CN105064186A - 黄土路基快速压实方法 - Google Patents

黄土路基快速压实方法 Download PDF

Info

Publication number
CN105064186A
CN105064186A CN201510478468.6A CN201510478468A CN105064186A CN 105064186 A CN105064186 A CN 105064186A CN 201510478468 A CN201510478468 A CN 201510478468A CN 105064186 A CN105064186 A CN 105064186A
Authority
CN
China
Prior art keywords
roller
rolling
loess
road roller
iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510478468.6A
Other languages
English (en)
Inventor
康成生
马来有
王强
张占旭
尚淑芳
裴欢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Shunda Construction Of Road And Bridge Co Ltd
Gansu Road and Bridge Construction Group Co Ltd
Original Assignee
Gansu Shunda Construction Of Road And Bridge Co Ltd
Gansu Road and Bridge Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Shunda Construction Of Road And Bridge Co Ltd, Gansu Road and Bridge Construction Group Co Ltd filed Critical Gansu Shunda Construction Of Road And Bridge Co Ltd
Priority to CN201510478468.6A priority Critical patent/CN105064186A/zh
Publication of CN105064186A publication Critical patent/CN105064186A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Road Paving Machines (AREA)

Abstract

本发明涉及一种黄土路基快速压实方法,该方法包括以下步骤:⑴机械组合选择:1~2台穿凸轮盔甲的YZ-18T振动压路机、1台带灌砂配重的铁三轮压路机3YJ-21T;⑵确定水平分层施工碾压厚度为压实层厚≤30cm;⑶对黄土路基进行整平;⑷测定黄土天然含水量;⑸沿路压路机碾压作业:所述YZ-18T振动压路机和所述铁三轮压路机3YJ-21T先后按不超过1.7km/h的碾压速度各碾压1遍,其中所述YZ-18T振动压路机Ⅰ挡强振,轮迹重合凸轮全宽的90%;所述铁三轮压路机3YJ-21TⅠ挡静压或Ⅱ挡,后轮轮迹重合30~50cm;碾压1遍结束后即可采用灌砂法检测压实度;若不符合规范要求,则最多各自复压1遍,总共不超过2遍。本发明快速经济且质量标准高。

Description

黄土路基快速压实方法
技术领域
本发明涉及公路路基土方工程施工领域,尤其涉及黄土路基快速压实方法。
背景技术
目前,我国公路行业标准JTGF10-2006《公路路基施工技术规范》P91表4-1对于不同填料路基的压实机械进行了笼统的选择,同时对于甘肃大部黄土地区特殊路基碾压程序、碾压的现场控制无针对性、可操作性不强——如①在黄土路基施工过程中,根据规范规定碾压宜在接近最佳含水量时进行碾压,但现场具体控制的范围是多少?②压路机的选择很多,有光轮、振动、凸轮、羊角碾、轮胎压路机等,到底何种组合是最有效且最为通用、投入最小?③碾压过程中压路机一般轮迹重合1/2或1/3轮宽,对于黄土路基是否最为高效?④碾压遍数一般情况下多少遍才能最快达到规定的压实度标准?
黄土路基具有湿陷性和易溶蚀、易冲刷、压缩变形量大等工程特性,导致黄土地区的路基易产生多种问题及病害。为了克服该种特殊路基的自身问题,最直接的工程措施就是对黄土路基的压实度严格控制,而当前公路基本建设项目工程量越来越大、工期越来越紧,施工单位各自的施工经验没有形成规范统一和标准化的施工工艺,现场技术人员施工经验缺乏而又无直接的参考数据和资料用于指导施工,导致具体的施工项目压实方法五花八门,设备投入不合理,对原本有限的工期造成一定的延误,路基施工质量离散性大、不均匀沉陷等工程病害多发。
发明内容
本发明所要解决的技术问题是提供一种快速经济且质量标准高的黄土路基快速压实方法。
为解决上述问题,本发明所述的黄土路基快速压实方法,包括以下步骤:
⑴机械组合选择:
1~2台穿凸轮盔甲的YZ-18T振动压路机、1台带灌砂配重的铁三轮压路机3YJ-21T;
⑵确定水平分层施工碾压厚度为压实层厚≤30cm;
⑶对黄土路基进行整平;
⑷测定黄土天然含水量,并使其含水量范围w达到如下标准:
w=[最佳含水量w0+0%,最佳含水量w0+2.5%];
⑸沿路压路机碾压作业:
所述YZ-18T振动压路机和所述铁三轮压路机3YJ-21T先后按不超过1.7km/h的碾压速度各碾压1遍,其中所述YZ-18T振动压路机Ⅰ挡强振,轮迹重合凸轮全宽的90%;所述铁三轮压路机3YJ-21TⅠ挡静压或Ⅱ挡,后轮轮迹重合30~50cm;
碾压1遍结束后即可采用灌砂法检测压实度;若不符合规范要求,则最多各自复压1遍,总共不超过2遍。
本发明与现有技术相比具有以下优点:
1、本发明施工质量稳定可靠、生产效率高、施工进度快。
由于施工方法的明确具体,现场施工质量离散性小,组织流水作业顺畅,显著缩短了大方量施工的循环周期。
2、本发明设备投入简单实用、降低了工程费用。
由于本发明采用通用的主流机型,充足投入机械费用小,同时因施工质量可靠,降低了工程返工等额外增加费用。
3、本发明有利于环保和职业健康安全。
由于工效的提高相对地降低了排放和燃油消耗,避免了复压或返工等造成施工人员劳动时间的不确定性延长,总体上降低了劳动强度。
4、本发明经在甘肃省庆阳市西合二级公路62.77km黄土路基305万填土方工程量及15个高填方路基[平均填方h>35m]的工程实体中实际应用,不但确保了工程质量,而且加快了施工进度,提高了机械化施工效率,取得了非常高的施工经济效益。
具体实施方式
黄土路基快速压实方法,包括以下步骤:
⑴机械组合选择:
1~2台穿凸轮盔甲的YZ-18T振动压路机、1台带灌砂配重的铁三轮压路机3YJ-21T。
⑵确定水平分层施工碾压厚度为压实层厚≤30cm。
⑶对黄土路基进行整平。
⑷测定黄土天然含水量,并使其含水量范围w达到如下标准:
w=[最佳含水量w0+0%,最佳含水量w0+2.5%]。
若黄土天然含水量小于最佳含水量时,简便高效的方法是根据计算补水量在取土场边装土边喷洒水,经过装土、卸车、摊铺、平整各工序及渗透时效,即可确保碾压时的含水量符合目标要求。
⑸沿路压路机碾压作业:
YZ-18T振动压路机和铁三轮压路机3YJ-21T先后按不超过1.7km/h的碾压速度各碾压1遍,其中YZ-18T振动压路机Ⅰ挡强振,轮迹重合凸轮全宽的90%(压路机宽度方向共有10列凸轮,压路机进退后错开1列凸轮继续碾压);铁三轮压路机3YJ-21TⅠ挡静压(适宜94%区及以上)或Ⅱ挡(压实90%-92%区路堤),后轮(轮宽60cm)轮迹重合30~50cm。
碾压1遍结束后即可采用灌砂法检测压实度;若不符合规范要求,则最多各自复压1遍,总共不超过2遍。
其中:碾压1遍是指压路机开始前进,后退原路返回,驱动轮重合2.0m(采用的压路机轮全宽2.20m),错轮不超过20cm碾压完成整个工作区段,即为1遍。

Claims (1)

1.黄土路基快速压实方法,包括以下步骤:
⑴机械组合选择:
1~2台穿凸轮盔甲的YZ-18T振动压路机、1台带灌砂配重的铁三轮压路机3YJ-21T;
⑵确定水平分层施工碾压厚度为压实层厚≤30cm;
⑶对黄土路基进行整平;
⑷测定黄土天然含水量,并使其含水量范围w达到如下标准:
w=[最佳含水量w0+0%,最佳含水量w0+2.5%];
⑸沿路压路机碾压作业:
所述YZ-18T振动压路机和所述铁三轮压路机3YJ-21T先后按不超过1.7km/h的碾压速度各碾压1遍,其中所述YZ-18T振动压路机Ⅰ挡强振,轮迹重合凸轮全宽的90%;所述铁三轮压路机3YJ-21TⅠ挡静压或Ⅱ挡,后轮轮迹重合30~50cm;
碾压1遍结束后即可采用灌砂法检测压实度;若不符合规范要求,则最多各自复压1遍,总共不超过2遍。
CN201510478468.6A 2015-08-07 2015-08-07 黄土路基快速压实方法 Pending CN105064186A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510478468.6A CN105064186A (zh) 2015-08-07 2015-08-07 黄土路基快速压实方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510478468.6A CN105064186A (zh) 2015-08-07 2015-08-07 黄土路基快速压实方法

Publications (1)

Publication Number Publication Date
CN105064186A true CN105064186A (zh) 2015-11-18

Family

ID=54493674

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510478468.6A Pending CN105064186A (zh) 2015-08-07 2015-08-07 黄土路基快速压实方法

Country Status (1)

Country Link
CN (1) CN105064186A (zh)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1645690A1 (de) * 2004-10-07 2006-04-12 Peter Doppler Vorrichtung zum Sanieren und Herstellen von tragfähigen Oberflächen
CN103993533A (zh) * 2014-06-13 2014-08-20 北京市政建设集团有限责任公司 用于黄土地区高填方路堤的综合压实方法
CN104746412A (zh) * 2015-04-01 2015-07-01 贵州新联爆破工程集团有限公司 一种湿陷性黄土路堤施工方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1645690A1 (de) * 2004-10-07 2006-04-12 Peter Doppler Vorrichtung zum Sanieren und Herstellen von tragfähigen Oberflächen
CN103993533A (zh) * 2014-06-13 2014-08-20 北京市政建设集团有限责任公司 用于黄土地区高填方路堤的综合压实方法
CN104746412A (zh) * 2015-04-01 2015-07-01 贵州新联爆破工程集团有限公司 一种湿陷性黄土路堤施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘嘉,庞文占: "黄土路基的常规压实方法研究", 《甘肃水利水电技术》 *

Similar Documents

Publication Publication Date Title
CN102996136B (zh) 盾构近距离下穿复合地基建筑物的变形控制方法
CN104612027B (zh) 用于道路修复加固的地聚合物注浆工艺
CN104358188A (zh) 湿陷性黄土路基填筑施工方法
CN206829119U (zh) 一种湿陷性黄土的预浸水地基处理结构
CN104131499A (zh) 一种用于沉降无砟轨道中线偏移纠偏方法
CN104179105B (zh) 一种逆作法刚性桩复合地基施工方法
CN103993533B (zh) 用于黄土地区高填方路堤的综合压实方法
CN104358196A (zh) 已通车公路路堤沉降处置结构的施工方法
CN103410072B (zh) 一种使用泡沫轻质土的环形试车道立体弧面的施工方法
CN109026013A (zh) 一种竖井滑模混凝土压光装置及压光方法
CN108682261B (zh) 一种土木工程中模拟煤层开采的实验教具
CN104060630A (zh) 防位移检查井施工工艺
CN104480956B (zh) 一种小直径模袋混凝土桩复合地基
CN106906715A (zh) 一种公路地裂缝的修补方法
CN105064186A (zh) 黄土路基快速压实方法
CN107060825A (zh) 一种应用于ⅲ级围岩的单洞四车道隧道分部协调施工方法
CN105350512A (zh) 一种碳酸盐岩块石填料强夯加冲击碾压的施工方法
CN103821070B (zh) 一种3d成型机械
CN119373508A (zh) 采煤地裂缝的修复方法和采煤地裂缝的修复装置
CN102425086A (zh) 高速客运专线过渡段路基水泥级配碎石填筑方法
CN204491385U (zh) 沥青混凝土路面再生修复压密注浆浅孔结构
CN203346857U (zh) 一种衬砌梯形渠道预制构件
CN202954381U (zh) 路基边坡的修整设备
CN208826824U (zh) 一种用于确定路基拱形骨架圆弧轮廓的新型模具
CN207193940U (zh) 一种小型打夯机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20151118