CN105200869B - 一种嵌入式轨道系统由上至下的快速施工方法 - Google Patents

一种嵌入式轨道系统由上至下的快速施工方法 Download PDF

Info

Publication number
CN105200869B
CN105200869B CN201510553112.4A CN201510553112A CN105200869B CN 105200869 B CN105200869 B CN 105200869B CN 201510553112 A CN201510553112 A CN 201510553112A CN 105200869 B CN105200869 B CN 105200869B
Authority
CN
China
Prior art keywords
rail
construction
prefabricated components
fixed
macromolecule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510553112.4A
Other languages
English (en)
Other versions
CN105200869A (zh
Inventor
焦洪林
杨刚
费学梅
罗炯
何云伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Chengdu Xinzhu Transportation Technology Co ltd
Original Assignee
Chengdu Xinzhu Road and Bridge Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Xinzhu Road and Bridge Machinery Co Ltd filed Critical Chengdu Xinzhu Road and Bridge Machinery Co Ltd
Priority to CN201510553112.4A priority Critical patent/CN105200869B/zh
Publication of CN105200869A publication Critical patent/CN105200869A/zh
Application granted granted Critical
Publication of CN105200869B publication Critical patent/CN105200869B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)
  • Road Paving Structures (AREA)

Abstract

本发明公开了一种嵌入式轨道系统由上至下的快速施工方法,包括以下施工步骤:对基底的线路中心控制线和高程控制线进行测量放线,并将钢轨、高分子预制构件运送至施工现场贮存;加工、连接钢筋网并将其沿轨道方向纵向铺设在基底上;将运送至施工现场的钢轨焊连并将焊接接头打磨平整;钢轨两侧粘结高分子预制构件;铺设钢轨组件并精调;现浇混凝土道床;养护及拆模。综上所述,由于采用了上述技术方案,本发明施工方法操作步骤简单、快捷,工序合理、新颖;步骤一、二、三可以同时施工,步骤四、五也可以同时施工,提高了施工效率;占地少,噪音小,周期短;固定工装能有效的调整和保持钢轨的几何形位,保证列车运行的安全舒适性。

Description

一种嵌入式轨道系统由上至下的快速施工方法
技术领域
本发明涉及一种轨道系统施工方法,尤其涉及一种嵌入式轨道系统由上至下的快速施工方法,属于轨道交通技术领域。
背景技术
随着城市交通压力的增大,城市轨道交通由于具有运量大、速度快、安全、准点、环保、节能等特点,在各城市大力发展。但是,城市轨道交通的施工周期长,占地面积大,粉尘噪音严重等施工问题,给城市交通,居民生活带来极大影响。
在先进的城市轨道交通技术领域,嵌入式轨道系统作为一种新型的无砟轨道系统,应当具有施工快速、建设成本低、占地面积小、美观环保等特点。
发明内容
本发明的发明目的在于:针对上述存在的问题,提供一种嵌入式轨道系统由上至下的快速施工方法,先调整轨道的几何形位,再浇注现浇混凝土道床,施工步骤简单、快速,对交通影响小、噪音低,绿色环保,有别于传统扣件施工形式。
本发明采用的技术方案是这样的:
一种嵌入式轨道系统由上至下的快速施工方法,包括以下施工步骤:
步骤一:施工准备
采用常规无砟轨道道床基底的测量放线方法,在施工现场对基底的线路中心控制线和高程控制线进行测量放线,作为钢轨组件铺设参考基准;并将钢轨、高分子预制构件运送至施工现场贮存;
步骤二:铺设钢筋网
加工、连接钢筋网并将其沿轨道方向纵向铺设在基底上;
步骤三:钢轨焊接
将运送至施工现场的钢轨焊连并将焊接接头打磨平整;
步骤四:钢轨两侧粘结高分子预制构件
将钢轨表面浮锈、灰尘清理干净后,在钢轨、高分子预制构件粘接面涂刷专用胶粘剂,将高分子预制构件粘接到钢轨轨腰两侧。为保证初始粘接效果,粘接好后用绑扎带将高分子预制构件固定在钢轨上,待浇注现浇混凝土道床时,再去除绑扎带;
步骤五:铺设钢轨组件并精调
以线路中心控制线为基准,调整钢轨位置并用固定工装将钢轨临时固定住以保证线路的几何形位满足设计要求且在后续施工过程中不会被扰动;
步骤六:现浇混凝土道床
在路面两侧用模板封模,混凝土应尽量均匀连续灌筑,并在灌筑过程中,随填随振捣密实;
步骤七:养护及拆模
混凝土可采取带模包裹、浇水、喷淋洒水措施进行保湿、潮湿养护。在混凝土强度达到10MPa时即可拆除模板。
作为优选,还包括步骤八:轨道周围景观铺设
根据城市景观要求对轨道周围进行沥青、砖石或绿化铺设。
作为优选,步骤五中,所述固定工装包括一根横板、两根支撑杆以及两块固定块,两根所述支撑杆设置在横板两端并临时固定在轨道两侧,每根支撑杆套接一根套管,两块所述固定块分别置于一根钢轨上且固定块底部设有与钢轨内侧的槽相匹配的凸起,固定块通过螺栓螺母固定在横板下方。设置套管的目的,是为了方便现浇混凝土道床完成之后,将横板、固定块取出重复利用,而套管则直接留在道床中。
作为优选,所述高分子预制构件一侧与钢轨轨腰侧面粘接固定,另一侧设计钢板或锚筋,与现浇混凝土道床实现有效锚固。
综上所述,由于采用了上述技术方案,本发明的有益效果是:
1、操作步骤简单、快捷,工序合理、新颖;
2、多个步骤可同时施工,比如步骤一、二、三,就可以同时施工,步骤四、五也可以同时施工,提高了施工效率;
3、占地少,噪音小,周期短;
4、起到调整、固定作用的固定工装能有效的调整和保持钢轨的几何形位,以保证列车运行的安全性、舒适性、稳定性。
附图说明
图1是本发明施工方法所涉及轨道的横截面结构示意图。
图2是本发明施工方法所涉及轨道的纵向结构示意图。
图3是本发明施工方法的施工流程图。
图中标记:1为固定工装,2为钢轨,3为高分子预制构件,4为混凝土道床,5为钢筋网,6为套管。
具体实施方式
下面结合附图,对本发明作详细的说明。
实施例:
本发明施工方法在实施过程中,所涉及的结构如图1、2所示。
一种嵌入式轨道系统由上至下的快速施工方法,包括如图3所示的施工步骤:
步骤一:施工准备
采用常规无砟轨道道床基底的测量放线方法,在施工现场对基底的线路中心控制线和高程控制线进行测量放线,作为钢轨组件铺设参考基准;并将钢轨2、高分子预制构件3运送至施工现场贮存;
步骤二:铺设钢筋网5
加工、连接钢筋网5并将其沿轨道方向纵向铺设在基底上。
步骤三:钢轨2焊接
将运送至施工现场的钢轨2焊连并将焊接接头打磨平整。
步骤四:钢轨2两侧粘结高分子预制构件3
将钢轨2表面浮锈、灰尘清理干净后,在钢轨2、高分子预制构件3粘接面涂刷专用胶粘剂,将高分子预制构件3粘接到钢轨2轨腰两侧。为保证初始粘接效果,粘接好后用绑扎带将高分子预制构件3固定在钢轨2上,待浇注现浇混凝土道床4时,再去除绑扎带。
所述高分子预制构件3一侧与钢轨2轨腰侧面粘接固定,另一侧设计钢板或锚筋,与现浇混凝土道床4实现有效锚固。
步骤五:铺设钢轨组件并精调
以线路中心控制线为基准,调整钢轨2位置并用固定工装1将钢轨2临时固定住以保证线路的几何形位满足设计要求且在后续施工过程中不会被扰动。
步骤五中,所述固定工装1包括一根横板、两根支撑杆以及两块固定块,两根所述支撑杆设置在横板两端并临时固定在轨道两侧,每根支撑杆套接一根套管,两块所述固定块分别置于一根钢轨2上且固定块底部设有与钢轨2内侧的槽相匹配的凸起,固定块通过螺栓螺母固定在横板下方。
步骤六:现浇混凝土道床
在路面两侧用模板封模,混凝土应尽量均匀连续灌筑,并在灌筑过程中,随填随振捣密实。
步骤七:养护及拆模
混凝土可采取带模包裹、浇水、喷淋洒水措施进行保湿、潮湿养护。在混凝土强度达到10MPa时即可拆除模板。
还包括步骤八:轨道周围景观铺设
根据城市景观要求对轨道周围进行沥青、砖石或绿化铺设。

Claims (4)

1.一种嵌入式轨道系统由上至下的快速施工方法,其特征在于包括以下施工步骤:
步骤一:施工准备
采用常规无砟轨道道床基底的测量放线方法,在施工现场对基底的线路中心控制线和高程控制线进行测量放线,作为钢轨组件铺设参考基准;并将钢轨、高分子预制构件运送至施工现场贮存;
步骤二:铺设钢筋网
加工、连接钢筋网并将其沿轨道方向纵向铺设在基底上;
步骤三:钢轨焊接
将运送至施工现场的钢轨焊连并将焊接接头打磨平整;
步骤四:钢轨两侧粘结高分子预制构件
将钢轨表面浮锈、灰尘清理干净后,在钢轨、高分子预制构件粘接面涂刷专用胶粘剂,将高分子预制构件粘接到钢轨轨腰两侧,为保证初始粘接效果,粘接好后用绑扎带将高分子预制构件固定在钢轨上,待浇注现浇混凝土道床时,再去除绑扎带;
步骤五:铺设钢轨组件并精调
以线路中心控制线为基准,调整钢轨位置并用固定工装将钢轨临时固定住以保证线路的几何形位满足设计要求且在后续施工过程中不会被扰动;
步骤六:现浇混凝土道床
在路面两侧用模板封模,混凝土应尽量均匀连续灌筑,并在灌筑过程中,随填随振捣密实;
步骤七:养护及拆模
混凝土可采取带模包裹、浇水、喷淋洒水措施进行保湿、潮湿养护,在混凝土强度达到10MPa时即可拆除模板。
2.根据权利要求1所述的一种嵌入式轨道系统由上至下的快速施工方法,其特征在于:
还包括步骤八:轨道周围景观铺设
根据城市景观要求对轨道周围进行沥青、砖石或绿化铺设。
3.根据权利要求1所述的一种嵌入式轨道系统由上至下的快速施工方法,其特征在于:步骤五中,所述固定工装包括一根横板、两根支撑杆以及两块固定块,两根所述支撑杆设置在横板两端并临时固定在轨道两侧,每根支撑杆套接一根套管,两块所述固定块分别置于一根钢轨上且固定块底部设有与钢轨内侧的槽相匹配的凸起,固定块通过螺栓螺母固定在横板下方。
4.根据权利要求1所述的一种嵌入式轨道系统由上至下的快速施工方法,其特征在于:所述高分子预制构件一侧与钢轨轨腰侧面粘接固定,另一侧设计钢板或锚筋,与现浇混凝土道床实现有效锚固。
CN201510553112.4A 2015-09-02 2015-09-02 一种嵌入式轨道系统由上至下的快速施工方法 Active CN105200869B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510553112.4A CN105200869B (zh) 2015-09-02 2015-09-02 一种嵌入式轨道系统由上至下的快速施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510553112.4A CN105200869B (zh) 2015-09-02 2015-09-02 一种嵌入式轨道系统由上至下的快速施工方法

Publications (2)

Publication Number Publication Date
CN105200869A CN105200869A (zh) 2015-12-30
CN105200869B true CN105200869B (zh) 2017-01-18

Family

ID=54948804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510553112.4A Active CN105200869B (zh) 2015-09-02 2015-09-02 一种嵌入式轨道系统由上至下的快速施工方法

Country Status (1)

Country Link
CN (1) CN105200869B (zh)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112064424B (zh) * 2020-08-07 2022-05-17 上海远通路桥工程有限公司 一种平交道口路段轨道快速施工方法
CN112761034B (zh) * 2020-12-24 2022-08-09 成都市新筑路桥机械股份有限公司 一种流体材料浇筑小车
CN116356617B (zh) * 2023-04-26 2025-07-25 中铁电气化局集团有限公司 一种地铁隧道嵌入式轨道散铺施工工法
CN116356614B (zh) * 2023-05-11 2025-08-08 成都市新筑交通科技有限公司 一种纵向轨排结构及其施工方法
CN116837675A (zh) * 2023-05-18 2023-10-03 中铁四局集团有限公司 铁路路肩焊轨工况下确保焊接接头质量的机械化施工方法
CN117071337A (zh) * 2023-08-21 2023-11-17 中铁一局集团有限公司 一种高等减振嵌入式轨道钢槽安装装置及安装方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008003843A2 (fr) * 2006-07-07 2008-01-10 Lohr Industrie Ensemble autonettoyant par garnissage de lacune pour rail au sol de guidage ou de roulage
CN101812819A (zh) * 2010-04-28 2010-08-25 中铁二十局集团有限公司 双块式无砟轨道整体施工工艺
CN103362036A (zh) * 2013-07-24 2013-10-23 成都市新筑路桥机械股份有限公司 一种嵌入式轨道系统的快速施工方法
CN103452014A (zh) * 2013-09-17 2013-12-18 浙江天铁实业股份有限公司 有轨电车吸振消声结构

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101557024B1 (ko) * 2013-03-06 2015-10-02 강남훈 3차원 입체형상을 갖는 레일매립형 콘크리트블록 제조방법 및 이 방법에 의해 제조된 레일매립형 콘크리트블록을 이용한 매립형 철도궤도 부설방법

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2008003843A2 (fr) * 2006-07-07 2008-01-10 Lohr Industrie Ensemble autonettoyant par garnissage de lacune pour rail au sol de guidage ou de roulage
CN101812819A (zh) * 2010-04-28 2010-08-25 中铁二十局集团有限公司 双块式无砟轨道整体施工工艺
CN103362036A (zh) * 2013-07-24 2013-10-23 成都市新筑路桥机械股份有限公司 一种嵌入式轨道系统的快速施工方法
CN103452014A (zh) * 2013-09-17 2013-12-18 浙江天铁实业股份有限公司 有轨电车吸振消声结构

Also Published As

Publication number Publication date
CN105200869A (zh) 2015-12-30

Similar Documents

Publication Publication Date Title
CN105200869B (zh) 一种嵌入式轨道系统由上至下的快速施工方法
CN105625104B (zh) 一种预制板式减振轨道结构系统及配套施工方法
CN101215812B (zh) 客运专线长枕埋入式大号无砟道岔施工方法
BR112013016308A2 (pt) método para produzir uma via férrea com laje
CN102650574A (zh) 一种高速铁路动力荷载模拟装置
CN101418535A (zh) 轨道交通隧道内整体道床的施工方法
CN108286210A (zh) 一种嵌入式道岔系统的快速施工方法
CN105350409B (zh) 城市轨道交通长枕式钢弹簧浮置板道床道岔施工方法
CN103088727B (zh) 一种轨道抗偏摆定距装置
CN201103082Y (zh) 嵌入式承重轨道
CN103374865B (zh) 无砟轨道板纵连铺设施工方法
CN107354826A (zh) 隧道内嵌入式轨道系统的快速施工方法
JP4620044B2 (ja) レール使用車両、特に鉄道のためのレール構造体
CN107313313B (zh) 预制聚氨酯固化道床的排架施工方法
CN1344835A (zh) 固定轨道车行道的双块混凝土铁道枕木
CN208604416U (zh) 一种拼装化连续支承轨道结构
CN107451305A (zh) 一种列车‑轨道‑结构耦合系统异步长高效动力分析方法
CN202099699U (zh) 弹性支撑隔振构件道床
CN104863025A (zh) 一种绿化段有轨电车整体道床的施工方法
KR100759923B1 (ko) 철도의 저형고 장지간 거더.
CN204343107U (zh) 分体式连续支撑无扣件道床系统
CN206233043U (zh) 钢轨及铁路轨道
CN2758310Y (zh) 双块式轨枕
CN100552135C (zh) 双块式无碴轨道砼灌注方法
CN204162955U (zh) 软土地区现代有轨电车路基刚度过渡结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190904

Address after: 225000 Room 103, 4 Blocks, Wankejin Street, East Stumiao Road, Yangzhou City, Jiangsu Province

Patentee after: Jiangsu Huadong culture and technology Financing Leasing Co.,Ltd.

Address before: 611430 Xinjin Industrial Park, Sichuan, Chengdu

Patentee before: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191223

Address after: 101300, room 711, building 2, building 1, Golden Road, Beijing, Shunyi District (Tianzhu comprehensive bonded area, -031)

Patentee after: Beijing culture science and technology finance leasing Limited by Share Ltd.

Address before: 225000 Room 103, 4 Blocks, Wankejin Street, East Stumiao Road, Yangzhou City, Jiangsu Province

Patentee before: Jiangsu Huadong culture and technology Financing Leasing Co.,Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20221212

Address after: 611430 Xinjin Industrial Park, Xinjin District, Chengdu, Sichuan

Patentee after: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.

Address before: 101300 room 711, 2 building, 1 Jin Hang Zhong Road, Shunyi District, Beijing (Tianzhu comprehensive bonded zone -031)

Patentee before: Beijing culture science and technology finance leasing Limited by Share Ltd.

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240116

Address after: 611400 No. 799, hope road, Wujin street, Xinjin District, Chengdu, Sichuan (Industrial Park)

Patentee after: Chengdu Xinzhu Transportation Technology Co.,Ltd.

Address before: 611430 Xinjin Industrial Park, Xinjin District, Chengdu, Sichuan

Patentee before: CHENGDU XINZHU ROAD & BRIDGE MACHINERY Co.,Ltd.