Application management method of BIM technology in sponge city construction Download PDFInfo
- Publication number
- CN106812145B CN106812145B CN201710086098.0A CN201710086098A CN106812145B CN 106812145 B CN106812145 B CN 106812145B CN 201710086098 A CN201710086098 A CN 201710086098A CN 106812145 B CN106812145 B CN 106812145B
- Authority
- CN
- China
- Prior art keywords
- module
- bim
- management
- construction
- monitoring
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F1/00—Methods, systems, or installations for draining-off sewage or storm water
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F2201/00—Details, devices or methods not otherwise provided for
- E03F2201/20—Measuring flow in sewer systems
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
- Cultivation Of Plants (AREA)
Abstract
Application management of the BIM technology in sponge urban construction, it is related to the construction in sponge city, and in particular to application management of the BIM technology in sponge urban construction.The modules of sponge city BIM site construction management module are connect with BIM host communication;Sponge city monitoring and maintenance adjustmenting management module includes that modules, the modules of sponge city monitoring and maintenance adjustmenting management module such as Data Detection operation and maintenance, river water level monitoring, greenery area monitoring, the monitoring of greenery patches water cut monitor, rainwater-collecting, precipitation monitoring, Groundwater level monitoring, reservoir level monitoring, wind speed temperature monitoring, Water Resource Adjustment & Distribution are connect with BIM host communication;Construction progress the management module construction progress and construction management all by BIM Host Administration;Water evaporation simulation in greenery patches simulates different vegetation greenery patchess by BIM host.All sponge urban construction all pass through BIM and are designed, simulate, construct, manage in the present invention, and the management such as are drained, irrigated by monitoring data everywhere.
Description
Technical field
The present invention relates to the construction in sponge city, and in particular to application management of the BIM technology in sponge urban construction
Method.
Background technique
Sponge city is new generation of city storm water man- agement concept, refers to that city is adapting to environmental change and reply rainwater band
Natural calamity come etc. has good " elasticity ", also referred to as " water elasticity city ".International term is " low shadow
Ring the building of exploitation storm-water system ".Water suction, water storage, infiltration, water purification when raining by the water stored " release " and are subject to benefit when needing
With." about the instruction for promoting sponge urban construction " is just clear, by sponge urban construction, reduces city to the maximum extent
Influence of the development & construction to ecological environment, by 70% rainfall on-site elimination and utilization.To the year two thousand twenty, 20% or more completed region of the city
Area reach target call;Area to the year two thousand thirty, 80% or more completed region of the city reaches target call.
Sponge city: when very heavy rains, rainwater can lake, artificial swamp, lawn, river irrigation canals and ditches, Green Roof, thoroughly
Road/square that water is mated formation etc. is largely accumulated, lower infiltration, and into underground soil, the rainwater of urban surface flowing reduces (rainwash
Reduce), the pressure of sewerage system is small, is flooded it is possible to prevente effectively from waterlogging occurs for city.The lake of sponge urban construction, people
Work wetland, lawn, so that city is more beautiful;Greenery area, the water surface area of substantial increase can improve the air quality in city,
Degradation floating dust;Alleviate city " tropical island effect ", mitigates city " urban dry island effect ";Rainwater is accumulated and is recycled, is saved
Water resource can partially alleviate the phenomenon of water resource anxiety.
BIM, simple to understand to be exactly Building Information Model, BIM construction is it can be understood that for Building Information Model and construction
Combine, thus BIM construction technology can be understood as application of the Building Information Model in building construction process, such as
Three-dimensional calculation amount, construction simulation, amplification sample etc., what can be done is also being continuously increased.
The street of present Chinese city is often dug, and civic complaint is frequently subjected to, and having its source in for often being dug is set
Meter cannot keep up with the variation of reality, especially be a lack of the task of design simulation this part.BIM technology can be in building, urban construction side
There is the function of simulation in face, but also fails to be applied in terms of sponge urban construction at present.Carry out in now domestic many cities
The construction in sponge city, but the construction progress in these sponge cities is slow, prevention waterlogging drought resisting effect is also not apparent.
Summary of the invention
In view of the defects and deficiencies of the prior art, the present invention intends to provide a kind of BIM technologies to build in sponge city
If the method for application management in, it promotes the construction in present sponge city, shortens design, construction, construction period, can be with
Design level is improved, guarantees the construct effects of biology in later period.
To achieve the above object, the present invention is using following technical scheme: it includes BIM host, the scene sponge city BIM
Construction management module, sponge city monitoring and maintenance adjustmenting management module, sponge city BIM site construction management module include construction
Field management module, Structural Analysis Module, outdoor scene analog module, ecological green land management module, construction progress management module, rainwater
Collecting device management module, storm water management analog module, water storage analog module, greenery patches water evaporation analog module, sponge city BIM
The modules of site construction management module are connect with BIM host communication;Sponge city monitoring and maintenance adjustmenting management module packet
The module of operation and maintenance containing Data Detection, river water level monitoring modular, greenery area monitoring modular, greenery patches water cut monitor module, rain
Water collects monitoring modular, precipitation monitoring modular, Groundwater level monitoring module, reservoir level monitoring modular, wind speed temperature prison
Module, Water Resource Adjustment & Distribution module are surveyed, the modules of sponge city monitoring and maintenance adjustmenting management module connect with BIM host communication
It connects;Construction progress the management module construction progress and construction management all by BIM Host Administration;Greenery patches water evaporation analog module
Different vegetation greenery patchess are simulated by BIM host.The construction in sponge city is from design, construction, simulation, operation, data in the present invention
Monitoring, system maintenance, later period Water Resource Adjustment & Distribution all pass through BIM host and are managed.
The construction site management module include site operation personal management module, live material stock management module,
Place allocation plan management module, building waste management module, supply chain management module, site operation personal management module pass through
BIM manages the work of construction site all personnel, can be with the disengaging of administrative staff, increase and decrease, the people including adjusting each construction teams and groups
Member etc.;Live material stock management module by BIM manage construction site all material distribution, storage, be conducive to using
When easily and efficiently distribute use, improve the service efficiency of materials in storage;Place allocation plan management module is responsible for passing through BIM
The field course layout for managing construction site, is mainly responsible for that the putting of live material, the setting of construction machinery is put, construction installation is set
It sets and puts;Building waste management module manages storage, placement, the cleaning of the building waste of construction site by BIM;Supply chain pipe
The supply of raw material needed for reason module is managed by BIM, time of marching into the arena, sequence of marching into the arena.
The Structural Analysis Module includes Storm Sewer System structure design module, sewer structure design module, rain dirt point
Flow structure designs module, greenery patches water storage structure designs module, river Drainage Design module, pumping plant install and design module, flood discharge is logical
Road designs module, roof vegetation water storage design module, porous pavement and designs module, and Structural Analysis Module passes through BIM host pair
Each plumbing, water storage, the river draining in sponge city are designed.
The outdoor scene analog module includes rainwater water delivery analog module, sewer rain-water drainage analog module, rainwater point
Stream draining analog module, greenery patches water storage draining analog module, river draining analog module, pumping plant draw water and drain analog module, let out
Big vast channel drainage analog module, roof vegetation water storage volatilization analog module, the permeable speed analog module in road surface, rain-water drainage are comprehensive
Analog module, water filling drought resisting comprehensive simulation module, these modules pass through BIM host and obtain actual scene by outdoor scene simulation
Situation.Be conducive to obtain actual reference data, and design and construction can be adjusted according to the case where simulation, to reach
To better effect.The water storage situation of each water storage part in available sponge city is simulated by rainwater water delivery.
The ecological green land management module includes greenery area management module, greenery patches seasonal variations management module, greenery patches
Moisture storage capacity management module, green land irrigation system management module, lawn watering management module, greenery area management module mainly exist
The greenery area in city is changed in BIM host, in real time to adjust related data in real time;Greenery patches seasonal variations management module is main
The area of urban green space is adjusted, according to season by BIM host to adjust related data in real time;Greenery patches moisture storage capacity management module
It is main that water storage data are adjusted according to the different of greenery patches moisture storage capacity of different vegetation by BIM host, and related data is sent to
BIM host;Green land irrigation system management module is to irrigate as needed greenbelt plants, and lawn watering management module is root
According to needing to drain greenbelt plants, and by it is related irrigate, draining data are obtained from BIM host and pass the data after operation
Give BIM host.
The rainwater-collecting EM equipment module includes sewer stormwater management design, sewer stormwater filter design, rainwater
The modules such as central drainage design, sewer stormwater management design module is mainly according to the location of the sewer, polywater face
Product designs the control management of relevant sewer pipes, the area of sewer discharge outlet, the mode of filtering and sewer valve
Design relevant rainwater-collecting equipment.
The storm water management analog module includes rainfall analog module, rain-water drainage analog module, sewer draining
Analog module, rain water reservoir water draining and accumulating analog module, these modules are mainly simulated rainfall, to simulate rain-water drainage
Situation simulates draining, the water storage situation of reservoir.This module be mainly Simulated rainfall size calculate in advance draining,
The case where water storage, and better design is made, and management sewer stormwater is adjusted according to precipitation in sponge city operations
Operation.To more preferably design, manage sewer stormwater.
The water storage analog module includes reservoir analog module, greenery patches water storage analog module, river water storage simulation mould
The case where block, reservoir filling analog module, these modules mainly simulate water storage, and according to extraneous temperature, wind speed, humidity,
Greenery patches situation simulates the variation of water storage, to simulate the water storage situation of change in sponge city, to make preferably design and pre-
Case.
The sponge city monitoring and maintenance adjustmenting management module on river by installing water level monitoring device and by water
Position information is real-time transmitted to BIM host, and greenery area monitoring modular is the change by greenery area in sponge Process of Urban Development
Change and variation real-time transmission is arrived into BIM host, the installation water content monitoring device and by the water content real-time transmission in greenery patches in greenery patches
To BIM host, rainwater-collecting amount monitoring device is installed in sewer stormwater, precipitation monitoring device is installed, Groundwater is installed
Position monitoring device installs water level monitoring device in reservoir, installs wind speed, temperature device, and the data of these monitoring devices are all real
When send BIM host to and monitored according to these water content, evaporation capacity, the water level of reservoir, the water level in river, reservoir
Water level formulates the scheme of Water Resource Adjustment & Distribution, and ensures the operation of each facility according to obtained monitoring data, if there is exception
Data Detection operation and maintenance module is needed to carry out abnormal alarm, and is safeguarded.
The present invention is by sponge urban design rainstorm come temporarily, rainwater can be in lake, artificial swamp, lawn, river ditch
Canal, Green Roof, road/square of permeable pavement etc. are largely accumulated, lower infiltration, into underground soil, the rainwater of urban surface flowing
It reduces (rainwash reduction), the pressure of sewerage system is small, is flooded it is possible to prevente effectively from waterlogging occurs for city.Sponge city
Lake, artificial swamp, the lawn of construction, so that city is more beautiful;Greenery area, the water surface area of substantial increase can improve city
The air quality in city, floating dust of degrading;Alleviate city " tropical island effect ", mitigates city " urban dry island effect ";To rainwater carry out accumulation and
It is recycled, saves water resource, can partially alleviate the phenomenon of water resource anxiety.
All sponge urban construction all pass through BIM and are designed, simulate, construct, manage in the present invention, and pass through monitoring
Data everywhere such as are drained, are irrigated at the management.Present invention facilitates the construction in present sponge city, shorten design, construction,
Design level can be improved in construction period, guarantees the construct effects of biology in later period.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this
Some embodiments of invention without any creative labor, may be used also for those of ordinary skill in the art
To obtain other drawings based on these drawings.
Fig. 1 is structural schematic block diagram of the invention;
Fig. 2 is the structural schematic block diagram of construction site management module in the present invention;
Fig. 3 is the structural schematic block diagram of Structural Analysis Module in the present invention;
Fig. 4 is the structural schematic block diagram of outdoor scene analog module in the present invention;
Fig. 5 is the structural schematic block diagram of ecological green land management module in the present invention;
Fig. 6 is the structural schematic block diagram of rainwater collecting device module in the present invention;
Fig. 7 is the structural schematic block diagram of storm water management analog module in the present invention;
Fig. 8 is the structural schematic block diagram of water storage analog module in the present invention.
Description of symbols: BIM host 1, sponge city BIM site construction management module 2, sponge city monitoring and maintenance tune
With management module 3.
Specific embodiment
Referring to shown in Fig. 1-Fig. 8, present embodiment the technical solution adopted is that: it is by BIM host 1, sponge city
BIM site construction management module 2, sponge city monitoring and maintenance adjustmenting management module 3 form, sponge city BIM site operation pipe
Reason module 2 include construction site management module, Structural Analysis Module, outdoor scene analog module, ecological green land management module, construct into
Thread management module, rainwater-collecting device management module, storm water management analog module, water storage analog module, the simulation of greenery patches water evaporation
Module, the modules of sponge city BIM site construction management module 2 with 1 communication connection of BIM host;The monitoring of sponge city
Safeguard adjustmenting management module 3 include Data Detection operation and maintenance module, river water level monitoring modular, greenery area monitoring modular,
Greenery patches water cut monitor module, rainwater-collecting monitoring modular, precipitation monitoring modular, Groundwater level monitoring module, reservoir level
Monitoring modular, wind speed temperature monitoring module, Water Resource Adjustment & Distribution module, sponge city monitoring and maintenance adjustmenting management module 3 it is each
Module with 1 communication connection of BIM host;Construction progress management module manages all construction progress and construction by BIM host 1
Management;Greenery patches water evaporation analog module simulates different vegetation greenery patchess by BIM host 1.In the present invention construction in sponge city from
Design, construction, simulation, operation, data monitoring, system maintenance, later period Water Resource Adjustment & Distribution all pass through BIM host 1 and are managed.
The construction site management module include site operation personal management module, live material stock management module,
Place allocation plan management module, building waste management module, supply chain management module, site operation personal management module pass through
BIM manages the work of construction site all personnel, can be with the disengaging of administrative staff, increase and decrease, the people including adjusting each construction teams and groups
Member etc.;Live material stock management module by BIM manage construction site all material distribution, storage, be conducive to using
When easily and efficiently distribute use, improve the service efficiency of materials in storage;Place allocation plan management module is responsible for passing through BIM
The field course layout for managing construction site, is mainly responsible for that the putting of live material, the setting of construction machinery is put, construction installation is set
It sets and puts;Building waste management module manages storage, placement, the cleaning of the building waste of construction site by BIM;Supply chain pipe
The supply of raw material needed for reason module is managed by BIM, time of marching into the arena, sequence of marching into the arena.
The Structural Analysis Module includes Storm Sewer System structure design module, sewer structure design module, rain dirt point
Flow structure designs module, greenery patches water storage structure designs module, river Drainage Design module, pumping plant install and design module, flood discharge is logical
Road designs module, roof vegetation water storage design module, porous pavement and designs module, and it is right that Structural Analysis Module passes through BIM host 1
Each plumbing, water storage, the river draining in sponge city are designed.
The outdoor scene analog module includes rainwater water delivery analog module, sewer rain-water drainage analog module, rainwater point
Stream draining analog module, greenery patches water storage draining analog module, river draining analog module, pumping plant draw water and drain analog module, let out
Big vast channel drainage analog module, roof vegetation water storage volatilization analog module, the permeable speed analog module in road surface, rain-water drainage are comprehensive
Analog module, water filling drought resisting comprehensive simulation module, these modules pass through BIM host and obtain actual scene by outdoor scene simulation
Situation.Be conducive to obtain actual reference data, and design and construction can be adjusted according to the case where simulation, to reach
To better effect.The water storage situation of each water storage part in available sponge city is simulated by rainwater water delivery.
The ecological green land management module includes greenery area management module, greenery patches seasonal variations management module, greenery patches
Moisture storage capacity management module, green land irrigation system management module, lawn watering management module, greenery area management module mainly exist
The greenery area in city is changed in BIM host 1, in real time to adjust related data in real time;Greenery patches seasonal variations management module master
The area of urban green space is adjusted, according to season by BIM host to adjust related data in real time;Greenery patches moisture storage capacity manages mould
Block mainly passes through BIM host 1 according to the different adjustment water storage data of the greenery patches moisture storage capacity of different vegetation, and related data is transmitted
To BIM host 1;Green land irrigation system management module is to irrigate as needed greenbelt plants, lawn watering management module
Be greenbelt plants are drained as needed, and correlation is irrigated, draining data obtain and will be after operation from BIM host 1
Data transmission is to BIM host 1.
The rainwater-collecting EM equipment module includes sewer stormwater management design, sewer stormwater filter design, rainwater
The modules such as central drainage design, sewer stormwater management design module is mainly according to the location of the sewer, polywater face
Product designs the control management of relevant sewer pipes, the area of sewer discharge outlet, the mode of filtering and sewer valve
Design relevant rainwater-collecting equipment.
The storm water management analog module includes rainfall analog module, rain-water drainage analog module, sewer draining
Analog module, rain water reservoir water draining and accumulating analog module, these modules are mainly simulated rainfall, to simulate rain-water drainage
Situation simulates draining, the water storage situation of reservoir.This module be mainly Simulated rainfall size calculate in advance draining,
The case where water storage, and better design is made, and management sewer stormwater is adjusted according to precipitation in sponge city operations
Operation.To more preferably design, manage sewer stormwater.
The water storage analog module includes reservoir analog module, greenery patches water storage analog module, river water storage simulation mould
The case where block, reservoir filling analog module, these modules mainly simulate water storage, and according to extraneous temperature, wind speed, humidity,
Greenery patches situation simulates the variation of water storage, to simulate the water storage situation of change in sponge city, to make preferably design and pre-
Case.
The sponge city monitoring and maintenance adjustmenting management module 3 on river by installing water level monitoring device and by water
Position information is real-time transmitted to BIM host 1, and greenery area monitoring modular is the change by greenery area in sponge Process of Urban Development
Change and variation real-time transmission is arrived into BIM host 1, the installation water content monitoring device and by the water content real-time transmission in greenery patches in greenery patches
To BIM host 1, rainwater-collecting amount monitoring device is installed in sewer stormwater, precipitation monitoring device is installed, Groundwater is installed
Position monitoring device installs water level monitoring device in reservoir, installs wind speed, temperature device, and the data of these monitoring devices are all real
When send BIM host 1 to and monitored according to these water content, evaporation capacity, the water level of reservoir, the water level in river, reservoir
Water level, formulate the scheme of Water Resource Adjustment & Distribution, and ensure the operation of each facility according to obtained monitoring data, such as occur abnormal
It needs Data Detection operation and maintenance module then to carry out abnormal alarm, and safeguards.
The present invention is by sponge urban design rainstorm come temporarily, rainwater can be in lake, artificial swamp, lawn, river ditch
Canal, Green Roof, road/square of permeable pavement etc. are largely accumulated, lower infiltration, into underground soil, the rainwater of urban surface flowing
It reduces (rainwash reduction), the pressure of sewerage system is small, is flooded it is possible to prevente effectively from waterlogging occurs for city.Sponge city
Lake, artificial swamp, the lawn of construction, so that city is more beautiful;Greenery area, the water surface area of substantial increase can improve city
The air quality in city, floating dust of degrading;Alleviate city " tropical island effect ", mitigates city " urban dry island effect ";To rainwater carry out accumulation and
It is recycled, saves water resource, can partially alleviate the phenomenon of water resource anxiety.
All sponge urban construction all pass through BIM and are designed, simulate, construct, manage in the present invention, and pass through monitoring
Data everywhere such as are drained, are irrigated at the management.
BIM is the effective means of building, urban construction designer raising designing quality.BIM is applied to sponge urban design
In, computer " will coordinate to integrate " work between bearing each Specialty Design, and it is available that scarce problem is touched in the mistakes and omissions in design work
Effectively control.
BIM is the effective means that owner understands construction quality.Owner is biggest beneficiary and the engineering of engineering high quality
The main policymaker of quality.But limited to by professional knowledge, the same designer of owner, supervisor, the exchange between contractor
There are certain difficulties.When owner requires indefinite to construction quality, cause change in the work more, quality is difficult to effectively control.BIM
The three dimensional design of image is provided for owner, owner can more clearly express oneself requirement to construction quality, such as building
Color, material, equipment requirement etc. are conducive to each side and carry out quality control efforts.
BIM is the effective means that project manager controls construction quality.Due to being digitlization using the drawing of BIM design
, computer can retrieval, differentiation, in terms of make the most of the advantage.No matter the item of supervising engineer or contractor
Mesh administrative staff need not hold thick drawing and crosscheck, it is only necessary to by some simple functions can rapidly,
The characteristic information of building member, such as the arrangement of reinforcing bar, the position of equipment reserving hole, scantling are accurately obtained,
It is live to assign instruction in time.It is the process of a resource cost moreover, building is become three-dimensional from plane.No matter building
It is completed, has begun construction or stocked up, the cost modified after finding the problem all is huge.Utilize BIM model
Carry out that virtual environment data is integrated with arrangement and method for construction, to construction project can constructive carry out emulation experiment, can find in advance
Quality problems.
The above is only used to illustrate the technical scheme of the present invention and not to limit it, and those of ordinary skill in the art are to this hair
The other modifications or equivalent replacement that bright technical solution is made, as long as it does not depart from the spirit and scope of the technical scheme of the present invention,
It is intended to be within the scope of the claims of the invention.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710086098.0A CN106812145B (en) | 2017-02-17 | 2017-02-17 | Application management method of BIM technology in sponge city construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201710086098.0A CN106812145B (en) | 2017-02-17 | 2017-02-17 | Application management method of BIM technology in sponge city construction |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106812145A CN106812145A (en) | 2017-06-09 |
| CN106812145B true CN106812145B (en) | 2019-02-22 |
Family
ID=59112537
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201710086098.0A Expired - Fee Related CN106812145B (en) | 2017-02-17 | 2017-02-17 | Application management method of BIM technology in sponge city construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106812145B (en) |
Families Citing this family (15)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107194112A (en) * | 2017-06-14 | 2017-09-22 | 成都智建新业建筑设计咨询有限公司 | The method being laid out based on BIM to garden landscape |
| CN108181939A (en) * | 2017-12-15 | 2018-06-19 | 北京无线电计量测试研究所 | System and method are moved by a kind of storage Volleyball Association |
| CN108229829A (en) * | 2018-01-05 | 2018-06-29 | 曹枭 | A kind of new city planing method based on sponge City Theory |
| CN107989151B (en) | 2018-01-15 | 2023-09-12 | 水利部交通运输部国家能源局南京水利科学研究院 | Regional rainwater allocation method |
| WO2020041989A1 (en) * | 2018-08-28 | 2020-03-05 | 苏州大学张家港工业技术研究院 | Method and system for designing sponge city on basis of total rainwater control |
| CN110222357B (en) * | 2019-04-12 | 2022-06-14 | 福州市规划设计研究院集团有限公司 | BIM modeling method for planning and constructing sponge city |
| CN110172916B (en) * | 2019-05-22 | 2020-11-10 | 中建五局土木工程有限公司 | Concrete maintenance method for high piers of bridges |
| CN110675067A (en) * | 2019-09-26 | 2020-01-10 | 北京金河水务建设集团有限公司 | BIM-based river channel information management system |
| CN111079212A (en) * | 2019-11-22 | 2020-04-28 | 南京金海设计工程有限公司 | Application method of BIM technology in sponge city construction |
| CN112012304A (en) * | 2020-08-28 | 2020-12-01 | 中冶东北建设(沈阳)工程技术有限公司 | Intelligent control system for sponge construction site and control method thereof |
| CN112012305B (en) * | 2020-09-09 | 2021-04-27 | 明光市白云建筑安装工程有限责任公司 | Urban construction water collection and drainage hub and application method thereof |
| CN114091149A (en) * | 2021-11-12 | 2022-02-25 | 国家电网有限公司 | Design optimization method for transformer substation sponge city |
| CN116341069A (en) * | 2023-03-27 | 2023-06-27 | 中国十七冶集团有限公司 | BIM-based construction method for optimizing efficient collection, water storage and water storage of rainwater in artificial lake |
| CN118729162A (en) * | 2024-06-13 | 2024-10-01 | 上海勘测设计研究院有限公司 | Urban waterlogging prevention and control method, device, electronic equipment and medium |
| CN118780579B (en) * | 2024-09-11 | 2025-01-14 | 公诚管理咨询有限公司 | A method for controlling the life cycle of construction data based on BIM |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202167019U (en) * | 2011-06-10 | 2012-03-14 | 上海市电力公司 | Device for construction simulation through Building Information Modeling |
| KR101465487B1 (en) * | 2013-12-23 | 2014-11-26 | 한국건설기술연구원 | Bim data processing system for extracting surface object of building |
| CN104866952A (en) * | 2015-04-28 | 2015-08-26 | 国家电网公司 | Three-dimensional digital management implementation method for hydropower station engineering project |
-
2017
- 2017-02-17 CN CN201710086098.0A patent/CN106812145B/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN202167019U (en) * | 2011-06-10 | 2012-03-14 | 上海市电力公司 | Device for construction simulation through Building Information Modeling |
| KR101465487B1 (en) * | 2013-12-23 | 2014-11-26 | 한국건설기술연구원 | Bim data processing system for extracting surface object of building |
| CN104866952A (en) * | 2015-04-28 | 2015-08-26 | 国家电网公司 | Three-dimensional digital management implementation method for hydropower station engineering project |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106812145A (en) | 2017-06-09 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106812145B (en) | Application management method of BIM technology in sponge city construction | |
| Yang et al. | Optimal designs of LID based on LID experiments and SWMM for a small-scale community in Tianjin, north China | |
| CN105089142B (en) | Concave rainwater storage and dispatching pool for green space and decentralized rainwater storage and dispatching pool system | |
| Rodríguez-Sinobas et al. | Techniques and criteria for sustainable urban stormwater management. The case study of Valdebebas (Madrid, Spain) | |
| CN106639180B (en) | A kind of rainwater accumulation system and its construction method for roof garden | |
| CN201976543U (en) | Green belt rain collecting automatic micro-sprinkling irrigation device | |
| CN107989151A (en) | A kind of region rainwater catchment system engineering system and concocting method | |
| CN204959952U (en) | Recessed formula greenery patches rainwater regulation dispatch pond and distributed rainwater regulation dispatch pond system | |
| CN205348351U (en) | Have quality of water purification performance's rainfall runoff control system concurrently | |
| CN201972229U (en) | Residential rainwater comprehensive utilization system device | |
| CN205259345U (en) | Greenery patches rain sewage's system of recycling | |
| CN106638219A (en) | Ramped urban road of sponge city | |
| CN110147591A (en) | Method is determined based on the greenery patches sponge power system capacity of light green coupling principle | |
| CN107190840A (en) | A kind of roof rainwater collection processing system suitable for old Urban re-development | |
| CN108625453A (en) | Skyscraper sponge City complex system | |
| CN109555275A (en) | A kind of roof garden Intelligent rain Collection utilization system | |
| CN205189099U (en) | Water storage device of collection, storage and cyclic utilization rainwater | |
| CN207075342U (en) | plant irrigation system based on building roof siphon drainage | |
| CN204994328U (en) | System for groove ponding is planted to prevention overline bridge | |
| CN207829056U (en) | Water circulation system based on construction project construction site | |
| CN105464190A (en) | Green space rain sewage reuse system | |
| CN204898779U (en) | Rainwater self -restraint device | |
| CN109098267A (en) | Mountainous Building synthesis rainwater prevention and control based on GIS with utilize system and method | |
| CN207727715U (en) | Sponge Comprehensive Utilization System of Urban Rainwater | |
| Carbone et al. | Water management: A way to achieve a more efficient irrigation system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190222 |