾挡墙坡度由下而上渐进增加,格宾网箱100按照阶梯形状码砌形成多级台阶式格宾高挡墙,且每级格宾高挡墙的坡度由下而上递增;In order to keep the structure stable, for the high gabion retaining wall with a height of >12m, a platform a, b is set at every 6m height, so that the whole gabion retaining wall is divided into multi-level steps, and the slope of each gabion retaining wall is determined by Gradually increase from bottom to top, and the gabion cages 100 are stacked according to the ladder shape to form a multi-level stepped gabion high retaining wall, and the slope of each level of gabion high retaining wall increases from bottom to top;
(6)格宾高挡墙表面绿化(6) Greening of the surface of the Gabion High Retaining Wall
格宾高挡墙施工至设计标高后,根据土壤、气候和景观要求,优选确定所需草种或灌木类型,尽早实施边坡绿化工作:①在格宾网箱100临空一侧进行喷播植草处理;②在各层格宾网箱100搭接空余位置铺设植生袋;③在格宾高挡墙顶部边坡位置进行草灌混种绿化坡面;After the construction of the gabion high retaining wall reaches the design elevation, according to the soil, climate and landscape requirements, the required grass species or shrub types are optimally determined, and the slope greening work is carried out as soon as possible: ① spray seeding on the side of the gabion cage 100 Grass planting treatment; ② Lay planting bags in the vacant positions of the gabion cages 100 on each layer; ③ Carry out grass-shrub mixed planting greening slopes at the top slope of the gabion high retaining wall;
进一步,步骤(1)中所述的再生材料是粗骨料、细骨料和细粒土。Further, the recycled materials described in step (1) are coarse aggregate, fine aggregate and fine-grained soil.
格宾网箱100由格宾网片101、横隔板102、拉筋网面103和网盖104构成:将格宾网片101垂直立起,拉伸因折叠而引起的褶皱,平整格宾网片,先采用格宾网片101在拉筋网面103上围合成顶部开口的箱状,再在格宾网箱100内插入横隔板102,最后盖上网盖104,拉筋网面103向外水平延伸,便于压实。The gabion cage 100 is composed of a gabion mesh 101, a transverse partition 102, a reinforcement mesh surface 103 and a mesh cover 104: the gabion mesh 101 is erected vertically, and the folds caused by folding are stretched to smooth the gabion Mesh, first use the gabion mesh 101 to form a box shape with an open top on the tension mesh surface 103, then insert the transverse partition 102 in the gabion cage 100, and finally cover the upper cover 104, and the tension mesh surface 103 Extends horizontally outward for easy compaction.
格宾高挡墙内设有PVC排水管400,以便于排水。The gabion high retaining wall is provided with a PVC drainage pipe 400 to facilitate drainage.
本说明书实施例所述的内容仅仅是对发明构思的实现形式的列举,本发明的保护范围不应当被视为仅限于实施例所陈述的具体形式,本发明的保护范围也包括本领域技术人员根据本发明构思所能够想到的等同技术手段。The content described in the embodiments of this specification is only an enumeration of the implementation forms of the inventive concept. The protection scope of the present invention should not be regarded as limited to the specific forms stated in the embodiments. The protection scope of the present invention also includes those skilled in the art. Equivalent technical means conceivable according to the concept of the present invention.
Claims (2)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710034318.5A CN106836244A (en) | 2017-01-17 | 2017-01-17 | Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710034318.5A CN106836244A (en) | 2017-01-17 | 2017-01-17 | Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN106836244A true CN106836244A (en) | 2017-06-13 |
Family
ID=59124157
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710034318.5A Pending CN106836244A (en) | 2017-01-17 | 2017-01-17 | Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106836244A (en) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700500A (en) * | 2017-09-14 | 2018-02-16 | 深圳百勤建设工程有限公司 | Slope retaining structure and slope supporting draining integral system |
| CN108086352A (en) * | 2018-02-01 | 2018-05-29 | 云南新创新交通建设股份有限公司 | A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure |
| CN108487269A (en) * | 2018-06-11 | 2018-09-04 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method of ecological assembled framework supporting form |
| CN109577351A (en) * | 2019-01-25 | 2019-04-05 | 中建五局土木工程有限公司 | Earthwork evacuation safety protection structure and earthwork evacuation safety protecting method |
| CN110055826A (en) * | 2019-04-28 | 2019-07-26 | 中铁二院工程集团有限责任公司 | A kind of enhanced ballast bed structure of cutting cogwheel railway and construction method |
| CN110747887A (en) * | 2019-10-27 | 2020-02-04 | 中铁二院工程集团有限责任公司 | Pile-supported gabion retaining wall structure and its construction method |
| CN113073680A (en) * | 2021-04-25 | 2021-07-06 | 中铁二院工程集团有限责任公司 | Slag disposal site retaining wall structure of plateau high-cold area and construction method thereof |
| CN113430987A (en) * | 2021-07-01 | 2021-09-24 | 长江勘测规划设计研究有限责任公司 | Ecological retaining wall structure capable of utilizing river channel excavation soil materials in situ and construction method thereof |
| CN114892710A (en) * | 2022-05-17 | 2022-08-12 | 湖北工业大学 | A tree-supported retaining wall and its construction method |
| CN115659460A (en) * | 2022-10-18 | 2023-01-31 | 中国电建集团昆明勘测设计研究院有限公司 | Airport stainless steel sewage interception and water diversion design method |
| CN116988509A (en) * | 2023-08-23 | 2023-11-03 | 北京市市政工程研究院 | Modular geogrid retaining wall with construction waste as filler and construction method |
Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103410167A (en) * | 2013-08-29 | 2013-11-27 | 深圳市福田建安建设集团有限公司 | Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method |
| CN203320547U (en) * | 2013-05-22 | 2013-12-04 | 中铁二院工程集团有限责任公司 | Gabion retaining wall with mixed padding |
| CN104018490A (en) * | 2014-05-13 | 2014-09-03 | 中冶集团武汉勘察研究院有限公司 | Z-shaped rectangular-section anti-skidding pile and construction method thereof |
| CN104612107A (en) * | 2015-02-02 | 2015-05-13 | 成军 | River channel reinforced gabion and water-permeable geotextile composite ecological slope protection retaining wall construction method |
| CN105421485A (en) * | 2015-10-30 | 2016-03-23 | 杭州江润科技有限公司 | Construction method of high-fill prefabricated cast-in-situ combined pile slab wall protection structure |
| KR20160128560A (en) * | 2015-04-28 | 2016-11-08 | 주식회사 본이앤씨 | Reinforced earth retaining wall with blocks of structure frame and wire mesh |
-
2017
- 2017-01-17 CN CN201710034318.5A patent/CN106836244A/en active Pending
Patent Citations (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN203320547U (en) * | 2013-05-22 | 2013-12-04 | 中铁二院工程集团有限责任公司 | Gabion retaining wall with mixed padding |
| CN103410167A (en) * | 2013-08-29 | 2013-11-27 | 深圳市福田建安建设集团有限公司 | Three-dimensional reinforced rigid-soft composite ecological retaining wall and construction method |
| CN104018490A (en) * | 2014-05-13 | 2014-09-03 | 中冶集团武汉勘察研究院有限公司 | Z-shaped rectangular-section anti-skidding pile and construction method thereof |
| CN104612107A (en) * | 2015-02-02 | 2015-05-13 | 成军 | River channel reinforced gabion and water-permeable geotextile composite ecological slope protection retaining wall construction method |
| KR20160128560A (en) * | 2015-04-28 | 2016-11-08 | 주식회사 본이앤씨 | Reinforced earth retaining wall with blocks of structure frame and wire mesh |
| CN105421485A (en) * | 2015-10-30 | 2016-03-23 | 杭州江润科技有限公司 | Construction method of high-fill prefabricated cast-in-situ combined pile slab wall protection structure |
Non-Patent Citations (2)
| Title |
|---|
| 于洪江等: "《公路施工技术》", 31 July 2015, 中国水利水电出版社 * |
| 陆陈强等: "抗滑桩与格宾挡墙联合生态护坡施工技术", 《公路工程》 * |
Cited By (16)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107700500B (en) * | 2017-09-14 | 2019-06-18 | 深圳百勤建设工程有限公司 | Slope retaining structure and slope supporting drain integral system |
| CN107700500A (en) * | 2017-09-14 | 2018-02-16 | 深圳百勤建设工程有限公司 | Slope retaining structure and slope supporting draining integral system |
| CN108086352A (en) * | 2018-02-01 | 2018-05-29 | 云南新创新交通建设股份有限公司 | A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure |
| CN108487269B (en) * | 2018-06-11 | 2023-08-15 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method of ecological assembly type frame support form |
| CN108487269A (en) * | 2018-06-11 | 2018-09-04 | 中国电建集团贵阳勘测设计研究院有限公司 | Construction method of ecological assembled framework supporting form |
| CN109577351A (en) * | 2019-01-25 | 2019-04-05 | 中建五局土木工程有限公司 | Earthwork evacuation safety protection structure and earthwork evacuation safety protecting method |
| CN109577351B (en) * | 2019-01-25 | 2024-04-19 | 中建五局土木工程有限公司 | Earthwork excavation safety protection structure and earthwork excavation safety protection method |
| CN110055826B (en) * | 2019-04-28 | 2023-09-22 | 中铁二院工程集团有限责任公司 | Construction method of cutting rack rail reinforced track bed structure |
| CN110055826A (en) * | 2019-04-28 | 2019-07-26 | 中铁二院工程集团有限责任公司 | A kind of enhanced ballast bed structure of cutting cogwheel railway and construction method |
| CN110747887A (en) * | 2019-10-27 | 2020-02-04 | 中铁二院工程集团有限责任公司 | Pile-supported gabion retaining wall structure and its construction method |
| CN113073680A (en) * | 2021-04-25 | 2021-07-06 | 中铁二院工程集团有限责任公司 | Slag disposal site retaining wall structure of plateau high-cold area and construction method thereof |
| CN113430987A (en) * | 2021-07-01 | 2021-09-24 | 长江勘测规划设计研究有限责任公司 | Ecological retaining wall structure capable of utilizing river channel excavation soil materials in situ and construction method thereof |
| CN114892710A (en) * | 2022-05-17 | 2022-08-12 | 湖北工业大学 | A tree-supported retaining wall and its construction method |
| CN114892710B (en) * | 2022-05-17 | 2024-04-19 | 湖北工业大学 | Tree bearing type retaining wall and construction method thereof |
| CN115659460A (en) * | 2022-10-18 | 2023-01-31 | 中国电建集团昆明勘测设计研究院有限公司 | Airport stainless steel sewage interception and water diversion design method |
| CN116988509A (en) * | 2023-08-23 | 2023-11-03 | 北京市市政工程研究院 | Modular geogrid retaining wall with construction waste as filler and construction method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106836244A (en) | Method for protecting steep slope roadbed by combining anti-slide piles and gabion high retaining wall | |
| CN102505695B (en) | Construction method for deep foundation pit of three-dimensional garage | |
| CN103758084B (en) | A kind of ecological riverway interlocking type building block and construct the construction that protects bank | |
| CN102383413B (en) | Method for constructing strengthened saturated-flow plastic silt soft soil foundation | |
| CN204645075U (en) | A kind of urban road soft foundation underground pipeline bracing means | |
| CN106703050A (en) | Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof | |
| CN105178125B (en) | A kind of lake region High-filled emkankment is blown sand embankments construction method and embankment structure | |
| CN114541429B (en) | Multistage slope-pasting loess high-fill slope protection treatment system | |
| CN104846840B (en) | A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method | |
| CN106930231A (en) | A kind of construction method of the engineering flood bank reinforcing that is applied to pass the flood period | |
| CN104264680A (en) | Foundation treatment method of collapsible loess slope cut-and-fill joint part | |
| CN105672450A (en) | Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure | |
| CN106869151A (en) | A kind of bridge construction method of deep foundation ditch | |
| CN111778793A (en) | A cavity collapse prevention structure and construction method | |
| CN116377780A (en) | Construction Method of High Fill Subgrade in Mountainous Highway | |
| CN112195965A (en) | Expansive soil cutting retaining wall | |
| CN111851546A (en) | A construction method for closed dewatering of dredging wells in deep foundation pit construction | |
| CN102235007B (en) | Method for supporting deep foundation with upper nail-lower pile combination | |
| CN219410378U (en) | Rock slope overhanging type road structure | |
| CN106320368A (en) | A construction method suitable for open-cut pipelines in composite strata | |
| CN219410355U (en) | Flexible side-width structure of high-fill embankment of existing railway | |
| CN112854254A (en) | Construction method for existing railway field level subgrade support in deep artificial waste slag area | |
| CN211421169U (en) | Reinforcement Structure of Gravity Retaining Wall for Filled Slope | |
| CN211228563U (en) | Assembled groundwater drainage blind ditch drainage system that oozes | |
| CN208293588U (en) | A kind of Cut Slopes of Expansive Soil reinforcement formula, which is changed, fills out compages |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| WD01 | Invention patent application deemed withdrawn after publication | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20170613 |