CN106400951A - 一种超高层建筑的水平与竖向结构同步施工方法 - Google Patents
一种超高层建筑的水平与竖向结构同步施工方法 Download PDFInfo
- Publication number
- CN106400951A CN106400951A CN201610882864.XA CN201610882864A CN106400951A CN 106400951 A CN106400951 A CN 106400951A CN 201610882864 A CN201610882864 A CN 201610882864A CN 106400951 A CN106400951 A CN 106400951A
- Authority
- CN
- China
- Prior art keywords
- wall
- building
- climbing
- horizontal
- platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/16—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
- E04B1/161—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, both being partially cast in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
- E04G11/20—Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
- E04G11/28—Climbing forms, i.e. forms which are not in contact with the poured concrete during lifting from layer to layer and which are anchored in the hardened concrete
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610882864.XA CN106400951B (zh) | 2016-10-10 | 2016-10-10 | 一种超高层建筑的水平与竖向结构同步施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610882864.XA CN106400951B (zh) | 2016-10-10 | 2016-10-10 | 一种超高层建筑的水平与竖向结构同步施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106400951A true CN106400951A (zh) | 2017-02-15 |
| CN106400951B CN106400951B (zh) | 2019-04-30 |
Family
ID=59229640
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610882864.XA Expired - Fee Related CN106400951B (zh) | 2016-10-10 | 2016-10-10 | 一种超高层建筑的水平与竖向结构同步施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106400951B (zh) |
Cited By (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107190975A (zh) * | 2017-07-14 | 2017-09-22 | 四川华西集团有限公司 | 超高层建筑施工综合模架系统 |
| CN107299755A (zh) * | 2017-07-14 | 2017-10-27 | 四川华西集团有限公司 | 可实现外模架和钢平台整体和局部顶升的液压顶升钢平台 |
| CN107489214A (zh) * | 2017-06-29 | 2017-12-19 | 深圳前海特辰科技有限公司 | 核心筒竖向与水平结构的平层施工方法 |
| CN108678400A (zh) * | 2018-06-11 | 2018-10-19 | 中建局集团建设发展有限公司 | 高寒地区建筑结构上的自动爬升暖棚系统及其施工方法 |
| CN110863649A (zh) * | 2019-12-09 | 2020-03-06 | 中建七局第四建筑有限公司 | 一种轻量化超高层施工液压顶升模架系统 |
| CN111877725A (zh) * | 2020-07-02 | 2020-11-03 | 上海建工集团股份有限公司 | 整体钢平台模架水平限位系统及其安装方法 |
| CN112177321A (zh) * | 2020-10-09 | 2021-01-05 | 浙大宁波理工学院 | 建筑物外墙及楼板的爬模施工设备和施工方法 |
| CN112723094A (zh) * | 2021-01-29 | 2021-04-30 | 中建三局集团华南有限公司 | 一种基于轻型钢平台同步爬升的集成附墙装置 |
| CN112727093A (zh) * | 2020-12-28 | 2021-04-30 | 中材建设有限公司 | 一种用于构建大跨度高层建筑物的爬升施工方法 |
| WO2023226410A1 (zh) * | 2022-05-23 | 2023-11-30 | 中建三局集团有限公司 | 施工集成平台的爬带式自动顶升系统及其使用方法 |
| CN119021460A (zh) * | 2024-09-30 | 2024-11-26 | 中国建筑第八工程局有限公司 | 超高层建筑水平结构同步施工系统及方法 |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE1915840A1 (de) * | 1969-03-28 | 1970-10-01 | Josef Strakata | Massiv-poroeses Hochbau-Objekt in einheitlich monolytischer oder Platten-Bauweise aus neuartigem Baustoff,insbesondere fuer kurze Bauzeit und maessige Baukosten |
| CN104847108A (zh) * | 2015-03-06 | 2015-08-19 | 中国建筑第八工程局有限公司 | 液压爬模结构及其施工方法 |
| CN105735481A (zh) * | 2016-03-01 | 2016-07-06 | 中国建筑第八工程局有限公司 | 高层建筑核心筒顶升平台爬升保温装置及其施工方法 |
-
2016
- 2016-10-10 CN CN201610882864.XA patent/CN106400951B/zh not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE1915840A1 (de) * | 1969-03-28 | 1970-10-01 | Josef Strakata | Massiv-poroeses Hochbau-Objekt in einheitlich monolytischer oder Platten-Bauweise aus neuartigem Baustoff,insbesondere fuer kurze Bauzeit und maessige Baukosten |
| CN104847108A (zh) * | 2015-03-06 | 2015-08-19 | 中国建筑第八工程局有限公司 | 液压爬模结构及其施工方法 |
| CN105735481A (zh) * | 2016-03-01 | 2016-07-06 | 中国建筑第八工程局有限公司 | 高层建筑核心筒顶升平台爬升保温装置及其施工方法 |
Cited By (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107489214A (zh) * | 2017-06-29 | 2017-12-19 | 深圳前海特辰科技有限公司 | 核心筒竖向与水平结构的平层施工方法 |
| CN107190975A (zh) * | 2017-07-14 | 2017-09-22 | 四川华西集团有限公司 | 超高层建筑施工综合模架系统 |
| CN107299755A (zh) * | 2017-07-14 | 2017-10-27 | 四川华西集团有限公司 | 可实现外模架和钢平台整体和局部顶升的液压顶升钢平台 |
| WO2019011319A1 (zh) * | 2017-07-14 | 2019-01-17 | 四川华西集团有限公司 | 可实现外模架和钢平台整体和局部顶升的液压顶升钢平台 |
| WO2019011321A1 (zh) * | 2017-07-14 | 2019-01-17 | 四川华西集团有限公司 | 超高层建筑施工综合模架系统 |
| GB2574153A (en) * | 2017-07-14 | 2019-11-27 | Sichuan Huashi Group Co Ltd | Integrated formwork system for super high-rise building construction |
| GB2574153B (en) * | 2017-07-14 | 2022-08-31 | Sichuan Huashi Group Co Ltd | Integrated formwork system for construction of super high-rise building |
| CN108678400A (zh) * | 2018-06-11 | 2018-10-19 | 中建局集团建设发展有限公司 | 高寒地区建筑结构上的自动爬升暖棚系统及其施工方法 |
| CN108678400B (zh) * | 2018-06-11 | 2023-12-01 | 中建一局集团建设发展有限公司 | 高寒地区建筑结构上的自动爬升暖棚系统及其施工方法 |
| CN110863649B (zh) * | 2019-12-09 | 2021-08-27 | 中建七局第四建筑有限公司 | 一种轻量化超高层施工液压顶升模架系统 |
| CN110863649A (zh) * | 2019-12-09 | 2020-03-06 | 中建七局第四建筑有限公司 | 一种轻量化超高层施工液压顶升模架系统 |
| CN111877725A (zh) * | 2020-07-02 | 2020-11-03 | 上海建工集团股份有限公司 | 整体钢平台模架水平限位系统及其安装方法 |
| CN112177321A (zh) * | 2020-10-09 | 2021-01-05 | 浙大宁波理工学院 | 建筑物外墙及楼板的爬模施工设备和施工方法 |
| CN112727093A (zh) * | 2020-12-28 | 2021-04-30 | 中材建设有限公司 | 一种用于构建大跨度高层建筑物的爬升施工方法 |
| CN112723094A (zh) * | 2021-01-29 | 2021-04-30 | 中建三局集团华南有限公司 | 一种基于轻型钢平台同步爬升的集成附墙装置 |
| WO2023226410A1 (zh) * | 2022-05-23 | 2023-11-30 | 中建三局集团有限公司 | 施工集成平台的爬带式自动顶升系统及其使用方法 |
| CN119021460A (zh) * | 2024-09-30 | 2024-11-26 | 中国建筑第八工程局有限公司 | 超高层建筑水平结构同步施工系统及方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106400951B (zh) | 2019-04-30 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106400951A (zh) | 一种超高层建筑的水平与竖向结构同步施工方法 | |
| CN103635643B (zh) | 高层钢结构建筑钢筋砼筒体的施工方法 | |
| CN106437130A (zh) | 一种用于超高层建筑施工的内顶外爬式模架施工平台 | |
| CN108643544B (zh) | 一种高空悬挑施工平台支架体系及施工方法 | |
| CN104453197B (zh) | 高空大悬挑砼结构型钢支撑平台 | |
| CN202090591U (zh) | 一种建筑施工升降式爬升模板 | |
| WO2023240813A1 (zh) | 一种核心筒斜墙施工的钢平台变形施工结构及方法 | |
| CN107246073A (zh) | 核心筒纵横结构同步施工结构及方法 | |
| CN105442839A (zh) | 一种悬挑结构模板排架的搭设方法 | |
| CN201962944U (zh) | 一种建筑施工液压爬升模板 | |
| WO2023240812A1 (zh) | 一种用于空中增加核心筒墙体的整体施工平台结构及方法 | |
| CN108331336A (zh) | 楼板同步施工的整体提升钢平台系统及其施工方法 | |
| CN108360380A (zh) | 一种桥梁墩柱施工作业平台及其施工方法 | |
| CN206233541U (zh) | 一种用于超高层建筑施工的内顶外爬式模架施工平台 | |
| CN115538792B (zh) | 一种利用住宅造楼机的楼体施工方法及楼体施工结构 | |
| CN209145256U (zh) | 装配式建筑专用爬架 | |
| CN203547125U (zh) | 立柱式整体钢平台液压爬模 | |
| CN107217831B (zh) | 超高层建筑核心筒水平结构施工方法 | |
| CN206956979U (zh) | 一种带顶柱的一字型剪力墙 | |
| CN203097281U (zh) | 一种核电站双层安全壳液压爬模 | |
| CN107268971B (zh) | 一种超高层建筑物的双重自提升式外爬架及应用方法 | |
| CN209760761U (zh) | 一种核心筒内施工平台和电梯核心筒施工结构 | |
| CN108019040B (zh) | 一种高层建筑转换层贝雷架平台施工方法 | |
| CN219031629U (zh) | 一种室内板材安装起重设备 | |
| CN210883041U (zh) | 箱梁钢筋笼吊具存放架 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB03 | Change of inventor or designer information | ||
| CB03 | Change of inventor or designer information |
Inventor after: Tang Jiyu Inventor after: Xue Qing Inventor after: Liu Dong Inventor after: Lin Zhonghe Inventor after: Ge Xianglin Inventor after: Tang Gewei Inventor after: Liang Yueli Inventor after: Luo Yifeng Inventor after: Ning Huahong Inventor after: Ding Yunbo Inventor after: Ren Yufeng Inventor before: Tang Jiyu Inventor before: Lin Zhonghe Inventor before: Ge Xianglin Inventor before: Tang Gewei Inventor before: Liang Yueli Inventor before: Luo Yifeng Inventor before: Ning Huahong |
|
| TA01 | Transfer of patent application right | ||
| TA01 | Transfer of patent application right |
Effective date of registration: 20190304 Address after: 200 000 Floor 27, 1568 Century Avenue, China (Shanghai) Free Trade Pilot Area, Pudong New Area, Shanghai Applicant after: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd. Applicant after: CHINA HUASHI ENTERPRISES Co.,Ltd. Applicant after: SICHUAN NO.6 CONSTRUCTION Co.,Ltd. Address before: 200122 Pudong New Area, Shanghai, China (Shanghai) free trade trial area 1568 Century Avenue 27 Applicant before: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd. |
|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190430 |