CN1052929C - Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting - Google Patents
Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting Download PDFInfo
- Publication number
- CN1052929C CN1052929C CN92115006A CN92115006A CN1052929C CN 1052929 C CN1052929 C CN 1052929C CN 92115006 A CN92115006 A CN 92115006A CN 92115006 A CN92115006 A CN 92115006A CN 1052929 C CN1052929 C CN 1052929C
- Authority
- CN
- China
- Prior art keywords
- side plate
- dummy bar
- minor face
- face side
- mould
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Continuous Casting (AREA)
Abstract
一种板坯连续浇铸的起动方法,包括如下步骤:把引锭杆安置在模具内上下方向中央部的所定位置;使短边侧板保持垂直,调整其与引锭杆之间的间隙至1-3mm;充填密封材料;注入钢水,形成凝固壳;开始向下拉拔引锭杆,当形成的凝固壳和侧板之间的钢水不再流动时,将短边侧板的上端部向外方向移动,在向下方向加上锥度进行连续浇铸。该方法可实现容易地拉拔引锭杆、平稳圆滑地起动引锭杆的目的。
A starting method for continuous casting of slabs, comprising the following steps: placing a dummy bar at a predetermined position in the center of the mold in the up-and-down direction; keeping the short-side side plate vertical, and adjusting the gap between it and the dummy bar to 1 -3mm; Fill the sealing material; Inject molten steel to form a solidified shell; Begin to pull the dummy bar downwards, when the molten steel between the formed solidified shell and the side plate no longer flows, turn the upper end of the short side plate outwards Move, taper in downward direction for continuous casting. The method can realize the purposes of easily pulling out the dummy bar and starting the dummy bar smoothly and smoothly.
Description
本发明涉及板坯连续浇铸的连续浇铸起动方法,其包括板坯连续浇铸的浇铸开始前引锭杆的安置方法。The invention relates to a continuous casting starting method for continuous casting of slabs, which includes a method for setting dummy rods before starting casting of continuous casting of slabs.
以往,在幅宽可变的板坯连续浇铸上,在其浇铸开始初期将引锭杆安置在模具内,通过以往幅宽可变连续浇铸装置使板坯的连续浇铸起动时,是采用以下说明的方法。Conventionally, in the continuous casting of slabs with variable width, the dummy bar is placed in the mold at the beginning of casting, and the continuous casting of slabs is started by the conventional variable width continuous casting device, and the following description is adopted. Methods.
图3(a)是以往板坯连续浇铸用的幅宽可变模具的平面略图,图3(b)是图2(a)的A-A向剖视图。在图上,1是模具的长边侧板,2是短边侧板。短边侧板2一方面被长边侧板1夹持着,同时通过安装在外侧的上下成一组的驱动装置3a、3b,将短边侧板2向板坯的幅宽方向移动,于是短边侧板2移动,使之能够进行板坯的幅宽尺寸的变更和调整。Fig. 3(a) is a schematic plan view of a conventional variable-width mold for continuous casting of slabs, and Fig. 3(b) is a sectional view taken along line A-A of Fig. 2(a). In the figure, 1 is the long-side side plate of the mold, and 2 is the short-side side plate. On the one hand, the short-
在这种情况下,长边侧板1的间隔通常是一定的,如要变更板坯厚度采用另外方法,例如更换短边侧板2等。In this case, the distance between the long-side side plates 1 is usually constant, and if the thickness of the slab needs to be changed, another method is used, such as replacing the short-
其次,参照图3(a)-(b)及图4(a)-(b),对使用上述模具10的以往板坯连续浇铸进行浇铸作业时顺序进行说明。Next, referring to Fig. 3(a)-(b) and Fig. 4(a)-(b), the sequence of the casting operation in conventional slab continuous casting using the
首先,在图4(a)上,当最初从模具10的下方或上方插入引锭杆4时,为使其插入容易应使驱动装置3a、3b动作,将短边侧板2的上端的位置按所定的宽度(铸造板坯宽度+热收缩的补偿量)加上余量安置好,这时应比所定的宽度扩大到足够大的位置,然后将短边侧板2按所定的宽度安置上。或者在当初就将短边侧板2按所定的宽度安置好,然后再插入比其宽度小20-60mm的引锭杆4。First, in Fig. 4(a), when inserting the
插入的引锭杆4,如图4(b)所示是被安置在模具10内的上下方向中央部的设定位置,一般是被安置在模具下端起1/3-1/2的位置。同时短边侧板2的下端部的间隔,应在下端部的所定宽度基础上,在其下方加上锥度。The inserted
在短边侧板2的下方加上锥度的理由是:在模具内形成的凝固壳随着冷却会发生很大的收缩特别是在板坯的幅宽方向,使短边侧板2和凝固壳6a之间产生间隙,所以考虑通常稳定铸造状态下发生的热收缩,在向下方向加上相当量的锥度,使下端部幅宽略窄。The reason for adding a taper to the bottom of the
至于长边侧板1,因为被浇铸的板坯厚度相对其幅宽来说较小,为几分之1左右,热收缩也小,所以通常不像短边侧板那样加上锥度。还有,当插入引锭杆4时,对厚度的余量也没有特别考虑的必要。引锭杆4和长边侧板1的间隙,应维持在使引锭杆动作必要的2-5mm左右。As for the long-side side plate 1, because the thickness of the cast slab is relatively small relative to its width, which is about 1/1, and the thermal shrinkage is also small, it is usually not tapered like the short-side side plate. Also, when inserting the
这样,先在模具10内安置上引锭杆4,在模具10和引锭杆4的间隙内,为不使钢水泄漏,充填具有弹性的耐热密封材料5。Like this,
其次如图4(c)所示,由中间包向模具浇入钢水6。为使能够拔出引锭杆4,被浇入的钢水应在模具10内被保持40秒左右。其间,钢水由模具10冷却,形成凝固壳6a。Next, as shown in Fig. 4(c),
在引锭杆4的头部做成有燕尾榫槽,在这个燕尾榫槽内流入的钢水凝固,使引锭杆4和铸件的结合严密,才能够用引锭杆拔出铸件。Dovetail tenon groove is made at the head of
其次如图4(d)所示,将引锭杆4一面向下方拉拔,一面继续浇入钢水5,其间凝固壳6a也同时长大,形成连续浇铸铸件。Next, as shown in Fig. 4(d), the
然而,像这样浇铸起动不稳定情况下,充填了密封材料5的引锭杆4的头部和起动初期壳6a的宽度,比模具10下部的宽度要大,要将引锭杆4从模具10下部通过拔出时,由于引锭杆4和壳6a与模具10之间的滑动,就需要非常大的拉拔力。However, when the casting start is unstable like this, the width of the head portion of the
此时,如壳6a未充分长大,由于和模具10之间的滑动,则壳6a破裂,发生所谓跑钢现象,还使模具10的下端部受损,其结果是发生生产效率低下,模具寿命降低,维修费用增加等问题。At this time, if the
针对这个问题,为得到能承受大拉拔力的壳体6a的强度,可使其在模具10内保持足够的时间,或如图4(b)所示,例如在模具10内的引锭杆4的上部装入冷却材11,以促进壳6a的生成凝固等。然而这些都会招致浇铸准备时间及运转成本的增加,便会发生给浇铸作业的自动化造成困难等新问题。In response to this problem, in order to obtain the strength of the
还有,在这种情况下,因为短边侧板成上开状,所以引锭杆上端部和模具之间的间隙较大,两侧合计为20-45mm,于是给密封材料的充填造成困难。这样也有增加浇铸准备时间、影响浇铸作业的自动化等问题。Also, in this case, because the short-side side plate is opened up, the gap between the upper end of the dummy bar and the mold is relatively large, and the total of the two sides is 20-45mm, which makes it difficult to fill the sealing material. . This also has problems such as increasing the casting preparation time and affecting the automation of casting operations.
本发明是鉴于上述问题而开发的。以提供使引锭杆的拉拔容易、连续浇铸能够圆滑起动的板坯连续浇铸的起动方法为目的。The present invention was developed in view of the above problems. It is an object of the present invention to provide a starting method for continuous casting of slabs which facilitates drawing of dummy rods and enables smooth starting of continuous casting.
本发明的目的是通过板坯连续浇铸的起动方法完成的,在将模具的短边侧板夹持于长边侧板、且使用短边侧板顺板坯的幅宽方向能够调整的连续浇铸模具进行的板坯连续浇铸中,其特征在于:将引锭杆安置在模具内的上下方向中央部的所定位置,接着将短边侧板保持垂直,使其和引锭杆之间的间隙分别调整为1-3mm,然后在长边侧板及短边侧板和引锭杆之间充填密封材料,随之开始浇入钢水,一面保持浇入的钢水,一面冷却形成凝固壳,接着开始拉拔引锭杆,一面将引锭杆向下方拉拔,一面在钢水不再流入形成的凝固壳和前记板之间时将短边侧板的上端部向外方向移动,在向下方向加上锥度进行连续浇铸。The object of the present invention is accomplished by a start-up method of continuous casting of slabs, in the continuous casting in which the short side plates of the mold are clamped to the long side plates and the short side plates can be adjusted along the width direction of the slab In the continuous casting of slabs by the mold, it is characterized in that the dummy bar is placed at a predetermined position in the center of the mold in the vertical direction, and then the short-side side plate is kept vertical so that the gap between the dummy bar and the dummy bar is respectively Adjust it to 1-3mm, then fill the sealing material between the long-side side plate and short-side side plate and the dummy rod, then start pouring molten steel, keep the poured molten steel while cooling to form a solidified shell, and then start pulling Pull the dummy bar, pull the dummy bar downwards, and move the upper end of the short-side side plate outward when the molten steel no longer flows into the formed solidification shell and the front plate, and add it in the downward direction. Taper for continuous casting.
如上述说明,按照本发明的连续浇铸的起动方法,是将短边侧板保持垂直,将其和引锭杆之间的间隙调整为1-3mm,使连续浇铸起动,所以形成的凝固壳和模具之间不发生异常的滑动力,用较小的拉拔力即可拉拔,于是能够防止在浇铸开始时由于壳的破裂发生的跑钢事故,提高生产效率和模具的寿命,更能减少模具的浇铸准备时间,节约冷却材料和浇铸时间及运转成本,也能促进浇铸作业的自动化。As described above, according to the starting method of continuous casting of the present invention, the short side plate is kept vertical, and the gap between it and the dummy rod is adjusted to 1-3mm to start continuous casting, so the formed solidified shell and There is no abnormal sliding force between the molds, and the drawing can be done with a small pulling force, so it can prevent the accident of running steel due to the cracking of the shell at the beginning of casting, improve production efficiency and the life of the mold, and reduce the The casting preparation time of the mold can save cooling materials, casting time and operating costs, and can also promote the automation of casting operations.
按照本发明的引锭杆安置方法,将短边侧板保持垂直,和引锭杆之间的间隙调整为1-3mm,然后向这个间隙充填密封材料,所以密封材料的充填变得容易,这样安置引锭杆进行连续浇铸时,可得到与上记同样的效果。According to the dummy bar placement method of the present invention, the short side side plate is kept vertical, and the gap between the dummy bar is adjusted to 1-3 mm, and then the gap is filled with sealing material, so the filling of the sealing material becomes easy, like this When the dummy bar is installed for continuous casting, the same effect as above can be obtained.
下面参照附图来进一步说明本发明。The present invention will be further described below with reference to the accompanying drawings.
图1是表示本发明的浇铸起动方法步骤一例的侧剖面略图,图(a)是在模具10内插入了引锭杆4的图,图(b)是短边侧板2保持垂直,与引锭杆的间隔分别调整为1-3mm的图,图(c)是开始向模具10内浇入钢水,使钢水表面上升形成凝固壳6a的图,图(d)是将短边侧板2的上端部向外方向移动,对着向下方向加上锥度进行连续浇铸的图;Fig. 1 is a schematic side sectional view showing an example of the steps of the casting starting method of the present invention, figure (a) is a figure in which a
图2(a)是表示拉拔开始后,加锥度开始时机过分落后情况下从本发明的模具拉拔铸件开始后的铸件状态的侧剖面略图,是图2(b)的B-B向剖面图,图2(b)是图2(a)的A-A向剖面图;Fig. 2 (a) is a side sectional schematic view showing the casting state after drawing the casting from the mold of the present invention under the situation that the taper starting timing is too late after the start of drawing, and is a sectional view of B-B of Fig. 2 (b), Fig. 2 (b) is the A-A direction sectional view of Fig. 2 (a);
图3(d)是用于板坯连续浇铸的幅宽可变模具的平面略图,图3(b)是图3(d)的A-A向视剖视图;Fig. 3(d) is a schematic plan view of a variable-width mold for continuous casting of slabs, and Fig. 3(b) is a sectional view taken along the direction A-A of Fig. 3(d);
图4是表示以往的连续浇铸起动方法步骤一例的侧剖面略图,图(a)是在模具10内插入了引锭杆4的图,图(b)是在短边侧板2的向下方向加上锥度的图,图(c)是向模具10内开始浇入钢水,使钢水上升形成凝固壳6a的图,图(d)是一面浇入钢水,一面通过引锭杆4将铸件向下拉拔进行连续浇铸的图。Fig. 4 is a schematic side sectional view showing an example of the steps of the conventional continuous casting starting method, the figure (a) is a figure in which the
下面参照表示本发明前记幅宽可变模具的图2(a)、(b),及表示本发明的起动方法一例的图1(a)-(d),进行详细说明。Referring to Fig. 2(a) and (b) showing the foregoing variable width mold of the present invention, and Fig. 1(a)-(d) showing an example of the starting method of the present invention, the details will be described below.
首先,如图1(a)所示,将短边侧板2的间隔调整为比引锭杆4的幅宽,单侧至少调宽10mm以上。First, as shown in Fig. 1(a), the distance between the short-
这是以扁平、宽幅的板坯为对象的模具的情况,特别是如果幅宽方向余量少,则插入引锭杆困难。短边侧板2和引锭杆4的间隔在幅宽方向的余量,单侧的理想值是25-45mm左右。This is the case of a die for a flat and wide slab, and it is difficult to insert a dummy bar especially if the margin in the width direction is small. The margin of the distance between the short-
其次如图1(b)所示,从模具10的下部插入引锭杆4,安置在模具内的上下方向中央位置的所定位置,例如从模具10的下端起1/3-1/2的位置。Next, as shown in Figure 1(b), insert the
接着将短边侧板2保持垂直,与引锭杆4的间隙分别调整为1-3mm,然后在长边侧板及短边侧板1、2和引锭杆4的间隙中充填密封材料5。如前所述引锭杆4和长边侧板1的间隙应维持在2-5mm左右。Then keep the short-
引锭杆4和各板1、2之间,考虑防止钢水泄漏及以后密封材料的充填作业方便,当然越小越好,但为了引锭杆4的动作平滑,有1-3mm左右是必要的。Between the
还有在这里使用的密封材料5,是用例如以SiO2、Al2O3、CaO为主要成分的耐火材料的粉末,加入硅树脂系列的耐热粘合剂进行拌合,使之具有适度的可塑性和粘性的耐热密封材料(例如格利特cc100…注册商标)。Also, the sealing
以上,引锭杆4的安置结束,其次如图1(c)所示,从中间包向模具10浇入钢水6。浇入的钢水在模具内应保持10-30秒以便能够拉拔引锭杆4、最好15-25秒左右,其间随着钢水表面的上升钢水被模具10冷却,形成凝固壳。As above, the setting of the
这样,在本发明的情况下比以往保持时间少些即可。这是因为初期是在无锥度下进行起动,壳与相接的短边模的摩擦力较小,所以壳的强度可以比以往的弱,于是减少拉拔力,就可减少加于壳上的力。In this way, in the case of the present invention, the holding time may be shorter than conventional ones. This is because the initial stage is to start without taper, and the friction between the shell and the connected short side mold is small, so the strength of the shell can be weaker than before, so reducing the pulling force can reduce the force on the shell. force.
引锭杆4头部形成有凹坑4a,钢水也流入该凹坑凝固,使引锭杆4与铸件的结合紧密,容易通过引锭杆拉拔铸件。A pit 4a is formed on the head of the
其次如图1(d)所示,一面将引锭杆4向下方拉拔一面继续浇入钢水6。此时,例如开始拉拔引锭杆4,在形成的凝固壳6a和模具板2之间钢水不再流入时(例如,在实施例记载的钢种、浴温、浇铸幅宽、浇铸速度(0.4m/分)的情况下是拉拔开始60秒后,或者是引锭杆通过模具下端时前后,最好在通过后),加上锥度的动作开始,最终要考虑前记的通常稳定浇铸状态下发生的热收缩,应将与之相当量在短边侧板2的上端部(或者上端部和下端部),按全幅宽(其间隔)的约1%程度(即各自短边的锥度为0.5%左右)向左右扩开,在向下方向加上锥度。Next, as shown in FIG. 1( d ),
所谓“在形成的凝固壳6a和模具板2之间,钢水不再流入时,锥度动作开始,加上锥度”是意味着在拉拔开始以后,在下记(1)及(2)作业事故的条件下赋予锥度,就是在形成的凝固壳具有在锥度变更时不发生事故(形成的凝固壳能够跟随移动的程度)的强度时开始赋予锥度的动作。The so-called "when the molten steel no longer flows between the formed
(1)拉拔开始后,如赋予锥度开始过快(比如拉拔开始后立刻加上锥度),在凝固壳6a的上端钢水流入凝固壳6a和模具板2之间,最终可能使壳破裂。所以应在铸件有了一定程度的拉拔速度时,开始赋予锥度的动作赋予其锥度。(1) After the drawing starts, if the taper is given too quickly (for example, the taper is added immediately after the drawing starts), molten steel flows into between the
(2)其次,过于缓慢时,如图2(a)、(b)所示(图2(a)是表示拉拔开始后赋予锥度开始过迟时在本发明模具处开始拉拔铸件后的铸件状态剖面略图,是图2(b)的B-B剖视图,图2(b)是图2(a)的A-A剖视图),凝固壳6a凝固收缩,凝固壳6a和模具板2之间的间隙7变大,造成壳成长不良(因为凝固壳的厚度薄),因而在该气隙7中,凝固壳6a由于钢水压力,发生凸起8,或者凝固壳6a一离开模具下端,凝固壳6a由于钢水压力发生凸起8a,因此凝固壳6a发生破裂,钢水可能从这里泄漏。(2) Secondly, when it is too slow, as shown in Figure 2 (a), (b) (Figure 2 (a) is to indicate that after the drawing starts, the taper begins to be given after the casting is started to be drawn at the mold of the present invention when it is too late. The casting state sectional sketch is the B-B sectional view of Fig. 2 (b), and Fig. 2 (b) is the A-A sectional view of Fig. 2 (a), the solidified
所以,拉拔开始后,铸件的拉拔有了速度时,如果平稳地赋予锥度,凝固壳即形成下去。Therefore, after the drawing starts, when the drawing speed of the casting is increased, if the taper is given smoothly, the solidified shell will be formed.
这期间,凝固壳6a也同时长大,由模具10拉拔引锭杆,继续进行连续浇铸作业形成铸件。During this period, the solidified
这样将短边侧板保持垂直,调整短边侧板2和引锭杆4的间隙为1-3mm,再安置引锭杆,于是填充密封材料5变得容易,可以减少浇铸的准备时间,促进密封材料的填充作业自动化。Keep the short-side side plate vertical like this, adjust the gap between the short-
这样与短边侧板2之间保持1-3mm的间隙安置引锭杆4进行连续浇注时,在引锭杆4由模具10的下部通过拔出时,引锭杆4、壳6a和模具10之间就没有异常的滑动力,可以用较小的拉拔力进行拔取。Keep the gap of 1-3mm between the
于是,可以防止拉拔时由于壳6a破裂而发生跑钢,减少浇铸准备时间,提高生产效率和模具寿命,更可以缩短在模具10内的保持时间,节约冷却材料,可以做到节约浇铸时间及运转成本,促进浇铸作业的自动化。Therefore, it is possible to prevent steel running due to the rupture of the
以下,就本发明的实施例加以说明。Hereinafter, examples of the present invention will be described.
温度1560℃下,由C0.04wt%、Mn0.25wt%、S0.010wt%、P0.015wt%、Sol.Al0.050wt%,以及铁和不可避免的杂质形成的钢水,浇入于模具内。用拉拔速度初期0.4m/分,正常1.6m/分制造宽1920mm、厚250mm的浇铸板坯(铸件)。At a temperature of 1560°C, molten steel composed of C0.04wt%, Mn0.25wt%, S0.010wt%, P0.015wt%, Sol.Al0.050wt%, iron and unavoidable impurities is poured into the mold. Casting slabs (castings) with a width of 1920mm and a thickness of 250mm were manufactured with a drawing speed of 0.4m/min at the initial stage and normally 1.6m/min.
在上记浇铸板坯(铸件)的制造中,浇铸板坯幅宽(冷换算值)=1,900mm的实施浇铸作业开始时的步骤,叙述如下。In the production of the cast slab (casting) described above, the procedure at the start of the cast slab width (cold conversion value) = 1,900 mm is described as follows.
(1)将模具短边侧板幅宽(间隔)设定为1,967mm,比引锭杆幅宽(1.917mm)大50mm。(1) Set the width (interval) of the side plate on the short side of the mold to 1,967mm, which is 50mm larger than the width of the dummy bar (1.917mm).
(2)将引锭杆插入模具,停止在所定位置(模具长900mm、从模具上端500mm的位置)。(2) Insert the dummy bar into the mold, and stop at a predetermined position (the position where the mold is 900 mm long and 500 mm from the upper end of the mold).
(3)将短边侧板保持垂直,使引锭杆和短边侧板的间隙为1.5mm,其间隔移动到1920mm。(3) Keep the short-side side plate vertical, so that the gap between the dummy bar and the short-side side plate is 1.5mm, and the distance is moved to 1920mm.
(4)充填引锭杆和模具之间的密封材料。(4) Fill the sealing material between the dummy rod and the mold.
(5)设置冷却材料,例如用焊接将钢片、铁板或铁棒组合而成。(5) Set the cooling material, for example, combine steel sheets, iron plates or iron rods by welding.
(6)由中间包向模具开始浇入钢水。(6) Start pouring molten steel from the tundish to the mold.
(7)钢水浇入后,为能够确保形成坚实的凝固壳所必需的最低保持时间,使钢水的水平面上升,在水平面达到离模具上端100-150mm的所定位置时,开始拉拔引锭杆。(7) After the molten steel is poured, in order to ensure the minimum holding time necessary to form a solid solidified shell, the level of the molten steel rises, and when the level reaches a predetermined position 100-150 mm from the upper end of the mold, the dummy bar is drawn.
(8)开始拉拔引锭杆后,由幅宽可变装置将短边侧板移动,使上端部向左右扩大,按短边侧板在向下方向具有的所定锥度率(即铸件幅宽)设定。(8) After starting to draw the dummy rod, the short-side side plate is moved by the width-variable device, so that the upper end is enlarged to the left and right, according to the predetermined taper ratio of the short-side side plate in the downward direction (that is, the casting width )set up.
另外,如图1(d)所示,模具的长度为:Ldo、短边侧板的下端部的间隔为Ld1,短边侧板的上端部的间隔为Ld2时,锥度比率TA(%/m)定义为下式(1)。
式中:In the formula:
TA:锥度比率(%/m)T A : Taper ratio (%/m)
Ld0:短边侧板的模具长度(m)。Ld0: Die length (m) of the side plate on the short side.
Ld1:短边侧板的模具下端部宽度(间隔)(mm)Ld1: Die lower end width (interval) (mm) of the short-side side plate
Ld2:短边侧板的模具上端部宽度(间隔)(mm)Ld2: Die upper end width (interval) (mm) of the short-side side plate
在上记工序(8),形成坚实的凝固壳,钢水向凝固壳6a和短边侧板2之间不再流入时(例如拉拔开始60秒后或引锭杆通过模具下端后),例如短边侧板的模具长Ld0为0.9m,短边侧板的模具下端部幅宽Ld1保持在1920mm,移动短边侧板的上下的幅宽可变装置(比如是液压缸),使短边侧板的模具上端部幅宽Ld2设定为1937mm(锥度比率TA=0.98%/m)。In the above-mentioned process (8), a solid solidified shell is formed, and when the molten steel no longer flows into between the solidified
按以上(1)-(8)的步骤操作的结果,如表1所示,缩短了准备时间,延长了模具的寿命,减少了浇铸开始时的事故等,与以往方法比较优越性是可以确认的。According to the results of the above (1)-(8) steps, as shown in Table 1, the preparation time is shortened, the life of the mold is prolonged, and accidents at the beginning of casting are reduced. Compared with the previous method, the superiority can be confirmed. of.
在本发明,例如在实施例记载的钢种、浇铸速度下,理想的锥度比率(%/m)范围,表示于下式(2)。In the present invention, for example, the range of the ideal taper ratio (%/m) is expressed by the following formula (2) under the steel types and casting speeds described in the examples.
0.5%/m≤TA≤2%/m…(2)0.5%/m≤T A ≤2%/m...(2)
将本发明的效果,汇总表示于表(2)。The effects of the present invention are summarized in Table (2).
表1
准备时间=将引锭杆插入模具内。在所定位置安置完了。密封作业完了(包括安置冷却材料作业)Preparation time = inserting the dummy rod into the mold. Finished at the desired location. The sealing operation is completed (including the placement of cooling materials)
表2
在上记表(2)中,由于本发明的起动方法所得的效果是起动时保持时间的短缩,准备时间的短缩,密封材料及冷却材料的减少,短边侧板寿命的延长,涛铸开始时事故的减少等,效果是显著的。In the above table (2), the effect of the starting method of the present invention is the shortening of the holding time during starting, the shortening of the preparation time, the reduction of sealing materials and cooling materials, the prolongation of the life of the short side plate, and the The effect is remarkable, such as the reduction of accidents at the start of casting.
还有,在上记表(2)中,由于本发明的引锭杆的安置方法所得的效果是,准备时间的短缩,密封材料及冷却材料的减少,浇铸开始时事故的减少等,效果显著。In addition, in the above table (2), the effect obtained by the dummy bar installation method of the present invention is the shortening of the preparation time, the reduction of sealing materials and cooling materials, the reduction of accidents at the beginning of casting, etc., the effect significantly.
Claims (19)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN92115006A CN1052929C (en) | 1992-12-30 | 1992-12-30 | Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN92115006A CN1052929C (en) | 1992-12-30 | 1992-12-30 | Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN1119136A CN1119136A (en) | 1996-03-27 |
| CN1052929C true CN1052929C (en) | 2000-05-31 |
Family
ID=4947221
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN92115006A Expired - Fee Related CN1052929C (en) | 1992-12-30 | 1992-12-30 | Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN1052929C (en) |
Families Citing this family (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN1724835B (en) * | 2004-07-19 | 2010-09-29 | 徐杰 | Method of preventing electricity burglar with easy broken layer on lock |
Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2023045A (en) * | 1978-06-14 | 1979-12-28 | Voest Alpine Ag | Method of starting a continuous casting plant |
| GB2094194A (en) * | 1981-03-11 | 1982-09-15 | Mannesmann Ag | Regulating convergence of continuous casting moulds |
| EP0114293A1 (en) * | 1982-12-21 | 1984-08-01 | Sms Schloemann-Siemag Aktiengesellschaft | Method of and installation for adjusting the taper of small face walls of continuous-casting ingots |
-
1992
- 1992-12-30 CN CN92115006A patent/CN1052929C/en not_active Expired - Fee Related
Patent Citations (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| GB2023045A (en) * | 1978-06-14 | 1979-12-28 | Voest Alpine Ag | Method of starting a continuous casting plant |
| GB2094194A (en) * | 1981-03-11 | 1982-09-15 | Mannesmann Ag | Regulating convergence of continuous casting moulds |
| EP0114293A1 (en) * | 1982-12-21 | 1984-08-01 | Sms Schloemann-Siemag Aktiengesellschaft | Method of and installation for adjusting the taper of small face walls of continuous-casting ingots |
Also Published As
| Publication number | Publication date |
|---|---|
| CN1119136A (en) | 1996-03-27 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105026073B (en) | Casting Equipment and the casting method using the Casting Equipment | |
| CN1947893A (en) | Method for mfg. aluminium alloy wheel hub | |
| US3530927A (en) | Method of fabrication of metals by pressure casting | |
| CN1052929C (en) | Method for starting continuous casting in continuous slab casting and method for setting a dummy bar prier to the start of casting of continuous slab casting | |
| JP2639758B2 (en) | How to start slab continuous casting | |
| CN113523208A (en) | Composite continuous casting machine and production method thereof | |
| JP4836303B2 (en) | Continuous casting mold | |
| CN214023373U (en) | An aluminum rod casting mold | |
| CN216828534U (en) | A kind of sand core mold for automobile clamp body casting | |
| CN212945399U (en) | Feeding device for antimony ingot production line | |
| JPS632534A (en) | Method of bottom pouring steel ingot making | |
| CN1045176C (en) | Casting mould for riser-free casting | |
| CN219153236U (en) | Insulation can is used in production of convenient electric smelting brick of unloading | |
| CN221109798U (en) | Compensation structure of wet film sand casting steering knuckle | |
| JP2639757B2 (en) | Start method of continuous slab casting | |
| KR102910305B1 (en) | Controlled casting of in-mold large-scale ingots using inductive variable power and variable frequency. | |
| CN214768732U (en) | High-extension high-compactness casting mold for brake system bracket | |
| CN211503671U (en) | Metal melting furnace | |
| CN102355964B (en) | Continuous casting method, short edge mould plate and continuous casting mold | |
| CN218946304U (en) | Support die casting die | |
| CN212945327U (en) | Aluminum ingot melting forming device | |
| JPH09192786A (en) | Mold for continuous casting of steel and continuous casting method | |
| CN208772390U (en) | A kind of brake drum casting mold | |
| RU2022692C1 (en) | Method of continuous casting of steel slabs | |
| CN120243852A (en) | A high homogenization and low cost casting billet static production process and equipment |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C06 | Publication | ||
| PB01 | Publication | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| C15 | Extension of patent right duration from 15 to 20 years for appl. with date before 31.12.1992 and still valid on 11.12.2001 (patent law change 1993) | ||
| OR01 | Other related matters | ||
| C19 | Lapse of patent right due to non-payment of the annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |