CN106401224A - Clean room factory structure - Google Patents

Clean room factory structure Download PDF

Info

Publication number
CN106401224A
CN106401224A CN201611052959.5A CN201611052959A CN106401224A CN 106401224 A CN106401224 A CN 106401224A CN 201611052959 A CN201611052959 A CN 201611052959A CN 106401224 A CN106401224 A CN 106401224A
Authority
CN
China
Prior art keywords
formations
return air
air passageway
operating space
production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611052959.5A
Other languages
Chinese (zh)
Inventor
罗桥
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chinese Electronics Engineering Design Institute
Original Assignee
Chinese Electronics Engineering Design Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chinese Electronics Engineering Design Institute filed Critical Chinese Electronics Engineering Design Institute
Priority to CN201611052959.5A priority Critical patent/CN106401224A/en
Publication of CN106401224A publication Critical patent/CN106401224A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H5/00Buildings or groups of buildings for industrial or agricultural purposes
    • E04H5/02Buildings or groups of buildings for industrial purposes, e.g. for power-plants or factories

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Respiratory Apparatuses And Protective Means (AREA)

Abstract

The invention discloses a clean room factory structure. The clean room factory structure comprises return air passageway structure parts located on the two sides, auxiliary production area structure parts located at the ends, operation area structure parts located in the center and extending in the direction perpendicular to the return air narrow lane structure parts, and at least one set of production equipment structure part located in the operation area structure parts, and further comprises quadrangular production aisle structure parts arranged between the operation area structure parts, the return air passageway structure parts and the auxiliary production area structure parts.

Description

Toilet's factory building construction
Technical field
The present invention relates to a kind of factory building construction, more particularly, to a kind of clean room arrangement construction.
Background technology
In electronics and information industry, for example, the high-technology field such as integrated circuit, FPD, electronic devices and components, product adds The aspects such as work precision, integrated level require more and more higher, much need to produce in clean environment, because clean environment engineering is made Valency is higher, therefore in order to save the construction investment at initial stage and the operation cost in later stage, is usually taken the behaviour of production equipment Make face side and human users area is arranged in higher clean area (also known as white area), production equipment main body and its auxiliary device cloth Put and require (also known as gray area) in relatively low region in cleaning.Therefore, in order to reduce the area in white area as far as possible, for toilet Interior human users area and the arrangement in production equipment area, be using similar " non-" font arrangement, i.e. operating space and main In centre, production equipment area, in both sides, forms similar " non-" font arrangement to passage, and concrete arrangement and use state are shown in Attached Fig. 1 and 2.
In FIG, 100 represent return air passageway formations, 200 represent auxiliary production district formations, 300 represent operating space structure Make portion, 400 represent production equipment formations, 500 represent produce aisle formations, 700 represent equipment move into passage formations, 800 represent escape stair formations.
In fig. 2, solid arrow represents that stream of people's route is illustrated, and dotted arrow represents that evacuation route is illustrated, double dot dash line arrow Head expression equipment is moved into route and is illustrated.
Using similar " non-" font arrangement, this scheme is relatively difficult to resolve the evacuation problem of certainly operating space personnel, and visit is walked The offering question of corridor, follow-up equipment move into problem.Its weak point is as follows:
1st, the evacuation problem of operating space personnel:Because main channel is located at the middle part of clean room, it is also operating personnel More region, operating personnel evacuate and mainly pass through main channel escape stair escape laterally, distant;With science and technology Continuous development, cost of land increases, and high tech electron factory list building construction area is increasing, causes in clean room The evacuation of middle part personnel is difficult to be increased.
2nd, visit the offering question in corridor:Clean room investment is larger, and major part belongs to high tech electron field, Ji Yaobao The clean production environment of barrier, meets the visit of Migrant women again, needs setting to visit corridor and (refers to Migrant women in non-clean area Clear production area and operating space are understood by observation window).Similar " non-" font arrangement, substantially cannot accomplish by non-clean Net aisle complete observation clear production area and the operation of operating personnel.
3rd, follow-up equipment move into problem:The clean room construction period is long, and investment is big, and electronic product updates comparatively fast, Therefore, the problems such as moving into, keep in repair of clean room follow-up equipment generally to be considered.Move into the cleaning in impact white area by main channel Environment and production, carry out equipment by both sides and move into, increased equipment removal path.
Therefore it provides a kind of toilet's factory building that can effectively solve the problem that an above-mentioned difficult problem is constructed to be badly in need of in the industry asking of solution Topic.
Content of the invention
For the deficiencies in the prior art, it is an object of the invention to provide a kind of toilet factory building construction, it can be effective Solve the evacuation problem of main channel operating personnel and the offering question visiting corridor.
The solution of the present invention, in line with the safe policy that people-oriented and design concept, takes operation in clear production factory building Both sides arrangement outside personnel channel, is similar to " returning " font arrangement.Additionally, factory center arrangement is set for production Standby move into passage.This meanwhile, can be conducive to visiting the setting of passage, also favorably with the rapid problem evacuated of effectively solving personnel Move into and keep in repair etc. work in follow-up equipment.
According to the present invention, provide a kind of toilet factory building construction, including:Return air passageway formations positioned at both sides, it is located at The operating space construction that the auxiliary production district formations of end, centrally located and edge extend perpendicular to the direction of return air passageway formations Portion and the least one set production equipment formations being located in operating space formations, wherein, factory building construction in toilet's wraps further Include the production aisle of the quadrangle being arranged between operating space formations and return air passageway formations and auxiliary production district formations Formations.
Preferably, factory building construction in toilet's may further include the return air passageway formations being arranged at every side and production Visit corridor formations between the formations of aisle.
Preferably, the centre of operating space formations can arrange equipment further and move into passage formations, and equipment is moved into Passage formations extends through operating space formations parallel to return air passageway formations.
The invention has the beneficial effects as follows:The present invention takes both sides arrangement outside operating personnel's passage, is similar to " returning " word Type arrangement, the personnel that efficiently solve evacuate rapidly, visit corridor setting and follow-up equipment moves into the related lance of maintenance etc. Shield.
Brief description
The present invention is further described below in conjunction with the accompanying drawings.
Fig. 1 is the organigram of prior art.
Fig. 2 is the construction use state schematic diagram of prior art.
Fig. 3 is the organigram of the present invention.
Fig. 4 is the construction use state schematic diagram of the present invention.
Specific embodiment
The present invention proposes a kind of toilet factory building construction, and it includes:Return air passageway formations 100 ' positioned at both sides, it is located at The auxiliary production district formations 200 ' of end, centrally located and along perpendicular to the direction of return air passageway formations 100 ' extend behaviour Make area's formations 300 ' and the least one set production equipment formations 400 ' being located in operating space formations 300 ', wherein, clean Clean room factory building construction further includes to be arranged at operating space formations 300 ' and return air passageway formations 100 ' and auxiliary production district The production aisle formations 500 ' of the quadrangle between formations 200 '.
Preferably, toilet's factory building construction may further include be arranged at the return air passageway formations 100 ' of every side with Produce the visit corridor formations 600 ' between aisle formations 500 '.
Preferably, the centre of operating space formations 300 ' can arrange equipment further and move into passage formations 700 ', Equipment is moved into passage formations 700 ' and is extended through operating space formations 300 ' parallel to return air passageway formations 100 '.
As a kind of non-limiting example embodiment, in figure 3 further it is shown that escape stair formations 800 '.
As a kind of non-limiting example embodiment, in the diagram, solid arrow represents that stream of people's route is illustrated, thick two point Dot arrows represent that Visitor Route is illustrated, and dotted arrow represents that evacuation route is illustrated, and thin dash-double-dot arrow represents that equipment is moved into Route is illustrated.
This layout of the present invention is conducive to evacuating personnel, the setting visiting corridor and follow-up equipment to move into and keep in repair; Exploitativeness is very strong.First, operating personnel both sides layout, reduces the crowded state of conventional centre gangway personnel, evacuating personnel More convenient;Secondly, external visit personnel just can whole can observe in clean plant without entering in clean area Producers and technological operation;Finally, copy passage mechanically in factory building central authorities setting production equipment master, both sides production equipment shares one Passage, has saved area, decreases to the impact producing operating space simultaneously.
Although here describes the preferred embodiment of the present invention in detail, it is to be understood that the invention is not limited in this In the concrete structure that describes in detail and illustrate, without departing from the spirit and scope of the present invention can be by the technology of this area Personnel realize other modifications and variant.

Claims (3)

1. a kind of toilet factory building construction, including:Return air passageway formations positioned at both sides, the auxiliary production district structure positioned at end Make portion, centrally located and edge perpendicular to the operating space formations of the direction of described return air passageway formations extension and positioned at institute State the least one set production equipment formations in operating space formations it is characterised in that factory building construction in described toilet is further Including four being arranged between described operating space formations and described return air passageway formations and described auxiliary production district formations The production aisle formations of side shape.
2. factory building construction in toilet as claimed in claim 1 is it is characterised in that factory building construction in described toilet further includes It is arranged at the visit corridor formations between the described return air passageway formations of every side and described production aisle formations.
3. factory building construction in toilet as claimed in claim 1 or 2 is it is characterised in that the centre of described operating space formations Setting equipment moves into passage formations further, and described equipment is moved into passage formations and prolonged parallel to described return air passageway formations Stretch and run through described operating space formations.
CN201611052959.5A 2016-11-24 2016-11-24 Clean room factory structure Pending CN106401224A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611052959.5A CN106401224A (en) 2016-11-24 2016-11-24 Clean room factory structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611052959.5A CN106401224A (en) 2016-11-24 2016-11-24 Clean room factory structure

Publications (1)

Publication Number Publication Date
CN106401224A true CN106401224A (en) 2017-02-15

Family

ID=58082719

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611052959.5A Pending CN106401224A (en) 2016-11-24 2016-11-24 Clean room factory structure

Country Status (1)

Country Link
CN (1) CN106401224A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101503916A (en) * 2009-03-30 2009-08-12 云南白药集团股份有限公司 Modularized factory building structure
CN201526176U (en) * 2009-03-30 2010-07-14 云南白药集团股份有限公司 Modularized workshop structure
CN202249008U (en) * 2011-10-13 2012-05-30 保定天威集团有限公司 Fully-closed and central air conditioner temperature controlling electromagnetic wire factory arrangement structure
GB2513782A (en) * 2009-06-03 2014-11-05 Bripco Bvba Data centre
CN104847139A (en) * 2015-04-13 2015-08-19 上海安集协康生物技术有限公司 Clean cell production workshop
CN106121291A (en) * 2016-06-27 2016-11-16 无锡宏纳科技有限公司 A kind of ultra-clean chamber with inner loop fan
CN206829697U (en) * 2016-11-24 2018-01-02 中国电子工程设计院 Toilet's factory building construction

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101503916A (en) * 2009-03-30 2009-08-12 云南白药集团股份有限公司 Modularized factory building structure
CN201526176U (en) * 2009-03-30 2010-07-14 云南白药集团股份有限公司 Modularized workshop structure
GB2513782A (en) * 2009-06-03 2014-11-05 Bripco Bvba Data centre
CN202249008U (en) * 2011-10-13 2012-05-30 保定天威集团有限公司 Fully-closed and central air conditioner temperature controlling electromagnetic wire factory arrangement structure
CN104847139A (en) * 2015-04-13 2015-08-19 上海安集协康生物技术有限公司 Clean cell production workshop
CN106121291A (en) * 2016-06-27 2016-11-16 无锡宏纳科技有限公司 A kind of ultra-clean chamber with inner loop fan
CN206829697U (en) * 2016-11-24 2018-01-02 中国电子工程设计院 Toilet's factory building construction

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
彭立敏、王薇: "《地下建筑规划与设计》", 30 September 2012, 中南大学出版社 *

Similar Documents

Publication Publication Date Title
Fjordholm et al. Statistical solutions and Onsager’s conjecture
He et al. Derivation of the image interaction for non-planar pointed emitter geometries: application to field emission I–V characteristics
MX2023003052A (en) Formulations comprising recombinant acid alpha-glucosidase.
CN106154607B (en) a lifting mechanism
ES2064114T3 (en) PROCEDURE FOR THE REALIZATION OF A VARIABLE DIALOGUE WITH TECHNICAL DEVICES.
CN106401224A (en) Clean room factory structure
CN206829697U (en) Toilet's factory building construction
PH12016501468B1 (en) Stiffeners for metallic logs structures
CN103178822A (en) Switching circuit
CN204117611U (en) A kind of radioprotector
CN101503916B (en) Modularized factory building structure
AR115479A1 (en) OUTDOOR VENTILATED GLASSING SYSTEMS AND GLASSING METHODS
WO2015200307A3 (en) Integrated micro-electromechanical switches and a related method thereof
WO2007059227A3 (en) Technique for providing a segmented electrostatic lens in an ion implanter
Chung et al. The Extension of the FinFET Generation Towards Sub-3nm: The Strategy and Guidelines
CN105007697A (en) Electrical control cabinet with double panels for protection
CN204826853U (en) Structure that subway station and building were built jointly
CN204791949U (en) Natural draft sound arrester
KR102663456B1 (en) Dust Protection Apparatus Using Electric Screen
CN202859923U (en) Radiotherapy equipment
CN206528652U (en) A kind of shape tube applied on connecting bridge
CN201243008Y (en) Sprinkling anti-pollution device
CN108049665A (en) A kind of large-scale scattered sundries feed bin storage system of intelligence and operation method for tackling high wind
TWM577813U (en) Enclosing mobile vehicle sterilization frame
CN107802354A (en) Medical saw drillstring component cleaning case

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170215