[go: up one dir, main page]

CN106166794A - A kind of preform production line - Google Patents

A kind of preform production line Download PDF

Info

Publication number
CN106166794A
CN106166794A CN201610742818.XA CN201610742818A CN106166794A CN 106166794 A CN106166794 A CN 106166794A CN 201610742818 A CN201610742818 A CN 201610742818A CN 106166794 A CN106166794 A CN 106166794A
Authority
CN
China
Prior art keywords
line
production line
station
prefabricated component
preform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610742818.XA
Other languages
Chinese (zh)
Inventor
彭旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Mingsheng Drawin Technology Investment Co Ltd
Original Assignee
China Mingsheng Drawin Technology Investment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Mingsheng Drawin Technology Investment Co Ltd filed Critical China Mingsheng Drawin Technology Investment Co Ltd
Priority to CN201610742818.XA priority Critical patent/CN106166794A/en
Publication of CN106166794A publication Critical patent/CN106166794A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B15/00General arrangement or layout of plant ; Industrial outlines or plant installations
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/04Producing shaped prefabricated articles from the material by tamping or ramming
    • B28B1/045Producing shaped prefabricated articles from the material by tamping or ramming combined with vibrating or jolting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/08Producing shaped prefabricated articles from the material by vibrating or jolting
    • B28B1/087Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould
    • B28B1/0873Producing shaped prefabricated articles from the material by vibrating or jolting by means acting on the mould ; Fixation thereof to the mould the mould being placed on vibrating or jolting supports, e.g. moulding tables
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B1/00Producing shaped prefabricated articles from the material
    • B28B1/52Producing shaped prefabricated articles from the material specially adapted for producing articles from mixtures containing fibres, e.g. asbestos cement
    • B28B1/523Producing shaped prefabricated articles from the material specially adapted for producing articles from mixtures containing fibres, e.g. asbestos cement containing metal fibres
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/14Apparatus or processes for treating or working the shaped or preshaped articles for dividing shaped articles by cutting
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B13/00Feeding the unshaped material to moulds or apparatus for producing shaped articles; Discharging shaped articles from such moulds or apparatus
    • B28B13/02Feeding the unshaped material to moulds or apparatus for producing shaped articles
    • B28B13/0215Feeding the moulding material in measured quantities from a container or silo
    • B28B13/023Feeding the moulding material in measured quantities from a container or silo by using a feed box transferring the moulding material from a hopper to the moulding cavities
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B17/00Details of, or accessories for, apparatus for shaping the material; Auxiliary measures taken in connection with such shaping
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B7/00Moulds; Cores; Mandrels
    • B28B7/38Treating surfaces of moulds, cores, or mandrels to prevent sticking
    • B28B7/382Devices for treating, e.g. sanding

Landscapes

  • Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Manufacturing & Machinery (AREA)
  • Structural Engineering (AREA)
  • Devices For Post-Treatments, Processing, Supply, Discharge, And Other Processes (AREA)

Abstract

The present invention proposes a kind of preform production line, including decorative layer production line and body production line, described decorative layer production line includes pouring form wire, curing line, line of cut and post treatment line according to what preform production order was sequentially arranged, described post treatment line is provided with heat-insulation layer and installs station, described body production line is arranged at the side of described post treatment line, and described body production line includes body concrete layer shaping station.The preform production line of said structure, the body production line of prefabricated component is arranged at the side of post treatment line, after prefabricated part body and decorative layer have produced, without long distance transportation, in-site installation can be carried out, therefore, the body production line preferably resolving pre existing product excessively separates with decorative layer production line, causes the problem that body production line is high with decorative layer production line installation cost.

Description

A kind of preform production line
Technical field
The present invention relates to building machinery field, particularly to a kind of preform production line.
Background technology
Wallboard prefabricated components mainly include sandwich wallboard at present, are divided into a page wall, outer page wall and guarantor therebetween Temperature layer.Sandwich wallboard production line includes spaced fast pulley, directive wheel and circulates above fast pulley and directive wheel Multiple moulds, the corresponding different operation position of each mould.Sandwich wallboard production line includes that at least two be arranged in parallel Transfer lines between x wire and connection x wire, fast pulley and directive wheel are along x wire layout, and transfer lines is provided with horizontal stroke Moving dolly, fast pulley and directive wheel are controlled by a set of control system, and cross traveling trolley is controlled by single control system.This sandwich Wallboard production line is applicable to the thickness production more than 100mm wallboard, but for the thickness preform production less than 100mm, its Relatively costly, control system is more complicated.
It addition, the preform production line used at present, there is also body production line and the decorative layer production line of prefabricated component Excessively separate, cause the problem such as prefabricated part body and decorative layer installation cost height.
In sum, how providing one to solve, pre existing product production cost is higher, control system is complicated and pre- The preform production line of one of the problems or problem such as product body and decorative layer installation cost height, has become those skilled in the art urgently Need to solve the technical problem that.
Summary of the invention
The technical problem to be solved in the present invention is: production cost is low, production efficiency is high and the quality of production is good to provide one Preform production line.
The solution of the present invention is achieved in that the present invention proposes a kind of preform production line, raw including decorative layer Produce line and body production line, described decorative layer production line include according to preform production order be sequentially arranged pour form wire, Curing line, line of cut and post treatment line, described post treatment line is provided with heat-insulation layer and installs station, and described body production line is arranged at The side of described post treatment line, described body production line includes body concrete layer shaping station.
Another technical scheme of the present invention is on above-mentioned basis, described in pour form wire successively include spray work Position, pour station and the station that vibrates.
Another technical scheme of the present invention is on above-mentioned basis, and described spray station is provided with for spraying for platform mould First flush coater of coating release agent;The described station that pours is provided with the casting machine for pouring prefabricated component;The described station that vibrates sets There is the vibrator for prefabricated component is vibrated.
Another technical scheme of the present invention is on above-mentioned basis, and described curing line includes precuring kiln and whole maintenance Kiln, is connected by transfer lines between described precuring kiln and whole curing kilns.
Another technical scheme of the present invention is on above-mentioned basis, and described transfer lines includes conveying track, described fortune First end of defeated track connects with described whole curing kilns, and described conveying track is provided with the fortune that can move back and forth on conveying track Defeated dolly.
Another technical scheme of the present invention is that, on above-mentioned basis, described transfer lines also includes for prefabricated component is hung The first loop wheel machine being filled on conveying track, described first loop wheel machine is arranged at the second end of described conveying track.
Another technical scheme of the present invention is, on above-mentioned basis, to be additionally provided with between described curing line and described line of cut Surface disposing line, described surface disposing line is additionally provided with at least one for the shot-blasting machine that preform surfaces carries out Shot Blasting.
Another technical scheme of the present invention is on above-mentioned basis, described surface disposing line also include the second loop wheel machine and Turntable, described second loop wheel machine is used for handling prefabricated component, and it is arranged at described surface disposing line one end near curing line;Described Turntable is for rotating prefabricated component, and it is arranged at described surface disposing line one end near line of cut.
Another technical scheme of the present invention is on above-mentioned basis, described line of cut be provided with the first cutting work station and It is respectively equipped with cutting machine in second cutting work station, and described first cutting work station and the second cutting work station;On described post treatment line It is additionally provided with installation of embedded parts station, after described installation of embedded parts station is arranged at described heat-insulation layer installation station.
Another technical scheme of the present invention is on above-mentioned basis, described body production line and described post treatment line phase To setting and parallel with post treatment line.
The preform production line of said structure, the body production line of prefabricated component is arranged at the side of post treatment line, prefabricated component After body and decorative layer have produced, it is not necessary to long distance transportation, in-site installation can be carried out, therefore, preferably resolve existing The body production line of prefabricated component excessively separates with decorative layer production line, causes body production line and decorative layer production line installation cost High problem.
Accompanying drawing explanation
The accompanying drawing of the part constituting the present invention is used for providing a further understanding of the present invention, and the present invention's is schematic real Execute example and illustrate for explaining the present invention, being not intended that inappropriate limitation of the present invention.
Fig. 1 is the overall structure schematic diagram of the present invention a kind of preform production line;
Fig. 2 is the part-structure schematic diagram of the present invention a kind of preform production line;
Fig. 3 is a kind of structural representation stirring apparatus for distributing in Fig. 1;
Fig. 4 is the structural representation of another kind of stirring apparatus for distributing in Fig. 1;
Fig. 5 is the structural representation of a kind of precuring kiln in Fig. 1;
Fig. 6 is the enlarged diagram in A portion in Fig. 5;
Fig. 7 is the structural representation of a kind of transport vehicle in Fig. 1;
Fig. 8 is another working state schematic representation of transport vehicle in Fig. 7;
Fig. 9 is the structural representation of a kind of nursing frame in Fig. 1;
Figure 10 is the structural representation of the first cutting machine in Fig. 1;
Figure 11 is the top view of Figure 10;
Figure 12 is the structural representation of the second cutting machine in Fig. 1;
Figure 13 is the top view of Figure 12;
Figure 14 is the structural representation of a kind of pipeline of the present invention;
Figure 15 is the top view of Figure 14;
Figure 16 is the structural representation of another kind pipeline of the present invention;
Figure 17 is the left view of Figure 16.
Reference corresponding relation is:
1 lapping machine 2 casting machine 3 vibrator
4 pipeline 5 precuring kiln 6 ingot strippers
7 first cleaning machine 8 first flush coaters 9 water stamper
10 first loop wheel machine 11 second loop wheel machine 12 shot-blasting machines
13 turntable 14 first line of cut 15 second lines of cut
16 second cleaning machine 17 air-dry machine 18 second flush coaters
19 whole curing kilns 20 positioner 21 elevator
22 thermoplastic machine 23 conveying tracks 24 pour form wire
25 surface disposing line 26 post treatment lines
101 103 moulds of cement plaster blender 102 cement mortar material distributing machine
104 first hopper 105 second hopper 106 first frames
107 operating room 108 mixing drum 109 storage tanks
110 first helical axis 111 steel fiber reinforced concrete blenders
112 steel fiber reinforced concrete material distributing machine 113 second helical axis
201 side plate 202 prefabricated component 203 bearings
204 first base 205 top board 206 fog rooms
207 water pipes
301 first bearing pin 302 second bearing pin 303 rollers
304 pedestal 305 the 3rd bearing pin 306 first support members
307 support seat 308 the 4th bearing pin 309 second support member
310 the 3rd support member 311 the 4th support member 312 vertical rods
313 the 5th support member 314 the 6th support member 315 oblique pull plates
316 underframe 317 pull bars
401 first crossbeam 402 second cross beam 403 the 3rd crossbeams
404 first cutter head 405 second cutter head 406 the 3rd cutter heads
407 first column 408 guide rail 409 second bases
410 first motor 411 second column 412 the 3rd columns
414 the 4th crossbeam 415 the 4th cutter head 416 second motors
417 the 3rd motors
501 cylinder 502 leg 503 conveyer belts
Detailed description of the invention
Describing the present invention below in conjunction with the accompanying drawings, the description of this part is only exemplary and explanatory, should not Protection scope of the present invention is had any restriction effect.Additionally, those skilled in the art are according to the description of presents, can be right In presents, the feature in embodiment and in different embodiment carries out respective combination.
The embodiment of the present invention is as follows, preform production line shown in Figure 1, and concrete station includes platform mould scavenger Position, releasing agent spray station, first water smash station, mesh sheet lays station, second water and smash station, the pre-buried station of prefabricated component, precuring Nurse position, demoulding station, whole maintenance station, handling station, ball blast station, rotation modified line station, cutting work station, prefabricated component clean Station, dry tack free station, prefabricated component displacement station, gluing station, XPS (warming plate) install station, thermoplastic protection station and Lifting station etc..It should be noted that the various stations of above-mentioned preform production line, the simply row of one of which specific embodiment Lift, remaining embodiment can optionally add wherein part station composition production line according to the needs produced;On it addition, The station stated simply is named according to function action, not with actual station position one_to_one corresponding, it is understood that there may be two with The situation that upper station action completes on a station position, depending on specifically arranging beat with production line.Concrete equipment mainly wraps Include be horizontally disposed with pipeline 4, can on pipeline 4 platform mould the 103, first cleaning machine 7, first flush coater 8 of movement, water stamper 9, Lapping machine 1, casting machine 2, vibrator 3, ingot stripper 6, transport vehicle, precuring kiln the 5, first loop wheel machine 10, whole curing kilns 19, second hang Machine 11, shot-blasting machine 12, turntable 13, line of cut, the second cleaning machine 16, air-dry machine the 17, second flush coater 18, positioner 20, liter Fall machine 21, thermoplastic machine 22 and track 23 etc..
As in figure 2 it is shown, first platform mould 103 is positioned on pipeline 4, pipeline 4 is provided with multiple rotatable power Unit, power unit includes motor and the transfer roller being connected with the output shaft of motor, when motor rotates, drives transfer roller to rotate, enters one Step drives the platform mould 103 on pipeline 4 to move horizontally.By the first cleaning machine 7, platform mould 103 is carried out, in platform mould 103 Spot and Impurity removal clean, then by the first flush coater 8 even application releasing agent on platform mould 103 inwall, during this, Platform mould 103 moves on pipeline 4 always, then carries out watering for the first time in platform mould 103 smashing by watering stamper 9, then passes through lapping Machine 1 carries out grid cloth laying in platform mould 103, by casting machine 2, platform mould 103 carries out second time the most again and pours, and passes through Vibrator 3 vibrates further, after having vibrated, just the built-in fittings such as reinforcing bar can be embedded in the prefabricated component 202 poured In, carry out maintenance in prefabricated component 202 being delivered to precuring kiln 5 by transport vehicle afterwards.
Preform production line as shown in Figure 1, more specifically, including decorative layer production line and body production line, decoration Layer production line includes pouring form wire 24, curing line, line of cut and post processing according to what prefabricated component 202 production sequence was sequentially arranged Line 26, post treatment line 26 is provided with heat-insulation layer and installs station, and body production line is then arranged at the side of post treatment line 26, body Production line specifically includes body concrete layer shaping station, by body concrete layer shaping station, completes body concrete layer Production.When producing body concrete layer, the decorative layer that process line comes is transported to body production line, decorative layer is shifted To bed die, mould of aiding the border areas, pour body concrete layer, finally give wallboard prefabricated component.
Further, pour form wire 24 to include spray station successively, pour station and the station that vibrates.More specifically, Spray station is provided with for the first flush coater 8 for platform mould spraying releasing agent;Pour station to be provided with for pouring prefabricated component The casting machine 2 of 202;The station that vibrates is provided with the vibrator 3 for vibrating prefabricated component 202.
Further, curing line includes precuring kiln 5 and whole curing kilns 19, logical between precuring kiln 5 and whole curing kilns 19 Cross transfer lines to connect.Transfer lines includes conveying track 23, and the first end of conveying track 23 connects with whole curing kilns 19, conveying track 23 are provided with the travelling bogie that can move back and forth on conveying track 23.Transfer lines also include for prefabricated component 202 lift to The first loop wheel machine 10 on conveying track 23, the first loop wheel machine 10 is arranged at the second end of described conveying track 23.
Further, it is additionally provided with surface disposing line 25 between curing line and described line of cut, surface disposing line 25 also sets There is at least one for the shot-blasting machine 12 that prefabricated component 202 surface is carried out Shot Blasting.Surface disposing line 25 also includes that second hangs Machine 11 and turntable 13, the second loop wheel machine 11 is for handling prefabricated component 202, and the second loop wheel machine 11 is arranged at described surface disposing line 25 and leans on One end of nearly curing line.Turntable 13 is for rotating prefabricated component 202, and it is arranged at described surface disposing line 25 near cutting One end of secant.
Further, line of cut includes the first line of cut and the second line of cut, and the first line of cut is provided with the first cutting work Position, the first cutting work station can carry out transverse cuts to prefabricated component 202;Second line of cut is provided with the second cutting work station, and second cuts Cut station and can prefabricated component 202 be carried out longitudinally cutting.Additionally, be additionally provided with installation of embedded parts station, built-in fitting on post treatment line 26 After installation station is arranged at heat-insulation layer installation station.
For body production line, (not shown), preferably it is oppositely arranged with post treatment line 26, and flat with post treatment line 26 OK, this set-up mode, the installation effectiveness of prefabricated component 202 body and decorative layer can be effectively improved.
As it is shown on figure 3, in one embodiment, by stirring apparatus for distributing, cement mortar is stirred and cloth, stirs Mix apparatus for distributing to include being horizontally placed on ground pipeline 4, cement plaster blender 101 and and cement plaster blender 101 with the use of cement mortar material distributing machine 102, pipeline 4 for transport platform mould 103, platform mould 103 can on pipeline 4 water Translation is dynamic.Cement plaster blender 101 includes the mixing drum 108 for being stirred mortar and is arranged at mixing drum 108 The discharging opening of bottom, cement mortar material distributing machine 102 is then arranged at the lower section of discharging opening.Cement mortar material distributing machine 102 includes cloth Material mouth, pipeline 4 is arranged at the lower section of cloth mouth, when mortar flows out from cloth mouth, can flow into the platform mould on pipeline 4 In 103, thus complete pouring of prefabricated component 202.The apparatus for distributing of said structure, first by cement plaster blender 101 to sand Slurry is stirred, during after stirring, mortar flows into cement mortar material distributing machine 102 below, then by cement mortar material distributing machine 102 Mortar is delivered in the platform mould 103 on pipeline 4 below, thus completes prefabricated component 202 cloth.Cement plaster blender 101 include the first frame 106 being arranged on horizontal plane, and the first hopper 104 of being arranged in the first frame 106 and stirring Cylinder 108, the first hopper 104 includes the charging aperture in the portion that is arranged on and is arranged at the discharging opening of its underpart, and the first hopper 104 from top to bottom its barrel dliameter taper into, discharging opening is positioned at above mixing drum 108.The discharge outlet of the first hopper 104 is additionally provided with Feeding device, feeding device is horizontally or diagonally arranged, and the import of feeding device connects with discharging opening, and the outlet of feeding device is placed in Above the charging aperture of mixing drum 108.In another kind of embodiment, the outlet of feeding device is direct with the charging aperture of mixing drum 108 Connecting, feeding device is directly delivered to the material in hopper in mixing drum 108.Feeding device is specially screw conveying device, Including feeding tube and the first helical axis 110 of being arranged in feeding tube, the first helical axis 110 can rotate in feeding tube, and The conveying to material is realized during rotating.Storage tank 109, specifically, storage tank 109 it is additionally provided with in first frame 106 Being placed in the top of mixing drum 108, storage tank 109 by pipeline or directly can connect with mixing drum 108, and it is used for storing various need Additive in material to be added to.Being additionally provided with the second hopper 105 in cement mortar material distributing machine 102, the second hopper 105 is arranged at The lower section of mixing drum 108.Being additionally provided with discharging portion on mixing drum 108, discharging portion is specifically arranged at the bottom of mixing drum 108, juxtaposition In the top of the second hopper 105, mortar can flow out from discharging portion, and flows directly into the second hopper 105.Need explanation It is that discharging portion can be oppositely arranged with the second hopper 105, it is also possible to directly contact is arranged or connected by pipeline and arranges, at this not Make concrete restriction.It is additionally provided with discharging unit, discharging unit and the second hopper 105 in cement mortar material distributing machine 102 to connect, goes out material list Unit is fixing with the second hopper 105 to be connected, and for convenience of cleaning, can also be detachable fixing connection between the two.More specifically, Discharging unit includes the base plate being fixedly installed, and be arranged on base plate can the cover plate of folding, the discharge outlet of discharging unit It is additionally provided with the shrouding that can open or close discharging opening.The first oil cylinder and the second oil cylinder it is additionally provided with in cement mortar material distributing machine 102, the The upper end of one oil cylinder is flexibly connected with the second hopper 105, and the lower end of the first oil cylinder is flexibly connected with discharging unit, and the first oil cylinder is stretched During contracting, the cover plate of discharging unit can be driven to move, or rotate around base plate.One end of second oil cylinder is flexibly connected with discharging unit, The other end is flexibly connected with the shrouding of discharging unit, when the second oil cylinder stretches, shrouding can be driven to realize discharging opening opened or Close.Additionally, the side of stirring apparatus for distributing is additionally provided with operating room 107.
As shown in Figure 4, in one embodiment, by stirring apparatus for distributing, steel fiber reinforced concrete is stirred and cloth Material, stirring apparatus for distributing specifically include be horizontally placed on ground pipeline 4, steel fiber reinforced concrete blender 111 and with Steel fiber reinforced concrete blender 111 with the use of steel fiber reinforced concrete material distributing machine 112, pipeline 4 for transport platform mould 103, Platform mould 103 can move horizontally on pipeline 4.Fiber transporting device is arranged on the top of steel fiber reinforced concrete blender 111, uses In fiber concrete being delivered in steel fiber reinforced concrete blender 111, steel fiber reinforced concrete blender 111 includes for fibre The dimension mixing drum 108 that is stirred of concrete and the discharging opening being arranged at mixing drum 108 bottom, and steel fiber reinforced concrete cloth Machine 112 is then arranged at the lower section of discharging opening.Steel fiber reinforced concrete material distributing machine 112 includes that cloth mouth, pipeline 4 are arranged at cloth mouth Lower section, when mortar flows out from cloth mouth, can flow in the platform mould 103 on pipeline 4, thus complete prefabricated component 202 Pour.The apparatus for distributing of said structure, is first stirred mortar by steel fiber reinforced concrete blender 111, mortar after stirring Flow in steel fiber reinforced concrete material distributing machine 112 below, then be delivered to it by 112 mortars of steel fiber reinforced concrete material distributing machine In platform mould 103 on the pipeline 4 of lower section, thus complete prefabricated component 202 cloth.Steel fiber reinforced concrete blender 111 includes setting The frame being placed on horizontal plane, and the first hopper 104 of being arranged in frame and mixing drum 108, the first hopper 104 includes setting The charging aperture in portion placed on it and be arranged at the discharging opening of its underpart, and the first hopper 104 its barrel dliameter from top to bottom gradually becomes Little, discharging opening is positioned at above mixing drum 108.Fiber transporting device is arranged at the discharge outlet of the first hopper 104, fiber conveying dress Putting and horizontally or diagonally arrange, the import of fiber transporting device connects with discharging opening, and the outlet of fiber transporting device is placed in mixing drum Above the charging aperture of 108.In another kind of embodiment, the outlet of described fiber transporting device is straight with the charging aperture of mixing drum 108 Connecing in succession, fiber transporting device directly can be delivered to the material in hopper in mixing drum 108.Feeding device is specially spiral transferring Material device, including feeding tube and the second helical axis 113 of being arranged in feeding tube, the second helical axis 113 can be in feeding tube Rotate, and realize the conveying to material during rotating.Storage tank 109, specifically, storage tank 109 it is additionally provided with in frame Being placed in the top of mixing drum 108, storage tank 109 by pipeline or directly can connect with mixing drum 108, and it is used for storing various need Additive in material to be added to.Being additionally provided with the second hopper 105 in steel fiber reinforced concrete material distributing machine 112, the second hopper 105 sets It is placed in the lower section of mixing drum 108.Being additionally provided with discharging portion on mixing drum 108, discharging portion is specifically arranged at the bottom of mixing drum 108, Being placed in the top of the second hopper 105, mortar can flow out from discharging portion, and flows directly into the second hopper 105.Need explanation , discharging portion can be oppositely arranged with the second hopper 105, it is also possible to directly contact is arranged or connected by pipeline and arranges, at this It is not especially limited.It is additionally provided with discharging unit, discharging unit and the second hopper 105 in steel fiber reinforced concrete material distributing machine 112 to connect, Discharging unit and the second fixing connection of hopper 105, for convenience of cleaning, can also be detachable fixing connection between the two.More Specifically, discharging unit includes the base plate being fixedly installed, and be arranged on base plate can the cover plate of folding, going out of discharging unit It is additionally provided with, at material mouth, the shrouding that can open or close discharging opening.Fiber transporting device includes multiple horizontally disposed feeding tube, and Multiple feeding tubes be arranged in parallel, are provided with rotatable second helical axis 113 in each transport tube, and the second helical axis 113 revolves When turning, the material of conveying barrel moves, thus drives material to realize cloth through discharging unit.Additionally, stirring apparatus for distributing Side be additionally provided with operating room 107.
Precuring kiln as shown in Figures 5 and 6, specifically includes horizontally disposed first base 204 and is arranged at first Kiln body on base 204, kiln body includes that mutually isolated multiple fog rooms 206, multiple fog rooms 206 are set up in parallel, Mei Geyang Position deposited by the prefabricated component vertically arranging multiple-layer horizontal state in protecting room 206, more specifically, as it can be seen, every layer of prefabricated component 202 deposit position is made up of multiple bearings 203, and bearing 203 specifically includes the first bearing and the second bearing being oppositely arranged, first On the inwall of the left and right sides that seat and the second bearing are respectively provided with fog room 206, and, the first base of each fog room 206 204 are additionally provided with for prefabricated component 202 is transported into fog room 206 or the rail transported from fog room 206, it should be noted that Rail may be disposed on horizontal plane, it is possible to is arranged on the first base 204.It is equipped with one or more in each fog room 206 Water pipe 207, meanwhile, is additionally provided with many steam pipes in each fog room 206, steam pipe connects with water pipe 207, heated after steaming Steam in steam pipe can enter in water pipe 207, and under the effect of water vapour, water and vapour with predetermined temperature can be from being opened in water Venthole on pipe 207 is emerged, the prefabricated component 202 in fog room 206 is carried out maintenance.The bottom of fog room 206 is additionally provided with Cistern, one end of water pipe 207 connects with cistern, and cistern, for supplying water for water pipe 207, specifically can arrange water in pond Pump, it is ensured that water pipe 207 has been in water state all the time.It is additionally provided with in cistern and adds hot charging for carry out heating for water or water vapour Putting, heater is additionally provided with acoustic filter, acoustic filter is for reducing the noise of heater, and heater is arranged at water pipe 207 One end, and connect with water pipe 207.Being additionally provided with at least one temperature sensor in fog room 206, temperature sensor is used for perception Temperature in fog room 206, and, temperature sensor is arranged on fog room 206 inwall, can be on the sidewall of both sides, also The top of fog room 206 can be arranged at.Being additionally provided with at least one humidity sensor in fog room 206, humidity sensor is used for Humidity in perception fog room 206, and, humidity sensor is arranged on fog room 206 inwall, can be the sidewall of both sides On, it is also possible to it is arranged at the top of fog room 206.The porch of each fog room 206 is additionally provided with door, on the first base 204 Being provided with chute, the lower end of door is placed in chute, and can slidably reciprocate in chute.For the setting of door, real at another kind Executing in example, door is arranged on the sidewall of fog room 206 also by hinge, or is arranged at the top of fog room 206, needs Illustrate, when door is arranged at the top of fog room 206 by hinge, also can arrange at the top of fog room 206 simultaneously The extensible members such as oil cylinder, for driving door to place around the top of fog room 206.Curing kilns also include the two pieces of phases being arranged at periphery To the side plate 201 arranged, two blocks of side plates 201 are vertically arranged, and its lower end is arranged on the first base 204, two blocks of side plates 201 upper End is additionally provided with top board 205, fixes and be connected between the two ends of top board 205 and the top of two blocks of side plates 201.It should be noted that with The side that door is relative, i.e. the rear portion shown in figure, also is provided with shrouding.Being additionally provided with travel control device on rail, row kind controls Device is for controlling transport vehicle parking spot on rail, and control transport vehicle time strictly according to the facts puts part position, pickup position etc..Right In the first bearing being oppositely arranged and the second bearing, it is shaped as inverted trapezoidal, more specifically, and the shape on inwall after its installation Shape is that chamfer is trapezoidal, and the first bearing and the second bearing are bolted or welding manner is fixed on fog room 206 inwall.
Transport vehicle as shown in Figure 7 and Figure 8, specifically includes moveable pedestal 304, supports seat 307 and is arranged at base The support component that seat 304 and at least two supported between seat 307 are oppositely arranged, each support component at least includes the first support Part 306 and the second support member 309, the first support member 306 and the first end of the second support member 309, i.e. lower end shown in figure divide Be not flexibly connected with pedestal 304, the first support member 306 and the second end of the second support member 309, i.e. upper end shown in figure with Support seat 307 connects.The prefabricated component transport vehicle of this structure, the first support member 306 and the second support member 309 can be extensible member, the When one support member 306 and the second support member 309 extend simultaneously, the jacking to prefabricated component 202 can be realized.Certainly, first support Part 306 and the second support member 309 can also be strut, and when the lower end of two struts moves closer to, it the most gradually uprises, it is achieved Jacking to prefabricated component 202, on the contrary, when the lower end of two struts is gradually disengaged, it is highly gradually lowered.Prop up support component to be specially Scissor type telescopic frame, the upper surface of pedestal 304 further respectively has the first bearing pin 301 and the second bearing pin 302, the first support member 306 Lower end be flexibly connected with pedestal 304 by the first bearing pin 301, the lower end of the second support member 309 is by the second bearing pin 302 and base Seat 304 is flexibly connected, and is flexibly connected, specifically may be used between the two ends of the first support member 306 and between the two ends of the second support member 309 Connected by bearing pin.And the distance between the first bearing pin 301 and the second bearing pin 302 can be adjusted in real time.For convenience of installing And dismounting, connection between the first support member 306 and the first bearing pin 301, between the second support member 309 and the second bearing pin 302 Connect the most optional detachable connection.First support member 306 and the second support member 309 are preferably oil cylinder or cylinder.When first When support member 306 and the second support member 309 extend, the whole height of prefabricated component transport vehicle is higher, on the contrary, then and step-down.Need explanation , in this embodiment, the jointed shaft between the first support member 306 and the second support member 309 can keep the first support member 306 and second stability between support member 309.It is further preferable that jointed shaft can be fixedly installed on the first support member 306, Second support member 309 is provided with the chute coordinated with jointed shaft.It is additionally provided with driving means, in a kind of technical scheme on pedestal 304 In, driving means is horizontally placed on pedestal 304, its one end and the first support member 306 or the first end of the second support member 309, I.e. lower end shown in figure is flexibly connected, and during driving means action, drives the first support member 306 or the second support member 309 times End moves horizontally on pedestal 304.Or, the two ends of driving means respectively with the first support member 306 and the second support member 309 Lower end is flexibly connected, and during driving means elongation, the lower end of the first support member 306 and the second support member 309 is located remotely from each other, now, The height reduction of prefabricated component transport vehicle.And when driving means shortens, the first support member 306 and lower end of the second support member 309 Close to each other, now, the height of prefabricated component transport vehicle uprises.For driving means, can be oil cylinder, it is also possible to for cylinder, go back It can be other extensible member.Support member also includes the 3rd support member 310 and the 4th support member 311, one end of the 3rd support member 310 It is flexibly connected with the second end of the first support member 306, i.e. upper end shown in figure, one end of the 4th support member 311 and second Second end of support member 309, i.e. upper end shown in figure are flexibly connected, and, with the 4th between the two ends of the 3rd support member 310 It is flexibly connected by jointed shaft between the two ends of support member 311.The upper end of the first support member 306 is provided with the 3rd bearing pin 305, the 3rd Support member 310 is flexibly connected with the first support member 306 by the 3rd bearing pin 305, and the upper end of the second support member 309 is provided with the 4th bearing pin 308, the 4th support member 311 is flexibly connected with the second support member 309 by the 4th bearing pin 308.Support member also includes the 5th support Part 313 and the 6th support member 314, one end of the 5th support member 313, specially lower end are movable with the upper end of the 3rd support member 310 Connecting, then upper end with the 4th support member 311, the lower end of the 6th support member 314 is flexibly connected, equally, and the 5th support member 313 Two ends between and the two ends of the 6th support member 314 between be flexibly connected by jointed shaft.It should be noted that except the 5th support Beyond part 313 and the second support member 309, it is also possible to be arranged as required to more support member, to increase prefabricated component fortune further The height of defeated car.Being additionally provided with multiple roller 303 moved for band moving base 304 on pedestal 304, the quantity of roller 303 is preferred Being four, be respectively arranged on four angles of pedestal 304, ground can be laid and lay oneself on the railway tracks, roller 303 can be walked on laying oneself on the railway tracks.Need To illustrate that, it is also possible to arranging actuating unit on pedestal 304, actuating unit can be motor, it is also possible to for other power Unit.
Prefabricated component storage rack as shown in Figure 9, including horizontally disposed underframe 316, one end of underframe 316 and/or two ends Being provided with many vertical rods 312, vertical rod 312 is vertically arranged, and its lower end is fixing with underframe 316 to be connected.Additionally, for increasing the strong of storage rack Degree, storage rack also sets up oblique pull plate 315, oblique pull plate 315 be shaped as right angled triangle, one bar right-angle side and underframe 316 Fixing connection, another right-angle side is fixing with vertical rod 312 to be connected.Certainly, as other alternative, brace also can reach identical Technique effect, one end of brace and underframe 316 is fixing to be connected, and the other end of brace is fixed with vertical rod 312 and is connected.Additionally, it is vertical Can also arrange many pull bars 317 between bar 312, the two ends of pull bar 317 are fixing with vertical rod 312 respectively to be connected.Depositing of this structure Storage frame, can store the prefabricated component 202 that polylith is vertically placed simultaneously, have compact conformation, and take up room little advantage.Need explanation , for preventing adjacent prefabricated component 202 from sticking together, pull bar 317 can also arrange polylith dividing plate, the most adjacent prefabricated component 202 are separated by dividing plate.
The first line of cut 14 as shown in Figures 10 and 11, including pipeline 4 and cutting mechanism, cutting mechanism is arranged at defeated The top of line sending 4, specifically includes horizontally disposed second base 409, and first can moved left and right on the second base 409 Frame and the second frame, and, the first frame is additionally provided with can in the first frame the first cutter sweep of movement, the second frame On also be provided with equally can in the second frame the second cutter sweep of movement.Prefabricated component 202 on pipeline 4 need to be cut Time, prefabricated component 202 can cut by the first frame and the second frame simultaneously, and, the first cutter sweep and the second cutting dress Put and not only can move left and right with the first frame and the second frame respectively, also can respectively in the first frame and the second frame on back and forth Mobile, therefore, from arbitrarily angled, prefabricated component 202 can be cut.First frame includes being vertically arranged on the second base 409 The first column 407 and be fixedly installed on the first crossbeam 401 at the first column 407 top, it is preferable that the first column 407 Quantity is two, and two first columns 407 are oppositely arranged, and first crossbeam 401 is horizontally disposed with, and its two ends are stood with two first respectively The top of post 407 is fixing to be connected, and the first cutter sweep can move back and forth along first crossbeam 401.Same, the second frame includes erecting The second column 411 being directly arranged on the second base 409 and the second cross beam 402 being fixedly installed on the second column 411 top, Preferably, the quantity of the second column 411 is two, and two second columns 411 are oppositely arranged, and second cross beam 402 is horizontally disposed with, its Two ends are fixing with the top of two second columns 411 respectively to be connected, and the second cutter sweep can move back and forth along second cross beam 402. Cutter sweep also includes the 3rd frame that can move left and right on the second base 409, and the 3rd frame is provided with can be in the 3rd frame 3rd cutter sweep of upper movement.As shown in Figure 10, when using the second frame as benchmark, the second frame maintains static, the One frame and the 3rd frame can move left and right along the second base 409 according to being sized, and now, the second cutter sweep can realize Front and back cutting, the first cutter sweep and the 3rd cutter sweep the most both can realize front and back cutting, it is also possible to cut about realization.With First frame is the same with the second frame, and the 3rd frame includes being vertically arranged at the 3rd column 412 on the second base 409 and consolidating Surely the 3rd crossbeam 403 at the 3rd column 412 top it is arranged at, it is preferable that the quantity of the 3rd column 412 is two, two the 3rd Column 412 is oppositely arranged, and the 3rd crossbeam 403 is horizontally disposed with, and its two ends are fixing with the top of two the 3rd columns 412 respectively to be connected Connecing, the 3rd cutter sweep can move back and forth along the 3rd crossbeam 403.Stand for convenience of first column the 407, second column 411 and the 3rd Post 412 moves, and in one embodiment, the upper surface of the second base 409 arranges two chutes, and two chutes be arranged in parallel, The lower end of first column the 407, second column 411 and the 3rd column 412 is arranged in chute respectively, and, the first column 407, Second column 411 and the 3rd column 412 can slidably reciprocate along draw-in groove.In another kind of embodiment, the second base 409 arranges two Bar guide rail 408, two guide rails 408 be arranged in parallel, and the lower end of first column the 407, second column 411 and the 3rd column 412 is respectively It is provided with the rail wheel coordinated with guide rail 408, i.e. first column the 407, second column 411 and the 3rd column 412 led by rolling rail wheel Move left and right on rail 408.First cutter sweep includes the first extensible member and the first cutter head 404, and the upper end of the first extensible member is arranged On first crossbeam 401, the first cutter head 404 is arranged at the lower end of the first extensible member, when the first extensible member stretches, drives the first cutter 404 move up and down.For the first extensible member, can be oil cylinder, can be cylinder, it is also possible to for other any possible stretching Part.First extensible member is preferably oil cylinder, and the lower end of oil cylinder is provided with the first mounting seat for installing the first cutter head 404, the first cutter 404 are arranged in the first mounting seat, and the position that the first cutter head 404 is in the first mounting seat is adjustable, along with the first cutter head 404 The change of the position in the first mounting seat, the cut direction of prefabricated component 202 is changed by the first cutter head 404 the most therewith.Need It is noted that the structure of the second cutter sweep, the 3rd cutter sweep and the first cutter sweep is consistent, the i.e. second cutter sweep Second cutter head 405, the 3rd cutter head 406 of the 3rd cutter sweep is the most scalable, the second cutter head 405 and installation of the 3rd cutter head 406 The equal scalable in position.In first cutter sweep, the second cutter sweep and the 3rd cutter sweep, at least one is provided with and turns to machine Structure, steering mechanism turns to for band dynamic cutter head, and i.e. when arranging steering mechanism on the first cutter sweep, steering mechanism can drive the One cutter head 404 turns to around the lower end degree of doing of the first extensible member.For prevent prefabricated component 202 in cutting process because of stress sideslip, Thus affect cutting accuracy, it is additionally provided with for for prefabricated on pipeline 4, in the first frame, in the second frame or in the 3rd frame The guider that part 202 guides.Or all can arrange on pipeline 4, in the first frame, in the second frame and in the 3rd frame Guider.The structure of guider can be varied, can be guide plate, it is also possible to for gathering sill, it is also possible to for other Any possible guide frame.For fixing prefabricated component 202 further, in addition to guider, on pipeline 4, in the first frame, The hold down gag for pushing down prefabricated component 202 it is additionally provided with in second frame or in the 3rd frame.Or on pipeline 4, first It is equipped with hold down gag in frame, in the second frame and in the 3rd frame, compresses prefabricated component 202 from multiple angles, prevent prefabricated Part 202 is beated because of stress in cutting process.The side of pipeline 4 is additionally provided with the motor for driving prefabricated component 202 to move, The quantity of motor is preferably several, drives prefabricated component 202 to move from multiple directions.
The second line of cut 15 as shown in FIG. 12 and 13, including cutting mechanism and pipeline 4, cutting mechanism is arranged at defeated The top of line sending 4, cutting mechanism includes the frame being fixedly installed, and the lower end of frame is fixedly installed on horizontal plane, or passes through seat Son is arranged on horizontal plane, and frame arranges multiple cutter sweep, and multiple cutter sweep can move horizontally in frame.This knot The prefabricated component cutting production line of structure, frame is fixedly installed, and multiple cutter sweeps are arranged in frame, and can move down in frame Dynamic, when needing to cut prefabricated component 202, pipeline 4 drives prefabricated component 202 to move at a predetermined velocity, multiple cutter sweeps Can simultaneously act on prefabricated component 202, thus complete the cutting to prefabricated component 202 from different perspectives.Frame includes being vertically arranged In the column of horizontal plane, the quantity of column is preferably two, and two root posts be arranged in parallel, and it is horizontal that the top of two root posts is provided with the 4th Beam 414, multiple cutter sweeps are arranged on the 4th crossbeam 414, and can move back and forth on the 4th crossbeam 414.Cutter sweep has Body includes the first cutter sweep and the second cutter sweep, and the cross section of the 4th crossbeam 414 is rectangle, including two sides, lower surface and Lower surface, two sides or the lower surface of the 4th crossbeam 414 be provided with chute, and the upper end of the first cutter sweep and the second cutter sweep sets Being placed in chute, more specifically, the upper end of the first cutter sweep and the second cutter sweep can arrange roller, and is existed by roller Move back and forth in chute.It should be noted that the cooperation between the first cutter sweep and the second cutter sweep and the 4th crossbeam 414 Mode can also be varied, and this is no longer going to repeat them.First cutter sweep includes the first extensible member and the first cutter head 404, The upper end of the first extensible member is connected with the 4th crossbeam 414, and the first cutter head 404 is arranged at the lower end of the first extensible member, and first stretches When part stretches, the first cutter head 404 can be driven to move up and down.First extensible member is preferably oil cylinder, and the lower end of oil cylinder is provided with for pacifying Filling the first mounting seat of the first cutter head 404, the first cutter head 404 is arranged in the first mounting seat, and the first cutter head 404 is in the first peace Position on dress seat is adjustable, and along with the change of first cutter head 404 position in the first mounting seat, the first cutter head 404 is to prefabricated The cut direction of part 202 changes the most therewith.It should be noted that the structure one of the second cutter sweep and the first cutter sweep Causing, the second cutter head 405 on the i.e. second cutter sweep is scalable, the installation site also scalable of the second cutter head 405.Cutter sweep Also include the 3rd cutter sweep, and, the structure of the 3rd cutter sweep and the first cutter sweep and the second cutter sweep is the same, i.e. The 3rd cutter head 406 on 3rd cutter sweep is scalable, the installation site also scalable of the 3rd cutter head 406.It should be noted that 4th cutter head 415 can also be set on the 4th crossbeam 414 and more have cutter head.First cutter sweep, the second cutter sweep and In three cutter sweeps, at least one is provided with steering mechanism, and steering mechanism turns to, i.e. when the first cutter sweep for band dynamic cutter head On time steering mechanism is set, steering mechanism can drive the first cutter head 404 to turn to around the lower end degree of doing of the first extensible member.Pre-for preventing Product 202 in cutting process because of stress sideslip, thus affect cutting accuracy, pipeline 4 be additionally provided with for for prefabricated component 202 guiders guided, or all can arrange guider in frame, or are respectively provided with guiding in pipeline 4 and frame Device.The structure of guider can be varied, can be guide plate, it is also possible to for gathering sill, it is also possible to any for other Possible guide frame.For fixing prefabricated component 202 further, in addition to guider, pipeline 4 is additionally provided with for pushing down pre- The hold down gag of product 202, or hold down gag is set in frame, or and it is equipped with compression in frame on pipeline 4 Device, compresses prefabricated component 202 from multiple angles, prevents prefabricated component 202 from beating because of stress in cutting process.For guiding dress Putting, including at least one piece of guide plate, guide plate is fixedly installed on pipeline 4 and/or in frame by extensible member.For compressing Device, including at least one block pressur plate, pressing plate is fixedly installed on pipeline 4 and/or in frame by extensible member.Except pipeline 4 Outside multiple second motors 416 of upper setting, one end of the 4th crossbeam 414 can also arrange multiple 3rd motor 417, the 3rd motor 417 are used for driving cutter sweep to move on the 4th crossbeam 414.
Such as Fig. 2,14 and Figure 15 preform production line, more specifically, preform production line includes pipeline 4 and arranges Multiple moulds 103 on pipeline 4, pipeline 4 includes at least two horizontal production lines 26 be arrangeding in parallel, two horizontal lifes The two ends producing line 26 are also respectively provided with the first longitudinal production line 24 and second longitudinal production line 25, and horizontal production line 26 includes two Horizontally disposed crossbeam, arranges multiple rotatable cylinder 501 between crossbeam, platform mould 103 can be by cylinder 501 at pipeline 4 On move horizontally.More specifically, cylinder 501 includes that the first cylinder, the two ends of the first cylinder are respectively arranged on two crossbeams, And the one or both ends of the first cylinder are additionally provided with the power set for driving cylinder 501 to rotate.Preferably, power set are Motor, motor includes output shaft, and output shaft is fixing with the end of cylinder 501 to be connected, and when motor rotates, drives output shaft to rotate, It is further driven to cylinder 501 rotate.In addition to the first cylinder, cylinder 501 also includes second tin roller, and the two ends of second tin roller are rotatable Be arranged on two crossbeams, and the first cylinder and second tin roller interval are arranged, and second tin roller is arranged at adjacent two piece the Between one cylinder.Be additionally provided with frictional layer on first cylinder and second tin roller, frictional layer be used for increasing platform mould 103 and cylinder 501 it Between frictional force, be specifically as follows rubber layer, it is sheathed on or is embedded on the first cylinder and second tin roller.Need explanation It is that the power set driving cylinder 501 to rotate can also be varied, will not enumerate at this.This set-up mode, pipeline 4 can realize stepless speed regulation, and the movement of prefabricated component 202 or platform mould 103 is the most steady.
As shown in Figure 16 and Figure 17, for pipeline 4, in another kind of embodiment, pipeline 4 includes two parallel horizontal strokes Beam and for supporting the leg 502 of crossbeam, arranges multiple cylinder 501 between two crossbeams, cylinder 501 periphery arranges conveyer belt 503, i.e. wrapped up by 503 cylinders 501 of conveyer belt, the two ends of cylinder 501 arrange motor equally, when motor rotates, rolling Cylinder 501 rotates, and is further driven to conveyer belt 503 and rotates, thus platform mould 103 or the prefabricated component 202 on driving conveying belt 503 revolves Turn.Ibid, this set-up mode, pipeline 4 can realize stepless speed regulation equally, it is achieved to platform mould 103 or the steady fortune of prefabricated component 202 Defeated.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For Yuan, under the premise without departing from the principles of the invention, it is also possible to make some improvements and modifications, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (10)

1. a preform production line, it is characterised in that include decorative layer production line and body production line, described decorative layer produces Line includes pouring form wire, curing line, line of cut and post treatment line, described rear place according to what preform production order was sequentially arranged Reason line is provided with heat-insulation layer and installs station, and described body production line is arranged at the side of described post treatment line, and described body produces Line includes body concrete layer shaping station.
Preform production line the most according to claim 1, it is characterised in that described in pour form wire successively include spray work Position, pour station and the station that vibrates.
Preform production line the most according to claim 2, it is characterised in that described spray station is provided with for for platform mould First flush coater of spraying releasing agent;The described station that pours is provided with the casting machine for pouring prefabricated component;The described station that vibrates It is provided with the vibrator for prefabricated component is vibrated.
Preform production line the most according to claim 1, it is characterised in that described curing line includes precuring kiln and supports eventually Protect kiln, connected by transfer lines between described precuring kiln and whole curing kilns.
Preform production line the most according to claim 4, it is characterised in that described transfer lines includes conveying track, described First end of conveying track connects with described whole curing kilns, and described conveying track is provided with and can move back and forth on conveying track Travelling bogie.
Preform production line the most according to claim 5, it is characterised in that described transfer lines also includes for prefabricated component Lifting the first loop wheel machine to conveying track, described first loop wheel machine is arranged at the second end of described conveying track.
Preform production line the most according to claim 1, it is characterised in that between described curing line and described line of cut also It is provided with surface disposing line, described surface disposing line is additionally provided with at least one for the throwing that preform surfaces is carried out Shot Blasting Ball machine.
Preform production line the most according to claim 7, it is characterised in that described surface disposing line also includes the second loop wheel machine And turntable, described second loop wheel machine is used for handling prefabricated component, and it is arranged at described surface disposing line one end near curing line;Institute Stating turntable for rotating prefabricated component, it is arranged at described surface disposing line one end near line of cut.
Preform production line the most according to claim 1, it is characterised in that described line of cut is provided with the first cutting work station It is respectively equipped with cutting machine with in the second cutting work station, and described first cutting work station and the second cutting work station;
Being additionally provided with installation of embedded parts station on described post treatment line, described installation of embedded parts station is arranged at described heat-insulation layer and installs After station.
Preform production line the most according to claim 1, it is characterised in that described body production line and described post processing Line is oppositely arranged, and parallel with post treatment line.
CN201610742818.XA 2016-08-26 2016-08-26 A kind of preform production line Pending CN106166794A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610742818.XA CN106166794A (en) 2016-08-26 2016-08-26 A kind of preform production line

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610742818.XA CN106166794A (en) 2016-08-26 2016-08-26 A kind of preform production line

Publications (1)

Publication Number Publication Date
CN106166794A true CN106166794A (en) 2016-11-30

Family

ID=57376955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610742818.XA Pending CN106166794A (en) 2016-08-26 2016-08-26 A kind of preform production line

Country Status (1)

Country Link
CN (1) CN106166794A (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106827176A (en) * 2017-02-27 2017-06-13 句容市新科预制构件有限公司 A kind of precast concrete equipment
CN106938494A (en) * 2016-12-29 2017-07-11 中民筑友科技投资有限公司 A kind of production technology of decorative panel
CN108000695A (en) * 2018-01-05 2018-05-08 河北益铁机电科技有限公司 Pretensioning prestressed concrete track board assembly line pours vibrating system and its application
CN110815524A (en) * 2019-10-23 2020-02-21 南京信息职业技术学院 Precast concrete slab maintenance system
CN110815534A (en) * 2019-09-27 2020-02-21 江苏元大建筑科技有限公司 PC component production line
CN111452208A (en) * 2020-06-02 2020-07-28 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 Section beam prefabricating assembly line adopting stub matching method
CN111844412A (en) * 2020-06-23 2020-10-30 中建西部建设建材科学研究院有限公司 Production process of ultrahigh-performance concrete-based large-hollow-rate wallboard
CN112108752A (en) * 2020-09-18 2020-12-22 湖南三一快而居住宅工业有限公司 Net piece automatic weld apparatus for producing
CN112277147A (en) * 2020-10-30 2021-01-29 长沙远大模块集成科技有限公司 Double-kiln double-distribution prefabricated part production line and production process
CN114800813A (en) * 2022-03-23 2022-07-29 中交一公局第四工程有限公司 Automatic production and processing device and method for prefabricated guardrail
CN116604698A (en) * 2023-02-22 2023-08-18 恒尊建设集团有限公司 A device for making concrete prefabricated parts

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3600481A (en) * 1966-06-08 1971-08-17 Walter Lanz Method for more rapidly producing aeroconcrete building elements
JPH0435905A (en) * 1990-05-31 1992-02-06 Ig Tech Res Inc Apparatus for successively manufacturing ceramic plate
CN101168265A (en) * 2007-12-04 2008-04-30 陈延东 Method for prefabricating thermal insulation slurry composite wall and floorslab
CN201979598U (en) * 2011-03-01 2011-09-21 天津市星兆防水保温工程有限公司 Production line of outer wall heat-preservation and decoration integral plate
CN103240800A (en) * 2012-02-03 2013-08-14 济南高新开发区七星实业有限公司 Composite insulation board production line
CN203317535U (en) * 2013-07-05 2013-12-04 泉州市祥达机械制造有限公司 Full automatic production line for composition insulation boards of walls
CN203821829U (en) * 2014-05-20 2014-09-10 宋廷善 Building compound insulated template and production line
CN203876032U (en) * 2014-04-03 2014-10-15 深圳海龙建筑制品有限公司 Automatic prefabricated part production system
CN104723449A (en) * 2015-02-12 2015-06-24 沈阳卫德住宅工业化科技有限公司 Automatic production line of building industrialization concrete precast members
CN105751366A (en) * 2016-05-09 2016-07-13 杜嫣然 Automatic production line for inorganic decorative sheet
CN105799051A (en) * 2016-05-06 2016-07-27 许迪茗 Production line for heat insulation and decoration integrated wallboards of outer wall structure
CN206030207U (en) * 2016-08-26 2017-03-22 中民筑友科技投资有限公司 Prefab production line

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3600481A (en) * 1966-06-08 1971-08-17 Walter Lanz Method for more rapidly producing aeroconcrete building elements
JPH0435905A (en) * 1990-05-31 1992-02-06 Ig Tech Res Inc Apparatus for successively manufacturing ceramic plate
CN101168265A (en) * 2007-12-04 2008-04-30 陈延东 Method for prefabricating thermal insulation slurry composite wall and floorslab
CN201979598U (en) * 2011-03-01 2011-09-21 天津市星兆防水保温工程有限公司 Production line of outer wall heat-preservation and decoration integral plate
CN103240800A (en) * 2012-02-03 2013-08-14 济南高新开发区七星实业有限公司 Composite insulation board production line
CN203317535U (en) * 2013-07-05 2013-12-04 泉州市祥达机械制造有限公司 Full automatic production line for composition insulation boards of walls
CN203876032U (en) * 2014-04-03 2014-10-15 深圳海龙建筑制品有限公司 Automatic prefabricated part production system
CN203821829U (en) * 2014-05-20 2014-09-10 宋廷善 Building compound insulated template and production line
CN104723449A (en) * 2015-02-12 2015-06-24 沈阳卫德住宅工业化科技有限公司 Automatic production line of building industrialization concrete precast members
CN105799051A (en) * 2016-05-06 2016-07-27 许迪茗 Production line for heat insulation and decoration integrated wallboards of outer wall structure
CN105751366A (en) * 2016-05-09 2016-07-13 杜嫣然 Automatic production line for inorganic decorative sheet
CN206030207U (en) * 2016-08-26 2017-03-22 中民筑友科技投资有限公司 Prefab production line

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106938494A (en) * 2016-12-29 2017-07-11 中民筑友科技投资有限公司 A kind of production technology of decorative panel
CN106938494B (en) * 2016-12-29 2019-12-10 中民筑友科技投资有限公司 Production process of decorative plate
CN106827176A (en) * 2017-02-27 2017-06-13 句容市新科预制构件有限公司 A kind of precast concrete equipment
CN108000695A (en) * 2018-01-05 2018-05-08 河北益铁机电科技有限公司 Pretensioning prestressed concrete track board assembly line pours vibrating system and its application
CN110815534A (en) * 2019-09-27 2020-02-21 江苏元大建筑科技有限公司 PC component production line
CN110815524A (en) * 2019-10-23 2020-02-21 南京信息职业技术学院 Precast concrete slab maintenance system
CN111452208A (en) * 2020-06-02 2020-07-28 中交二航局第四工程有限公司安徽混凝土装配化构件分公司 Section beam prefabricating assembly line adopting stub matching method
CN111452208B (en) * 2020-06-02 2021-07-13 中交二航局第四工程有限公司 A short-line matching method segment beam prefabrication line
CN111844412A (en) * 2020-06-23 2020-10-30 中建西部建设建材科学研究院有限公司 Production process of ultrahigh-performance concrete-based large-hollow-rate wallboard
CN112108752A (en) * 2020-09-18 2020-12-22 湖南三一快而居住宅工业有限公司 Net piece automatic weld apparatus for producing
CN112277147A (en) * 2020-10-30 2021-01-29 长沙远大模块集成科技有限公司 Double-kiln double-distribution prefabricated part production line and production process
CN114800813A (en) * 2022-03-23 2022-07-29 中交一公局第四工程有限公司 Automatic production and processing device and method for prefabricated guardrail
CN116604698A (en) * 2023-02-22 2023-08-18 恒尊建设集团有限公司 A device for making concrete prefabricated parts

Similar Documents

Publication Publication Date Title
CN106166794A (en) A kind of preform production line
CN105538495B (en) The production technology of complex heat-preservation Light trabses
CN104191513B (en) Automatic production line of small plastic-concrete components
CN109624042B (en) Prestressed pipe pile production system
US9308669B2 (en) Automated concrete structural member fabrication system
US3523343A (en) System for the production of cast concrete members
CN203973737U (en) The process units of complex heat-preservation Light trabs
US9409311B1 (en) Automated concrete structural member fabrication system, apparatus and method
CN107538607A (en) A kind of production line and production method of heat preservation dismounting-free formwork for building
CN107747270A (en) A kind of municipal equipment for the road surface roadbed repairing that cement concrete after rain can be recessed
CN106335129A (en) Automatic production system for leak joint plate for livestock breeding
CN206030207U (en) Prefab production line
CN206030206U (en) Prefab production line
CN106272940A (en) A kind of preform production line
CN118621743A (en) Slope lining slipform construction trolley and slope lining construction method
CN206578964U (en) A kind of Combined production line of heat preservation dismounting-free formwork for building
CN117863341A (en) Concrete prefabricated member processing device and processing method
CN206186077U (en) Prefab production line
CN205255245U (en) Building wallboard automatic production line
CN206926070U (en) A kind of preform production line
CN107538608A (en) A kind of Combined production line and production method of heat preservation dismounting-free formwork for building
CN206030208U (en) Prefab production line
CN206030209U (en) Prefab production line
CN112405823A (en) Leak board production line
CN203818307U (en) Concrete distributing device of prestressed centrifugal pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161130